589A7-21-132 Wichita Bid Drawings 08_Electrical 1 of 2.pdf

PDF 7 MB Posted

Attached to
Z2DA--589A7-21-132 Construct Centralized Emergency Power System
Solicitation number
36C25526R0125
Issued by

About this file

Summary

This document package comprises bid documents for the Construct Centralized Emergency Power System project at Robert J. Dole VA Medical Center in Wichita, Kansas (Project No. 589A7-21-132). The project is issued by the U.S. Department of Veterans Affairs, Office of Construction and Facilities Management, with an issue date of March 26, 2026. The engineering team includes Miller-Remick LLC as the professional engineer of record, with supporting consultants including IMEG Corp (electrical), Stanton Engineering Services LLC (fire and life safety), Oculus Inc (architectural), Professional Engineering Consultants PA (structural), and Mabbett & Associates Inc (hazardous materials).

The project scope encompasses demolition and renovation of the facility's electrical systems, construction of a new generator building (Building 37), installation of centralized medium-voltage generators to replace existing building-level generators, and construction of new underground concrete-encased ductbanks for medium-voltage, emergency, and low-voltage cables. Key deliverables include electrical demolition and removal work, installation of new pad-mounted transformers and automatic transfer switches for nine buildings, construction of new interconnected generator systems with paralleling switchgear and control systems, lightning protection systems, grounding infrastructure, and comprehensive testing and commissioning. The work must be coordinated to maintain facility operations throughout construction, with phased implementation allowing work to proceed one building at a time while maintaining emergency power coverage through temporary generators as required. All work must comply with the National Electrical Code, state and local codes, and manufacturers' specifications.

View the file

Other files

File Type Posted
589A7-21-132 Wichita Bid Drawings 01_General_Complete.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 3 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 4 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 10 of 10.pdf PDF
02_Structural.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 2 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 6 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 07_Mechanical 1 of 2.pdf PDF
589A7-21-132 Wichita Bid Drawings 06_Fire Protection_Complete.pdf PDF
589A7-21-132 Wichita EPS_Bid Docs - Specifications - Volume I.pdf PDF
589A7-21-132 Wichita Bid Drawings 07_Mechanical 2 of 2.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 9 of 10.pdf PDF
04_Fire Protection and Fire Alarm Narrative.pdf PDF
589A7-21-132 Wichita Bid Drawings 02_HazMat_Complete.pdf PDF
589A7-21-132 Wichita EPS_Bid Docs - Specifications - Volume II.pdf PDF
36C25526R0125_1.docx DOCX document
852.219-75 VA Notice of Limitations on Subcontracting General Construction.pdf PDF
589A7-21-132 Wichita Bid Drawings 09_Fire Alarm_Complete.pdf PDF
05_Mechanical Narrative.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 1 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 5 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 05_Architectural Complete.pdf PDF
01_Civil Narrative.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 8 of 10.pdf PDF
589A7-21-132 Wichita Bid Drawings 03_Civil 7 of 10.pdf PDF
06_Electrical.pdf PDF
03_Architectural Narrative.pdf PDF
589A7-21-132 Wichita Bid Drawings 08_Electrical 2 of 2.pdf PDF
589A7-21-132 Wichita Bid Drawings 04_Structural_Complete.pdf PDF
APPENDIX 2- PRICE BREAKDOWN AND CALCULATION OF SELF-PERFORMED and SUBCONTRACTED WORK.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NO. DESCRIPTION DATE

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

ELECTRICAL

ABBREVIATIONS & SYMBOLS

E-001

MJRTO

FIRE

S

CR

IC

MDMD

RX RX

RX

ES

TYPICAL DEVICE MOUNTING HEIGHTS

ALL DIMENSIONS SHOWN ARE TYPICAL, U.O.N.

NONE

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

ELECTRICAL

NOTES

E-002

MJRTO

1. THE CONTRACTOR SHALL INCLUDE IN HIS BID ALL COSTS ASSOCIATED WITH

RELOCATION AND REMOVAL OF ELECTRICAL WORK AS DESCRIBED IN THE

DRAWINGS AND SPECIFICATIONS WITH ALLOWANCES FOR EXPECTED OR

UNFORESEEN ISSUES WHEN CONCEALED WORK HAS BEEN EXPOSED. NO

ADDITIONAL CLAIMS FOR WORK ASSOCIATED WITH DEMOLITION WILL BE

ACCEPTED, UNLESS, IN CERTAIN CASES, CONSIDERED JUSTIFIABLE BY THE

ENGINEER.

2. NOTE THAT THE FACILITY WILL BE OPERATIONAL DURING THE COURSE OF

THIS PROJECT.

2.1. THE CONTRACTOR IS TO COORDINATE ALL OF THE DEMOLITION WORK

WITH THE FACILITY PERSONNEL TO MINIMIZE DISTURBING THE

OPERATING EQUIPMENT, WIRING AND SYSTEMS.

2.2. THE CONTRACTOR SHALL PERFORM REMOVAL AND DEMOLITION WORK

WITH MINIMAL INTERFERENCE WITH EXISTING SYSTEMS.

2.3. IF NECESSARY THE CONTRACTOR SHALL PROVIDE TEMPORARY POWER

FOR THE FACILITY.

3. DEMOLITION AND REMOVAL OF WORK SHALL BE PERFORMED IN A NEAT AND

PROFESSIONAL MANNER. THE CONTRACTOR SHALL RESTORE, PATCH, PAINT,

ETC., ANY INTERIOR/EXTERIOR BUILDING SURFACE TO ITS ORIGINAL

CONDITION.

4. REFER TO ELECTRICAL DEMOLITION AND RENOVATION PLANS FOR NEW

EQUIPMENT LAYOUT AND EXTENT OF EQUIPMENT BEING REPLACED,

RELOCATED, OR REMOVED. COORDINATE WITH ALL TRADES AS TO EXTENT OF

EQUIPMENT BEING REMOVED OR RELOCATED. CLOSELY COORDINATE THE

EXTENT OF DEMOLITION SCOPE OF WORK WITH ARCHITECT, ENGINEER

AND/OR MECHANICAL PLANS. PATCH AND PAINT (TO MATCH SURROUNDING

CONDITIONS) ALL OPENINGS CREATED BY THIS DEMOLITION.

5. EXISTING CONDITIONS, EQUIPMENT, MATERIALS & SIZES ARE SHOWN FOR

REFERENCE ONLY. VERIFY EXISTING CONDITIONS AND BRING ANY

DISCREPANCIES TO THE ENGINEER'S ATTENTION IN WRITING PRIOR TO BID

SUBMISSION.

6. ELECTRICAL CONTRACTOR SHALL BE RESPONSIBLE FOR ALL ELECTRICAL

DEMOLITION WORK FOR THIS PROJECT WHETHER OR NOT SPECIFICALLY

INDICATED ON THIS OR OTHER DEMOLITION PLANS. THIS WORK SHALL

INCLUDE BUT IS NOT LIMITED TO THE DISCONNECTION, REMOVAL AND

DISPOSAL OF; LIGHTING FIXTURES, PANELBOARDS, DISCONNECT SWITCHES,

RECEPTACLES, JUNCTION BOXES, WIRE, CABLE, CONDUIT, MOUNTING

HARDWARE STRAPS OR CABLES, ELECTRICAL SERVICES ETC. PER THE SCOPE

OF WORK FOR THIS PROJECT.

7. THE ELECTRICAL CONTRACTOR SHALL REMOVE ALL ELECTRICAL OUTLETS,

SWITCHES, ETC., INCLUDING ASSOCIATED WIRING, CONDUITS, COVERS,

BOXES, ETC., WHERE SHOWN ON THE DEMOLITION DRAWING. WHERE THE

REMOVAL OF THESE ITEMS DISRUPTS EXISTING WIRING THAT IS TO REMAIN,

THE CONTRACTOR SHALL INSTALL IN THE CEILING SPACE; JUNCTION BOXES

AND OTHER DEVICES AND PROVIDE BYPASS CONNECTIONS NECESSARY TO

MAKE CIRCUITS AFFECTED CONTINUOUS AND READY FOR OPERATION.

OTHERWISE, WIRING SHALL BE REMOVED BACK TO THE NEAREST ELECTRICAL

JUNCTION BOX THAT IS TO REMAIN OR TO THE SOURCE PANELBOARD.

8. ALL WORK MUST BE SCHEDULED AND PERFORMED AS NOT TO INTERRUPT

NORMAL OPERATIONS. REMOVAL OF ITEMS THAT WILL CAUSE ANY TYPE OF

TEMPORARY SHUTDOWN SHALL BE PERFORMED DURING OFF-PEAK HOURS.

ALL SUCH OUTAGES SHALL BE SCHEDULED AND COORDINATED WITH OWNER

FIELD REPRESENTATIVE TO ENSURE ESSENTIAL SERVICES OR AREAS CAN BE

MAINTAINED.

9. THE CONTRACTOR SHALL NOTIFY THE OWNER AT THE APPROPRIATE TIME OF

THE PROJECTED DEMOLITION AND PHASING SCHEDULE SO THAT REMOVAL OR

RELOCATION OF AFFECTED UTILITIES MAY BE CARRIED OUT IN COORDINATION

WITH THE PROJECT REQUIREMENTS. THE CONTRACTOR SHALL CLOSELY

FOLLOW THE DEMOLITION AND PHASING SCHEDULE AND PROCEED IN THE

SPECIFIED SEQUENCE.

10. THE SHUTDOWN OF EXISTING BUILDING ELECTRICAL SERVICES SHALL BE

COORDINATED WITH THE OWNER. MAKE APPROPRIATE ARRANGEMENTS AT

LEAST 5 BUSINESS DAYS PRIOR TO A SHUTDOWN.

11. THE CONTRACTOR SHALL REMOVE AND/OR RELOCATE ALL EXISTING

ELECTRICAL WORK WHICH INTERFERES WITH THE NEW ELECTRICAL AND

ARCHITECTURAL LAYOUTS IN FULL COORDINATION WITH THE ENGINEER'S

DEMOLITION PLANS. ALL SYSTEMS WHICH ARE NO LONGER REQUIRED TO

FUNCTION SHALL BE DE-ENERGIZED AND DISCONNECTED AT THE POWER

SUPPLY SOURCE.

12. ELECTRICAL CONTRACTOR SHALL PROVIDE AND MAINTAIN ANY CONNECTIONS

/ DISCONNECTIONS AS NEEDED TO ENSURE ADEQUATE SAFETY AND

PROTECTION OF ALL PERSONNEL AND EQUIPMENT.

13. ALL ELECTRICAL PANELS SHALL BE MAINTAINED AS WORKING PANELS

THROUGHOUT CONSTRUCTION AND WILL CONTINUE TO MAINTAIN CIRCUITS

FOR EXISTING LIGHTING OR EQUIPMENT TO REMAIN. PROVIDE AS NECESSARY

TEMPORARY LIGHTING AND ELECTRICAL FEEDS TO ANY DEVICES THAT MAY BE

REQUIRED FOR UNINTERRUPTED USE. PROVIDE TEMPORARY CONNECTIONS

FOR RELOCATED EQUIPMENT DURING CONSTRUCTION.

14. ELECTRICAL CONTRACTOR SHALL ENSURE THAT ANY DEVICES AND/OR

FIXTURES LOCATED OUTSIDE OF DEMOLITION WORK AREA ARE NOT

AFFECTED BY REMOVAL OF WIRING AND/OR CIRCUITING. WIRING/CONDUIT

SHALL BE LEFT IN A SAFE CONDITION, LABELED FOR ITS USE, AND EXTENDED

AS REQUIRED TO MAINTAIN CIRCUIT CONTINUITY, INCLUDING ALL APPLICABLE

CONTROLS.

15. PORTIONS OF FEEDER RUNS THAT SHALL BE REMOVED OR ABANDONED AS A

RESULT OF DEMOLITION WORK, BUT WHICH ARE REQUIRED TO REMAIN

ENERGIZED, SHALL BE CUT AT CONVENIENT LOCATIONS, REROUTED AND

RECONNECTED. NEW FEEDER EXTENSIONS SHALL MATCH EXISTING FEEDER

EXTENSIONS IN ALL ASPECTS INCLUDING BUT NOT LIMITED TO CABLE TYPE,

CONDUIT SIZES, CONDUCTOR AMPACITY, ETC..

16. ALL EXISTING LOW VOLTAGE WIRING FOR FIRE ALARM/SECURITY, SOUND,

AND/OR TELECOMMUNICATIONS THAT IS NOT REUSED SHALL BE REMOVED IN

ITS ENTIRETY BY THE RESPONSIBLE CONTRACTOR. ALL EXISTING LOW

VOLTAGE WIRING FOR MECHANICAL SYSTEMS THAT ARE NOT USED SHALL BE

REMOVED IN ITS ENTIRETY BY THE CONTRACTOR.

17. CONTRACTOR IS TO EXERCISE EXTREME CAUTION WHEN CUTTING SLAB TO

AVOID DAMAGE TO ANY EXISTING CONDUITS, PIPING, ETC. THAT MAY BE

CONCEALED IN OR BENEATH THE SLAB. ANY FLOOR SLAB AFFECTED BY THE

REMOVAL OF DEVICES FED VIA UNDERGROUND CONDUIT OR WIRING, SHALL

BE FIRESTOPPED AND PATCHED BY THE GENERAL CONTRACTOR AND TO

MATCH SURROUNDING FLOOR.

18. ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR DISCONNECTING,

RELOCATING, AND/OR RECONNECTING ALL EXISTING EQUIPMENT THAT IS TO

REMAIN, EVEN IF THIS EQUIPMENT IS NOT SHOWN ON PLANS OR PANEL

SCHEDULES. ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR EXTENDING

EXISTING CIRCUITS FROM EXISTING EQUIPMENT THAT IS REMAINING TO NEW

LOCATION. CONTRACTOR SHALL MATCH EXISTING GAUGE WIRE FROM

EXISTING BREAKER TO RELOCATED EQUIPMENT.

19. IN THE EVENT THAT ELECTRICAL PLANS CALL FOR EXISTING WIRING TO BE

REUSED, THE ELECTRICAL CONTRACTOR SHALL SURVEY EXISTING WIRING,

BOXES, ETC. TO DETERMINE IF THE EXISTING BRANCH CIRCUIT MAY BE

REUSED FOR NEW EQUIPMENT (IF WIRING REMAINS IN ITS ORIGINAL CONDUIT).

ELECTRICAL CONTRACTOR SHALL DETERMINE THAT THE ENTIRE RUN OF

EXISTING POWER CONDUIT AND WIRING, FROM SOURCE PANEL TO LOAD FOR

WIRING TO BE REUSED, IS FEASIBLE FOR REUSE AND MEETS THE

REQUIREMENTS OF THE NATIONAL ELECTRICAL CODE, STATE AND LOCAL

CODES HAVING JURISDICTION.

IN INSTANCES WHERE EXISTING CIRCUITS ARE TO BE EXTENDED OR

REUSED, ELECTRICAL CONTRACTOR SHALL DISCONNECT EXISTING BRANCH

CIRCUIT AND LEAVE IN A SAFE CONDITION (TAG AND LABEL ITS USE) FOR

FUTURE RECONNECTION DURING RENOVATION PHASE.

20. ALL WIRING NOT INDICATED FOR REUSE SHALL DISCONNECTED AND REMOVED

FROM LOAD TO SOURCE (INCLUDING DATA, COMMUNICATION, OR TELEPHONE

WIRING). ANY CONDUITS STUBBED OUT OF MASONRY SURFACE SHALL BE CUT

INTO SURFACE AND PATCHED TO MATCH SURROUNDING CONDITIONS.

21. PANELBOARD CABINETS SHALL NOT BE USED FOR OTHER PURPOSES THAN

CIRCUIT BREAKER INSTALLATIONS AND DISTRIBUTION POINTS, AND SHALL

NOT BE USED AS A JUNCTION OR PULLBOX.

22. ALL UNUSED OUTLET BOXES THAT ARE TO REMAIN SHALL BE PROVIDED WITH

MATCHING BLANK COVERS.

23. ALL RACEWAYS WHICH ARE EXPOSED AS A RESULT OF NEW WORK SHALL BE

REMOVED AND REROUTED CONCEALED BEHIND FINISHED SURFACES.

24. EXISTING RACEWAYS THAT ARE NOT BEING REUSED SHALL BE REMOVED

BACK TO THE NEAREST JUNCTION OR PULLBOX, AND THE OPENINGS BLANKED.

ANY CONDUITS PENETRATING MASONRY SURFACES SHALL BE CUT INTO

SURFACE, PATCHED, AND PAINTED TO MATCH SURROUNDINGS.

25. DISCONNECT, RELOCATE OR REMOVE ELECTRICAL INSTALLATIONS AND

EQUIPMENT AS INDICATED BY PLANS AND AS REQUIRED BY CHANGES IN

CONSTRUCTION. WHERE EXISTING ELECTRICAL INSTALLATIONS INTERFERE

WITH NEW WORK AND WHERE SUCH INSTALLATIONS ARE TO REMAIN IN USE,

THE NEW INSTALLATIONS SHALL BE RELOCATED AND/OR RECONNECTED TO

COORDINATE WITH THE WORK INDICATED ON THE CONTRACT DRAWINGS.

DETERMINE AND COORDINATE ALL EQUIPMENT LOCATIONS PRIOR TO INITIAL

ROUGH-IN.

26. DISCONNECT AND RELOCATE/RECONNECT ANY ELECTRICAL LINES, BRANCH

CIRCUITS, DEVICES (INCLUDING FIRE ALARM DEVICES), ETC. AND REPAIR PULL

BOXES THAT MAY BE DISTURBED DURING THIS RENOVATION. UNLESS NOTED

OTHERWISE, ALL EXISTING ELECTRICAL WORK WHICH WILL NOT BE RENDERED

OBSOLETE AND WHICH MAY BE DISTURBED DUE TO ANY CHANGES REQUIRED

UNDER THE CONTRACT, SHALL BE RESTORED TO ITS ORIGINAL OPERATING

CONDITION AT NO COST TO OWNER. IF ANY EQUIPMENT TO REMAIN IS

DAMAGED DURING CONSTRUCTION, IT SHALL BE REPLACED WITH NEW (WITH

NO COST APPLIED TO OWNER).

27. FOR EXISTING PANELS MODIFIED AS PART OF THIS PROJECT, E.C. SHALL TEST

AND KEEP ALL EXISTING WORKING CIRCUIT BREAKERS AND SHALL USE THEM

FOR NEW EQUIPMENT, DEVICES, LIGHTING, AND/OR SPARES. E.C. SHALL

REPLACE NON-WORKING BREAKERS WITH NEW "IN KIND" BREAKERS. PROVIDE

BLANK COVERS/COVERPLATES FOR ALL EXPOSED CIRCUIT BREAKER SPACES

(THOSE WITHOUT INSTALLED CIRCUIT BREAKERS; EXPOSED BUS BARS) FOR

PERSONNEL PROTECTION.

26. ALL MATERIALS AND EQUIPMENT TO BE DEMOLISHED ARE TO BE DISPOSED OF

BY THE CONTRACTOR, UNLESS DIRECTED OTHERWISE BY THE OWNER.

CONTRACTOR IS RESPONSIBLE FOR DISPOSAL OF ALL MATERIALS IN

ACCORDANCE WITH LOCAL AND FEDERAL LAWS. ALL MATERIALS THAT ARE

CONSIDERED TO BE RECYCLABLE ARE TO BE RECYCLED ACCORDINGLY BY

THE CONTRACTOR.

27. REMOVAL OF BRANCH CIRCUITS IN ASSOCIATED PANELS SHALL BE

COORDINATED WITH THE REMOVAL OF EQUIPMENT IN SPECIFIED AREA. REFER

TO RENOVATION PLANS AND ELECTRICAL PANEL SCHEDULES FOR NEW

CIRCUITING ARRANGEMENT. ANY WIRING OR CIRCUITS BEING REVISED SHALL

MEET MINIMUM WIRE SIZES AS INDICATED ON DRAWINGS. ELECTRICAL

CONTRACTOR SHALL REMOVE WIRING/CONDUIT BACK TO SOURCE FROM

UNUSED OR ABANDONED CIRCUITS, LABEL CIRCUIT BREAKER AS "SPARE", AND

LEAVE IN THE "OFF" POSITION.

28. EXISTING PANELBOARD DIRECTORIES AFFECTED BY THE ALTERATION WORK

SHALL BE REPLACED WITH NEW "TYPED" DIRECTORIES, TO ACCURATELY

REFLECT THE BRANCH CIRCUIT WIRING MODIFICATIONS AND EXISTING

CONDITIONS.

ELECTRICAL DEMOLITION NOTES:

1. THESE DRAWINGS WERE PREPARED FROM INFORMATION TAKEN FROM THE

AVAILABLE BUILDING DRAWINGS, ARCHITECTURAL BACKGROUNDS PROVIDED

BY THE OWNER AND FIELD SURVEY INFORMATION COMPILED BY THE

ENGINEERING DESIGN TEAM FOR THE PURPOSE OF ENGINEERING DESIGN.

EXISTING CONDITIONS ARE SHOWN AS ACCURATELY AS POSSIBLE. THERE IS

THE POSSIBILITY THAT CONDITIONS SHOWN ARE NOT EXACTLY AS EXISTING.

CONTRACTOR SHALL VERIFY ALL DIMENSIONS, ELEVATIONS, LOCATIONS,

SIZES AND CONDITIONS AT THE SITE AND REPORT ANY DISCREPANCIES TO

THE ARCHITECT PRIOR TO BEGINNING INSTALLATION OR FABRICATION WORK.

1.1. DRAWINGS ARE DIAGRAMMATIC.

1.2. SHOULD IT APPEAR THAT THE WORK INTENDED TO BE DESCRIBED OR

RELATED WORK ARE NOT SUFFICIENTLY DETAILED OR EXPLAINED ON

THE DRAWINGS, OR IN THE SPECIFICATIONS, CONSULT THE ENGINEER

FOR NECESSARY CLARIFICATIONS, AND CONFORM TO THOSE

CLARIFICATIONS INSOFAR AS THEY ARE CONSISTENT WITH THE

ORIGINAL DRAWINGS AND SPECIFICATIONS. IN NO CASE SHALL WORK

PROCEED IN UNCERTAINTY.

1.3. EQUIPMENT ARRANGEMENTS ARE DESIGNED TO SHOW PREFERRED

CONFIGURATIONS TO SUIT KNOWN CONDITIONS. ACTUAL INSTALLATION

BY CONTRACTOR MAY BE ALTERED AS REQUIRED TO SUIT FIELD

CONDITIONS ENCOUNTERED DURING CONSTRUCTION WITHOUT

COMPROMISING THE INTENT OF THE ORIGINAL DESIGN.

1.4. THE CONTRACTOR SHALL CHECK AND VERIFY ALL DIMENSIONS AND

CONDITIONS AT SITE PRIOR TO STARTING WORK.

2. THE CONTRACTOR WILL BE RESPONSIBLE FOR ENSURING THAT ALL RULES

AND REGULATIONS, INCLUDING THOSE WHICH MAY BE ISSUED BY THE OWNER,

ARE BEING OBSERVED, PARTICULARLY WORKPLACE SAFETY AND THE

CONDUCT OF ALL THOSE EMPLOYED DIRECTLY AND INDIRECTLY BY HIM ON

THE PREMISES, AND THE OWNER'S EMPLOYEES WHO MAY BE IMPACTED OR

AFFECTED BY CONSTRUCTION ACTIVITIES. THE CONTRACTOR WILL INSTALL

SIGNAGE, BARRIERS, AND OTHER MEANS TO PROVIDE WARNING AND

PERSONNEL SAFETY. PLACEMENT OF THESE ITEMS WILL BE COORDINATED

WITH THE OWNER AND HIS ONGOING OPERATIONS AND WILL PROMPTLY BE

REVISED WHEN WORK IN A PARTICULAR AREA HAS BEEN COMPLETED.

2.1. DURING PERFORMANCE OF WORK, THE CONTRACTOR SHALL BE

RESPONSIBLE FOR PROVISION AND MAINTENANCE OF WARNING SIGNS,

LIGHT SIGNAL DEVICES, GUARD LIGHTS, BARRICADES, GUARD RAILS,

FENCES AND OTHER DEVICES, APPROPRIATELY LOCATED ON AND

AROUND THE JOB SITE WHICH GIVE PROPER AND UNDERSTANDABLE

WARNING TO PERSONS WITH REGARD TO HAZARDOUS CONDITIONS,

EQUIPMENT AND OPERATIONS BEING PERFORMED IN CONJUNCTION

WITH THE WORK.

3. THIS INSTALLATION WILL CONFORM TO ALL CODES AND THE REQUIREMENTS

OF FEDERAL, STATE, AND LOCAL REGULATORY AGENCIES HAVING

JURISDICTION INCLUDING, BUT NOT LIMITED TO THE FOLLOWING:

ELECTRICAL: NATIONAL ELECTRIC CODE: NFPA 70 - LATEST EDITION

4. ALL WORK WILL BE LAWFULLY EXECUTED IN A NEAT AND WORKMANLIKE

MANNER AND WILL BE COMPLETED IN ACCORDANCE WITH THE GOVERNING

CODES (ABOVE), INDUSTRY STANDARDS, AND IN CONFORMANCE WITH THE

MANUFACTURERS RECOMMENDATIONS AND REQUIREMENTS.

5. WORK UNDER THIS CONTRACT SHALL CONSIST OF THE CONTRACTOR

PROVIDING ALL LABOR, MATERIALS, AND SERVICES, INCLUDING WORK NOT

SPECIFICALLY SHOWN BUT REASONABLY IMPLIED. THIS SHALL INCLUDE

CUTTING, PATCHING AND RESTORATION OF EXISTING SURFACES DAMAGED

DURING THE CONSTRUCTION. CONTRACTOR SHALL ALSO PROVIDE ALL

EQUIPMENT SHOWN OR SPECIFIED OR AN APPROVED EQUIVALENT.

SUBSTITUTED EQUIPMENT OR MATERIALS SHALL NOT BE INSTALLED UNTIL

GIVEN WRITTEN APPROVAL BY THE OWNER.

6. EACH TRADE CONTRACTOR SHALL BE WHOLLY RESPONSIBLE FOR PROVIDING,

INSTALLING, AND MAINTAINING ALL TEMPORARY POWER SOURCES AND ANY

REQUIRED UTILITIES FOR ANY TEMPORARY MECHANICAL, PLUMBING, AND/OR

ELECTRICAL EQUIPMENT OR SYSTEMS (REQUIRED BY THEIR INDIVIDUAL

TRADES SCOPE OF WORK) DURING THE COURSE OF CONSTRUCTION AND

PHASING/SEQUENCING OF WORK. THIS SHALL INCLUDE BUT NOT BE LIMITED

TO THE INSTALLATION AND ROUTING OF: TEMPORARY FEEDERS, CONDUIT,

TRANSFORMERS, ON-SITE GENERATOR PACKAGES, OVERCURRENT

PROTECTION DEVICES, DISCONNECTS, CONNECTIONS AND DISCONNECTION

OF EQUIPMENT, ETC. ALL ELECTRICAL WORK MUST BE PERFORMED BY A

LICENSED ELECTRICIAN. REFER TO SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL BE RESPONSIBLE FOR COSTS INCURRED FOR

NONCOMPLIANCE WITH THESE CONTRACT DOCUMENTS. CONTRACTOR WILL

NOT BE ALLOWED CHANGE ORDERS FOR PROBLEMS ARISING FROM NEGLECT

OF PROVISIONS INCLUDED IN THESE CONDITIONS.

8. MAINTAIN ORDERLY HOUSEKEEPING DURING CONSTRUCTION, AND UPON

SUBSTANTIAL COMPLETION PERFORM FINAL CLEANUP. REMOVE

CONSTRUCTION RUBBISH, SCAFFOLDING, EQUIPMENT, TEMPORARY

PROTECTION, TEMPORARY FIELD STRUCTURES, AND OTHER MATERIALS OR

EQUIPMENT THAT WAS REQUIRED IN CONNECTION WITH THE CONSTRUCTION,

BUT NOT A PERMANENT PART THEREOF.

9. THOSE PERFORMING WORK AS A CONTRACTOR MUST EXAMINE SUBSTRATES

AND CONDITIONS UNDER WHICH THE WORK IS TO BE PERFORMED AND NOTIFY

THE CONTRACTOR IN WRITING, OF CONDITIONS DETRIMENTAL TO THE

PROPER AND TIMELY COMPLETION OF THE WORK. COMMENCEMENT OF WORK

BY A TRADE ON A SURFACE OR CONSTRUCTION SHALL IMPLY ACCEPTANCE OF

SUCH SURFACE OR CONSTRUCTION. DO NOT PROCEED WITH INSTALLATION

UNTIL UNSATISFACTORY CONDITIONS HAVE BEEN CORRECTED.

10. THE CONTRACTOR SHALL SECURE ALL APPLICATIONS AND PAY ANY AND ALL

FEES AS REQUIRED. THE CONTRACTOR SHALL GIVE ALL NECESSARY NOTICES

AND CERTIFICATES OF INSPECTION REQUIRED BY THE AUTHORITIES HAVING

JURISDICTION. DELIVER ALL CERTIFICATES AND APPROVALS TO THE OWNER

AGENT PRIOR TO FINAL ACCEPTANCE OF THE WORK. THE CONTRACTOR MUST

FILE NECESSARY DRAWINGS, PREPARE DOCUMENTS AND MAKE

APPLICATIONS FOR EACH REQUIRED INSPECTION, PRIOR TO COMMENCING

WORK TO AVOID DELAYS DURING CONSTRUCTION.

11. CONTRACTOR SHALL SUBMIT SHOP DRAWINGS AND MANUFACTURERS DATA

SHEETS ON ALL EQUIPMENT AND MATERIALS SPECIFIED ON DRAWINGS FOR

APPROVAL BY OWNER OR AGENT FOR THE OWNER. THESE DRAWINGS OR

SHEETS SHALL CONTAIN ALL NECESSARY DATA, I.E., MANUFACTURER,

CATALOG NUMBER, SIZE, DIMENSIONS, CAPACITY, WIRING DETAILS AND ALL

OTHER ENGINEERING DATA AND DETAILS NECESSARY FOR COMPLETE

CLARITY AND INSTALLATION.

12. THE CONTRACTOR SHALL KEEP ONE SET OF THE LATEST ISSUE OF DRAWINGS

WHICH SHALL REFLECT THE ACTUAL INSTALLED CONDITIONS AND

CONNECTIONS OF ALL EQUIPMENT AND DEVICES. THE CONTRACTOR SHALL

PROVIDE COPIES OF ALL MAINTENANCE INFORMATION AND INSTRUCTIONS

RECEIVED WITH EQUIPMENT AND SYSTEMS. ALL "AS-BUILT" DRAWINGS AND

MISCELLANEOUS INFORMATION SHALL BE GIVEN TO THE OWNER AND

ENGINEER AT COMPLETION OF WORK. THE CONTRACTOR SHALL GUARANTEE

ALL MATERIAL AND LABOR TO BE FREE FROM DEFECTS FOR A ONE YEAR

PERIOD FROM THE TIME OF OWNER ACCEPTANCE. ANY DEFECTS OCCURRING

DURING THIS PERIOD SHALL BE CORRECTED BY THE CONTRACTOR AT NO

ADDITIONAL COST TO THE OWNER.

13. CONTRACTOR IS TO PROVIDE ALL REQUIRED SCAFFOLDING, LADDERS,

RIGGING, HOISTING AND ALL OTHER EQUIPMENT REQUIRED FOR THE

INSTALLATION OF THEIR WORK.

14. ESTABLISH PASSAGE CLEARANCES REQUIRED TO DELIVER, INSTALL AND

ERECT ALL REQUIRE EQUIPMENT. IF STRUCTURES, EQUIPMENT AND SYSTEMS

MUST BE ALTERED TO PROVIDE PASSAGE OF EQUIPMENT, THE CONTRACTOR

SHALL RESTORE STRUCTURES, EQUIPMENT AND SYSTEMS TO THEIR ORIGINAL

CONDITION AT THE CONTRACTOR'S EXPENSE; INCLUDING REMOVING AND

REPLACEMENT OF ALL CEILING AS REQUIRED TO COMPLETE THE WORK.

15. THE CONTRACTOR SHALL REPLACE ALL FIREPROOFING MATERIAL, INCLUDING

SPRAY APPLIED AND MASONRY TYPES, THAT IS REMOVED TO ACCOMMODATE

EQUIPMENT, HANGERS, ANCHORS, ETC. ALL FIREPROOFING MATERIAL THAT

IS INTEGRAL TO THE RATING OF AN EXISTING FIRE-RATED ASSEMBLY SHALL

BE REPLACED SO THAT THE FULL FIRE RATING IS PRESERVED.

GENERAL NOTES AND CONDITIONS:

1. ALL ELECTRICAL WORK SHALL BE COORDINATED WITH THE CONSTRUCTION

MANAGER/GENERAL CONTRACTOR AND ALL OTHER DISCIPLINES INVOLVED IN

THIS PROJECT.

1.1. CONTRACTOR SHALL REVIEW ALL TRADES' CONTRACT DOCUMENTS AND

APPLICABLE SHOP DRAWINGS TO DETERMINE SPECIFIC MOUNTING

LOCATIONS FOR ELECTRICAL EQUIPMENT.

1.2. VERIFY EXACT LOCATIONS AND MOUNTING OF ALL LIGHT FIXTURES,

SWITCHES, RECEPTACLES, OUTLETS, FIRE ALARM DEVICES, VOICE/DATA

DEVICES AND OTHER EQUIPMENT WITH ARCHITECTURAL DRAWINGS AND

IN THE FIELD PRIOR TO ROUGH-IN. IN CENTERING OUTLETS AND

LOCATION BOXES, ALLOW FOR OVERHEAD PIPES, DUCTS AND

MECHANICAL EQUIPMENT VARIATIONS IN FIREPROOFING AND

PLASTERING, WINDOW AND DOOR TRIM, PANELING, HUNG CEILINGS AND

THE LIKE, AND CORRECT ANY INACCURACY RESULTING FROM FAILURE

TO DO SO WITHOUT EXPENSE TO OWNER.

1.3. LOCATIONS INDICATED FOR LOCAL WALL SWITCHES ARE SUBJECT TO

MODIFICATIONS AT OR NEAR DOORS. COORDINATE WITH

ARCHITECTURAL AND/OR ENGINEERING PLANS AND INSTALL SWITCH ON

SIDE OPPOSITE HINGE. VERIFY FINAL HINGE LOCATIONS IN FIELD PRIOR

TO SWITCH OUTLET INSTALLATION.

2. THE CONDUITS SHOWN ON THESE DRAWINGS ARE DIAGRAMMATIC IN NATURE,

THEY SHOW THE GENERAL ARRANGEMENT AND SIZE OF THE CONDUITS. THEY

ARE NOT INTENDED TO SHOW EVERY OFFSET OR INTERFERENCE THAT MAY

BE ENCOUNTERED. CONTRACTOR IS RESPONSIBLE FOR ROUTING ALL

CONDUIT IN THE MOST EFFICIENT MANNER IN ACCORDANCE WITH PROJECT

SPECIFICATIONS.

3. ALL CONTRACTOR SUPPLIED MATERIALS SHALL BE NEW AND UL APPROVED

(OR APPROVED BY ANOTHER NATIONALLY RECOGNIZED ORGANIZATION).

4. ALL EQUIPMENT SHALL BE INSTALLED IN A NEAT AND WORKMANLIKE MANNER,

RECTILINEAR TO BUILDING STRUCTURE. HORIZONTAL OR CROSS RUNS IN

PARTITIONS AND WALLS NOT PERMITTED.

5. UNLESS OTHERWISE STATED, ALL ABOVE GROUND WIRING SHALL BE IN

CONDUIT, 3/4 INCH MINIMUM SIZE FOR ELECTRIC SERVICES. ALL CONDUIT

BENDS SHALL BE OF THE LONG RADIUS TYPE. ALL OUTDOOR WIRING SHALL BE

IN CONDUIT, 3/4 INCH MINIMUM SIZE. ALL MOTORS AND TRANSFORMERS SHALL

HAVE FLEXIBLE CONNECTIONS TO MINIMIZE VIBRATION. REFER TO

ELECTRICAL SPECIFICATIONS FOR ADDITIONAL INFORMATION.

6. ALL WIRING SHALL BE RUN CONCEALED IN CONDUIT UNLESS SPECIFIED

OTHERWISE.

7. CONTRACTOR SHALL USE TRAPEZE TO SUPPORT MULTIPLE CONDUITS FROM

BUILDING STEEL

8. SECURE ALL SUPPORTS TO BUILDING STRUCTURE BY STEEL FOR VERTICAL

SUPPORT AND BY MEANS OF TOGGLE BOLTS ON HOLLOW MASONRY UNITS,

EXPANSION SHIELDS IN CONCRETE OR BRICK. MACHINE SCREWS ON METAL

SURFACE, AND WOOD SCREWS ON WOOD CONSTRUCTION. NAILS, RAWL OR

WOOD PLUGS NOT PERMITTED. SUPPORT HORIZONTAL RUNS OF METALLIC

CONDUITS NOT MORE THAN 10 FT. APART. SUPPORT RACEWAY RISERS AT

EACH FLOOR LEVEL. RUN EXPOSED RACEWAYS PARALLEL WITH OR AT RIGHT

ANGLES TO WALLS.

9. ALL CONDUIT INSTALLATIONS CROSSING EXPANSION JOINTS SHALL HAVE

EXPANSION OR EXPANSION/DEFLECTION TYPE FITTINGS AS REQUIRED. NOTE:

FOR THE EXACT LOCATIONS OF EXPANSION JOINTS, SEE OWNER FOR

EXISTING STRUCTURAL DRAWINGS.

10. ALL UNDERGROUND CONDUITS SHALL BE SEALED TO PREVENT THE ENTRY OF

WATER OR GASES.

11. PASS RACEWAYS OVER WATER, STEAM, OR OTHER PIPING WHEN PULL BOXES

ARE NOT REQUIRED. NO RACEWAY SHALL BE INSTALLED WITHIN 6 IN. OF

STEAM OR HOT WATER PIPES, OR APPLIANCES, EXCEPT CROSSINGS WHERE

RACEWAY SHALL BE AT LEAST 2 IN. FROM PIPE COVER.

12. FURNISH PULL STRING IN EACH RACEWAY RUN OVER 10 FT IN WHICH WIRING

IS NOT INSTALLED.

13. CUT STEEL CONDUIT ENDS SQUARE, REAM SMOOTH, PAINT MALE THREADS OF

FIELD THREADED CONDUIT WITH GRAPHITE BASE PIPE COMPOUND. DRAW UP

TIGHT WITH CONDUIT COUPLINGS.

14. ALL WIRING SHALL BE STRANDED COPPER CONDUCTOR. MINIMUM SIZE #12

AWG (POWER) & 14 AWG (CONTROL), 600 VOLT INSULATION THW/THWN.

REFERENCE SPECIFICATIONS FOR MORE INFORMATION.

15. GROUNDING SHALL BE INSTALLED IN ACCORDANCE WITH THE NATIONAL

ELECTRICAL CODE REGARDING ELECTRODE, GROUNDING AND BONDING

REQUIREMENTS FOR SERVICE, EQUIPMENT AND ENCLOSURES. ALL

EQUIPMENT SHALL BE PROVIDED WITH A SEPARATE GROUNDING

CONDUCTOR.

16. CONNECT CONDUIT TO MOTOR CONDUIT TERMINAL BOXES WITH FLEXIBLE

CONDUIT (MINIMUM 18 IN. LENGTH AND 50% SLACK). DO NOT TERMINATE IN OR

FASTEN RACEWAYS TO MOTOR FOUNDATION.

17. PROVIDE SEPARATE RACEWAYS FOR CONDUCTORS OF NORMAL AND

EMERGENCY CIRCUITS. IN COMMON BOXES, PROVIDE BARRIERS BETWEEN

EMERGENCY AND NORMAL WIRING.

18. LEAVE WIRE SUFFICIENTLY LONG TO PERMIT MAKING FINAL CONNECTIONS.

19. WIRE COLOR CODING: PER CODE. WHERE COLOR-CODED CABLE IS NOT

AVAILABLE, CERTIFY IN WRITING AND REQUEST PERMISSION FOR OVERLAP

COLOR TAPING OF CONDUCTORS (MINIMUM LENGTH 6") IN ACCESSIBLE

LOCATIONS. COLOR CODING, ONCE SELECTED, MUST BE USED CONSISTENTLY

FOR THE ENTIRE PROJECT.

20. PULL NO THERMOPLASTIC WIRES AT TEMPERATURES LOWER THAN 32°F.

21. PROVIDE CABLE SUPPORTS FOR WIRE IN RISER CONDUITS AS REQUIRED BY

CODE.

22. ALL SWITCHES SHALL BE MOUNTED AT 48" (TOP OF THE TOGGLE SWITCH)

ABOVE THE TOP OF FINISHED FLOOR, UNLESS OTHERWISE NOTED. ALL

RECEPTACLES SHALL BE MOUNTED AT 18" ABOVE THE TOP OF FINISHED

FLOOR, UNLESS OTHERWISE NOTED.

23. PROVIDE PULL BOXES AS INDICATED AND WHEREVER NECESSARY TO

FACILITATE PULLING OF WIRE AND COORDINATE LOCATIONS WITH OTHER

TRADES.

24. FOR EMPTY RACEWAY RUNS, PROVIDE PULL BOXES EVERY 100FT AND AS

INDICATED. COORDINATE LOCATIONS WITH OTHER TRADES.

25. JUNCTION AND PULL BOXES: LOCATE GENERALLY NOT EXPOSED IN FINISHED

SPACES. WHERE NECESSARY, REROUTE CONDUITS OR MAKE OTHER

ARRANGEMENTS FOR CONCEALMENT. COVERS OF JUNCTION AND PULL

BOXES SHALL BE ACCESSIBLE.

26. SUPPORT JUNCTION AND PULL BOXES INDEPENDENTLY TO BUILDING

STRUCTURE WITH NO WEIGHT BEARING ON CONDUITS.

27. FIRESTOP SHALL BE INSTALLED WHENEVER WIRING OR RACEWAYS CROSS

FIRE RATED WALLS.

28. PANELBOARDS, DISCONNECTS, AUTOMATIC TRANSFER SWITCHES, ETC.,

SHALL BE MOUNTED SO THAT THE DISTANCE FROM THE TOP CIRCUIT

BREAKER OPERATING HANDLE, TO THE TOP OF THE FINISHED FLOOR SHALL

NOT EXCEED 6'-6" (MAX.).

29. ALL PANELS SHALL BE BALANCED AS EVENLY AS POSSIBLE ACROSS PHASES.

ALL PANELS SHALL HAVE PERMANENT DIRECTORIES. CIRCUIT CHANGES

SHALL BE REFLECTED ON "AS BUILT" DRAWINGS.

30. ALL SURFACE MOUNTED PANELS AND PANELBOARDS INSTALLED ON THE

INSIDE FACE OF EXTERIOR WALLS, ABOVE GRADE OR IN OTHER LOCATIONS

CONSIDERED AS DAMP, SHALL BE MOUNTED SO AS TO MAINTAIN A 1/4" AIR

SPACE BETWEEN THE ENCLOSURE AND THE FACE OF THE WALL.

31. ALL NEW ELECTRICAL PANELS SHALL BE LOCKABLE. PROVIDE OWNER WITH

TWO (2) KEYS PER PANEL.

32. MCC OR PANEL COMPARTMENT DESIGNATIONS ARE AS INDICATED BELOW:

32.1. BLANK- NOT INTENDED FOR USE, COVERPLATE ONLY.

32.2. SPACE- CONTAINS NECESSARY BUS AND HARDWARE FOR FUTURE

ADDITION OF BREAKERS OR STARTERS WITHIN RANGE SHOWN.

32.3. SPARE- CONTAINS A COMPLETE BREAKER OR STARTER INSTALLED, SIZE

AS INDICATED, AVAILABLE FOR FUTURE USE.

33. EXACT LOCATION OF MECHANICAL EQUIPMENT THAT REQUIRE ELECTRICAL

CONNECTIONS ARE SHOWN ON THE MECHANICAL DRAWINGS.

34. ALL DEVICES SHALL BE ADEQUATELY IDENTIFIED WITH PERMANENT LABELS

OR TAGS. WIRING SHALL BE IDENTIFIED AS TO PHASING AND CONDUCTOR

IDENTIFICATION.

35. CONDUIT HOMERUNS SHOWN ON THE DRAWING WITH MORE THAN 3 CURRENT

CARRYING CONDUCTORS ARE SHOWN DIAGRAMMATICALLY. CONTRACTOR

SHALL NOT INSTALL MORE THAN 3 CURRENT CARRYING CONDUCTORS IN A

RACEWAY UNLESS DONE SO STRICTLY BY THE NATIONAL ELECTRIC CODE.

36. EACH BRANCH CIRCUIT HOMERUN SHALL HAVE NO MORE THAN THREE

CIRCUITS. EACH BRANCH CIRCUIT HOMERUN SHALL HAVE A SEPARATE

NEUTRAL & GREEN INSULATED EQUIPMENT GROUNDING CONDUCTOR.

37. MULTI-GANG BACKBOXES FOR DIFFERENT VOLTAGES AND TYPES OF

EMERGENCY AND NORMAL BRANCH WIRING DEVICES SHALL HAVE DIVIDERS

BETWEEN DEVICES.

38. ALL TEMPORARY WIRING, LIGHTING AND POWER CIRCUITS AND DEVICES

SHALL BE INSTALLED TO MEET THE LATEST REQUIREMENTS OF THE NATIONAL

ELECTRICAL CODE, LOCAL, STATE AND FEDERAL REQUIREMENTS FOR SUCH

TEMPORARY INSTALLATION.

39. THE ELECTRICAL CONTRACTOR SHALL ENSURE THAT RECEPTACLES USED

FOR HAND TOOLS AND OTHER MISCELLANEOUS EQUIPMENT SHALL BE

INSTALLED WITH GROUND FAULT INTERRUPTER OR OTHER APPROVED AND

RECOGNIZED INTERRUPTING SENSORS.

40. EXISTING FIREPROOFING PENETRATED OR DAMAGED DURING WORK SHALL BE

BROUGHT BACK TO EXISTING RATING UPON COMPLETION OF WORK.

41. THE COMPLETE INSTALLATION SHALL BE TESTED AT COMPLETION OF WORK,

TO BE FREE OF GROUNDS AND SHORT CIRCUITS CONDITIONS. ALL INTERLOCK

CIRCUITS SHALL BE TESTED TO VERIFY CORRECT OPERATION OF EACH

DEVICE. ALL ROTATING EQUIPMENT SHALL BE JOGGED TO VERIFY CORRECT

ROTATION BEFORE PERMANENTLY ENERGIZING.

42. CONTRACTOR SHALL COORDINATE AND SCHEDULE ALL WORK AND

SHUTDOWNS OF EQUIPMENT WITH FACILITY.

43. EXCAVATION FOR UNDERSLAB OR UNDERGROUND INSTALLATION OF

CONDUITS SHALL BE APPROACHED WITH EXTREME CAUTION SO AS NOT TO

DAMAGE EXISTING UNDERGROUND PIPING, WIRING AND CONDUITS.

44. ELECTRICAL CONTRACTOR SHALL PROVIDE CONSTRUCTION

MANAGER/GENERAL CONTRACTOR A SURFACE PENETRATING RADAR SURVEY

FOR THE PURPOSE OF LOCATING ALL UNDERGROUND (OR IN-SLAB) CONDUITS,

PIPING, UTILITIES, STRUCTURAL MEMBERS, ETC. IN ALL AREAS WHERE SLAB

CUTTING MAY OCCUR (FOR THE PURPOSES OF ELECTRICAL WORK REQUIRED).

SURVEY MUST BE COMPLETED TWO WEEKS PRIOR TO CUTTING OF ANY SLAB.

THE CONTRACTOR SHALL ASSUME THE RESPONSIBILITY (AND ALL

ASSOCIATED COSTS) OF REPAIRING AND/OR REPLACING ANY SYSTEMS

DAMAGED BY THE SLAB CUTTING PROCEDURES, WHEN PREVENTATIVE

MEASURES WERE NOT CONSIDERED OR UTILIZED. COST FOR SURVEY(S)

SHALL BE SUBMITTED AS A SEPARATE LINE ITEM PRICE (WHEN APPLICABLE).

45. THE ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING VOLTAGE,

PHASE, MCA, MOCP, REQUIRED FOR ALL EQUIPMENT PROVIDED BY OTHER

CONTRACTORS PRIOR TO PURCHASING AND INSTALLING CONDUCTORS,

BREAKERS, DISCONNECTS, CONDUIT, ETC. VERIFY RATINGS WITH FINAL,

APPROVED CONTRACTOR EQUIPMENT SUBMITTALS AND EQUIPMENT

NAMEPLATES DIRECTLY WITH THE PROVIDING CONTRACTOR.

46. UNLESS NOTED OTHERWISE WITHIN THE PROJECT CONSTRUCTION

DOCUMENTS AND SPECIFICATIONS, ALL NEW ELECTRICAL DEVICES INDICATED

ON THE ELECTRICAL PLANS SHALL BE PROVIDED BY THE ELECTRICAL

CONTRACTOR (EXAMPLE: DISCONNECT SWITCHES, CIRCUIT BREAKERS,

WIRING, CONDUIT, ETC.). VARIABLE FREQUENCY DRIVES, VFD CONTROL

PANELS, DISCONNECT SWITCHES, COMBINATION MOTOR

STARTER/DISCONNECTS AND ASSOCIATED COMPONENTS FOR NEW

EQUIPMENT PROVIDED BY OTHERS SHALL BE PROVIDED BY THE

CORRESPONDING CONTRACTOR AND INSTALLED BY THE ELECTRICAL

CONTRACTOR (WHEN NOT FACTORY INSTALLED).

47. IT IS THE RESPONSIBILITY OF THE ELECTRICAL CONTRACTOR TO REVIEW THE

ELECTRICAL PLANS AND SPECIFICATIONS, AS WELL AS ALL RELATED PROJECT

PLANS AND SPECIFICATIONS FROM OTHER DISCIPLINES, TO BECOME FAMILIAR

WITH THE FULL PROJECT SCOPE AND COORDINATED RESPONSIBILITIES.

CONFLICT OF INTENDED RESPONSIBILITIES SHALL BE BROUGHT TO

ENGINEERS ATTENTION, PRIOR TO SUBMISSION OF BID.

48. DURING THE COURSE OF CONSTRUCTION, COORDINATION AND FINAL

TURNOVER, IT IS THE RESPONSIBILITY OF THE ELECTRICAL CONTRACTOR TO

WORK CLOSELY WITH ALL CONTRACTORS AND TRADESMEN IN ORDER TO

ENSURE A SMOOTH RUNNING AND CAREFULLY COORDINATED INSTALLATION.

49. ELECTRICAL CONTRACTOR SHALL BE RESPONSIBLE TO COORDINATE WITH

OTHER TRADES FOR ITEMS IN THEIR SCOPE OF WORK WHICH COULD REQUIRE

ADDITIONAL ELECTRICAL WORK, (DISCONNECTION, RECONNECTION, ETC.) AND

ARE NOT INDICATED ON THE ELECTRICAL DRAWINGS.

50. ALL MECHANICAL/PLUMBING EQUIPMENT CONTROLS RATED 10V AND ABOVE

SHALL BE WIRED BY A LICENSED ELECTRICIAN.

GENERAL ELECTRICAL NOTES:

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

1. REFER TO SHEETS E-001 AND E-002 FOR SYMBOLS, ABBREVIATIONS AND

NOTES.

2. REFER TO SHEET ES102 AND CIVIL DRAWINGS FOR LOCATION OF ALL NEW

AND EXISTING DUCTBANKS AND MANHOLES.

3. ALL MEDIUM VOLTAGE CABLES SHOWN AS DEMOLISHED ON THIS PLAN SHALL

BE PULLED OUT OF THE UNDERGROUND DUCTBANK AND REMOVED AFTER

NEW DUCTBANK IS CONSTRUCTED. DUCTBANKS AND MANHOLES SHALL BE

EXISTING TO REMAIN AS PATHWAYS FOR NEW MEDIUM VOLTAGE CABLES OR

AS SPARE PATHWAYS. CONTRACTOR SHALL FIELD VERIFY VIABILITY OF

EXISTING CONDUIT PATHWAY FOR REUSE WITH NEW MV CABLE. PROVIDE

SCOPING OF EXISTING CONDUIT TO ENSURE INTEGRITY.

4. TO MINIMIZE DISRUPTION TO THE CAMPUS, WORK SHOWN ON THIS PLAN WILL

NOT PROCEED UNTIL NEW UNDERGROUND CONCRETE ENCASED NORMAL

POWER DUCTBANK IS INSTALLED IN ITS ENTIRETY AND NEW CABLES ARE

PULLED.

GENERAL SHEET NOTES:

ELECTRICAL

DEMOLITION

CAMPUS SINGLE LINE DIAGRAM

ED601

MJRLIB

SCALE: NTS

DEMOLITION

EXISTING TO

REMAIN

(E) MAIN SWITCHGEAR 35, BUILDING 35A

12470V, 3Ø, 4W, 34KA MOMENTARY BRACING

TIE BREAKER

1200AF

1200AT

3P

PAWNEE

LINE 12-12

M1

EASTBOROUGH

LINE 12-34

(E)

SELECTOR

SWITCH 2

(E) XFMR

500 KVA

12470-480/2770V

CATH LAB

BLDG 2

(H1)

BLDG 19

(E)

SELECTOR

SWITCH 61

(E) XFMR

1000 KVA

12470-480/2770V

(SWGR 61)

BLDG 61

(E)

SELECTOR

SWITCH 55

(E)

SELECTOR

SWITCH 19

(E) XFMR

500 KVA

12470-480/2770V

(E)

SELECTOR

SWITCH 34

(E) XFMR

1000 KVA

12470-480/2770V

(SWGR 34A)

BLDG 34

(E)

SELECTOR

SWITCH 41

(E) XFMR 41

225 KVA

12470-480/2770V

(ML4B)

BLDG 4

(E)

SELECTOR

SWITCH 49

(E)

SELECTOR

SWITCH 42

(E) XFMR

500 KVA

12470-480/2770V

(SWGR 61)

BLDG 5,6,7

(E)

SELECTOR

SWITCH 60

(E) XFMR

300 KVA

12470-208/120V

(SWGR 61)

BLDG 60

(E) SELECTOR

SWITCH 53

NEAR BLDG 11

(SWGR 53)

NEAR BLDG 11

(SWGR 49)

BLDG 1

(SWGR 55)

BLDGS 3 & 26

NEW/TEMPORARY

WORK

1200AF

1200AT

3P

M1

(E) XFMR

1000 KVA

480-12470V

SOLAR SYSTEM

SPACE SPACE

EXISTING MEDIUM VOLTAGE FEEDER TAG (TYPICAL)

SEE ES101 FOR LOCATIONS OF FEEDERS WITHIN

EXISTING DUCTBANKS.

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

1. REFER TO SHEETS E-001 AND E-002 FOR SYMBOLS, ABBREVIATIONS AND

NOTES.

2. REFER TO SHEET ES101 FOR LOCATION OF ALL GENERATORS THAT SHALL BE

DEMOLISHED AS PART OF THIS PROJECT SCOPE.

3. ALL EQUIPMENT AND PATHWAYS SHOWN ON THIS DRAWING SHALL BE

EXISTING TO REMAIN, UNLESS OTHERWISE NOTED.

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1. AFTER THE EMERGENCY SYSTEM LOOP AND NEW MEDIUM VOLTAGE

GENERATORS ARE INSTALLED, TESTED, COMMISSIONED AND FULLY

OPERATIONAL, BUILDING GENERATOR DEMOLITION CAN BE STARTED.

ELECTRICAL CONTRACTOR SHALL PROVIDE A TEMPORARY GENERATOR AS

REQUIRED TO POWER THE EMERGENCY SYSTEM OF EACH BUILDING WHILE

NEW TRANFORMER IS BEING SET, TESTED AND FINAL CONNECTIONS ARE

MADE. CUTOVERS SHALL OCCUR ON WEEKENDS. NOTIFY VA COR AT LEAST 2

WEEKS IN ADVANCE OF ANY EMERGENCY POWER OUTAGE. FEEDER TO

GENERATOR SHALL BE EXISTING TO REMAIN FOR REUSE WITH TEMPORARY

GENERATOR AND NEW TRANSFORMER.

TEMPORARY GENERATOR CONNECTION WILL VARY FROM BUILDING TO

BUILDING AND SHALL BE EVALUATED AT EACH SITE INDEPENDENTLY BY E.C. IN

BUILDINGS WHERE THERE IS A MAIN EMERGENCY PANEL, THE TEMPORARY

GENERATOR SHALL BE LUGGED ONTO THE MAIN CIRCUIT BREAKER OR PANEL

BUS. WHERE THE GENERATOR IS WIRED DIRECTLY TO THE TRANSFER SWITCH,

TEMPORARY GENERATOR SHALL BE LUGGED TO THE (E) ATS.

2. MAINTAIN EXISTING SIGNALING WIRE CONDUIT FROM ATS TO GENERATOR FOR

EXTENSION TO NEW GENERATOR BUILDING VIA NEW UNDERGROUND

CONCRETE ENCASED DUCTBANK. ELECTRICAL CONTRACTOR SHALL PROVIDE

TWO (2) NEW #10 TWISTED PAIR STRANDED CONTROL WIRES BETWEEN

EXISTING ATS AND NEW MEDIUM VOLTAGE GENERATORS. NEW CONTROL

WIRES SHALL BE RUN IN THE NEW LOW VOLTAGE DUCTBANK. REFER TO ES102

AND CIVIL DRAWINGS FOR FURTHER INFORMATION ON DUCTBANK ROUTING.

ELECTRICAL

DEMOLITION BUILDING

SINGLE LINE DIAGRAMS

ED602

MJRTO

DEMOLITION

EXISTING TO

REMAIN

NEW/TEMPORARY

WORK

(D) GENERATOR "62"

352KW

480-VOLT

G

SCALE: NTS

(E) ATS-20

480-VOLT, 225A

CRITICAL

(E) DISTRIBUTION

(E) ATS-21

480-VOLT, 225A

EQUIPMENT

(E) DISTRIBUTION

(E) ATS-22

480-VOLT, 100A

LIFE SAFETY

(E) DISTRIBUTION

(E) ATS-23

480-VOLT, 100A

CRITICAL

(E) DISTRIBUTION

(D) GENERATOR "26"

300KW

208-VOLT

G

SCALE: NTS

(D) GENERATOR "31"

242KW

208-VOLT

G

SCALE: NTS

(E) ATS-3

208-VOLT, 400A

LIFE SAFETY

(E) DISTRIBUTION

1200A

(E) PANEL "31"

400A

(E) ATS-1

208V, 400A

EQUIPMENT

(E) DISTRIBUTION

400A 200A 400A 200A

(E) ATS-1FP

208-VOLT

(E) ATS-2

208-VOLT, 400A

CRITICAL

(E) DISTRIBUTION

(E) ATS-2FP

208-VOLT

(E) FIRE PUMP40

(E) FIRE

PUMP

(D) GENERATOR "31A"

242KW

240-VOLT

G

SCALE: NTS

(E) ATS-4

240-VOLT, 800A

EQUIPMENT

(E) DISTRIBUTION

(D) GENERATOR "1B & 2"

500KW

480-VOLT

G

SCALE: NTS

(E) ATS-6

480-VOLT, 600A

EQUIPMENT

(E) DISTRIBUTION

(E) PANEL "1B & 2"

600A

(E) ATS-5

480-VOLT, 225A

CRITICAL

(E) DISTRIBUTION

250A

SCALE: NTS

(D) TEMPORARY ROLLUP

GENERATOR "21"

65KW

208-VOLT

G

(D) MTS-21

208-VOLT

EXTERIOR

(E) DISTRIBUTION

SCALE: NTS

(D) GENERATOR "5"

80KW

208-VOLT

G

(E) ATS-BUILDING 5

208-VOLT

LIFE SAFETY

(E) DISTRIBUTION

(E) ATS-10

208-VOLT

(E) DISTRIBUTION

SCALE: NTS

(D) GENERATOR "13"

115KW

208-VOLT

G

(E) ATS-8

240-VOLT

(E) DISTRIBUTION

(E) PANEL "2"

250A

(E) ATS-9

208-VOLT

(E) DISTRIBUTION

400A

(E) XFMR

9-KVA

208V-240V

(D) GENERATOR "34"

800KW

480-VOLT

G

SCALE: NTS

(E) ATS-16

480-VOLT, 225A

LIFE SAFETY

(E) DISTRIBUTION

1200A

(E) PANEL "34"

225A

(E) ATS-18

208-VOLT, 150A

CRITICAL

(E) DISTRIBUTION

70A 400A 400A 600A

(E) ATS-14

480-VOLT

400A

EQUIPMENT

(E) DISTRIBUTION

(E) ATS-15

480-VOLT

600A

(E) ATS-12

480-VOLT, 600A

EQUIPMENT

(E) DISTRIBUTION

(E) DISTRIBUTION (E) DISTRIBUTION

(E) XFMR-60

45-KVA

480V-208V

(E) ATS-17

208-VOLT, 225A

LIFE SAFETY

(E) DISTRIBUTION

(E) ATS-19

208-VOLT, 200A

ZENITH

(E) DISTRIBUTION

100A

(E) ATS-11

480-VOLT, 225A

CUMMINS

(E) DISTRIBUTION

(E) INFILL PROJECT ATS

ASCO 7000

208-VOLT

(E) DISTRIBUTION

(E) ATS-13

480-VOLT

400A

CRITICAL

WW

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

F

IR

E L A

N E

FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE FIRELANE

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

FIRELANE

F

IR

E L A

N E

FIRELANE

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELANE

FIRELANE

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

(D)2000KVA PAD MOUNTED XFMR

UTILITY TRANSFORMERS

(D)15KV SWITCHGEAR

MH-2A

MH-2B

(D)LOAD BANK

(D)PANEL 03-35A-01-2

MH-2

MH-3

SELECTOR SWITCH "53":

- XFMR 44562, T-43, 208V

- XFMR T-44, 240V

(D) GENERATOR "5"

100KVA, 80KW, 208V

BLDGS 5, 6 & 7

SELECTOR SWITCH "42"

EE 9811

SELECTOR SWITCH "60":

- FEEDERS 1, 2, & 3

MH-5

MH-5.5

SELECTOR SWITCH "41" BYPASS

MH-8

MH-7

MH-4B

SELECTOR SW "34"

XFMR 44541 TL-23

(D) GENERATOR "34"

800KW, 480V

BUILDINGS 24 & 60

SELECTOR SW "49"

BLDG 1:

- 49-6, 5, 4, 3, 2, 49

(D) 2 GENERATORS "31" & "31A"

303KVA, 242 KW, 208V & 240V

BLDGS 1, 1A, 2, 4 & 19

OHM-8

OHM-9

SELECTOR SW "55"

SWGR

(D) GENERATOR "26"

300KW, 208V

BLDGS 3, 26, 29 & 61

(D) GENERATOR "1B & 2"

629KVA, 500KW, 480V

SELECTOR SW "2" &

XFMR 137631, TL-36 B2

SELECTOR SW "19" &

XFMR 54947, TL-32, 500KVA

(D) GENERATOR "62"

352-KW, 480V

MH-6

MH-11

HV-10

F1 F7F2 F3

F5F4

F1 F7F2

F3 F5F4

F1 F3

F1 F3

F1 F3

F1 F3

F7 F2F4

F5F2 F4

F7 F5F2

F4

F5 F7

F5 F7

F2 F4

F2 F4

F2 F4

F5 F7

(D) TEMPORARY ROLLUP

GENERATOR "21"

65KW, 208V

(D) GENERATOR "13"

115KW, 208V

BLDGS 12, 13, 16 & 20

SEE DETAIL 1/EP402

FOR FURTHER

INFORMATION.

SEE DETAIL 2/EP402

FOR FURTHER

INFORMATION

SEE DETAIL 6/EP403

FOR FURTHER

INFORMATION.

SEE DETAIL 1/EP403

FOR FURTHER

INFORMATION

SEE DETAILS 3&4/EP402

FOR FURTHER

INFORMATION.

(E) U.G. FUEL TANKS

(D) XFMR 03-35-01-1

75KVA

(D)PANEL 03-35A-01-1

(D)PANEL 03-35A-01-3

(D)LIGHT POLE

(D)LIGHT POLE

(D)LIGHT POLE

(D) U.G. FUEL TANK

SEE DETAIL 5/EP402

FOR FURTHER

INFORMATION

SEE DETAILS 6&7/EP402

FOR FURTHER

INFORMATION

SEE DETAIL 2/EP403

FOR FURTHER

INFORMATION

SEE DETAIL 5/EP403

FOR FURTHER

INFORMATION.

SEE DETAILS 3&4/EP403

FOR FURTHER

INFORMATION.

(D) U.G. FUEL TANK

SEE DETAIL 3/EP401

FOR FURTHER

INFORMATION.

SEE DETAIL 4/EP401

FOR FURTHER

INFORMATION

SEE DETAILS 1&2/EP401

FOR FURTHER

INFORMATION.

(D) U.G.

FUEL TANK

(D) MTS-21

SELECTOR SW "61"

(E)SOLAR CANOPY ELECTRICAL

GEAR. SEE CIVIL DRAWINGS

NO. DESCRIPTION DATE

PLAN

NORTH

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

KEYPLAN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

20 12

34, 34A

1B

2A

5B

1A

35A

7A

1C

5A

3A

1. REFER TO SHEETS E-001 AND E-002 FOR SYMBOLS, ABBREVIATIONS AND

NOTES.

2. ALL ELECTRICAL EQUIPMENT SHOWN ON THIS DRAWING SHALL BE EXISTING

TO REMAIN, UNLESS OTHERWISE NOTED.

3. EQUIPMENT TAGS SHOWN DARK AND DASHED INDICATE MEDIUM VOLTAGE

FEEDERS MARKED FOR DEMOLITION. EQUIPMENT TAGS SHOWN LIGHT SHALL

BE EXISTING TO REMAIN. FEEDERS SHALL BE REMOVED FROM EXISTING

DUCTBANKS AND REPLACED WITH THE NEW NORMAL POWER FEEDER LOOP.

SEE CIVIL DRAWINGS, ES102 AND E-600 SERIES DRAWINGS FOR FURTHER

INFORMATION.

4. SEE DRAWING ED601 FOR FURTHER INFORMATION ON EQUIPMENT TO BE

DEMOLISHED.

GENERAL SHEET NOTES:

ELECTRICAL

DEMOLITION

SITE PLAN

ES101

MJRTO

SCALE: 1" = 60'-0"

DEMOLITION

EXISTING TO

REMAIN

NEW/TEMPORARY

WORK

1. PHASE 1 OF THIS PROJECT ENTAILS THE CONSTRUCTION OF THE NEW

GENERATOR BUILDING AND ALSO THE CONSTRUCTION OF THE NEW NORMAL,

EMERGENCY AND LOW VOLTAGE DUCTBANKS.

2. NEW MEDIUM VOLTAGE GENERATORS SHALL FULLY BE TESTED AND

COMMISSIONED BEFORE PROCEEDING.

3. PHASE 2 OF THIS PROJECT WILL REPLACE (9) BUILDING-LEVEL EMERGENCY

GENERATORS WITH PAD-MOUNTED TRANSFORMERS. A TEMPORARY

GENERATOR IS REQUIRED FOR THIS WORK TO ENSURE THAT THE BUILDING

WILL NOT BE LEFT WITHOUT EMERGENCY POWER. THE TEMPORARY

GENERATOR SIZE AND VOLTAGE SHALL BE COMMENSURATE WITH THE SIZE

OF EACH DEMOLISHED GENERATOR. CONTRACTOR SHALL NOTIFY VA OF AN

EMERGENCY POWER SHUTDOWN AT LEAST 2 WEEKS IN ADVANCE.

4. THIS WORK CAN PROCEED ONE BUILDING AT A TIME, HOWEVER MULTIPLE

GENERATORS CAN BE REPLACED AT THE SAME TIME, PROVIDED THAT

MULTIPLE TEMPORARY GENERATORS ARE AVAILABLE.

GENERAL PHASING NOTES:

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELAN

E

FIR

ELANE

FIRELANE

FIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANEFIRELANE

UTILITY TRANSFORMERS

MH-2A

MH-2B

MH-2

MH-3

SELECTOR SWITCH "53":

- XFMR 44562, T-43, 208V

- XFMR T-44, 240V

SELECTOR SWITCH "42"

EE 9811

SELECTOR SWITCH "60":

- FEEDERS 1, 2, & 3

MH-5

MH-5.5

SELECTOR SWITCH "41" BYPASS

MH-8

MH-7

MH-4B

SELECTOR SW "34"

XFMR 44541 TL-23

SELECTOR SW "49"

BLDG 1:

- 49-6, 5, 4, 3, 2, 49

OHM-8

OHM-9

SELECTOR SW "55"

SWGR

SELECTOR SW "2" &

XFMR 137631, TL-36 B2

SELECTOR SW "19" &

XFMR 54947, TL-32, 500KVA

MH-6

MH-11

HV-10

F1 F7F2

F1 F7F2

F1

F1

F1

F1

F7 F2

F2

F7 F2

F7

F7

F2

F2

F2

F7

SELECTOR SW "61"

NEW FENCE WITH DUAL AUTHENTICATION

SCREENING GATE SYSTEM. SEE DETAILS 5

& 6/EP403 FOR CONNECTION INFORMATION

FOR POWER AND SECURITY SYSTEMS.

NEW GENERATOR BUILDING 37

SEE INTERIOR ELECTRICAL PLANS

FOR FURTHER INFORMATION

NEW CONCRETE ENCASED DUCTBANK

SEE CIVIL DRAWINGS FOR FURTHER

INFORMATION.

F4F4

F4

F4

F4

(N) MANHOLE MH-18N

& MANHOLE MH-21E

(N) MANHOLE MH-15N

& MANHOLE MH-16E

F4 (N) MANHOLE MH-17N

& MANHOLE MH-17E

F4

F4 F5

F5

F4 F5

(N) MANHOLE MH-14N

& MANHOLE MH-15E

(N) MANHOLE MH-13N

& MANHOLE MH-13E

F4 F5

(N) MANHOLE MH-10N

& MANHOLE MH-10E F4

F5

F3

F3

F3

(N) XFMR-5, 112.5-KVA

12470-VOLT::208-VOLT

(N) XFMR-21, 75-KVA

12470-VOLT::208-VOLT

(N) XFMR-31 & XFMR-31A,

300-KVA, 12470-VOLT::208-VOLT

300-KVA, 12470-VOLT::240-VOLT

(N) XFMR-26, 225-KVA

12470-VOLT::208-VOLT

(N) XFMR-62, 300-KVA

12470-VOLT::480-VOLT (N) XFMR-2, 750-KVA

12470-VOLT::480-VOLT

(N) XFMR-34, 750-KVA

12470-VOLT::480-VOLT

(N) XFMR-13, 150-KVA

12470-VOLT::208-VOLT

(N) MANHOLE MH-12N

& MANHOLE MH-12E

(N) MANHOLE MH-16N

(N) MANHOLE MH-19N

E1

E1

E1

E1

E1

E2

E1 E2 E2

E2

E2

E1

E2

NEW CONCRETE ENCASED DUCTBANK

FOR UTILITIES TO NEW BUILDING. SEE

EP400 SERIES FOR CONTINUATION.

E1 E1

E1

E2

(N) ATS-21, 208-VOLT, 225-AMP

NEMA 3R RATED

NEW PAD MOUNTED LOAD BANK AND

TRANSFORMER MOUNTED ON SKID RAILS

F3 F3

(N) MANHOLE MH-20N

& MANHOLE MH-20E

E1

BUILDING 35A. SEE DRAWING EP101

FOR FURTHER INFORMATION.

MH-2A

MH-2B

F3

F3

F3

E1

(N) MANHOLE MH-14E

F5

(N) MANHOLE MH-19E

(N) MANHOLE MH-18E

E1

E2

F4

F4

E2

NO. DESCRIPTION DATE

PLAN

NORTH

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

KEYPLAN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

20 12

34, 34A

1B

2A

5B

1A

35A

7A

1C

5A

3A

1. REFER TO SHEETS E-001 AND E-002 FOR SYMBOLS, ABBREVIATIONS AND

NOTES.

2. ALL NEW MANHOLES AND HANDHOLES SHALL BE LOCKABLE.

3. THIS DRAWING IS DIAGRAMMATIC. SEE E-600 SERIES AND CIVIL DRAWINGS

FOR FOR FURTHER INFORMATION ON NEW DUCTBANKS, MANHOLES,

HANDHOLES AND NEW ELECTRICAL EQUIPMENT. ATS/LOW VOLTAGE CABLING

SHALL HAVE HANDHOLES LOCATED AS SHOWN ON CIVIL DRAWINGS.

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1. RUN NEW MEDIUM VOLTAGE NORMAL POWER CABLES IN EXISTING CONCRETE

ENCASED DUCTBANK FROM MANHOLE TO SELECTOR SWITCH. SPARE

CONDUIT PATHWAY WILL BE MADE AVAILABLE VIA DEMOLITION OF EXISTING

FEEDER.

2. NEW UNDERGROUND CONCRETE ENCASED DUCTBANK FOR EMERGENCY

LOOP CABLES TO LOCATION OF EXISTING PAD FOR DEMOLISHED GENERATOR.

3. NEW UNDERGROUND CONCRETE ENCASED DUCTBANK CONDUITS SHALL BE

EXTENDED AS REQUIRED FOR LOOP FEEDER TERMINATIONS UNDER THE

EXISTING GENERATOR CONCRETE PAD AT THE LOCATION OF EACH OF THE

TWO (2) LOOP FEED SWITCHES.

ELECTRICAL

NEW WORK SITE PLAN

ES102

MJRTO

SCALE: 1" = 60'-0"

UNDERGROUND

EXISTING TO

REMAIN

NEW/TEMPORARY

WORK

1. PHASE 1 OF THIS PROJECT ENTAILS THE CONSTRUCTION OF THE NEW

GENERATOR BUILDING AND ALSO THE CONSTRUCTION OF THE NEW NORMAL,

EMERGENCY AND LOW VOLTAGE DUCTBANKS.

2. NEW MEDIUM VOLTAGE GENERATORS SHALL FULLY BE TESTED AND

COMMISSIONED BEFORE PROCEEDING.

3. PHASE 2 OF THIS PROJECT WILL REPLACE (9) BUILDING-LEVEL EMERGENCY

GENERATORS WITH PAD-MOUNTED TRANSFORMERS. A TEMPORARY

GENERATOR IS REQUIRED FOR THIS WORK TO ENSURE THAT THE BUILDING

WILL NOT BE LEFT WITHOUT EMERGENCY POWER. THE TEMPORARY

GENERATOR SIZE AND VOLTAGE SHALL BE COMMENSURATE WITH THE SIZE

OF EACH DEMOLISHED GENERATOR. CONTRACTOR SHALL NOTIFY VA OF AN

EMERGENCY POWER SHUTDOWN AT LEAST 2 WEEKS IN ADVANCE.

4. THIS WORK CAN PROCEED ONE BUILDING AT A TIME, HOWEVER MULTIPLE

GENERATORS CAN BE REPLACED AT THE SAME TIME, PROVIDED THAT

MULTIPLE TEMPORARY GENERATORS ARE AVAILABLE.

GENERAL PHASING NOTES:

(E) PANEL EE109836

(E) BATTERIES

(E) HINDLE POWER PANEL

(E) PANEL EE109823

(E) PANEL EE109834(D) PLC BOX

SECT. 9

EASTBOROUGH SWITCHGEAR

PAWNEE SWITCHGEAR

SECT. 8 SECT. 7 SECT. 6 SECT. 5

SECT. 1 SECT. 2 SECT. 3 SECT. 4

(E) PAWNEE UTILITY

LINE TRANSFORMER (E) EASTBOROUGH UTILITY

LINE TRANSFORMER

(E) BUS

BETWEEN

SWITCHGEAR

(N)

SECT. 0

SECT. 5 SECT. 6 SECT. 7 SECT. 8 SECT. 9

(E) BUS BETWEEN SWITCHGEAR

(E) PANEL EE109836

VENT

VENT

BUS 2

P.T.

FUTURE

(SPARE)

FEEDER

F4

FUTURE

(SPARE)

FEEDER

F3

FEEDER

F5

MAIN 2

AUX-2

CPT-2

GEN-1

(SPARE)

AUX-G

SECT. 1 SECT. 2 SECT. 3 SECT. 4

(E) BUS BETWEEN SWITCHGEAR

MAIN 1

AUX-1

CPT-1

FEEDER

F7

FEEDER

F2

FEEDER

F1

1000KVA

SOLAR

XFMR

BUS 1

TIE

AUX-1

BUS 1

PT

(E) BATTERIES

(E) PANEL EE109834

(E) EXHAUST FAN

(N)

CIRCUIT

BREAKER

SPARE

(N)

CIRCUIT

BREAKER

FEED F9

(D) PLC BOX

NO. DESCRIPTION DATE

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

BID DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

Phase

ENGINEER OF RECORDCONSULTANT CONSTRUCT CENTRALIZED

EMERGENCY POWER SYSTEM

589A7-21-132

Project Director

2026-03-26

321 4 5 6 7 8 9 10

A

B

C

D

E

F

21 4 5 6 7 8 9 10

A

C

D

E

F

M-R PROJECT NO: 0499-0162

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

Civil / Site Utility Engineering:Hazardous Materials:

MABBETT & ASSOCIATES, INC.

Fire & Life Safety:

STANTON ENGINEERING SERVICES, LLC

Architectural:

OCULUS, INC.

Structural:

PROFESSIONAL ENGINEERING

CONSULTANTS, PA (PEC)

IMEG, CORP. 37

1. REFER TO SHEETS E-001 AND E-002 FOR SYMBOLS, ABBREVIATIONS AND

NOTES.

2. ALL ELECTRICAL EQUIPMENT SHOWN ON THIS DRAWING SHALL BE EXISTING

TO REMAIN, UNLESS OTHERWISE NOTED.

GENERAL SHEET NOTES:

ELECTRICAL

POWER PLAN

BUILDING 35A

EP101

MJRTO

SCALE: 1/4" = 1'-0"

SCALE: 1/4" = 1'-0"

SCALE: 1/4" = 1'-0"

3 3 O

S

2 31 4

A

B

C

'EM1'

'EM1'

'EM1' 'EM1'

'EM1'

'A1''A1''A1'

'A1'

'W1'

'X1'

'W1'

'W1'

'X1'

'W1''W1''W1'

'W1'

'W1'

'X1'

'W1'

'A1''A1''A1'

2 2 2 2

'A1'

'A1'

'A1'

31313131

31 31

31 31 31

31 31

EL1-7

EL1-7

EL1-7

EL1-7

EL1-7

EL1-7

EL1-7

EL1-7

'EM1' EL1-7

'C1''C1''C1'

'C1''C1''C1'

'C1''C1'

313131

GENERATOR

ROOM

FIRE RISER

ROOM

SWITCHGEAR

ROOM

'W1' 31 'W1' 31

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

CONSULTANTS

321 4 5 6 7 8 9 10

NO.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .