2.2.1(c) Attachment C-Specs for Doors for Earle_07.28.26_OR.pdf
PDF 1 MB Posted
- Solicitation number
- 70FBR226R00000016
- Issued by
-
Federal Emergency Management Agency
About this file
This document is a Specifications for Exterior Door Replacement, dated July 28, 2026, issued by the U.S. Department of Homeland Security/FEMA Region II for work at Naval Weapons Station Earle in Colts Neck, New Jersey.
The requirement involves providing and installing double-acting automated access doors at the front and side entrances of Building C-54 to maintain a safe FEMA workspace environment. The front door dimensions are 9'11" X 7'11" and the side door dimensions are 6'3" X 7'11". All doors must feature aluminum framed construction with anodized bronze satin finish and dark desiccant strips. Specific performance requirements include wind load resistance per ASCE/SEI 7, thermal movement accommodation for 67 degrees Celsius, windborne debris impact resistance per ASTM E1886, condensation resistance, water resistance, and air infiltration resistance standards. Materials must comply with ASTM specifications for aluminum sheet metal and extrusions with minimum thickness requirements. Doors must include thermally broken stiles and rails, removable weather stripping, and welded or interlocked dovetail joints. A 20-year manufacturer's warranty against material and manufacturing defects is required.
Bidders must conduct a mandatory site visit to examine existing conditions and submit proposals not exceeding ten pages with drawings and product data for approval prior to purchase. The pre-installation meeting must occur minimum 30 days before work begins with required participants including the Contracting Officer's Representative, contractor, and installer. Installation tolerances are tightly specified (maximum 3mm variation in 3m for plumb/level). All contractors must comply with Wage Determination Davis Bacon No. NJ20260037 Mod 1 for Monmouth County, New Jersey. Personnel entering the naval base must be U.S. citizens with valid driver's licenses and vehicle registration; all vehicles undergo inspection by base security. Evaluation criteria are listed in descending order of importance: Technical Specifications (Factor 1), Past Performance (Factor 2), and Price (Factor 3), with non-price factors combined being slightly more important than price. Questions must be submitted by September 8, 2026 at 10:00 am ET, and responses are due by September 11, 2026 at 11:00 am ET.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Homeland Security/ FEMA Region II
1 World Trade Center, 52nd Floor New York, New York 10007.
Specifications for Exterior Door Replacement
Dated: July 28, 2026
1. Introduction
This requirement is to provide and install double acting automated access doors at both the front and side of the building to accommodate and maintain a safe FEMA workspace environment for staff to Building C-54 at Naval Weapons Station EARLE, in Colts Neck, NJ.
2. Instructions to bidders
A. Bidders are requested to submit an estimate for work as described in the “Statement of
Work” (SOW). The estimate shall include the cost of all labor, materials, equipment rentals, etc.
B. A mandatory site visit will be conducted. Contractors will provide a list of attendees, prior to site visit. Contractors are required to bring Identification to the site visit and are subject to vehicle inspection prior to being granted access to the base.
C. Before submitting a proposal, maximum of ten (10 pages), and drawings, the bidders shall carefully examine and visit the site at NWS Earle Colts Neck, NJ and check existing conditions during the site visit. The bidders will utilize the Earle Floor Plan (PDF document supplied by FEMA) as a tool in locating entrances in question. The Earle
Floor Plan identifies the approximate location of all spaces. Should the bidders find discrepancies in / or omissions from the scope of work listed below, bidder shall notify the Contracting Officer, who will send written instruction to all bidders regarding this discrepancy or omission.
D. The contractor is to submit product data and finish samples for approval prior to application or purchase.
E. Location
The work is located at: Naval Weapons Station Earle
201 New Jersey Route 34, Bldg. C-54, Colts Neck, NJ 07722
70FBR226R00000016 Page 55 of 77
Please Note: Security Information for NWS Earle:
Naval Weapons Station Earle’s security performs a background check on all personnel entering the Naval Base. Driver’s must be U.S. citizens and are required to present a valid driver’s license, vehicle registration, and proof of insurance. All vehicles, exterior and interior, will be thoroughly inspected by base security.
F. All bidders shall use the Wage Determination Davis Bacon No. NJ20260037 Mod 1 dated 05/18/2026 for Monmouth County, NJ. The McNamara-O’Hara Service Contract Act requires contractors and subcontractors performing services on prime contracts in excess of $2,500 to pay service employees in various classes no less than the wage rates and fringe benefits found prevailing in the locality, or the rates (including prospective increases) contained in a predecessor contractor's collective bargaining agreement. The Department of
Labor issues wage determinations on a contract-by-contract basis in response to specific requests from contracting agencies. These determinations are incorporated into the contract.
3. Related Specifications
A. Aluminum framed entrances
B. Door Dimensions
a. Front Door (photo A.) – 9’11” X 7’11”
b. Side Door (photo B.) – 6’3” X 7’11”
Photo A. Photo B.
70FBR226R00000016 Page 56 of 77
4. Related Requirements
A. Door Finish and Color: Section 09 06 00, Anodized Bronze Satin Finnish with dark desiccant strips.
B. Glass and Glazing: Section 08 80 00, GLAZING
C. Hardware: Section 08 71 00, DOOR HARDWARE.
D. Automatic Door Actuators: Section 08 71 13, AUTOMATIC DOOR OPERATORS.
E. Aluminum Finish and Color: Section 09 06 00, SCHEDULE FOR FINISHES.
5. Pre-installation Meetings
A. Conduct pre-installation meeting at project site, minimum 30 days before beginning
Work of this section.
a. Required Participants:
i. Contracting Officer's Representative (COR)
ii. Contractor
iii. Installer
b. Meeting Agenda: Distribute agenda to participants minimum 3 days before meeting.
i. Installation schedule
ii. Installation sequence
iii. Preparatory work
iv. Protection before, during, and after installation
v. Installation
vi. Terminations
vii. Transitions and connections to other work
viii. Other items affecting successful completion.
c. Document and distribute meeting minutes to participants to record decisions affecting installation
6. Submittals
A. Submittal Drawings: Minimum of 1 to 2 (half size) scale
a. Show size, configuration, fabrication and installation
b. Show anchorage and reinforcement
c. Show interface and relationship to adjacent work, including thermal, air and water barrier continuity
B. Manufacturer’s Literature and Data
a. Description of each product
b. Door, each type
c. Entrance and Storefront Construction
d. Installation instructions
70FBR226R00000016 Page 57 of 77
e. Warranty
C. Samples
a. Door Corner Section: Minimum 450mm X 450mm (18” x 18”) for each specified door type showing head rail and hinge stile Aluminum Anodized
b. Finish with sample extrusions minimum of 150mm (6”) long for each specified color in sets of three showing maximum color range.
7. Quality Assurance
A. Manufacturer Qualifications
a. Regularly manufactures specified products
B. Installer Qualifications
a. Regularly installs specified products
b. Installed specified products with satisfactory service on a minimum of five (5) similar installations over the course of the last five (5) years.
c. Project experience list – Provide contact names and addresses for completed projects
C. Welders and Welding Procedures Qualifications: AWS D1.2/D1.2M
8. Delivery, Storage and Handling
A. Deliver Products in manufacturer’s original sealed packaging
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, color, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.
D. Store products indoors in dry, weather tight facility
E. Protect products from damage during handling and construction operations
9. Warranty
A. Construction warranty, FAR Clause 52.246-21 – Warranty of construction
B. Manufacturer's Warranty: Warrant painted finish against material and manufacturing defects
a. Warranty period: 20 years
10. Products
A. System performance
a. Delegated design: Prepare submittal documents including design calculations and drawings signed and sealed by registered design professional, licensed in New
Jersey.
i. Minor deviations to details shown on drawings to accommodate manufacturer’s standard products may be accepted by Contracting
70FBR226R00000016 Page 58 of 77
Officer's Representative when deviations do not affect design concept and specified performance.
b. Design aluminum framed entrances and storefronts complying with specified performance:
i. Wind Load Resistance: ASCE/SEI 7; Design criteria as indicated on
Drawings when tested according to ASTM E330/E330M.
1. Maximum Deflection: 1/175 of span, maximum with minimum 1.65 safety factor.
ii. Thermal Movement: Accommodate ambient temperature range of 67 degrees C (120 degrees F).
iii. Windborne Debris Impact Resistance: Pass ASTM E1886.
1. Openings within 9144 mm (30 feet) of Grade: ASTM E1996 large missile test.
2. Other Openings: ASTM 1996 small missile test.
iv. Condensation Resistance: NFRC 500.
1. Fixed Framing: 45 CRF, minimum.
v. Water Resistance: ASTM E331; No uncontrolled penetration at380 Pa (8 psf), minimum, pressure differential.
vi. Fixed Framing Air Infiltration Resistance: ASTM E283; 0.30 L/s/sq. m
(0.06 cfm/sf), maximum at 300 Pa (6.24 psf), minimum, pressure differential.
vii. Entrance Doors Air Infiltration Resistance: ASTM E283; maximum allowable at 75 Pa (1.57 psf), minimum, pressure differential.
1. Single Doors: 2.5 L/s/sq. m (0.5 cfm/sf).
2. Paired Doors: 6 L/s/sq. m (1.2 cfm/sf).
B. Materials
a. Aluminum:
i. Sheet Metal: ASTM B209M (ASTM B209), minimum 1.6 mm (0.063 inch) thick.
ii. Extrusions: ASTM B221M (ASTM B221).
1. Framing: Minimum 3 mm (0.125 inch) wall thickness.
2. Glazing Beads, Moldings, and Trim: Minimum 1.25 mm (0.050 inch) thick.
70FBR226R00000016 Page 59 of 77
iii. Color Anodized Aluminum: Provide aluminum alloy required to produce specified color.
b. Stainless Steel: ASTM A240/A240M; Type 302 or Type 304.
c. Thermal Break: Manufacturer standard low conductive material retarding heat flow in the framework, where insulating glass is scheduled.
C. Products – General
a. Provide aluminum framed entrances from one manufacturer.
b. Provide aluminum entrances, systems from same manufacturer.
D. Frames
a. Framing Members: Extruded aluminum, thermally broken.
b. Stops: Provide integral fixed stops and glass rebates and snap-on removable stops.
c. Provide concealed screws, bolts and other fasteners.
d. Secure cover boxes to frames behind lock strike cutouts.
E. Stile and Rail Doors
a. Stiles and Rails: Extruded aluminum, thermally broken.
i. Thickness: 45 mm (1 3/4 inch).
ii. Stiles and Head Rails: 101.6 mm (3 1/2 inches) wide.
iii. Bottom Rails: 152.4 mm (10 inches) wide.
b. Single-Acting Doors:
i. Bevel: 3 mm (1/8 inch) at lock, hinge, and meeting stile edges.
ii. Clearances: 2 mm (1/16 inch) at hinge stiles, 3 mm (1/8 inch) at lock stiles and top rails, and 5 mm (3/16 inch) at floors and thresholds.
c. Glass Rebates: Integral with stiles and rails.
d. Glazing Beads: Extruded aluminum, 1.3 mm (0.050 inch) thick. Integral with stiles and rails or applied type, snap fit secured.
e. Stile and Rail Joints: Welded or interlocked dovetail joints between stiles and rails.
i. Clamp door together through top and bottom rails with 9 mm (3/8 inch) primed steel tie rod extending into stiles and having self-locking nut and washer at both ends.
ii. Reinforce stiles and rails to prevent door distortion when tie rods are tightened.
iii. Provide compensating spring type washer under each nut for stress relief.
iv. Construct joints to remain rigid and tight when door is operated.
f. Weather stripping: Removable, woven pile type (silicone treated) weather stripping
70FBR226R00000016 Page 60 of 77 attached to aluminum or vinyl holder.
i. Make slots for applying weather stripping integral with doors and door frame stops.
ii. Apply continuous weather stripping to heads, jambs, bottom, and meeting stiles of doors and frames so doors swing freely and close positively.
F. Fabrication
a. Form metal parts and fit and assemble joints, except joints designed to accommodate movement. Seal joints to resist air infiltration and water penetration.
b. Factory assemble doors.
G. Finishes
a. Aluminum Anodized Finish: NAAMM AMP 500.
i. Color Anodized Finish: AA C22A42 or AA C22A44; Class I Architectural,
0.018 mm (0.7 mil) thick.
b. Aluminum Paint finish:
i. Baked Enamel or Powder Coat: AAMA 2603; polyester resin, minimum 0.4 mm (1.5 mil) film thickness.
H. Accessories
a. Barrier Coating: ASTM D1187/D1187M.
b. Fasteners:
i. Aluminum: ASTM F468, Alloy 2024.
ii. Stainless Steel: ASTM F593, Alloy Groups 1, 2 and 3.
c. Anchors: Aluminum or stainless steel; type to suit application.
d. Galvanizing Repair Paint: MPI No. 18.
e. Touch Up Paint: Match shop finish.
11. Execution
A. Preparation
a. Examine and verify substrate suitability for product installation.
i. Coordinate floor closer installation recessed into concrete slabs.
ii. Coordinate anchor installation built into masonry and concrete.
70FBR226R00000016 Page 61 of 77
b. Protect existing construction and completed work from damage.
c. Clean substrates. Remove contaminants capable of affecting subsequently installed product's performance.
d. Apply barrier coating to aluminum surfaces in contact with dissimilar metals.
B. Installation – General
a. Install products according to manufacturer's instructions
i. When manufacturer's instructions deviate from specifications, submit proposed resolution for Contracting Officer's Representative consideration.
b. Install aluminum framed entrances and storefronts plumb and true, in alignment and to lines shown on drawings.
c. Anchor frames to adjoining construction at heads, jambs and sills.
d. Provide concealed aluminum clips to connect adjoining frame sections.
e. Install door hardware and hang doors.
f. Adjust doors and hardware uniform clearances and proper operation.
g. Touch up damaged factory finishes.
i. Repair galvanized surfaces with galvanized repair paint.
ii. Repair painted surfaces with touch up primer.
h. Tolerances:
i. Variation from Plumb, Level, Warp, and Bow: Maximum 3 mm in 3 m (1/8 inch in 10 feet).
ii. Variation from Plane: Maximum3 mm in 3.65 m (1/8 inch in 12 feet); 6 mm
(1/4 inch) over total length.
iii. Variation from Alignment: Maximum 1.5 mm (1/16 inch) in line offset and maximum 3 mm (1/8 inch) corner offset.
iv. Variation from Square: Maximum 3 mm (1/8 inch) diagonal measurement differential.
C. Protection, Cleaning and repairing
a. Clean exposed aluminum and glass surfaces. Remove contaminants and stains.
b. Protect aluminum framed entrances and storefronts from construction operations.
c. Remove protective materials immediately before acceptance.
d. Repair damage
70FBR226R00000016 Page 62 of 77
Evaluation Factors
Requirement: Consolidated Requirement (RRCC Refresh, Roof, Doors and Concrete)
The Government will award a firm fixed-price contract resulting from this solicitation to the Offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. This procurement is being conducted in accordance with the procedures of Federal Acquisition Regulation (FAR) Part 12.203, Evaluation of Acquisition of Commercial Products and Commercial Services The acquisition will be a best value contract. Offerors are cautioned that award(s) may not necessarily be made to the lowest priced proposal.
Price should always be fair, reasonable, and realistic. Technical/price tradeoff where other evaluation factors, when combined, cost/price may become a critical factor if two or more offerors are determined to be essentially equal following the evaluation of all factors other than cost or price.
The Government will evaluate proposal submissions based on the following evaluation factors, listed in descending order of importance:
Factor 1 – Technical Specifications
Factor 2 – Past Performance
Factor 3 – Price
All non-price factors, when combined, are slightly more important than price.
Factor 1: Technical Specifications
Offerors will be evaluated on their ability to demonstrate technical sufficiency in their proposed technical and management approach to perform and support the requirements of the Statement of Work (SOW). This section of the offeror’s proposal shall address information regarding how the proposal logistical support task areas will be performed, the various resources that will be used to facilitate performance, and an identification of potential difficulties in conducting the work with practical suggestions for overcoming these difficulties.
Offerors will be evaluated on their ability to develop a work plan in response to the SOW. Offerors must demonstrate an understanding of ALL OF THE FOLLOWING:
• Scope of technical requirements
• Complexity of technical requirements
• Performance requirements & objectives
• Pertinent work tasks & deliverables
70FBR226R00000016 Page 65 of 77
Factor 2: Past Performance
Provide past performance information for services directly related and relevant to the services to be performed under the SOW. To be considered relevant, the services must have been performed within the past five years. Include three references consisting of ALL OF THE FOLLOWING:
- Project title/description
- Role (Prime/Subcontractor)
- Contract number
- Dollar value & contract type
- Period of performance
- Agency or company for which the work was performed
- Summary of the work products/services
- Name/contact information of client point of contact
FEMA reserves the right to utilize past performance information other than the information submitted with the quotations received in conducting the evaluation. This may be a favorable CPARS rating.
However, if these are utilized and a Vendor does not have any ratings since they have not done business with the government, they will receive a neutral rating in the evaluation later that cannot be used against them.
RATING FOR PAST
PERFORMANCE
DESCRIPTION
Superior Based on an offeror’s past performance record, no doubt exists that the offeror will successfully perform the required effort.
Satisfactory Based on an offeror’s past performance record, it is likely that the offeror will successfully perform the required effort.
Unsatisfactory Based on an offeror’s past performance record, it is not likely that the offeror will successfully perform the required effort.
Neutral No relevant performance record is identifiable upon which to base a meaningful performance rating. This is neither a negative nor positive assessment.
RATING DESCRIPTION
Superior Exceeds requirements; outstanding approach and understanding.
Satisfactory Meets requirements; strengths and weaknesses are balanced.
Unsatisfactory Fails to meet requirements; significant weaknesses or deficiencies.
70FBR226R00000016 Page 66 of 77
Factor 3: Price
The price proposal will be evaluated for price reasonableness through comparison with other proposed prices and may include other price analysis techniques.
The price proposal will not be given a confidence rating, but unit prices and discounts will be evaluated to ensure prices are fair and reasonable.
-SPACE BELOW INTENTIONALLY LEFT BLANK-
Questions regarding this Request for Proposal (RFP) shall be directed via email to brenda.cruzrodriguez@fema.dhs.gov and a copy to brendaliz.pinero@fema.dhs.gov. Telephone inquiries will not be honored. All questions must be received no later than Tuesday, September 8, 2026, at 10:00 am ET.
Responses regarding this RFP shall be directed via email to brenda.cruzrodriguez@fema.dhs.gov and a copy to brendaliz.pinero@fema.dhs.gov.
All responses must be received no later than Friday, September 11, 2026, at 11:00 am ET.
70FBR226R00000016 Page 67 of 77 mailto:brenda.cruzrodriguez@fema.dhs.gov mailto:brendaliz.pinero@fema.dhs.gov mailto:brenda.cruzrodriguez@fema.dhs.gov mailto:brendaliz.pinero@fema.dhs.gov
| 2.2.1(d) Attachment D-Notice to Offerors-Statement of Contractor Assurance.pdf |
| U.S. Department of Homeland Security |
| 500 C Street, SW |
| Washington DC 20472 |
| 2.2.1(g) Attachment G-CLIN Pricing Excel Sheet.pdf |
| Pricing Proposal |
| 1.1.3 SOW_CONSOLIDATED - Roof Doors RRCC and Concrete_ v5_08.19.2026 Security Edits.pdf |
| STATEMENT OF WORK FOR: |
| Comprehensive Facility Upgrades for Building C-54, Naval Weapons Station, Earle |
| Statement of Work (SOW) for Comprehensive Facility |
| Upgrades for Building C-54, Naval Weapon Station Earle |
| 1. Purpose |
| The purpose of this project is to provide comprehensive facility upgrades to Building C-54 at Naval Weapons Station Earle (NWSE). The scope includes: |
| 1) Installation and upgrade of automated, ADA-compliant access doors at exterior entry points (please see attachment A for more details), as well as installation of nine (9) wood doors with glazed windows for conference rooms and offices within the fa... |
| 2) Repair, restoration, and waterproofing of the office building roof. |
| 3) Renovation and modernization of the Regional Response Coordination Center (RRCC), including flooring, walls, electrical and communication infrastructure. |
| 4) Repair, patching, and expansion of exterior cement surfaces, including the loading dock, sidewalks, and patio area, to improve safety, accessibility, and support future facility enhancements. |
| These upgrades will enhance safety, accessibility, operational reliability, and compliance with all applicable standards to support FEMA’s mission requirements. |
| 2. Background |
| 3. Scope of Work (Summary) |
| Please also refer to Attachment A Specs for doors and Attachment B A100 Floor plan for details. |
| Background Investigations: |
| Low Risk without Information System Access: |
| Low Risk with Information System Access: |
| Moderate Risk: |
| High Risk: |
| Background Investigation Process: |
| Continued Eligibility and Reinvestigation: |
| Exclusion by Contracting Officer: |
| OPSEC Training: |
| Insider Threat Training: |
| 2.2.1 Solicitation 70FBR226R00000016.pdf |
| Solicitation/Contract/Order for commercial products and commercial services |
| Requisition number |
| Contract number |
| Award/Effective date |
| Order number |
| Solicitation number |
| Solicitation issue date |
| For solicitation information call: |
| Name |
| Telephone number |
| Offer due date/local time |
| Issued by |
| Code |
| This acquisition is |
| NAICS |
| Size standard |
| Delivery for free on board (FOB) destination unless block is marked |
| Discount terms |
| This contract is a rated order under the defense priorities and allocations system - DPAS |
| Rating |
| Method of solicitation |
| Deliver to |
| Code |
| Administered by |
| Code |
| Contractor/Offeror |
| Code |
| Facility code |
| Telephone number |
| Check if remittance is different and put such address in offer |
| Payment will be made by |
| Code |
| Submit invoices to address shown in block 18a unless block below is checked |
| Accounting and appropriation data |
| Total award amount |
| Solicitation incorporates by reference |
| Addenda |
| Contract/purchase order incorporates by reference |
| Addenda |
| Contractor is required to sign this doc. and return: |
| Award of contract: reference |
| Signature of offeror/contractor |
| Name and title of signer |
| Signer date signed |
| Signature of contracting officer |
| Name of contracting officer |
| Contracting officer date signed |
| Authorized for local reproduction. Previous edition is not usable |
| Standard Form 1449 (Rev. 11/2021) |
| Quantity in column 21 has been |
| Signature of authorized government representative |
| Date |
| Printed name and title of authorized government representative |
| Mailing address authorized government representative |
| Telephone number of authorized government representative |
| Email number of authorized government representative |
| Ship number |
| Voucher number |
| Amount verified correct for |
| Payment |
| Check number |
| Stock record (S/R) |
| S/R account number |
| S/R voucher number |
| Paid by |
| I certify this account is correct and proper for payment |
| Signature and title of certifying officer |
| Date |
| Received by |
| Received at |
| Date received |
| Total containers |