This document contains a solicitation notice and bid sheets for construction services for a bankruptcy and probation courts consolidation project. The solicitation is issued by the General Services Administration's Northeast and Caribbean Region Public Buildings Service for general construction services at the Conrad B. Duberstein Courthouse in Brooklyn, New York. The NAICS code for the project is 236220 for commercial and institutional building construction, and the solicitation is set aside for small businesses with average annual receipts of $39.5 million or less over three years. The bid sheets provide line items for construction phases, general contractor fees, unit pricing, and multiple optional additions. Proposals are due by the date specified, and a pre-proposal conference will be held on December 19, 2019. Interested offerors must register on beta.sam.gov and contact the point of contact for additional details.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Sheet Tab 1
| Duberstein Courthouse - Bankruptcy Consildation Project | ||||
| Offerer Name: | ||||
| ITEM | SERVICES FOR BID | QTY | UNIT | AMOUNT |
| A. | Phase 1 Construction Phase Services | |||
| A.1 | A10 - Foundations | 1 | LS | |
| A.2 | A20 - Basement Construction | 1 | LS | |
| A.3 | B10 - Superstructure | 1 | LS | |
| A.4 | B20 - Exterior Enclosure | 1 | LS | |
| A.5 | B30 - Roofing | 1 | LS | |
| A.6 | C10 - Interior Construction | 1 | LS | |
| A.7 | C20 - Stairs | 1 | LS | |
| A.8 | C30 - Interior Finishes | 1 | LS | |
| A.9 | D10 - Conveying | 1 | LS | |
| A.10 | D20 - Plumbing | 1 | LS | |
| A.11 | D30 - HVAC | 1 | LS | |
| A.12 | D40 - Fire Protection | 1 | LS | |
| A.13 | D50 - Electrical | 1 | LS | |
| A.14 | E10 - Equipment | 1 | LS | |
| A.15 | E20 - Furnishings | 1 | LS | |
| A.16 | F10 - Special Construction | 1 | LS | |
| A.17 | F20 - Selective Building Demolition | 1 | LS | |
| A.18 | CSO Guard Services for Off Hour Disruptive Work | 1 | LS | |
| A.19 | Construction Phase Subtotal (sum of A.1 through A.18) |
| ITEM | SERVICES FOR BID | QTY | UNIT | AMOUNT |
| B. | G.C. Overhead, Profit, & Bonding Costs | |||
| B.1 | G.C. Overhead and Profit (___% x A.19) | 1 | LS | |
| B.2 | G.C. Bonding Costs (___% x A.19) | 1 | LS | |
| B.3 | G.C. OH, Profit, & Bonding Subtotal (sum of B.1 thru B.2) | |||
| B.4 | Estimated Cost of Construction at Award (total = A.19 + B.3) |
C. Unit Prices - See Div 012700 Unit Prices for descriptions of each item. For C.1 through C.5 insert the proposed unit cost for each line item and multiply that cost by the indicated quantity. Insert the product of those numbers on the total line. Unit costs shall include all costs including Overhead, Profit, and Bonding Costs. These costs shall not also be included in Section A.
| ITEM | SERVICES FOR BID | QTY | UNIT | UNIT COST | TOTAL AMOUNT | ||
| C.1 | Sheet S 002 - Detail 3 - performing the probe, documenting the existing conditions, and restoring the fireproofing (anticipated concrete encasements) | 12 | EA | X | = |
C.2 Sheet S 002 - Detail 4 - performing the probe, documenting the existing conditions, and restoring the fireproofing (anticipated concrete encasements) 12 EA X =
C.3 Sheet S 202 - Detail 1 - Beam to Column Flange connections 10 EA X =
C.4 Sheet S 202 - Detail 2 - Beam to Column Web connection 5 EA X =
| C.5 | Sheet S 202 - Detail 3 - Beam to Girder connections | 20 | EA | X | = |
| C.6 | Unit Price Total (sum of C.1 through C.5) |
| ITEM | SERVICES FOR BID | QTY | UNIT | AMOUNT |
| D. | Add Options (Not included in base proposal above. Shall include all costs including Overhead, Profit, and Bonding Costs.) |
D.1 Option 1A - Phase 2 Probation Construction (See Bid Sheet 2, Sections F and G for break down. Lump sum shall be Item G.4 from Bid Sheet 2) 1 LS
| D.2 | Option 1B - Johnson Street Entrance Reactivation (See Bid Sheet 2, Sections H for break down. Lump sum shall be Item J.4 from Bid Sheet 2) | 1 | LS |
| D.3 | Option 2 - Bankruptcy - 2nd Floor Courtyard | 1 | LS |
| D.4 | Option 3 - Scope for GSA Space | 1 | LS |
| D.5 | Option 4A - Bankruptcy - IT Cabling | 1 | LS |
| D.6 | Option 4B - Probation - IT Cabling | 1 | LS |
| D.7 | Option 5 - Bankruptcy - DIRRT Partition | 1 | LS |
| D.8 | Option 6 - Bankruptcy - DIRRT Partition up to 5' above Base 10' Height | 1 | LS |
| D.9 | Option 7 - Bankruptcy - New Paint at 1st Floor Atrium | 1 | LS |
| D.10 | Option 8 - Probation - Curtain Wall Modification | 1 | LS |
| D.11 | Option 9A - Bankruptcy - High CAC Ceiling | 1 | LS |
| D.12 | Option 9B - Probation - High CAC Ceiling | 1 | LS |
| D.13 | Options Total (sum of D.1 through D.12) |
E.1 Proposal Grand Total = Items B.4 + C.6 + D.13 + G.3 + J.3
&A Page &P of &N
Bid Sheet Tab 2
| Duberstein Courthouse - Probation Build Out Project | ||||
| Offerer Name: | ||||
| ITEM | SERVICES FOR BID | QTY | UNIT | AMOUNT |
| F. | Option 1A. - Probation Construction Phase Services | |||
| F.1 | A10 - Foundations | 1 | LS | |
| F.2 | A20 - Basement Construction | 1 | LS | |
| F.3 | B10 - Superstructure | 1 | LS | |
| F.4 | B20 - Exterior Enclosure | 1 | LS | |
| F.5 | B30 - Roofing | 1 | LS | |
| F.6 | C10 - Interior Construction | 1 | LS | |
| F.7 | C20 - Stairs | 1 | LS | |
| F.8 | C30 - Interior Finishes | 1 | LS | |
| F.9 | D10 - Conveying | 1 | LS | |
| F.10 | D20 - Plumbing | 1 | LS | |
| F.11 | D30 - HVAC | 1 | LS | |
| F.12 | D40 - Fire Protection | 1 | LS | |
| F.13 | D50 - Electrical | 1 | LS | |
| F.14 | E10 - Equipment | 1 | LS | |
| F.15 | E20 - Furnishings | 1 | LS | |
| F.16 | F10 - Special Construction | 1 | LS | |
| F.17 | F20 - Selective Building Demolition | 1 | LS | |
| F.18 | CSO Guard Services for Off Hour Disruptive Work | 1 | LS | |
| F.19 | Option 1A. Probation Construction Phase Subtotal (sum of F.1 through F.18) |
| G. | G.C. Overhead, Profit, & Bonding Costs | ||
| G.1 | G.C. Overhead and Profit (___% x F.19) | 1 | LS |
| G.2 | G.C. Bonding Costs (___% x F.19) | 1 | LS |
| G.3 | G.C. Option 1A OH, Profit, & Bonding Subtotal (sum of G.1 through G.2) | ||
| G.4 | Estimated Cost of Option 1A (total = F.19 + G.3) |
| H. | Option 1B - Johnson Street Entrance Reactivation Construction Phase Services | ||
| H.1 | A10 - Foundations (Shell) | 1 | LS |
| H.2 | A10 - Foundations (Tenant Improvements) | 1 | LS |
| H.3 | A20 - Basement Construction (Shell) | 1 | LS |
| H.4 | A20 - Basement Construction (TI) | 1 | LS |
| H.5 | B10 - Superstructure (Shell) | 1 | LS |
| H.6 | B10 - Superstructure (TI) | 1 | LS |
| H.7 | B20 - Exterior Enclosure (Shell) | 1 | LS |
| H.8 | B20 - Exterior Enclosure (TI) | 1 | LS |
| H.9 | B30 - Roofing (Shell) | 1 | LS |
| H.10 | B30 - Roofing (TI) | 1 | LS |
| H.11 | C10 - Interior Construction (Shell) | 1 | LS |
| H.12 | C10 - Interior Construction (TI) | 1 | LS |
| H.13 | C20 - Stairs (Shell) | 1 | LS |
| H.14 | C20 - Stairs (TI) | 1 | LS |
| H.15 | C30 - Interior Finishes (Shell) | 1 | LS |
| H.16 | C30 - Interior Finishes (TI) | 1 | LS |
| H.17 | D10 - Conveying (Shell) | 1 | LS |
| H.18 | D10 - Conveying (TI) | 1 | LS |
| H.19 | D20 - Plumbing (Shell) | 1 | LS |
| H.20 | D20 - Plumbing (TI) | 1 | LS |
| H.21 | D30 - HVAC (Shell) | 1 | LS |
| H.22 | D30 - HVAC (TI) | 1 | LS |
| H.23 | D40 - Fire Protection (Shell) | 1 | LS |
| H.24 | D40 - Fire Protection (TI) | 1 | LS |
| H.25 | D50 - Electrical (Shell) | 1 | LS |
| H.26 | D50 - Electrical (TI) | 1 | LS |
| H.27 | E10 - Equipment (Shell) | 1 | LS |
| H.28 | E10 - Equipment (TI) | 1 | LS |
| H.29 | E20 - Furnishings (Shell) | 1 | LS |
| H.30 | E20 - Furnishings (TI) | 1 | LS |
| H.31 | F10 - Special Construction (Shell) | 1 | LS |
| H.32 | F10 - Special Construction (TI) | 1 | LS |
| H.33 | F20 - Selective Building Demolition (Shell) | 1 | LS |
| H.34 | F20 - Selective Building Demolition (TI) | 1 | LS |
| H.35 | CSO Guard Services for Off Hour Disruptive Work (TI) | 1 | LS |
| H.36 | Option 1B - Johnson Street Entrance Reactivation Construction Phase Subtotal (sum of H.1 through H.35) |
| J. | G.C. Overhead, Profit, & Bonding Costs | ||
| J.1 | G.C. Overhead and Profit (___% x H.36) | 1 | LS |
| J.2 | G.C. Bonding Costs (___% x H.36) | 1 | LS |
| J.3 | G.C. Option 1B OH, Profit, & Bonding Subtotal (sum of J.1 through J.2) | ||
| J.4 | Estimated Cost of Option 1B (total = H.36 + J.4) |