This document is a Stormwater Management and Sediment & Erosion Control Approval issued by the Maryland Department of Environment (MDE) for a U.S. General Services Administration (GSA) project. The approval pertains to the Centers for Medicare and Medicaid Services Culvert Replacement in Baltimore County, with a project location at latitude/longitude 39.3170, -76.7645 and a land disturbance of 0.50 acres. The project was prepared by Langan Engineering & Environmental Services and has an effective date of July 3, 2025.

The approval document outlines six key conditions, including a three-year completion timeline, compliance with all current laws and regulations, requirements for sediment control and stormwater management facilities, and mandatory notifications to the MDE/WSA Compliance Program. A stormwater management waiver has been granted for this project in accordance with Maryland Stormwater Management and Erosion & Sediment Control Guidelines for State and Federal Projects. The approval is specific to the culvert replacement component of the broader CMS Headquarters Back on Campus-Phase 4 project.

View the file

Other files

File Type Posted
Amendment 8-CMS Phase 4- RFIs.pdf PDF
Solicitation Amendment 47PD0225R0055_0008.pdf PDF
Solicitation Amendment 47PD0225R0055_0007.pdf PDF
Amendment 7-CMS Phase 4- RFIs - 2025-09-03.pdf PDF
Solicitation Amendment 47PD0225R0055_0006.pdf PDF
Amendment 6-CMS Phase 4- RFIs-2025-09-02.pdf PDF
Revised SF 1442 2025 08 26 .pdf PDF
CMS Phase 4-Pricing Sheet 20250827.xlsx XLSX spreadsheet
Revised Solicitation CMS Phase 4 Amendment 5 2025 08 25.pdf PDF
Solicitation Amendment 47PD0225R0055_0005 2025 08 27.pdf PDF
CMS BOCp4_Attic Stock Minimums R.xlsx XLSX spreadsheet
CMS Phase 4- RFI Responses0250828.pdf PDF
Revised Agreement - CMS Phase 4 Construction.pdf PDF
CMS Phase 4-SOW Cover Sheet-R1.pdf PDF
CMS Phase 5-Amendment 4.zip ZIP file
Amendment 3-Revised Solicitation 2025 08 20.pdf PDF
Amendment 3-CMS P4 08-14-25 site visit signed.pdf PDF
Solicitation Amendment 47PD0225R0055_0003 2025 08 20.pdf PDF
Amendment 2-25-SF-0138 MDE Stamped Plans - CMMS Culvert Replacement - GSA - 2025-04-08.zip ZIP file
Solicitation Amendment 47PD0225R0055_0002.pdf PDF
Solicitation Amendment 0001_ 47PD0225R0055.pdf PDF
Amendment 1- CMS BOC Phase 4 Pre-Proposal Conference Presentation.pptx PPTX presentation
Amendment 1-CMS - Building Standards (8702) - February 2025 Rev Reduced.zip ZIP file
16 CMS Culvert Project Specifications.pdf PDF
04 SF 1442 .pdf PDF
08 CMS Site Visit Form.pdf PDF
01 RFP CMS Phase 4 Restrooms - North Culvert - CMS Conferencing Center Woodlawn Maryland.pdf PDF
12 GSA527-21a.pdf PDF
03 CMS Phase 4- Reps and Certs GC MAY 2025.pdf PDF
13 MDE Wetland Extension Letter.pdf PDF
00 CMS Phase 4 SOW Cover Sheet.pdf PDF
07 CMS BOC P4-Procurement RFI Log.xlsx XLSX spreadsheet
CMS Back on Campus Phase 4 Design DRAFT 100 Percent CD Specifications 07242025.pdf PDF
CMS Back on Campus Phase 4 Design 100 Percent CD Drawings The CCC And Restrooms 07242025.pdf PDF
02 Agreement -- CMS Phase 4 Construction.pdf PDF
09 Past Performance Questionnaire.pdf PDF
05 Wage Determination MD20250108 Mod 01.pdf PDF
10 Prior Experience on Relevant Projects Offeror Worksheet .docx DOCX document
14 MDE Wetland Approval.pdf PDF
11 SF24-23a (1).pdf PDF
06 CMS Phase 4-Pricing Sheet 20250805.xlsx XLSX spreadsheet
CMS Back on Campus Phase 4 Design DRAFT 100 Percent CD Final Basis of Design Report 07242025.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STORMWATER MANAGEMENT AND SEDIMENT & EROSION CONTROL APPROVAL

STATE/FEDERAL PROJECTS

SEDIMENT & STORMWATER PLAN REVIEW DIVISION

MDE NUMBER: 25-SF-0138 APPROVED BY: ____________________________________

Program Manager, Sediment, Stormwater, and Dam Safety EFFECTIVE DATE: July 3, 2025 (Pursuant to Criteria Noted Below)

IN COMPLIANCE WITH: Environment Article, Sections 4-106 and 4-205 Annotated Code of Maryland

APPROVAL IS HEREBY GRANTED: U.S. General Services Administration ADDRESS: 100 S. Independence Mall West

Philadelphia, PA 19106 Attn: Mr. Jacob Wyshinski

HEREINAFTER KNOWN AS OWNER,

FOR THE PLANS AND SPECIFICATIONS PRESENTED FOR: Contract No. n/a AI No.134787 GSA - Centers for Medicare and Medicaid Services Culvert Replacement - Baltimore County

Latitude/Longitude: 39.3170, -76.7645 LOD: 0.50 acres

PREPARED BY: Langan Engineering & Environmental Services This APPROVAL is granted subject to the following conditions:

1. This Approval shall become null and void if the construction authorized herein has not been completed within three (3) years from the granting of this Approval, except that these limits may be extended at the discretion of the Department when requested by the owner or authorized agent.

2. This Approval is subject to all laws and regulations now in effect and may be revoked if it is subsequently determined that this authorization violates other laws of the State. Construction shall comply with approved terms.

3. The location and dimensions of all sediment control structures and stormwater management facilities, as well as grading, excavation, and filling shall be in accordance with plans approved by the Department of the Environment/ Water and Science Administration (MDE/WSA). The owner or authorized agent shall obtain written approval from the MDE/WSA for any plan modifications or changes. A copy of the approved plan with any approved modifications and this Approval shall be available at the construction site for reference during the construction period.

4. Off-site borrow or waste sites require local county and Soil Conservation District approvals if they are located on private property or MDE/WSA approval if on State or federal property. Local approval numbers shall be furnished to the MDE/WSA Inspector.

5. The Owner or his authorized agent shall notify the MDE/WSA Compliance Program at (410) 537-3510, at least seven (7) days prior to initiation of the project and five (5) days after work ends.

6. A stormwater management waiver has been granted for this project in accordance with Section 3.3.A of the Maryland Stormwater Management and Erosion & Sediment Control Guidelines for State and Federal Projects.