Amend 0004 Contractor RFIs and Responses 3.pdf

PDF 55 KB Posted

Attached to
Eastern Multiple Award Task Order Contract (MATOC) Replacement Federal contract opportunity
Solicitation number
47PL0122R0035
Issued by
General Services Administration Public Buildings Service Region 10

About this file

This document provides responses to contractor questions regarding a federal solicitation for construction services. The General Services Administration's Northwest/Arctic Region is seeking proposals for an Eastern Multiple Award Task Order Contract to provide construction projects in federally owned and leased facilities in Eastern Washington, Eastern Oregon, and Idaho. The contract term is five years with a maximum value of $70 million to be awarded across six contracts. Task order solicitations will use various project delivery methods, including design-bid-build and design-build, for tenant improvements, building repairs, and exterior work valued between $25,000 to $5 million. Responses clarify that engineered drawings are not required, unknown waste can be disposed of through the city sewer system with required approvals, and the existing sump pump does not need replacement for bidding purposes.

View the file

Other files for this federal contract opportunity

Other files attached to Eastern Multiple Award Task Order Contract (MATOC) Replacement, newest first.
File Type Posted
Amend 0007 Attachment F Seed Project Price and Services Schedule Rev2.xlsx XLSX spreadsheet
Amend 0007 SF30 47PL0122R0035.pdf PDF
Amend 0007 Contractor RFIs and Responses.pdf PDF
Amend 0006 Attachment F Seed Project Price and Services Schedule Rev1.xlsx XLSX spreadsheet
Amend 0006 Contractor RFIs and Responses.pdf PDF
Amend 0006 SF30 47PL0122R0035.pdf PDF
Amend 0006 Attachment F Seed Project Price and Services Schedule Rev1.xlsx XLSX spreadsheet
Amend 0005 SF30 47PL0122R0035.pdf PDF
Amend 0005 Contractor RFIs and Responses 4.pdf PDF
Amend 0004 SF30 47PL0122R0035.pdf PDF
Amend 0004 Site Visit Sign In Sheet 2 Redacted.pdf PDF
Amend 0003 SF30 47PL0122R0035.pdf PDF
Amend 0003 Contractor RFI_s and Responses 2.pdf PDF
Amend 0003 2019 Asbestos Reinspection Survey Report Thomas S Foley USCH.pdf PDF
Amend 0002 Contractor RFIs and Responses.pdf PDF
Amend 0002 SF30 47PL0122R0035.pdf PDF
Amend 0002 Exhibit 6 Past Performance Questionnaire Rev1.docx DOCX document
Amend 0002 R10 EMATOC SOW 04222022.pdf PDF
Amend 0001 SF1442 47PL0122R0035.pdf PDF
Amend 0001 SF30 47PL0122R0035.pdf PDF
Amend 0001 RFP EMATOC 47PL0122R0035.pdf PDF
Amend 0001 Attachment D - TORFP Seed Project.pdf PDF
Attachment C Example of TO Reps and Certs.docx DOCX document
Exhibit 2 Read Me First - CUI Document.pdf PDF
7.5 Submittal Transmittal Form.xls XLS spreadsheet
7.11 Project Management Information System.pdf PDF
RFP EMATOC 47PL0122R0035.pdf PDF
EMATOC Agreement.pdf PDF
Attachment B Example of TO Agreement.docx DOCX document
Exhibit 1 3490.3 Policy.pdf PDF
Exhibit 4 Contractor Project Experience Form.docx DOCX document
Exhibit 5 Key Personnel Resume Form.docx DOCX document
Exhibit 8 IDIQ Price Schedule.xlsx XLSX spreadsheet
SF1442 47PL0122R0041 Seed Project.pdf PDF
7.6 Controlled Unclassified Information 34903.pdf PDF
GSA527-21.pdf PDF
SF1442 47PL0122R0035 EMATOC.pdf PDF
Attachment A EMATOC Terms and Conditions.pdf PDF
Attachment D TORFP Seed Project.pdf PDF
Attachment E Seed Project SOW.pdf PDF
Attachment F Seed Project Price and Services Schedule.xlsx XLSX spreadsheet
7.1 Vendor Security Training.pdf PDF
7.4 Sample OF 306.pdf PDF
Attachment G Seed Project Wage Determination.pdf PDF
Exhibit 3 GSAAffiliatedCustomerAccounts.pdf PDF
Exhibit 6 Past Performance Questionnaire.docx DOCX document
Exhibit 7 GSA Security Manual.pdf PDF
7.2 Sample ROCAL.xlsx XLSX spreadsheet
7.3 Sample CIW Form 850.docx DOCX document
7.7 R10 NCMMS Asset ImpExp Template.xlsx XLSX spreadsheet
Show all 50

Eastern Multiple Award Task Order Contract (MATOC) Replacement has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

25 July 2022

RFP 47PL0122R0035 EMATOC & 47PL0122R0041 Sump Pump Seed Project Pre-Proposal Requests For Information (RFI) and Responses 3

1.) Question: Has the city of Spokane approved dumping an unknown quantity into the city sewer system?

Answer: Required notifications and/or approvals from the City of Spokane will be addressed by GSA.

2.) Question: Although not noted in the requirements, but stated in the project title, is it the expectation of the project to have engineered stamped drawings?

Answer: No, engineered stamped drawings will not be required. Refer to the Statement of Work (SOW), Section 2.1 on which 'Shop Drawings' are required.

3.) Question: The pictures of the sump in the elevator floor show it to be in poor shape.

We didn’t get the opportunity to inspect the sump ourselves and can’t be certain from the pictures of its structural integrity. For bidding purposes should we assume we will need to remove the existing one and build a new one?

Answer: For the purpose of bidding, assume the existing sump does NOT need to be replaced.