This is a CLIN Pricing Proposal Excel sheet for contract 70FBR226R00000016, detailing pricing for facility improvement work at Naval Weapons Station Earle (NWSE) Building C-54.
The pricing template encompasses six primary contract line item numbers (CLINs) broken into material and labor cost sub-CLINs: (1) Front and side external door replacement (4 units), (2) Internal door replacement (9 units), (3) RRCC facility upgrade (1 lot), (4) Exterior concrete repairs and sidewalk expansion work (1 lot), (5) Training room wall reinforcement and finish restoration (1 lot), and (6) Project bonding at 3% of total project cost (1 lot). The sheet provides columns for CLIN numbers, buyer descriptions referencing specific Statement of Work sections (3.1 through 3.4), quantities, units of measure (EA or LOT), vendor pricing fields, unit prices, and total prices. All pricing fields remain blank in this template version, showing only one completed entry of $4.00 total price for CLIN 0001A (material costs for external door replacement at $1.00 per EA × 4 EA). The template is structured to facilitate vendor cost proposals for the base period work at this naval facility.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment P: CLIN Pricing Proposal Excel Sheet 70FBR226R00000016_0001
CLIN Buyer Description Quantity Unit Vendor Unit Price Total Price
Naval Weapons Station Earle (NWSE) Building C-54 Door Replacement (Front and Side - External) in accordance with the Statement of Work (SOW). Refer to Section 3.1 of the SOW
0001A NWSE Building C-54 Door Replacement (Front and Side - External) Material Costs
4 EA $ 1.00 $ 4.00
0001B NWSE Building C-54 Door Replacement (Front and Side - External) Labor Costs
4 EA $ -
Naval Weapons Station Earle (NWSE) Building C- 54 Door Replacement (Internal doors) in accordance with the Statement of Work (SOW).
Refer to Section 3.1 of the SOW.
0002A NWSE Building C-54 Door Replacement (Internal doors) Material Costs
9 EA $ -
0002B NWSE Building C-54 Door Replacement (Internal doors) Labor Costs
9 EA $ -
Naval Weapons Station Earle (NWSE) Building C- 54 RRCC Facility Upgrade in accordance with the Statement of Work (SOW). Refer to Section 3.2 of the SOW.
0003A NWSE Building C-54 RRCC Facility Upgrade Material Costs
1 LOT $ -
0003B NWSE Building C-54 RRCC Facility Upgrade Labor Costs
1 LOT $ -
Naval Weapons Station Earle (NWSE) Building C- 54 Exterior Concrete Repairs and Sidewalk Expansion Work in accordance with the Statement of Work (SOW). Refer to Section 3.3 of the SOW.
0004A NWSE Building C-54 Exterior Concrete Repairs and Sidewalk Expansion Work Material Costs
1 LOT $ -
0004B NWSE Building C-54Exterior Concrete Repairs and Sidewalk Expansion Work Labor Costs
1 LOT $ -
Naval Weapons Station Earle (NWSE) Building C- 54 Training Room Wall Reinforcement and Finish Restoration in accordance with the Statement of Work (SOW). Refer to Section 3.4 of the SOW.
0005A NWSE Building C-54 Training Room Wall Reinforcement and Finish Restoration Material Costs
1 LOT $ -
Line Item(s) Base Period
0005B NWSE Building C-54 Training Room Wall Reinforcement and Finish Restoration Labor Costs
1 LOT $ -
0006 Bonding - 3% of total cost of the project 1 LOT $ -
Total Cost $ -