Amendment 1- CMS BOC Phase 4 Pre-Proposal Conference Presentation.pptx
PPTX presentation 2 MB Posted
- Solicitation number
- 47PD0225R0055
About this file
This file is an Amendment 1 Pre-Proposal Conference Presentation for the CMS Back on Campus - Phase 4 Construction Services contract (Solicitation Number 47PD0225R0055). The project, located at the CMS Headquarters in Woodlawn, Maryland, involves comprehensive renovation work including replacing 16 sets of restrooms across multiple buildings, constructing a conferencing center on C1, and an alternate North Culvert replacement. The project has a total duration of 650 calendar days, with specific constraints including restroom phasing and construction timing restrictions.
The solicitation is set aside for small businesses with a project estimated between $15-20 million and a NAICS code of 236220. Key procurement dates include RFP release on 8/5/25, virtual pre-proposal conference on 8/11/25, site visit on 8/14/25, RFIs due 8/25/25, and proposals due 9/5/25 at 2PM. Proposal evaluation will focus on three technical factors: Management Plan, Prior Experience, and Past Performance, with these non-price factors being significantly more important than price. Required submittal documents include pricing bid sheets, forms 1442 and 24, financial documentation, and a bid bond of $17 million. The project involves multiple partners including CMS Facilities Team, GSA, O&M contractor Dae Sung, Mills + Schnoering Architects, and Procon & Hill International.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PROPOSAL CONFERENCE
August 11th, 2025
CMS Back on Campus - Phase 4 Construction Services
47PD0225R0055
AGENDA
Project Overview Proposal Process Technical Proposals Price Proposals Method of Award Key Milestones Questions and Answers
WOODLAWN, MARYLAND
CMS HEADQUARTERS
Project Partners Centers for Medicare and Medicaid Services (CMS) Facilities Team Tenants General Services Administration (GSA) Project Team O&M contractor (Dae Sung) Mills + Schnoering Architects Procon & Hill International
PROJECT OVERVIEW
Project Area -Auditorium, Central, South, back road Project Scope Replacements of 16 sets of restrooms 650 calendar days from NTP (Oct 2025 to July 2027) Conferencing center on C1 210 calendar days from 11/1/26 (5/30/27) Alternate for the North Culvert 180 calendar days from NTP (Oct 2025 to April 2026) Project Constraints Restroom phasing: 1 set per building per floor Conferencing Center: can not start on site construction until 11/1/26 North Culvert: MDE & US Army Corp Permit restrictions.
Occupied and Secured building
South Building
Construction Procurement Schedule RFP release 8/5/25 Virtual pre-proposal 8/11/25 Site Visit Thursday 8/14/25 @ 9:30am send site visit forms in by 8/12/25 @ 1PM RFIs due 8/25/25 @ 2PM responses expected by Friday 8/29/25 Proposals due Friday 9/5/25 at 2PM
TECHNICAL PROPOSALS
Technical Factor 1: Management Plan 10 pages Factor 2: Prior Experience on Relevant Projects 1 attachment for 3 submitted projects Factor 3: Past Performance on Relevant Projects Questionnaire:
1 attachment for the 3 different projects
PRICE PROPOSALS
Price Pricing Bid Sheet-signed Form 1442 and all amendments acknowledged Section 301 “Representations and Certifications” Standard Form 24, Bid Bond ($17M) The information required under FAR 52.215-1(c)(2) Joint Ventures agreement and documentation Financial Info for last 3 years by CPA Balance Sheet Profit and Loss Statement Statement of Cash Flow GSA Form 527-Contractor’s Qualification & Financial Info-signed Amendments Amendments will be issued to all parties via www.sam.gov
METHOD OF AWARD
The Offeror whose offer conforming to the Solicitation will be the best value to the Government, Total Evaluated Price and other factors considered. In addition to Total Evaluated Price, the following non-price factors shall be used to evaluate offers:
Management Plan Prior Experience on Relevant Projects Past Performance on Relevant Projects Non-Price Factors, when combined, are significantly more important than Total Evaluated Price.
Tradeoff Information: Non-Price Factors, when combined, are significantly more important than Total Evaluated Price To be considered for award all factors must receive a rating of “Acceptable” or higher.
The government will rate each proposal against all evaluation criteria in the solicitation.
If any factor is rated “marginal” or “unacceptable” the government will notify the offeror of the rating, and that their proposal may not be considered for award.
QUESTIONS?
THANK YOU