Amendment 0003.pdf

PDF 443 KB Posted

Attached to
MMAC Base Maintenance Renovation Federal contract opportunity
Solicitation number
6973GH-20-R-00062
Issued by
Department of Transportation Federal Aviation Administration Non-Franchise Acquisition Services

About this file

This amendment to solicitation 6973GH-20-R-00062 provides revised specifications, drawings, and pricing terms for the renovation of the Base Maintenance Building at the Mike Monroney Aeronautical Center. The successful offeror will provide all labor, materials, equipment, and services to complete seismic upgrades to concrete and steel, replace the roofing system, upgrade exterior walls and windows, and modernize plumbing, electrical, mechanical, and fire suppression systems. The amendment extends the response deadline to July 22, 2020 and adds unit pricing for metal roof deck replacement, concrete slab removal and replacement, and variances in drilled pier depths to the revised Attachment 1 pricing schedule. It also includes minutes from the pre-proposal conference and site visits held on June 29 and July 1, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to MMAC Base Maintenance Renovation, newest first.
File Type Posted
Amendment 0006.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003 Drawing Revisions.pdf PDF
20. Amendment 0002.pdf PDF
Revised Attachment 10-BMB Past Performance Survey-dated 6-29-2020.pdf PDF
Amendment 0001.pdf PDF
Attachment 2 MMAC-BMB-Type B-Final IFC Specifications-R1.pdf PDF
Attachment 1-Section B-Supplies or Services-Prices.pdf PDF
Attachment 4-Chapter_33 Construction Safety.pdf PDF
Attachment 7-SF25A.pdf PDF
Attachment 10-BMB Past Performance Survey.pdf PDF
Attachment 5-DAVIS BACON WAGE DETERMINATION.pdf PDF
16. 6973GH-20-R-00062.pdf PDF
Attachment 13 OCAT 00310 Anti Non-Collusion Affidavit.pdf PDF
Attachment 9-Operational Control Docs.pdf PDF
Attachment 3e-MMAC-BMB Type B-Final IFC Drawings-VOLUME 1_R1 pages 141thru173.pdf PDF
Attachment 3a-MMAC-BMB Type B-Final IFC Drawings-VOLUME 1_R1 pages 1thru25.pdf PDF
Attachment 11-Client Authorization Letter.pdf PDF
Attachment 6-SF 25.pdf PDF
Attachment 8-Contractor Release.pdf PDF
Attachment 3-Volume 2-MMAC-BMB Type B-Final IFC Drawings-VOLUME 2-R1.pdf PDF
Attachment 12-OCAT 00320 Business Relationship Affidavit (002).pdf PDF
Attachment 3b-MMAC-BMB Type B-Final IFC Drawings-VOLUME 1-R1 pages 26thru45.pdf PDF
Attachment 3c-MMAC-BMB Type BFinal IFC Drawings-VOLUME 1_R1 pages 46thru90.pdf PDF
Attachment 3d-MMAC-BMB Type B-Final IFC Drawings-VOLUME 1_R1 pages 91thru140.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 2

0003 06/19/2020

AAQ-731 FAC. & AVIATION SAFETY ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

AAQ0731-AFN

OKLAHOMA CITY OK 73125

AAQ-731 FAC. & AVIATION SAFETY ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

AAQ731-AFN

OKLAHOMA CITY OK 73125

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

6973GH-20-R-00062

1 copies to the issuing office.

06/19/2020

(x)

NOTE: The Line Items listed in Section B of this SIR are for Government use only.

Offerors shall complete Revised Attachment 1, Section B/Pricing of this document for the contract line item pricing.

The purpose of this amendment is to provide the Pre-Proposal Conference and Site Visit

Minutes, Mechanical Room Site Visit Minutes, Revised Attachment 1, Section B - Supplies and

Services, Questions and Answers for Questions 10 through 40, and update specifications and drawings.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-20-R-00062/0003

FIRST: Pre-Proposal Conference and Site Visit

Minutes as well as Mechanical Room Site Visit

Minutes are hereby added to this amendment.

SECOND: Attachment 1, Section B - Supplies and

Services included in the original SIR is hereby superseded and replaced with Revised Attachment

1, Section B - Supplies and Services.

THIRD: Questions and Answers 10 through 40 are hereby added to this amendment.

FOURTH: Duct insulation schedule, Piping insulation schedule, Specification 01 2700 Unit

Prices are hereby provided in this amendment.

FIFTH: Drawing CD101, Drawing C-101, Drawing

AD100, Drawing AD100, Drawing A-218, Drawing

A-218, Drawing AE202, Drawing AE203, Drawing

AE701, Drawing AE703, Drawing AF112, Drawing

AF113, Drawing AF600, Drawing AF601, Drawing

S-102, Drawing M-601 and Drawing M-602 are all revised and updated with revisions marked

Amendment 0003.

SIXTH: The due date for proposals is hereby extended as follows:

From: 5:00 p.m. CT on July 20, 2020

To: 5:00 p.m. CT on July 22, 2020

ITEM SUPPLIES/SERVICES TOTAL

0001 Base Maintenance Building Renovation $

0002 Optional Item 1 - North Canopy $

Add canopy, perforated metal screen wall and foundations. Refer to Drawing Sheet A-102

0003 Optional Item 2 - West Canopy, Planter and Patio $ Add canopy, performated metal screen wall and foundations, concrete planter and bench, planter drainage and concrete patio. Refer to Drawing Sheet A-103.

0004 Optional Item 3 - Parking Lot $

Construct parking lot addition and associated sidewalks, lighting, etc., as shown in drawings. Refer to Drawing Sheets C-101, C-102 and C-105

0005 Maintenance/Defect Security $

Constractor shall provide cost of providing the Maintenance/Defect Security as required in Clause H.8.

Total Proposal Including All Options $

Unit Prices: refer to Specification Section 01 2700 0001 Unit Price No. 1: Replace deteriorated metal roof deck. Unit of Measurement: 100 SF $ per 100 SF

0002 Unit Price No. 2: Sawcut, remove, and replace concrete slab. Unit of Measurement: SY. $ per SY

0003 Unit Price No. 3: Drilled pier depth. Unit of Measurement: LF. (Note: 19’ pier depth is in the base bid. This unit price will be used to add to or deduct from the base bid depending on the actual depth of the piers.) $ per LF

CLIN Worksheet The contractor shall furnish a price for all labor, tools, materials, equipment, and supplies, necessary to accomplish the following breakout items. The pricing of these items will not affect the project award. These prices should be included in prices above and are only for FAA internal use.

0001 Base Maintenance Building

Seismic Concrete $

Seismic Steel $

Exterior Walls, Doors and Windows $

Plumbing - Utility Services and Roof Drain System (Restrooms and Break Areas not included) $

Roof Replacement (not including Shop Area) $

Electrical (not including telecommunication or security) $

Mechanical $

Natural Gas $

Fire Suppression $

DTFAAC-17-R-00187

PART I - SECTION B

SUPPLIES OR SERVICES AND PRICES/COST

The contractor shall furnish all personnel, materials, equipment, training, supplies, and other items necessary to perform all work necessary for the Base Maintenance Building Renovation in accordance with all terms, conditions, and provisions set forth herein.

6973GH-20-R-00062, BASE MAINTENANCE RENOVATION

PRE-PROPOSAL CONFERENCE MINUTES AND SITE VISIT ATTENDEES

The Pre-Proposal Conference for 6973GH-20-R-00062, Base Maintenance Renovation was held by telecon at 10:00 am on June 29, 2020. in Room 10B of the MMAC Visitors Center. The following people were present for the conference:

Company

StructSure Projects StructSure Projects StructSure Projects The Korte Company The Korte Company Southwind Construction Southwind Construction Southwind Construction Delta Electrical Contractors, Inc.

HGL Construction, Inc.

HGL Construction, Inc.

Flintco, LLC Flintco, LLC Globe Construction

FAA

FAA

FAA

FAA

Name

Ali Tweel Phillip Brandon Krista Scott Dan Bowlware Coleman Parrish Wendy Martin Ryan Mitchell Bill Kemp Michael Stalsworth Pat Renshaw Ali Curtis Guy Jackson Cory Rackley Peter Morrical Liz King Jon Berkman Monte Thurman Cynthia Cooper

Attendees were advised of the following:

• SIR closing date is July 20, 2020

• AAQ and Contractor Community need to work together for this acquisition to be successful. AAQ values contractor input – keep it coming.

• Amendment 0001 was issued this weekend and contained Revised Past Performance Survey, Revised wording to Provision L.3, Instructions for Preparation and Submission of Offerors and Questions and Answers 1 through 9.

• betaSAM is a new process for everyone - CO verified that SIR documents and Amendment 0001 documents were available in betaSAM. Revised Past Performance Survey was not included and CO will ensure that this document is added.

• This acquisition is being competed utilizing full and open competition. Ask attendees to be sure to provide 8(a) certification letter from SBA in Section I of proposal if you are an 8(a) firm and if you are a large business, be sure to include you subcontracting plan as part of Provision L.3.

• In order to be fair to all potential offerors, including those not present for the

• conference, all questions shall be submitted in writing to the contracting officer.

• As a reminder, even if there are discussions as a result of the conference, the

• SIR package, including all attachments, remains unchanged unless it is formally

• changed by a SIR amendment.

• Ask if the offerors want to go over Questions and Answers 1 through 9 or if the answers are sufficient.

• Due to COVID-19 restrictions, there will be 2 separate site visits on

Wednesday, July 1, 2020.

• The acquisition method being utilized for this procurement is Performance Price Tradeoff and more specific details are included in Sections L and M of the SIR.

• As a reminder, even if there are discussions as a result of the conference, the SIR package, including all attachments, remains unchanged unless it is formally changed by a SIR amendment.

• The list of conference attendees will be provided in the upcoming SIR amendment.

• Use of camera, video equipment or other recording devices are not permitted.

• Due to COVID-19 restrictions and to keep the site visits limited to 10 people, there will be two site visits on July 1, 2020. The first site visit will be held from 9:00 to 10:30 and the second site visit will be held from 10:30 to noon. Vendors will be notified of which site visit they are scheduled to attend. Vendors are encouraged to wear a face mask.

• Pre-proposal conference was concluded at 11:00

The following individuals were present for the site visit that was held on July 1, 2020 starting at 9:00 am:

Cory Rackley Guy Jackson Wendy Martin Ryan Mitchell Dan Bowlware Brian Wintersheidt Monte Thurman Cyndy Cooper

Flintco Flintco Southwind Southwind The Korte Company

LWPB

FAA

FAA

The following individuals were present for the site visit that was held on July 1, 2020 starting at 10:30 am:

JW Ward Brandon Box Jerry Hamm Ali Curtis Peter Morrical Tim Michael Stalsworth Benny Lawson David Gilbert Brian Winterscheidt Rick Siler Liz King Jon Berkman Cyndy Cooper

Firetrol Rick Scott Construction HGL Construction HGL Construction Globe Construction Delta Electric Delta Electric Oklahoma Roofing and Sheet Metal Shiloh Enterprises

LWPB

LWPB

FAA

FAA

FAA

BASE MAINTENANCE RENOVATION

6973GH-20-R-00062

SITE VISIT

JULY 12, 2020

The following people were present for the mechanical room site visit that was held at 9:00 am.

Brian Coates Coates Roofing Company, Inc.

Peter Morrical Globe Construction Co.

Dave Gilbert Shiloh Enterprises, Inc.

Evan León Alva Roofing Company Terry Branstetter Total Demolition Services, llc Bryan Gann Midwest Wrecking Jason Cook Metropolitan Mechanical Rick Siler LWPB Monte Thurman FAA Liz King FAA

The following people were present for the mechanical room site visit that was held at 10:00 am.

Michael Stalsworth Delta Electrical Contractors, Inc.

Chris Hatcher Oil Capital Electric W. J. Wolfe Wattie Wolfe Company Tim Millsap Millsap Electric Dan Bowlware Korte Construction Dan Ross Southwind Construction Services, LLC Kendall Shuck Go Forth Plumbing & Mechanical, LLC Rick Siler LWPB

The following people were present for the mechanical room site visit that was held at 11:00 am.

Guy Jackson Flintco, LLC Damon D. McClure Harrison-Orr Air Conditioning, LLC Jared Bowerman Hunter Mechanical & Controls, Inc.

Chris Brezny Nemecek Interior Construction Zack McNeely Matherly Mechanical Contractor Rick Siler LWPB

BASE MAINTENANCE RENOVATION

6973GH-20-R-00062

QUESTIONS AND ANSWERS

JUNE 29, 2020

Question 10: Specification 00 0102 Project information states Hazardous material removal is in our scope. However it does not elaborate on what the material is nor does it quantify the material. Could you please lets us know what this material is and approximately how much so we can properly quote?

Answer 10: FAA is performing the Asbestos remediation under another contract.

Lead-Based Paint removal/remediation is required to be performed by the contractor, and is addressed on drawing G-002, General Note 4. FAA has provided to LWPB prior surveys/reports documenting locations that Lead-Based paint occurs or is suspected in several locations throughout the building. However, FAA had previously directed us to NOT include the surveys/reports in the Contract Documents, or a spec for lead remediation procedures, which would better define the GC’s scope for this task.

Drawing AD100, Demo General Note 6, instructs the contractor to treat any PCB ballasts discovered, as hazardous waste. Presence of such ballasts is unknown.

We are not aware of any other hazardous materials in the building.

Question 11: In chapter 33 construction safety, there is a reference made to follow OSHA regulations and MMAC policy (33-2). Can you please inform us as to the MMAC safety policy for construction projects?

Answer 11: The Reference is to FAA AC Order 3900.21, Chapter 33, Section 2, which states that “all” personnel including construction contractors must adhere to the Construction Safety requirements in Chapter 33 of the order. Please see attached FAA AC Order 3900.21, Chapter 33 and referenced FAA AC Order 3900.19 Chapters 13 and 17.

Question 12: The mechanical and electrical sub-contractors are required to submit past performance surveys (or questionnaires). To whom do they submit them? Our discussion at the site lead me to believe that the General Contractors would submit ONE electrical PPS and ONE Mechanical PPS with our bid package. Please confirm.

Answer 12: The FAA envisions that the general contractor will decide who will be their mechanical and electrical subcontractor prior to submitting their proposal in response to this SIR. Provision L.3 of the SIR entitled Instructions for Preparation and Submission of Proposals, paragraph (f), Section II – Past Performance Information, states that the Offeror, along with their Mechanical and Electrical subcontractors, will send PPS to clients who are familiar with the work demonstrated through previous contracts of a similar nature. This paragraph also states that Offerors shall request a minimum of two (2) with a maximum of four (4) Past Performance Surveys as a general contractor as well as a minimum of two (2) with a maximum of four (4) Past Performance Surveys for their mechanical subcontractor and a minimum of two (2) with a maximum of four (4) Past Performance Surveys for their electrical subcontractor. All completed PPS’s shall be submitted directly to the contracting officer at cynthia.cooper@faa.gov.

Question 13: Referencing the term mechanical contractor: Do BOTH the plumbing and HVAC sub-contractors need to submit a past performance survey or only the

HVAC?

Answer 13: If the general contractor has selected a subcontractor that will be performing the plumbing portion of the contract and a separate subcontractor performing the HVAC portion of the contract, then PPS’s will be required for both subcontractors.

Question 14: The HVAC Duct Specification 230713 only list the outside air ducts and mixed air plenums to received insulation, what is the intent for the supply, return air & exhaust?

Answer 14: Please see attached PDFs of Additional Schedules for HVAC Duct and Piping Insulation.

Question 15: The HVAC Equip. 230716 & HVAC Piping 230719 list the equipment and piping systems but no schedule of materials or thicknesses, can this information be provided prior to bid?

Answer 15: Please see response to Question 14.

Question 16: Mechanical and Electrical Subcontractors are requesting a site visit to look at the basement area of the building. We understand that this area is still being abated and that access to this area was unavailable during the initial walkthrough. We request an additional walkthrough to this area and additional time of 2.5 weeks following the additional site visit in order for the mechanical/ electrical subcontractors to process the site visit information and complete their estimates.

Answer 16: Mechanical Site Visit was held on July 14, 2020. Unfortunately, the FAA’s schedule does not allow for an extension of 2.5 weeks.

Question 17: Page number G002 references that the general contractor is responsible for lead abatement. Can you provide an environmental report as to the locations of the lead contaminated areas?

Answer 17: Please see response to Question 10.

Question 18: The HVAC Duct Specification 230713 only list the outside air ducts and mixed air plenums to received insulation, what is the intent for the supply, return air & exhaust?

Answer 18: Please see response to Question 14.

Question 19: The HVAC Equip. 230716 & HVAC Piping 230719 list the equipment and piping systems but no schedule of materials or thicknesses, can this information be provided prior to bid?

Answer 19: Please see response to Question 14.

Question 20: Page PD 121 has a note (remove storm drain piping in hatched area) however there is no roof drain piping shown. Please advise.

Answer 20: The mechanical engineer was not able to verify exact locations and exact routing of existing storm drainage piping in this area. Field verification will be required by subcontractors for quantities and extent of piping to be demolished.

Question 21: What is the depth of the drilled piers shown the Detail 1/S-102?

Answer 21: Based on the geotech report, bidders should assume the bearing stratum is 19’-0” below finish floor.

Question 22: The bidding notes on sheet AD100 call for us to palletize and deliver carpet to building 50. Can you please identify where building 50 is, presuming it is on campus.

Answer 22: Building 50 is on campus, please see attached map showing project site in relation to building 50, we ask that the contractor coordinate a time to meet with the FAA inspector at Building 50 to gain access into the building. The contractor needs to keep the carpet tiles clean and dry. Palletize and shrink wrap removed carpet in order for carpet to be recycled. Do not leave carpet tiles outside at any time during removal or delivery.

Question 23: Sheet AD213 shows equipment X02 to be moved and stored and reinstalled (demo note Q06). What is equipment X02? (presume a copier)

Answer 23: X02 is an ice maker and X04 is a refrigerator.

Question 24: Regarding low voltage systems conduit

a. Will all systems be required complete pipe back to control source/closet?

Or

b. Can a cable tray be used in corridors back to closets and low voltage stub ups be routed to the tray?

c. If tray is acceptable can the systems cabling be installed on same tray system?

Answer 24: Yes, option A: all systems are required to complete pipe back to control source/closet.

Question 25: In the working hour clause F.1 it clearly indicates that all demo work is to be afterhours 6 pm to 6 am. I want to inquire if this is a correct clause so I can communicate that to our bidding subcontractors. My understanding is the building will be occupied in portions, but not necessary in the areas we are working and the building will not be fully occupied. Can the demo take place during normal working hours?

Answer 25: Typically, if the buildings are occupied, demolition is conducted afterhours to minimize the impact to the occupants; however, since the only occupants in the building work 24/7, there is no benefit for having the demolition after hours. Demolition can be performed during normal working hours.

Question 26: When the structural criteria for the job is entered on the ISAT website for seismic design it says there is no seismic bracing required. Is Seismic bracing required for this job? If so, please provide required seismic criteria for seismic bracing design.

Answer 26: Confirmed with Structural Engineer, project site is seismic design Category B, therefore seismic bracing is not required. Only vibration isolation.

Question 27: Doors C116B and C116C on the door schedule are referred to as being elevation 16. Elevation 16 is not shown on the drawings. Please provide clarification.

Answer 27: Door C116B, frame 16 is correct and a frame elevation will be added to the drawings by a future Amendment. Door C116C should be frame 16 OPP.

Question 28: Unit prices identified in 01 2700 are not listed on the bid form. Are the unit prices required to be submitted with our bid? If yes, please provide a revised bid form.

Answer 28: Revised Attachment 1, Section B – Supplies and Services will be added to SIR Amendment 0003.

Question 29: Drawing S-100 calls for unit pricing for drilled pier casings per lf and per pier. Is this unit pricing to be provided? If so, please add to the list of unit prices.

Answer 29: Revised Attachment 1, Section B – Supplies and Services will be added to SIR Amendment 0003.

Question 30: The solicitation F.3 Work by others, states that asbestos containing materials will be removed by others. Drawing G-002 Demo General Note 5 states that there is also lead-based paint to be mitigated/removed by the general contractor. Is the lead-based paint mitigation/removal by others as well? If not, what are the extents of the lead-based paint that needs to be mitigated/removed? Is there a test report defining the extent of this work? If so, please provide.

Answer 30: Please see response to Question 10.

Question 31: The solicitation F.3 Work by others, states that asbestos abatement must be accommodated by the general contractor in the construction schedule. It is our understanding that the asbestos abatement is currently taking place. Will the abatement be complete prior to the start of construction? If not, please provide the anticipated durations, by phase, that need to be accommodated in the construction schedule.

Answer 31:

Pre-construction: Asbestos abatement is currently in progress and will be complete in areas that are accessible prior to the start of construction.

Phase 1A: Contractor will demo this area.

Phase 1A Asbestos abatement: will take place in Phase 1A after demo opens up access to new areas that require abatement, 3 weeks required for abatement.

Phase 1A: Contractor will renovate this area.

Phase 1B: Contractor will demo this area.

Phase 1B Asbestos abatement: will take place in Phase 1B after demo opens up access to new areas that require abatement, 3 weeks required for abatement.

Phase 1B: Contractor will renovate this area.

60 days required between completion of Phase 1 and start of Phase 2: Per the specifications, Phase #2 work at the site shall not start until 60 days minimum after the Owner’s acceptance of, and the AHJ’s issuance of a Certificate of Occupancy for, Phase #1 work, to allow time for relocation of people & furniture (by others), and to allow time for asbestos remediation (by others).

Phase 2: Contractor will demo this area.

Phase 2 Asbestos abatement: will take place in Phase 2 after demo opens up access to new areas that require abatement, 6 weeks required for abatement.

Phase 2: Contractor will renovate this area.

Question 32: Please confirm that the standard warranty on the project is one year.

Answer 32: Refer to Clause 3.10.1-20 for construction warranties.

Question 33: During the site visit, there were some areas that were inaccessible. Will an additional site visit be available? If so, will subcontractors be permitted to attend?

Answer 33: Mechanical Room Site Visit was held on July 14, 2020.

Question 34: With the possibility of another site visit, will the proposal due date be extended?

Answer 34: The proposal due date is extended to July 22, 2020 in Amendment 0003.

Question 35: Section 01 10 00, Paragraph 1.03, Item C, Phase #1 Completion of Work states the period of performance for this work 820 calendar days. Item D, Phase #2, states this work cannot start for 60 days after Phase #1 is complete. However, a period of performance is not provided. Please provide POP for Phase #2.

Answer 35: 820 calendar days is for the complete project all phases included. The 60 days is for the time in between Phase 1 and Phase 2.

Question 36: The Plumbing Spec seems to have enough of the information needed, but the HVAC Duct (230713) only lists the Outside Air Ducts and Mixed Air Plenums to receive insulation, what will the S/A and R/A require? The HVAC Equip. (23016) and HVAC Pipe (230719) lists all of the Equip. & Pipe Systems but no schedule of materials or thicknesses. There appears to be quite a bit of exposed areas on this project as well and that is not addressed in any of the spec. sections. Will the exposed ducts receive external insulation, will they be lined or is no insulation required?

Answer 36: Please see response to Question 14.

Question 37: Can proposals in response to this SIR be submitted in person?

Answer 37: Potential offerors need to keep in mind that access to the Mike Monroney Aeronautical Center has been reduced due to COVID-19 restrictions. Potential offerors also need to keep in mind that contracting personnel from AAQ have been working remotely for several months due to COVID-19 restrictions and will continue to work remotely for some time to come. Because of these situations, SIR Provision L.3

INSTRUCTIONS FOR PREPARATION AND SUBMISSION OF PROPOSALS,

paragraph (b) was specifically designed to say “Documentation shall be submitted electronically in accordance with Section L, Provision 3.2.2.3-20. Clause 3.2.2.3-20 OFFERS (JAN 2018), paragraph (a) says “The offeror (you) must submit responses to this SIR by the following electronic means pdf version provided via email”.

Potential offerors are advised that failure to comply with these constructions may result in your proposal not being considered. Potential offerors are further advised that there are size restrictions on attachments to emails that may be submitted in response to this SIR and are cautioned to not wait until the very last minute to submit proposals. AMS

Clause 3.2.2.3-14 Late Submissions, Modifications and Withdrawals of Submittals is included in Section L of this SIR and will apply to any late proposals received.

Question 38: Would the FAA consider material substitutions?

Answer 38: Specification 01 6000 specification included in the SIR provided makes no provision for reviewing substitutions prior to receipt of proposals. Within 10 days after contract award, the successful offeror may submit substitution requests that may or may not be approved; therefore potential offerors are requested to provide their proposal based upon the current SIR requirements. The future successful contractor is put on notice that the responsibility to provide all the necessary data in order to enable the FAA to potentially review product substitutions after contract award rests solely with the future successful contractor. General requests that do not provide complete data, catalogs without specific proposed products identified, and links to a manufacturer’s site requiring the FAA to find the applicable data ourselves will not be reviewed.

Question 39: Are liquidated damages applicable to this requirement?

Answer: No

Question 40: We have had numerous request for a secondary site visit to tour the entire building. Will it be possible to conduct a second, whole building site visit?

Answer 40: The FAA has already allowed for a site visit for the entire site and a secondary site visit for the mechanical room. All potential contractors have had the opportunity to view the site. No further site visits will be allowed.

Technical Specification ISSUED FOR CONSTRUCTION

DTFAAC-16-D-00036 01 2700 - 1 UNIT PRICES

FAA BMB Renovation Type B Amendment 003 07/15/2020

SECTION 01 2700

UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for unit prices.

B. Related Section:

1. Section 01 2800 "Modification Procedures" for procedures for submitting and handling Change Orders.

1.2 DEFINITIONS

A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.

1.3 PROCEDURES

A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.

B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.

C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.

D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.

PART 2 - PRODUCTS – Not Used

PART 3 - EXECUTION

3.1 SCHEDULE OF UNIT PRICES

A. Unit Price No. 1:

Technical Specification ISSUED FOR CONSTRUCTION

DTFAAC-16-D-00036 01 2700 - 2 UNIT PRICES

FAA BMB Renovation Type B Amendment 003 07/15/2020

1. Description: Replace deteriorated metal roof deck, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD410, AD420, S- 301, S-302 and Mechanical/Plumbing Drawings for known quantities of metal deck replacement and infill that are required in the Base Bid and are excluded from this unit pricing.

2. Unit of Measurement: 100 SF.

B. Unit Price No. 2:

1. Description: Sawcut, remove, and replace concrete slab, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD200-series and S-200 series drawings for known quantities of slab removal and replacement that are required in the Base Bid and are excluded from this unit pricing.

2. Unit of Measure: SY.

C. Unit Price No. 3:

1. Description: Drilled pier depth, plus or minus from the depths indicated. Base Bid depths shall assume that bearing stratum is located 19’-0” below finish floor per the Geotechnical Report, and shall include the required pier embedment into the bearing stratum as shown on the drawings.

2. Unit of Measure: LF.

END OF SECTION

FAA MMAC - BMB RESPONSE TO RFI 07.10.2020

C. Boaldin

AIRFLOW DUCT LOCATION INSULATION TYPE THICKNESS INCHES JACKET NOTES

SUPPLY ABOVE CEILING

1.5 PCF DENSITY FLEXIBLE FIBERGLASS WITH 2 MIL REINFORCED FOIL VAPOR

BARRIER

3" FSK 1-3

SUPPLY EXPOSED BOARD INSULATION WITH SEALED ALUMINUM JACKET 2" ALUMINUM 1-4

EXHAUST ABOVE CEILING UNINSULATED - - -

NOTES:

1. INSULATION THICKNESS

2. SEE DIV 23 SPECIFICATIONS FOR ADDITIONAL INFORMATION.

3. UNLESS OTHERWISE NOTED ON PLANS AND SPECIFICATIONS.

4. ALL DUCT SHALL BE INSULATED TO A MINIMUM OF 10' FROM EXTERIOR CONNECTION TO EQUIPMENT OR THROUGH WALL.

5. INSULATED DUCTWORK ABOVE THE ROOF SHALL BE 2" R-8 PER ENERGY CODE.

DUCT INSULATION AND JACKET SCHEDULE

FAA MMAC - BMB 07.10.2020

C. Boaldin

LOCATION MATERIAL PIPE SIZE THICKNESS INCHES NOTES

INTERIOR SCH 80 CARBON STEEL 1" AND SMALLER 1 1-3

INTERIOR SCH 40 CARBON STEEL > 1" PIPE 1.5 1-3

EXTERIOR UNDERGROUND SCH 40 CARBON STEEL > 1" PIPE 2 1-3

EXTERIOR ABOVEGROUND SCH 40 CARBON STEEL > 1" PIPE 2 1-4

INTERIOR SCH 80 CARBON STEEL 1" AND SMALLER 1 1-3

INTERIOR SCH 40 CARBON STEEL > 1" PIPE 1.5 1-3

EXTERIOR SCH 40 CARBON STEEL > 1" PIPE 2 1-4

NOTES:

1. INSULATION THICKNESS INDICATED SHALL BE THE MINIMUM THICKNESS AND INSTALLED TO MANUFACTURER'S INSTRUCTIONS. INCREASE THICKNESS AS REQUIRED TO MEET

CURRENT LOCAL CODE.

2. SEE DIV 23 SPECIFICATIONS FOR ADDITIONAL INFORMATION REGARDING ACCEPTABLE MATERIALS, ETC.

3. UNLESS OTHERWISE NOTED ON PLANS AND SPECIFICATIONS.

4. PROVIDE ADDITIONAL PROTECTIVE ALUMINUM JACKETING FOR PIPING, FITTINGS, AND VALVES.

CHILLED WATER PIPING

PIPING INSULATION

SYSTEM

HEATING WATER PIPING

RESPONSE TO RFI

Attachment 1 Section B - Supplies or Services-Prices REVISED 7.14.2020.pdf
Table 1
01 2700-Unit Prices_AM3.pdf
PART 1 - GENERAL
PART 1 - GENERAL
1.1 SUMMARY
1.1 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
A. Section includes administrative and procedural requirements for unit prices.
B. Related Section:
B. Related Section:
1. Section 01 2800 "Modification Procedures" for procedures for submitting and handling Change Orders.
1. Section 01 2800 "Modification Procedures" for procedures for submitting and handling Change Orders.
1.2 DEFINITIONS
1.2 DEFINITIONS
A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appr...
A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appr...
1.3 PROCEDURES
1.3 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
B. Measurement and Payment: Refer to individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
PART 2 - PRODUCTS – Not Used
PART 2 - PRODUCTS – Not Used
PART 3 - EXECUTION
PART 3 - EXECUTION
3.1 SCHEDULE OF UNIT PRICES
3.1 SCHEDULE OF UNIT PRICES
A. Unit Price No. 1:
A. Unit Price No. 1:
1. Description: Replace deteriorated metal roof deck, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD410, AD420, S-301, S-302 and Mechanical/Plumbing Drawings for known quantities of metal deck replacemen...
1. Description: Replace deteriorated metal roof deck, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD410, AD420, S-301, S-302 and Mechanical/Plumbing Drawings for known quantities of metal deck replacemen...
1. Description: Replace deteriorated metal roof deck, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD410, AD420, S-301, S-302 and Mechanical/Plumbing Drawings for known quantities of metal deck replacemen...
2. Unit of Measurement: 100 SF.
2. Unit of Measurement: 100 SF.
B. Unit Price No. 2:
B. Unit Price No. 2:
1. Description: Sawcut, remove, and replace concrete slab, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD200-series and S-200 series drawings for known quantities of slab removal and replacement that are...
1. Description: Sawcut, remove, and replace concrete slab, in excess of the quantities depicted on the Demolition and Construction Drawings. Refer to AD200-series and S-200 series drawings for known quantities of slab removal and replacement that are...
2. Unit of Measure: SY.
2. Unit of Measure: SY.
C. Unit Price No. 3:
C. Unit Price No. 3:
1. Description: Drilled pier depth, plus or minus from the depths indicated. Base Bid depths shall assume that bearing stratum is located 19’-0” below finish floor per the Geotechnical Report, and shall include the required pier embedment into the be...
1. Description: Drilled pier depth, plus or minus from the depths indicated. Base Bid depths shall assume that bearing stratum is located 19’-0” below finish floor per the Geotechnical Report, and shall include the required pier embedment into the be...
2. Unit of Measure: LF.
2. Unit of Measure: LF.
A-218.pdf
Sheets
A-218 - FLOOR PLAN - AREA C - PHASE 1B