About this file

This addendum modifies the specifications and drawings for a construction services solicitation to consolidate bankruptcy and probation courts at the Conrad B. Duberstein U.S. Courthouse. Key changes include adding sections for ornamental metalwork, solid surface fabrications, spray-applied fire resistive materials, all-glass doors and partitions, access flooring, interior stone facing, and special coatings. It also clarifies elevator usage, finishes, signage, partitions, millwork, doors, ductwork, and other building elements.

The related solicitation seeks general construction services for Phase 1 and Phase 2 of the project on a total small business set-aside. The NAICS code is 236220 with a $39.5 million size standard. Interested small businesses should register in SAM and attend the pre-proposal conference on December 19, 2019. Proposals are due as indicated and must include four paper and one electronic copy. The General Services Administration is the contracting agency.

View the file

Other files

File Type Posted
Additional Responses for RFIs 1-24-2020.pdf PDF
Solicitation Amendment 2 -SF30.pdf PDF
Duberstein GC Bid Sheets_Rev 2.xlsx XLSX spreadsheet
GSA 012700 Unit Prices FY15 Update Oct. 1 2014.pdf PDF
01 COBie Quick Reference Guide.pdf PDF
RFI Responses Duberstein.pdf PDF
Copy of Specifications Addendum 1.pdf PDF
07 COBie Playbook Training.pdf PDF
Door Hardware Photos2.jpg JPG image
Door Hardware Photos1.jpg JPG image
02b COBie Requirements Specification.pdf PDF
Door Hardware Photos3.jpg JPG image
Narrative Addendum 1 rev 20-0114.pdf PDF
03b COBie Sample - As-Built Workbook.xlsx XLSX spreadsheet
Solicitation Amendment 1 -SF30.pdf PDF
04 COBie Information Delivery Plan (IDP).docx DOCX document
00 COBie Playbook - READ ME FIRST.pdf PDF
Duberstein GC Bid Sheets_Rev 1.xlsx XLSX spreadsheet
Asset ImpExp Template-simple 7-22-16 (with RKT Edits 6-27-17).xlsx XLSX spreadsheet
06 Quick Start Guide - Definitions.pdf PDF
05 Responsibility Matrix.xlsx XLSX spreadsheet
GSA 012700 Unit Prices FY15 Update Oct. 1, 2014.pdf PDF
SF 1442 Form.pdf PDF
Duberstein Courts Consolidation - Prebid Agenda 2019 12 19.pdf PDF
Walkthrough Sign in 2019 12 19.pdf PDF
Attachment A4 - Past Performance Questionnaire.docx DOCX document
GC Reps&Certs sep19 (1).docx DOCX document
Attachment A1 - Experience Summary Table.docx DOCX document
GSA_Form_527.pdf PDF
Conrad B. Duberstein U.S. Courthouse GC Agreement 2019 12 12.pdf PDF
Wage Determination 2019 12 11.pdf PDF
SF 1442 Form.pdf PDF
Attachment A3 - Sample Key Personnel Resume Format (1).pdf PDF
Conrad B. Duberstein U.S. Courthouse GC Solicitation 2019 12 12.pdf PDF
Duberstein GC SOW - Final (2019.11.18).pdf PDF
GC Bid Sheets.xlsx XLSX spreadsheet
SF24-16d (1).pdf PDF
Attachment A2 - Project Fact Sheet.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONRAD. B. DUBERSTEIN U.S. BANKRUPTCY COURTHOUSE

BANKRUPTCY & PROBATION CONSOLIDATION

PHASE 1 & PHASE 2

ADDENDUM NO.01

January 13, 2019

This Addendum contains changes to the requirements of the Contract Documents and Specifications.

Such changes are to be incorporated into the Construction Documents and shall apply to the work with the same meaning and force as if they had been included in the original document. Wherever this Addendum modifies a portion of a paragraph of the specifications or a portion of any Drawing, the remainder of the Paragraph or Drawing shall remain in force.

NOTE: Provisions of all Contract Documents apply.

SPECIFICATIONS

Item 1. Specifications Table of Contents

ADD the following:

05 70 00 Ornamental Metalwork 06 61 16 Solid Surface Fabrications 07 81 0 Spray-applied Fire Resistive Materials 08 14 13 Stile and Rail Doors 08 41 26 All-Glass Doors and Partitions 09 71 13 Glass Reinforced Gypsum Fabrications 09 69 00 Access Flooring 09 75 00 Interior Stone Facing 09 98 00 Special Coatings 10 14 00 Signage 10 21 13 Toilet Compartments

Item 2. Specifications Section 011000 Summary

REMOVE Specific language regarding period of performance dates

Item 3. Specifications Section 08 14 13 Stile and Rail Doors

ADD Section 2.2.B.2 Face Veneer Grade: AA

Item 4. Specifications Section 10 14 00 Signage

ADD Section 1.2.A.3 Pre-spaced self-adhesive vinyl vinyl letters at north wall of Corridor 02239 (Option 5).

ADD Section 2.2 Applied Vinyl: Die-cut characters from vinyl film of nominal thickness of 3 mils (0.076 mm) with pressure-sensitive adhesive backing, suitable for exterior applications.

PHASE 1 & PHASE 2

Addendum No. 1 January 13, 2020

Item 5. Specifications Section 10 22 19 Demountable Partitions

ADD construction, finish, electrical, and hardware details

Item 6. Specifications Section 11 14 13 Turnstiles

ADD basis of design product, 56” high tempered glass panels

PHASE 1 DRAWINGS

Item 7. Drawing G-002

ADD 2 doors as per Keynote 2

REVISE 1 door to be 44” wide

CLARIFY area for passage of contractors but not for work

ADD sticky mats

CLARIFY Elevator 10 as designated elevator for construction access

CLARIFY protection materials and extent

Item 8. Drawing G-003

CLARIFY protection materials and extent

Item 9. Drawing AD-102

ADD The following note: “Salvage existing wood paneling from north wall of Room 2580.”

Item 10. Drawing A-112

CLARIFY bar grill at south end of Case Admin 02234. In lieu of “New continuous linear diffuser bar grill” note shall read “New architectural linear bar grille for entire length along existing curtain wall.”

PHASE 1 & PHASE 2

Addendum No. 1

Item 11. Drawing A-502

ADD General Notes.

Item 12. Drawing A-701

ADD Partition Types T9, T10, T11 and T12.

Item 13. Drawing A-731, Detail 11

CLARIFY spacing of angle bracket

DELETE plastic laminate access panel

REPLACE with solid surface removable access panel with concealed fasteners and hardware.

(SS-6)

Item 14. Drawing A-731, Detail 13

ADD solid wood finger pull and stop.

Item 15. Drawing A-732, Detail 5

ADD blocking at apron

CLARIFY solid surface SS-1 material top and apron.

Item 16. Drawing A-732, Detail 9

ADD plastic laminate PL-1 at banquette apron

Item 17. Drawing A-900

CLARIFY wallcovering at fabric wrapped panels FP-2, FP-3, FP-4. (Carnegie Xorel)

CLARIFY thickness of fabric wrapped panel insulating material (2” thick)

Item 18. Drawing A-910

CLARIFY Door types, material, widths, thickness, and hardware sets.

CLARIFY Door and frame assembly for Doors 01125 and 01125A shall be STC 55.

CLARIFY the following doors are existing/relocated 1080A, 1080B, 1080C, and 01188.

Item 19. Drawing A-911

PHASE 1 & PHASE 2

Addendum No. 1

CLARIFY Door Types 5 and 6 shall be transparent finish wood veneer doors with hardwood reveal to match existing.

Item 20. Drawing DM-102

CLARIFY extent of existing trunk ducts to remain

Item 21. Drawing M-102

CLARIFY new ductwork to accommodate 2 areas of high ceiling at either end of main Corridor 02239 including at Circulation Hub 02119A.

Item 22. Drawing E-102

CLARIFY at Training AV Closet 02249, the (4) AV conduits shall be routed vertically through column enclosure at Grid F and Grid 10.

Item 23. Drawing E-202

ADD Type L16 recessed continuous linear light fixture to illuminate the tiled wall (east wall) in Break Room 02248 similar at Phase 2 Probation Staff Lounge 01032. Run fixture north-south along the entire length of wall.

PHASE 2 PROBATION DRAWINGS

Item 24. Drawing G-002 1st Floor South – Temporary Facilities

CLARIFY designated passenger elevator for construction access

Item 25. Drawing G-003 1st Floor South – Temporary Facilities

CLARIFY Ceiling Condition at third floor, below poke throughs in Training Room 040144.

Item 26. Drawing A-112 First Floor North Reflected Ceiling Plan

CLARIFY partition to jog around existing duct

Item 27. Drawing A-701 Partition Types

ADD Partition Types T9, T10, T11 and T12.

ADD Top of Wall Details

Item 28. Drawing M-102 1st Floor North Mechanical Plan

PHASE 1 & PHASE 2

Addendum No. 1

ADD Fire Dampers/Fire Smoke Dampers

ADD Duct Wrap

MODIFY Ductwork

Item 29. M-103 4th Floor Mechanical Plan

ADD Fire Dampers

PHASE 2 JOHNSON STREET DRAWINGS

Item 30. Drawing A-101 Demolition and New Construction Floor Plan

CLARIFY restoration of materials

Item 31. Drawing A-102 Ceiling Plan

CLARIFY cleaning of ceiling

ATTACHMENTS

Specifications

TOC

011000 Summary 102219 11413

Phase 1 Drawings

G-002 1st Floor South – Temporary Facilities G-003 2nd Floor North – Temporary Facilities A-502 Demountable Partitions Elevations A-701 Partition Types A-731 Millwork Details II A-732 Millwork Details III A-900 Finish Legend A-910 Door Schedule DM-102 2nd Floor Mechanical Demolition Plan M-102 2nd Floor Mechanical Plan

Phase 2 Probation Drawings G-002 Ground Floor – Temporary Facilities G-003 1st Floor South – Temporary Facilities A-112 First Floor North Reflected Ceiling Plan A-701 Partition Types

PHASE 1 & PHASE 2

Addendum No. 1

M-102 1st Floor North Mechanical Plan M-103 4th Floor Mechanical Plan

Phase 2 Johnson Street Drawings A-101 Demolition and New Construction Floor Plan

A-102 Ceiling Plan

****END OF ADDENDUM****