Amend 0007 Contractor RFIs and Responses.pdf
PDF 60 KB Posted
- Attached to
- Eastern Multiple Award Task Order Contract (MATOC) Replacement Federal contract opportunity
- Solicitation number
- 47PL0122R0035
About this file
This document contains questions and responses related to a solicitation for an Eastern Multiple Award Task Order Contract (MATOC) Replacement. The solicitation seeks bids for six indefinite delivery indefinite quantity construction contracts to support projects in federally owned and leased facilities in Eastern Washington, Eastern Oregon, and Idaho. The construction scope of work includes tenant improvements, building repairs and alterations, conveyance systems, roofing, mechanical, electrical and plumbing systems, and exterior improvements. Awarded contractors will deliver completed construction projects on schedule and within budget. The contract maximum value is $70 million over five years. Task order solicitations will be issued by GSA offices in Region 10 and adhere to FAR competitive procedures. A pre-proposal site walk for an included Seed Project will be held on July 6, 2022.
View the file
Other files for this federal contract opportunity
Show all 50
Eastern Multiple Award Task Order Contract (MATOC) Replacement has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 August 2022
RFP 47PL0122R0035 EMATOC & 47PL0122R0041 Sump Pump Seed Project Pre-Proposal Requests For Information (RFI) and Responses 6
1.) Question: On the revised attachment F, on the Price Breakout Worksheet (tab 3), Note #1 says “Information shall provide this additional pricing backup documentation in CSI format.” Is this required?
Answer: Yes, reference RFP EMATOC 47PL0122R0035.pdf, L-5.2. Tab 2, Factor 1 - Cost/Price Proposal for the Seed Project for details on how to fulfill this requirement.
2.) Question: On attachment F, on the Evaluated Price Info Sheet (tab 4), Item #3 Evaluated Future modifications Mark-up Costs…. Please explain what amount we would want to put in the box for “(Est Future Mods Direct Costs)”.
Answer: Attachment F revised to only request modification mark-up rate and evaluated Government caused delay costs. See Attachment F Seed Project Price and Services Schedule Rev2.xlsx.
3.) Question: On form SF1442 for the MATOC (ending in 0035), how do we complete page 3?
Answer: No values are required for page 3 of SF 1442 47PL0122R0035. In accordance with RFP EMATOC 47PL0122R0035.pdf, M-4.2. Tab 2 - SF 1442 signed by Authorized Offeror, the 1442 needs to be signed by an Authorized Offeror.
4.) Question: Is the duration listed on the revised Attachment F sheet 4 Note regarding the period of performance correct?
Answer: Attachment F revised to only request modification mark-up rate and evaluated Government caused delay costs. See Attachment F Seed Project Price and Services Schedule Rev2.xlsx.
5.) Question: Do we need to acknowledge we received the revised Seed Project Price sheet updated 2 August or just sign Amendment 006 dated 1 August and include the most recent spreadsheet with our proposal. They both have the exact same name and appear to be identical spread sheets as what we downloaded yesterday.
Answer: No, please just acknowledge Amendment 0007 as Attachment F has been revised again. See Attachment F Seed Project Price and Services Schedule Rev2.xlsx.