This document is Amendment 0006 to a solicitation for a Design-Bid-Build Construction Project to correct shoreline erosion at the U.S. Coast Guard Station Siuslaw River in Florence, Oregon. The amendment provides responses to Pre-Proposal Inquiries and revises specifications and drawings, including changes to sheet pile installation requirements, vibration monitoring, and utility disruption. The solicitation is only available to the successful NMACC III Pool 1 offerors. Key details include:

  • The in-water work window is November 1 to February 15, and sheet piles/tie-backs are to be installed above the highest measured tide.
  • Contractor is responsible for maintaining utilities to the floating dock/covered mooring during up to 3 weeks of disruption.
  • Quality Assurance Manager, Project Manager, and Superintendent must have experience on at least 3 similar projects, regardless of contract delivery method.
  • An AISC certified shop and erector are no longer required.
  • Offerors are reminded to acknowledge receipt of this amendment in their proposal.

View the file

Other files

File Type Posted
Price Proposal Form Rev 6.pdf PDF
SF 30 Station Siuslaw Amendment 0010.pdf PDF
Suislaw EA_w all signatures (June 2024).pdf PDF
Draft MMPA IHA_USCG Station Siuslaw_41624.pdf PDF
SF 30 Station Siuslaw Amendment 0009 and continuation sheet.pdf PDF
Amendment 0008 with Price Proposal Rev 5 - 19JUL2024.pdf PDF
Amendment 0007 03JUL2024.pdf PDF
Permit 2. BA_USCG Station Siuslaw.pdf PDF
STA Siuslaw Amendment 0005 with Site Visit Log.pdf PDF
STA Siuslaw Amendment 0005 Attachment PPI 073 Fiber Box Picture.pdf PDF
Permit 5. DEQ 401 WQC USCG Station Siuslaw River Covered Moorage and Shoreline 2023-651- signed.pdf PDF
STA Siuslaw Amendment 0005 Attachment PPI 076 Fuel Picture.pdf PDF
Permit 6. Section 408 No Alteration - USCG Covered Moorage and Shoreline.pdf PDF
Permit 3. CZMA Federal Consistency Determination_USCG Station Siuslaw.pdf PDF
STA Siuslaw Amendment 0005 STA Siuslaw Additional Specifications Update 06-27-2024 (PPI 075).pdf PDF
STA Siuslaw Amendment 0005 Attachment Geotechnical Report 1-26-2024.pdf PDF
Permit 1. Final JPA_USCG Station Siuslaw_revised.pdf PDF
Permit 4. Suislaw EA_w all signatures (June 2024).pdf PDF
STA Siuslaw Amendment 0004.pdf PDF
STA Siuslaw Amendment 0004 USCG SIUSLAW GEOTECHNICAL REPORT (version 12-07-2023).pdf PDF
STA Siuslaw Amendment 0001.pdf PDF
STA Siuslaw Amendment 0003.pdf PDF
STA Siuslaw Amendment 0002.pdf PDF
Task Order Announcement Station Siuslaw Correct Shore Erosion.pdf PDF
USCG Siuslaw FINAL Dwgs 2024.04.16.pdf PDF
USCG Siuslaw Drawings 100 percent Wall Plan.pdf PDF
USCG Siuslaw RFP Specs_Final 2024.04.16.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

70Z05024R43000003; CORRECT SHORELINE EROSION AT USCG STATION SIUSLAW, FLORENCE, OR

The purpose of this amendment is to provide responses to Pre-Proposal Inquiries, and Specification/Drawing revisions.

USCG FDCC SEATTLE

915 SECOND AVE, RM 2664

SEATTLE, WASHINGTON 98174-1011

70Z05024R43000003

1 10

07/02/2024

05/29/2024

70Z05024R43000003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

ENCLOSED DOCUMENT: N/A

A. REVISIONS TO THE TASK ORDER ANNOUNCEMENT/AMENDMENT ATTACHMENTS

The Geotechnical Report dated 01/26/2024 that was provided via Amendment 0005 replaced the Geotechnical Report that was provided via Amendment 0004.

B. REVISIONS TO THE SPECIFICATIONS/DRAWINGS

1.

Section 31 14 16 - 1.5.3

REMOVE:

“A pile driven below the specified butt elevation must be corrected by one of the following methods approved by the Engineer:

a. The pile is spliced (if approved).”

REPLACE WITH:

“A pile driven below the specified butt elevation must be corrected by one of the following methods approved by the Engineer:

a. The pile is spliced. Contractor to submit splice details to the Engineer for review and approval prior to installation in the field. Contractor's design for splice to be signed and sealed by a licensed structural engineer.”

2.

Section 31 14 16 – 2.1

REMOVE:

“Submit detail drawings for sheet piling, including fabricated sections, showing complete piling dimensions and details, driving sequence and location of installed piling.”

REPLACE WITH:

“Submit detail drawings for sheet piling, including fabricated sections, showing complete piling dimensions and details, driving sequence and location of installed piling. Submit details of temporary grading or shoring as required for pile installation and proper alignment. Work shall adhere to the construction considerations provided in the Geotechnical Report.”

3.

Section 31 14 16 – 3.3.1.2.a INSERT at end:

“Temporary grading or shoring as required for maintaining proper alignment shall adhere to the construction considerations provided in the Geotechnical Report.”

4.

Section 31 14 16 – 3.3.1.2.c

REMOVE:

“Take adequate precautions to ensure that pilings are driven plumb. Where possible, drive Z-pile with the ball end leading. If an open socket is leading, a bolt or similar object placed in the bottom of the interlock will minimize packing material into it and ease driving for the next sheet. If at any time the forward or leading edge of the piling wall is found to be out-of-plumb in the plane of the wall the piling being driven must be driven to the required depth and tapered pilings must be provided and driven to interlock with the out-of-plumb leading edge or other approved corrective measures must be taken to insure the plumbness of succeeding pilings. The maximum permissible taper for any tapered piling must be 1/8 inch per foot of length.”

REPLACE WITH:

“Take adequate precautions to ensure that pilings are driven plumb. Where possible, drive Z-pile with the ball end leading. If an open socket is leading, a bolt or similar object placed in the bottom of the interlock will minimize packing material into it and ease driving for the next sheet. If at any time the forward or leading edge of the piling wall is found to be out-of-plumb in the plane of the wall, submit corrective measures to restore the plumbness of succeeding pilings to the Engineer for review and approval. Tapered pilings, if used, must interlock with the leading edge of the out-of-plumb pile for the full driving depth. The maximum permissible taper for any tapered piling must be 1/8 inch per foot of length.”

5.

Section 31 14 16 – 3.3.1.2.e

REMOVE:

“Driving assistance using augering will be permitted as approved in the submittal process.”

REPLACE WITH:

“Driving assistance using simultaneous augering will be permitted as approved in the submittal process. The continuous flight auger attachment shall be used to penetrate ahead of the sheet piles while pressing in the sheet piles at the same time. The size of the auger shall be in accordance with equipment specifications as required to assist in pile installation and minimize the disturbance to the soil strata. Care shall be taken not to remove the soil.”

6.

Section 31 14 16 – 3.3.2

REMOVE:

“Provide pile splicing information and details for Government review and approval prior to installation in the field.”

REPLACE WITH:

“Contractor to submit splice details to the Engineer for review and approval prior to installation in the field. Contractor's design for splice to be signed and sealed by a licensed structural engineer.”

7.

Section 31 14 16 – 3.3.2.b

REMOVE:

“Cut holes in pilings for bolts, rods, drains or utilities in a neat and workmanlike manner, as shown or as directed.”

REPLACE:

“Cut holes in pilings for bolts, rods, drains or utilities as shown or as directed and meet the requirements for workmanship in accordance with Section 05 12 00 Structural Steel.”

8.

Section 31 14 16 – 3.8

REMOVE:

“Prepare a geotechnical instrumentation program to monitor settlement and lateral movement of all permanent structures, utilities, and bluff slope during pile driving. The design and distribution of instrumentation must demonstrate an understanding of the need, purpose and application of each proposed type.

Provide two monitoring point locations per building and two monitoring points at the stone/concrete retaining wall and storm facility. The monitoring points shall be on opposite sides of the building, with one point landside and one point riverside to assess any differential. The Contractor shall submit the proposed monitoring locations to the Engineer for approval.”

REPLACE WITH:

“Prepare a geotechnical instrumentation program to monitor settlement and lateral movement of all permanent structures, utilities, and bluff slope during pile driving. The design and distribution of instrumentation must demonstrate an understanding of the need, purpose and application of each proposed type. At a minimum, provide two monitoring point locations per building, two monitoring points at the stone/concrete retaining wall and storm facility, and three monitoring points along the north and south property lines west of Coast Guard Road. The monitoring points on the buildings shall be placed on opposite sides of the building, with one point landside and one point riverside to assess any differential. The Contractor shall submit the proposed monitoring locations to the Engineer for approval.”

9.

Section 31 14 16 – 3.9

REMOVE:

“The Contractor shall employ the services of a qualified vibration monitoring consultant. Monitoring point locations and frequency of data collection shall be as determined by the Contractor's Consultant and are subject to the approval of the Engineer. Vibration monitoring shall be a continuous and uninterrupted process and must be in place prior to the start of any construction activity. All vibration monitors for the project shall be programmed to actuate an alarm when the Threshold Value or Limiting Value is reached. The alarm notification protocol shall consist of the immediate notification of the Engineer (or his/her authorized representative) and the Contractor.”

REPLACE WITH:

“The Contractor shall employ the services of a qualified vibration monitoring consultant. Monitoring point locations and frequency of data collection shall be as determined by the Contractor's Consultant, at a minimum shall include three monitoring points along the north and south property lines west of Coast Guard Road, and are subject to the approval of the Engineer. Vibration monitoring shall be a continuous and uninterrupted process and must be in place prior to the start of any construction activity. All vibration monitors for the project shall be programmed to actuate an alarm when the Threshold Value or Limiting Value is reached. The alarm notification protocol shall consist of the immediate notification of the Engineer (or his/her authorized representative) and the Contractor.”

10.

Section 01 57 19, Page 16, INSERT:

“3.13 VIBRATION MONITORING

Provide vibration monitoring throughout entire construction duration. See 31 14 16 - 3.9 VIBRATION MONITORING for specific requirements.”

11.

Section 31 14 16 - 1.5.2

REMOVE:

“Lift piles to ensure that the maximum permissible curvature is not exceeded.

Holes may be burned above the cutoff length for lifting piles into the leads. If there is evidence of pile damage during driving due to the holes, Contracting Officer may forbid the burning of holes. Do not damage piles when dragging piles across the ground or barge deck.”

REPLACE WITH:

“Lift piles to ensure that the maximum permissible curvature is not exceeded.

No holes may be burned above the cutoff length for lifting piles into the leads.

Do not damage piles when dragging piles across the ground or barge deck.”

12.

Section 01 14 00, page 1 INSERT at end:

“1.1.1.1 IN - WATER WORK WINDOW

The in-water work window is NOVEMBER 1ST current year to FEBRUARY 15TH following year. Sheet piles and tie backs are to be installed above Highest Measured Tide (HMT) and are not considered in-water work."

13.

Section 01 14 00, page 1

1.1.4 REMOVE:

"The Government will remove and relocate Government property in the areas of the site areas, bridgeway, and floating dock scheduled to receive work, prior to Contractor work in the respective areas."

1.1.4 INSERT:

"The Government will remove portable equipment in the site area as needed for the contractor to complete their work. The Contractor is responsible for all utilities running under the bridgeway to the waterfront area. The utilities may be down for the same 3-week period the bridgeway is allowed to be inaccessible. If the Contractor needs more than 3 weeks to disrupt bridgeway access and utilities to floating docks/covered mooring then temporary utilities will be re-established at the end of the 3 weeks until the utilities can be returned to their original condition"

14.

Drawing Sheet CD100:

REMOVE:

Key Notes 15, 19, and 20

INSERT:

"New" Key Note 15: Contractor is responsible for maintaining all utilities down to the floating dock/covered mooring during work. Utilities may be disrupted for the same 3 weeks as the bridgeway disruption. At the end of the three-week disruptions utilities must be reestablished.

15.

Section 01 50 00

1.11 REMOVE:

"Any one continuous period of no access to either the covered moorings, the exterior float, or both, must be less than one week in duration and must be arranged with and approved by the COR or their representative with no less than 30 calendar days’ notice prior to the beginning of that loss of access."

1.11 INSERT:

“Access to the Covered Mooring and Floating dock may be restricted for a maximum of 3 consecutive weeks. If contract work requires the access to the mooring to be restricted longer than 3 weeks, the Contractor will provide alternate access as well as restore all utility services to the Covered Mooring/Floating dock structure.”

16.

Section 01 30 00 para 1.7.5

"Design-Build"

17.

Section 05 05 23.16, article 1.4.1, page 3:

“Fabricate work in an AISC Certified Fabrication Plant, Category BU. Erect work by an AISC Certified Erector, Category CSE.”

C. ANSWERS TO OFFEROR QUESTIONS:

PPI 013

A separate file labeled “USCG Siuslaw Drawings 100% Wall Plan” is included in the solicitation. This appears to be the same files that are already included under the file “USCG Siuslaw FINAL Drawings 2024.04.16”. Please advise if the “Wall Plan” file has any differences from the drawings in the “FINAL Drawings” file, and which set of S-001 – S-102 drawings should be utilized. Please advise if “USCG Siuslaw Drawings 100% Wall Plan” should be disregarded.

Answer: The "USCG Siuslaw Drawings 100% wall Plan" was sent out by mistake, disregard that file that includes 4 dwg sheets.

The drawings labeled "USCG Siuslaw FINAL Dwgs 2024.04" include the correct version of the wall plans and should be followed.

PPI 019

Specification Section 01 14 00 – “Work Restrictions” does not clearly identify any working constraints regarding the in-water work. We see no time constraints for our construction in dealing with environmental windows, such as fish window limitation. Will there be any for this project and if so, where are we to find this information in the specifications?

Answer:

In Section 01 14 00, page 1 INSERT at end:

“1.1.1.1 IN - WATER WORK WINDOW

The in-water work window is NOVEMBER 1ST current year to FEBRUARY 15TH following year. Sheet piles and tie backs are to be installed above Highest Measured Tide (HMT) and are not considered in-water work."

PPI 020

Specification Section 01 14 00 1.1.4 – “Occupied and Existing Buildings” includes a statement that describes the effort to remove and relocate government property in areas of the “site areas, bridgeway, and floating dock.” Regarding the “site areas,” what items are being relocated by USCG? Does this include work per Notes 16 and 17 on CD100? What else?

Answer: USCG will move portable equipment/gear in the site area, the contractor is responsible for what is required on Sheet CD100 Key Notes 14, 16 and 17. see revised spec sections, and revised Key Notes

In Section 01 14 00, page 1

1.1.4 REMOVE: "The Government will remove and relocate Government property in the areas of the site areas, bridgeway, and floating dock scheduled to receive work, prior to Contractor work in the respective areas."

1.1.4 INSERT: "The Government will remove portable equipment in the site area as needed for the contractor to complete their work. The Contractor is responsible for all utilities running under the bridgeway to the waterfront area. The utilities may be down for the same 3-week period the bridgeway is allowed to be inaccessible. If Contractor need more than 3 week to disrupt bridgeway access and utilities to floating docks/covered mooring then temporary utilities will be re-established at the end of the 3 weeks until the utilities can be returned to their original condition"

Drawing Sheet CD100:

REMOVE: Key Notes 15, 19, and 20 INSERT: "New" Key Note 15: Contractor is responsible for maintaining all utilities down to the floating dock/covered mooring during work. Utilities may be disrupted for the same 3 weeks as the bridgeway disruption. At the end of the three-week disruptions utilities must be reestablished.

PPI 032

REFERENCE: Section 01 50 00, Paragraph 1.11 QUESTION: Section 01 50 00, Paragraph 1.11 Government access to the Covered Moorage and floating dock can only be restricted for a continuous period of no longer than 1 week. Would the Coast Guard consider extending this duration? The potential complete temporary removal of the Access Bridge and Pile for Crane Barge and Drilling equipment access on site would require a longer duration to complete the Erosion Wall. Please advise if temporary moorage of the Vessels is available elsewhere and if access can be restricted for several months to the covered moorage.

Answer:

In Section 01 50 00

1.11 REMOVE: "Any one continuous period of no access to either the covered moorings, the exterior float, or both, must be less than one week in duration and must be arranged with and approved by the COR or their representative with no less than 30 calendar days’ notice prior to the beginning of that loss of access."

1.11 INSERT:

“Access to the Covered Mooring and Floating dock may be restricted for a maximum of 3 consecutive weeks. If contract work requires the access to the mooring to be restricted longer than 3 weeks, the Contractor will provide alternate access as well as restore all utility services to the Covered Mooring/Floating dock structure.”

PPI 040

REFERENCE: Section 01 30 00, Paragraph 1.7.5 and Section 01 45 00, Paragraph 1.4.2.1 QUESTION: There are requirements for the Quality Assurance Manager in Spec Section 01 30 00 para

1.7.5 that indicate this person cannot also be the Superintendent or Project Manager, and that they must have at least 3 similar design-build project experiences. As this project is Design-Bid-Build, is the requirement to have similar design-build experience still necessary? Note that Spec Section 01 45 00 para 1.4.2.1 contains similar restriction on the Quality Program Manager not being the Project Manager or Superintendent.

Answer: QAM, PM, Superintended should have project experience of at least 3 similar project regardless of contract delivery vehicle. QPM may not be the same person as PM or Superintendent, however may be a shared responsibility as the SSHO.

Section 01 30 00 para 1.7.5 Remove: "Design-Build"

PPI 044

In-water work window is not specified in contract documents. Without permitting information, offerors cannot properly plan the schedule for the project. Please advise on the following:

a. In-water work window timeframe

b. Work to be considered “in-water” – specifically, is sheet pile work considered “in-water”? Are tie-backs considered “in-water”?

Answer: Reference PPI #19. See previous response.

PPI 046

Spec: 01 30 00 1.7.5: 1.7.5 Quality Assurance Manager (QAM) refers to experience with 3 design-build projects, however, this project is not design build. Please remove the design-build reference from the QAM requirements.

Answer: See PPI Response 40. Experience will be from similar project regardless of contract delivery vehicle.

PPI 074

REFERENCE: Section 05 05 23.16, page 3 Specs in 05 05 23.16 pg 3 call for an AISC Certified Shop – Category BU (Building Fabricator) and we are an AISC Certified Bridge Fabricator – Simple Bridge. It also calls for an AISC Certified Erect.

Please advise if an AISC Certified Shop is Required. If so, would a Simple Bridge Cert be acceptable?

Answer: Use of an AISC certified shop will not be required.

Use of an AISC certified erector will not be required.

In section 05 05 23.16, article 1.4.1, page 3:

REMOVE:

“Fabricate work in an AISC Certified Fabrication Plant, Category BU. Erect work by an AISC Certified Erector, Category CSE.”

PPI 084

Although the period for RFI’s has closed, we are requesting to be permitted to submit a question regarding the metal sheet piling (Spec Section 31 41 16; Drawing Sheets S-101, S-102, S-401).

There is only one source for the NZ28 steel sheet piling shown in the contract drawings. Please see attached a data sheet showing the PZC28 grade 60 steel sheet piling being submitted for consideration as a substitution. Please confirm that this pile and interlock style will be an acceptable approved equal for the project.

Answer: The proposed sheet piling is an acceptable substitution to what was specified on the plans.

All other terms and conditions remain unchanged. The Proposal due date IS NOT EXTENDED.