This document contains questions and answers related to a Request for Proposals (RFP) for a Yellowstone & Grand Teton Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) 2024 issued by the Department of Transportation Federal Highway Administration. The RFP seeks proposals for construction services within Yellowstone and Grand Teton National Parks and surrounding areas, to be awarded through an IDIQ contract structure. Key details include services required encompass a range of construction elements including bridge construction over 100 feet, paving of at least 3,500 tons, and permeable backfill. The response date for proposals was January 25, 2024. Amendments to the RFP provided additional clarification on RFP requirements and adjusted some minimum quantities. Questions and answers indicate task orders issued under the contract may include requirements for the use of project labor agreements on large projects over $35 million.

View the file

Other files

File Type Posted
QA_01-25-2024.pdf PDF
Amendment A005.pdf PDF
J.2 Technical Information Form 1_A004.pdf PDF
QA_01-16-2024_2.pdf PDF
J.4 Past Performance Form 2_A001.pdf PDF
QA_01-16-2024.pdf PDF
J.2 Technical Information Form 1_A004.pdf PDF
Amendment A004.pdf PDF
QA_01-05-2024.pdf PDF
Amendment A003.pdf PDF
QA_01-03-2024.pdf PDF
QA_12-28-2023.pdf PDF
Amendment A002.pdf PDF
QA_12-27-2023.pdf PDF
Amendment A001.pdf PDF
QA_12-20-2023.pdf PDF
QA_12-18-2023.pdf PDF
RFP_Yellowstone MATOC_Final.pdf PDF
J.3 YELL 12(5)_PLANS_70pct.pdf PDF
J.2 Technical Information Form 1.pdf PDF
J.3 Sample Project YELL 12(5).pdf PDF
J.1 MASTER SUBCONTRACTING PLAN.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

69056723R000013

Yellowstone, Grand Teton, & Surrounding area MATOC 2024

# General Technical Question Answer Date

1 X

We are respectfully requesting a bid due date extension of 2 weeks due to the lost time over the holidays. This will allow us and our team to provide the best proposal possible.

At this time the Government does not intend on extending the proposal due date.

12/18/2023

2 X

In regards to the technical proposal (7) Bridge construction of a vehicular bridge 100‐feet or longer, is it acceptable to use a bridge that has a total structure length of over 100 feet with tie backs or wing walls etc. or does the span have to be 100‐feet or longer?

This will be addressed under Amendment

A001.

12/20/2023

3 X

Regarding Factor 3, Past Performance, does

FHWA have a specific form to provide State

DOT’s that do not perform performance evaluations as part of their contract administration? If not, can FHWA provide the scoring criteria they would like an owner to use for the five sub factors listed for the past performance evaluation?

This will be addressed under Amendment

A001.

12/20/2023

4 X

Will the President's Executive Order (14063) ‐

Use of Project Labor Agreements for Federal

Construction Projects, for projects larger than

$35M be enforced for task orders that meet this criteria? Enforcing this requirement will limit the amount of Contractors that submit on this solicitation.

Federal Acquisition Circular (FAC) 2024‐02 was published in the Federal Register

December 22, 2023 implementing

Executive Order 14063 with an effective date of Jan 22, 2024. It is anticipated the use of project labor agreements for certain federal construction projects may be required at the task order level for projects solicited during the period of performance of this Multiple Award Task Order Contract

(MATOC). If applicable, this requirement will be stated in each subsequent Task

Order. A summary of the final rule can be found at the following link:

https://www.federalregister.gov/documen ts/2023/12/22/2023‐27736/federal‐ acquisition‐regulation‐use‐of‐project‐labor‐ agreements‐for‐federal‐construction‐ projects. Offerors are advised to review solicitations for project specific requirements.

12/27/2023

Check General or Technical

5 X

The requirements on the Recent and Relevant

Experience Forms that the projects are in the last 5 years and needing to be able to check at least 4 boxes make this a challenging requirement to meet, so we are requesting one of the following changes:

1. Allow projects to have been completed in the last 10 years (instead of 5 years);

2. Reduce the amount of boxes that need to be checked to two as long as all 7 requirements are met across the projects submitted; or

3. Not require that all 7 boxes need to be satisfied if the Contractor can show ample relevant experience.

The Government does not intend to adjust the recent and relevant work experience requirements.

12/27/2023

6 X

In reference to Amendment A001 and Technical information construction element #7 is it the entire structure that has to be greater than 100 feet in length?

This will be addressed under Amendment

A002.

12/27/2023

7 X

Is there Geotech data available for Lulu pass and Post Creek pits to help determine material quality?

There is no Geotech data available for Lulu pass or Post Creek pits at this time.

12/27/2023

8 X

Is there a way to get the contact information for the prime contractors who get awarded this contract so we can reach out for subcontracting opportunities?

Once the Indefinite‐Delivery Indefinite

Quantity (IDIQ) contracts are awarded, the contact information for prime contractors that receive awards will be made available to the public.

12/28/2023

9 X

Regarding Bid Item A0400 Backfill, Permeable, the specifications are not listed in the SPC or FP‐

14. Can you clarify what material specifications to use for this item.

This will be addressed under Amendment

A003.

1/3/2024

10 X What does CEC stand for?

It was the predecessor to DUNS, now UEI, and stood for Contractor Establishment

Code. Came out in 1998. Nothing related to our YELL MATOC solicitation.

1/5/2024

11 X Can you relax Construction Element 6, Paving –

8000 tons minimum to 4000 tons minimum?

This will be addressed under Amendment

A004.

1/5/2024

12 X Will a project that has an unsatisfactory rating not be evaluated?

Proposals will be evaluated against the criteria on page M‐1 through M‐6.

1/5/2024

13 X Can you please provide the wage requirement for this project?

See B‐Pages in Attachment J.3 Sample

Project.

1/5/2024

14 X

In Amendment A004, form J.4 Past

Performance Form 2 is called out as an attachment but the form is not included in the

Attachments/Links portion of the contract advertisement page. Will this form be included on the advertisement page or is it available for download from another site?

J.4 Past Performance Form 2 was added under Amendment A001 and not revised under Amendment A004. For administrative convenience, in addition to already being included under Amendment

A001, this form will also be uploaded separately as an attachment on SAM.gov.

1/16/2024

15 X

I see that addendum #4 posted with a change to 3500 minimum tons required to meet the paving criteria. The new J2 form that was posted as a part of addendum 4 says 4000 tons.

I just wanted to point out the discrepancy.

The new J2 form that was uploaded for administrative convenience has been updated to match the form that was revised and included under Amendment

A004.

1/16/2024

16 X

It appears amendment 5 to this solicitation added the following two FAR clauses:

52.222‐34 Project Labor Agreement (Jan 2024)

Alternate II JAN 2024

52.222‐33 Notice of Requirement for Project

Labor Agreement (Jan 2024) Alternate III JAN

Is it the intent of FHWA to include these FAR

Clauses in all of the bid task orders under this upcoming MATOC?

These will be included at the task order level when the threshold of large‐scale construction project is met.

1/25/2024

17 X

Could FHWA distinguish the difference between the two added FAR clauses as they read differently, however, both are added in amendment.

52.222‐33 Notice of Requirement for

Project Labor Agreement, is a provision applicable during solicitations. 52.222‐34

Project Labor Agreement, is a clause applicable after award.

1/25/2024

18 X

Would FHWA be able to provide insight/information as to who the senior procurement officer will be on this MATOC for exceptions to be granted to FAR 52.222‐34

Project Labor Agreements.

See FAR 22.504. Exceptions to Project

Labor Agreements may be granted by an agencies Senior Procurement Executive

(SPE). Requesting exceptions to this requirement is a Government function, so all requests or recommendations for exceptions to this requirement should be submitted through the appropriate

Contracting Officer.

1/25/2024