This solicitation notice seeks proposals for general construction services for the Bankruptcy and Probation Courts Consolidation Project at the Conrad B. Duberstein Courthouse in Brooklyn, New York. The project involves renovations across multiple floors of the courthouse building. The General Services Administration (GSA) Northeast and Caribbean Region Public Buildings Service will administer the contract as a total small business set-aside, where the applicable NAICS code is 236220 with a size standard of $39.5 million average annual receipts. Interested small businesses should review the full solicitation documents available through SAM.gov and attend the pre-proposal conference scheduled for December 19, 2019. Proposals are due on the date specified in the solicitation. The selected contractor will be responsible for renovations including demolition, concrete, masonry, metals, woodwork, thermal/moisture protection, openings, finishes, specialties, equipment, furnishings and conveying equipment.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum 1
January 13, 2020
Bankruptcy & Probation Consolidation TABLE OF CONTENTS Conrad B. Duberstein U.S. Courthouse TOC-1
SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT. FOR OFFICIAL USE ONLY Do not remove this notice. Properly destroy or return documents when no longer needed.
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
DIVISION 2 - EXISTING CONDITIONS
SECTION
02 41 19 Selective Demolition
DIVISION 3 - CONCRETE
03 54 16 Cement Leveling Compound
DIVISION 4 - MASONRY
04 90 00 Stone Restoration
DIVISION 5 - METALS
05 50 00 Miscellaneous Metals 05 70 00 Ornamental Metalwork 05 73 13 Ornamental Glass Rail System
DIVISION 6 - WOOD, PLASTICS AND COMPOSITES
06 10 53 Miscellaneous Rough Carpentry 06 40 23 Interior Architectural Woodwork 06 61 16 Solid Surface Fabrications
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07 81 00 Sprayed Fire Resistive Materials 07 84 13 Firestopping 07 84 43 Joint Firestopping 07 92 00 Joint Sealants 07 92 19 Acoustical Joint Sealants
Conrad B. Duberstein U.S. Courthouse TOC-2
DIVISION 8 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08 14 16 Flush Wood Doors 08 14 13 Stile and Rail Wood Doors 08 41 26 All Glass Doors and Partitions 08 52 80 Ballistic Security Windows 08 71 00 Hardware 08 80 00 Glazing 08 83 00 Mirrors
DIVISION 9 - FINISHES
09 01 20 Interior Plaster Patching 09 22 16 Non-Structural Metal Framing 09 27 13 Glass Fiber Reinforced Fabrications 09 29 00 Gypsum Drywall 09 30 13 Ceramic Tiling 09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Tile Flooring 09 68 13 Tile Carpeting 09 69 00 Access Flooring 09 71 13 Glass Reinforced Gypsum Fabrications 09 75 00 Interior Stone Facing 09 77 23 Fabric Wrapped Panels 09 91 23 Interior Painting 09 98 00 Special Coatings
DIVISION 10 - SPECIALTIES
10 14 00 Signage 10 21 13 Toilet Partitions 10 22 19 Demountable Partitions 10 28 13 Toilet Accessories
DIVISION 11 - EQUIPMENT
11 14 13 Turnstiles 11 18 00 Security Equipment
Conrad B. Duberstein U.S. Courthouse TOC-3
DIVISION 12 - FURNISHINGS
12 24 13 Window Shades 12 36 61 Quartz Countertops 12 48 13 Entrance Mats
DIVISION 13 - SPECIAL CONSTRUCTION
NOT USED
DIVISION 14 - CONVEYING EQUIPMENT
NOT USED
DIVISION 21 - FIRE SUPPRESSION
21 00 00 General Requirements for Fire Suppression 21 01 00 Operation and Maintenance of Fire Suppression 21 05 00 Common Work Results for Fire Suppression 21 05 19 Meters and Gauges for Fire Suppression Systems 21 05 23 General-Duty Valves for Water-Based Fire Suppression Piping 21 05 29 Hangers and Supports for Fire Suppression Piping and Equipment 21 05 48.13 Seismic Controls for Fire Suppression Piping and Equipment 21 05 53 Identification for Fire Suppression Piping and Equipment 21 12 00 Fire Suppression Standpipes 21 12 23 Fire Suppression Hose Valves 21 13 13 Wet-Pipe Sprinkler Systems
DIVISION 22 - PLUMBING
22 00 00 General Requirements for Plumbing 22 01 00 Operation and Maintenance of Plumbing 22 05 00 Common Work Results for Plumbing 22 05 19 Meters and Gauges for Plumbing Piping 22 05 23 General-Duty Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 48.13 Seismic Controls for Plumbing Piping and Equipment 22 05 53 Identification for Plumbing Piping and Equipment 22 05 76 Facility Drainage Piping Cleanouts 22 07 00 Plumbing Insulation 22 11 16 Domestic Water Piping 22 11 19 Domestic Water Piping Specialties 22 13 16 Sanitary Waste and Vent Piping
Conrad B. Duberstein U.S. Courthouse TOC-4
22 13 19 Sanitary Waste Piping Specialties 22 33 00 Electric Domestic Water Heaters 22 42 00 Commercial Plumbing Fixtures
DIVISION 23 - HEATING, VENTILATING AND AIR CONDITIONING
23 00 00 General Requirements for HVAC Work 23 01 00 Operation and Maintenance of HVAC Systems 23 05 00 Common Work Results for HVAC Work 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 14 Common Motor Control Requirements for HVAC Equipment 23 05 16 Expansion Fittings and Loops for HVAC Piping 23 05 19 Meters and Gauges for HVAC Piping 23 05 23 General-Duty Valves for HVAC Piping 23 05 24 Relief Valves for HVAC Systems and Equipment 23 05 25 Strainers for HVAC Systems 23 05 29 Hangers and Supports for HVAC Piping, Ducts and Equipment 23 05 48.16 Vibration Isolation for HVAC Piping, Ducts and Equipment 23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 00 HVAC Insulation 23 09 00 Instrumentation and Control for HVAC Systems 23 09 93 Sequence of Operations for HVAC Controls 23 21 13 Piping for HVAC Systems and Equipment 23 21 16 Hydronic Piping Specialties 23 21 23 Hydronic Pumps for HVAC 23 31 13 Metal Ducts 23 31 19 HVAC Casings and Plenums 23 33 13 Dampers 23 33 19 Duct Silencers and Acoustic Treatment 23 33 33 Ducts, Casings and Plenum-Mounted Access Doors 23 33 43 Flexible Connectors 23 34 00 HVAC Fans 23 36 00 Air Terminal Units 23 37 13 Diffusers, Registers and Grilles 23 41 00 HVAC Air Filtration Products 23 81 23 Packaged Self-Contained Computer Room Air Conditioners
(CRAC)/Technology Room Air Conditioners (TRAC) 23 82 33 Convectors and Radiant Heaters
DIVISION 26 - ELECTRICAL
26 00 00 General Requirements for Electrical 26 05 00 Common Work Results for Electrical 26 05 07 Access Doors and Color-Coded Identification in General Construction 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 20 Heating Cable
Conrad B. Duberstein U.S. Courthouse TOC-5
26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 33.23 Surface Raceways for Electrical Systems 26 05 36 Cable Trays for Electrical Systems 26 05 48.13 Seismic Controls for Electrical Systems 26 05 48.16 Vibration Isolation for Electrical Systems 26 05 53 Identification for Electrical Systems 26 05 73 Overcurrent Protective Device Coordination, Short Circuit and Arc-Flash
Analysis 26 09 23 Lighting Control Devices 26 22 13 Low-Voltage Distribution Transformers 26 24 16 Panelboards 26 27 13 Electricity Submetering 26 27 19 Multi-Outlet Assemblies 26 27 26 Wiring Devices 26 28 16 Enclosed Switches and Circuit Breakers 26 51 00 Interior Lighting
DIVISION 27 - COMMUNICATIONS
27 00 00 General Work Results for Communications 27 04 00 Ladder Rack 27 05 26 Grounding and Bonding for Communications Systems 27 10 00 Conduit 27 11 00 Equipment Room Fittings 27 11 16 Communications Cabinets, Rack, Frames, and Enclosures
27 51 19 Electronic Sound Masking System
DIVISION 28 – ELECTRONIC SAFTETY AND SECURITY
28 05 00 Common Work Results for Security Management Systems 28 05 26 Grounding and Bonding for Security Management Systems 28 31 00 Fire Detection and Alarm
Bankruptcy & Probation Consolidation SUMMARY Conrad B. Duberstein U.S. Courthouse 011000
SECTION 011000 – SUMMARY
PART 1 - GENERAL
1.1 PROJECT INFORMATION
A. Project Name and Location:
1. Bankruptcy and Probation Consolidation, Conrad B. Duberstein Courthouse
2. 271 Cadman Plaza, Brooklyn, NY 11201
B. Project Summary Description:
We understand that the project entails the design and build-out of office space for the consolidation of
Bankruptcy and Probation as follows:
Bankruptcy (Phase I): Renovation of 5,041 SF of space on the First Floor, 13,798 SF on the Second Floor and paint and carpet upgrades to 3,125 SF of office space within Zone 3 Historical Space on the second floor. We understand that this 3,125 SF space is classified as a “Free Zone” and that renovations should
“respect any historic elements (windows, doors, trim. Cornices, fireplaces and any other Historic Features).
Probation (Phase 2): Renovation of 1,276 SF on the Ground Floor, 29,856 SF on the First Floor, 8,201 SF on the fourth floor. We understand that the First Floor main lobbies, atrium, Johnson Street entrance, and exterior of the building are designated Zone 1 Preservation Zones. These spaces are public and historic. All work within Zone 1 will conform to the restoration guidelines and will be conducted with the input of a
Historic Preservation Specialist from RMA. We understand that all design recommendations are subject to review by GSA Historic Preservation specialist, David Anthone, for NHPA compliance including door signage, door security access hardware, cameras.
C. Architect: The term Architect refers to the project designer. The Architect's status relative to the construction will be stated in writing by the Contracting Officer prior to the pre-construction conference. The project was designed by: Dattner Architects
D. Project Delivery Method: traditional
E. Key Consultants
1. MEP Engineer
2. Structural Engineer
3. Historical Consultant
4. Acoustics
5. Lighting Design
F. Commissioning Agent – TBD
G. Construction Manager - A CMa will be on site 5 days per week for the duration of the construction in both the base contract and option 1.
H. All roles will be delineated in writing by the Contracting Officer prior to or at the pre-construction conference.
I. Phasing
The project has two phases. The base contract is for renovation of the US Bankruptcy Court space at the first and second floors. This is “phase 1.” Option 1 of the contract is for space for which is for the US Probation Office on the ground floor, first floor and fourth floor. Option 1 work will begin after the completion of the base contract work. This is “phase 2.”
J. Period of Performance
(1) Commencement. The Contractor shall commence performance of the Work within 10 days after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 238 calendar days from issuance of Notice to Proceed (NTP) for phase 1 and no later than 280 calendar days from issuance of Notice to Proceed (NTP) for phase 2.
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 28 calendar days of Substantial Completion for phase 1 and within 42 calendar days of Substantial Completion for phase 2.
K. Property: The project includes the following Government furnished property to be installed by the
Contractor. The contractor shall advise GSA at least 30 days in advance of when the property should be delivered.
1. MILO projector
1.5 MISCELLANEOUS PROVISIONS
A. Work in existing facilities shall correspond in all respects with the existing conditions to which it connects, or to similar existing conditions, in materials, workmanship and finish.
B. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract.
Work out of alignment where exposed by removal of existing work shall be called to the attention of GSA. Necessary corrective work shall be as directed.
1. Replacements of existing conditions that are removed shall match similar existing conditions.
2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.
3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.
4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.
C. Existing structures will remain in place.
D. Existing utility services with related meters and equipment will remain in place.
E. Removed items indicated to remain the property of the Government shall be stored on site where directed by the Contracting Officer.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 011000
Bankruptcy & Probation Consolidation DEMOUNTABLE PARTITIONS Conrad B. Duberstein U.S. Courthouse 10 22 19-1
SECTION 10 22 19 - DEMOUNTABLE PARTITIONS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 BUY AMERICAN REQUIREMENTS
A. The Contractor shall adhere to any and all requirements of FAR Subpart 25.2, also known as the “Buy American Act”, and other federal trade agreements as applicable to this specific Contract.
B. Additional information on the Buy American requirements can be found at the Federal Acquisition Regulation website (http://www.acquisition.gov/far/).
1.3 SUMMARY
A. Section Includes:
1. Manufactured partition framing assemblies.
2. Glass and glazing.
3. Doors, frames, and door hardware.
4. Accessories.
B. Related Requirements:
1. Section 08 71 00 "Finish Hardware."
2. Section 08 80 00 "Glass and Glazing."
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for integrated prefabricated interior partitions.
2. Provide product data sheets for all types of hardware, fasteneings and accessories.
B. Samples: Submit samples of each required finish and color. Prepare samples on same materials which will be used in partition assemblies.
1. Provide manufacturer's standard size samples for verification of support system and each type, color, and texture of exposed finish, full thickness and the following minimum sizes:
a. Extrusion components.
b. Tile finishes.
c. Linear trim and base.
d. Door face finishes.
e. Glazing.
Conrad B. Duberstein U.S. Courthouse 10 22 19-2
C. Shop Drawings: Submit shop drawings for fabrication and erection of partition assemblies which are not fully described by manufacturer's data. Show anchorage and accessory items and finishes.
D. Coordination Drawings
1. Provide all final engineered drawings relevant to material inclusions within, or connections to the moveable wall product.
2. Provide architectural plans locating moveable wall products, including wall finishes and construction of surfaces with which the moveable wall system interfaces with or connects to.
3. Electrical Drawings: Coordinate electrical provisions to be included in moveable partitions with final circuited electrical engineering drawings and schedules.
1.5 QUALITY ASSURANCE
A. Manufacturer: Provide office partition system manufactured by a single firm specializing in production of this type of work, with a minimum of three (3) years' experience.
B. Installer Qualifications: All products listed in this section shall be installed by a single installer with a minimum of two
(2) years' documented experience in installing products of the same type and scope as specified, and must be approved by the manufacturer.
C. Shop Assembly: Preassemble items in shop to greatest extent possible. Disassemble units only to extent necessary for shipping and handling limitations. Clearly mark units for reassembly and coordinated installation.
D. Glazing materials shall comply with the requirements of 16 CFR Part 1201 and/or ANSI Z97.1-2004, and shall bear markings as required by Chapter 24 of the International Building Code.
1.6 PERFORMANCE REQUIREMENTS
A. Structural Performance: Modular partitions shall be capable of withstanding the effects of gravity loads, dead loads, and the following loads and stresses within limits and under conditions indicated:
1. Transverse Load: Lateral deflection of the overall span when tested under a uniformly distributed load of 5 psf in accordance with ASTM E72 where L = modular partition wall height:
a. Solid Walls: Not more than L/120.
b. Glass Walls: Not more than L/175 or 3/4 inch (19 mm) which ever is more stringent.
2. Mechanical Strength: Capable of withstanding static loads in accordance with ANSI/BIFMA X5.6.
3. Seismic Performance: Provide modular partitions capable of withstanding effects of seismic motions determined according to the currently adopted building codes.
B. Acoustical Performance: Where STC ratings are indicated, provide partitions with STC rating determined by testing an identical system to ASTM E90 and classified in accordance with ASTM E413.
1. Sound Transmission Coefficient (STC) range shall be determined in accordance with Sound Transmission Test by Two-Room Method and reported in accordance with ASTM E90 and ASTM E413 for frequency data.
Tested assembly shall have been assembled in the same manner the modular partitions to be installed on the project.
2. Test results vary based on glass or solid wall configuration, and implementation of perimeter enhancements at base building connections.
Conrad B. Duberstein U.S. Courthouse 10 22 19-3
a. Solid wall results range up to 50 STC performance.
b. Glass wall performance is limited by the glass specified. Coordinate requriements with the modular partition manufacturer.
C. Surface-Burning Characteristics: Tested in accordance with ASTM E84 by a qualified independent testing agency.
1.7 DELIVERY, STORAGE AND HANDLING
A. Deliver aluminum panel partition components cartoned or crated to provide protection during transit and job storage.
B. Inspect partition components upon delivery for damage. Minor damages may be repaired, provided finish items are equal to new work and acceptable to the Architect. Remove and replace damaged items as directed.
C. Store partition components on raised platforms in vertical positions with blocking between units to allow air circulation. Keep stored material covered and protected from damage.
PART 2 - PRODUCTS
2.1 PARTITION SYSTEM
A. Provide aluminum wall system by DIRTT Environmental Solutions, or other acceptable manufacturers offering functionally and aesthetically equivalent products as indicated on the drawings.
1. Include all wood, glass and metal doors that are an integral part of walls.
2. Construction: Stick built/unitized wall
3. Mullion Extrusion Profile: Rectilinear extrusions
4. Base: Low profile base
5. Frames: Slate Powdercoat
6. Style 1: Two lite – centermount frame
7. Style 2: Glass over solid wall stack
8. Style 3: Single sided TAOS wall
9. Glass for frames:
a. 6mm clear tempered glass
b. 10mm clear tempered glass
10. Tiles for solid wall:
a. Dove DC52 chromacoat
b. Xorel nexus 910- fabric wrapped tile
c. Xorel nexus 905- fabric wrapped tile
d. Australian Walnut quarter cut veneer
e. Write away tile – darkred
f. Magnetic markerboard
11. Barn doors: (qty62) 4” style aluminum with glass insert
Conrad B. Duberstein U.S. Courthouse 10 22 19-4
12. Glass for barn doors: 6mm clear tempered glass
13. Barn door hardware:
a. Dirtt barn door track with slowdown close
b. Dirtt 30” bar pull
c. Accurate 9100ADAL-3 entry lock set, with standard factory keys
14. Electric: (233) level one – one gang modular box; includes factory installed box with cutout in tile and faceplates. Wiring and devices by others.
15. Electric: (4) level one – two gang modular box; includes factory installed box with cutout in tile and faceplates. Wiring and devices by others.
16. Electric: (43) level one – three gang modular box; includes factory installed box with cutout in tile and faceplates. Wiring and devices by others.
1.
2.2 SYSTEM DESCRIPTION
A. Factory assembled, site installed, moveable, reusable interior solid and glazed partitions, including structure, face mounted finished tiles, modular and non-modular metal framing and doors to accept a variety of millwork, finishes, building services components, technology, and accessories.
B. System is floor-supported, floor-to-ceiling site constructed in configurations shown on the Shop Drawings. Top channels hold modular partitions in place and accommodate height adjustments to suit floor-to-ceiling dimensional variations and similar site specific requirements.
1. Where modular partitions are not clipped to ceilings or other overhead construction, additional structural review and system engineering will be required by the manufacturer.
C. Panel Attachment: Unitized aluminum frame assembly to support face mounted tiles in orientation and module increments as shown on the Drawings.
D. Partially Unitized Solid Wall system shall be comprised of modular components which can be disassembled, relocated / field cut and substantially reused.
E. Face tiled finishes applied to lightweight frame system, may be monolithic or segmented with the ability to span off-module, or across multiple frames in segments or monoliths, vertically and horizontally.
F. Manufacturer shall provide integrated strategy for accommodating accessory channels and reveals integrated into the structural frame allowing universal horizontal alignment to support millwork, furniture, storage and accessories without defacing or damaging face tile or structural frame.
1. Materials manufactured by others shall not exceed the modular partition manufacturer’s limitations or tested performance.
G. Manufacturer shall provide accommodation / provision for the embedding of technology in the wall cavity: structural framing shall allow for universal non standard AV display, sound, and various support equipment to be mounted in the cavity of the wall with all required structural brackets, wire management, access and ventilation equipment to prevent overheating.
Conrad B. Duberstein U.S. Courthouse 10 22 19-5
H. Manufacturer shall provide ability for independent configuration / finish. Each side of wall must have the capability for variable aesthetic and function to suit different requirements. This will allow for the one side of the wall to have a totally independent function than the other to meet each organizations requirement.
I. Manufacturer shall accommodate and provide provisions for additional embedded elements (ie sofas, exam tables, chaises, charting stations, and millwork) in the wall cavity as documented.
1. Embedded elements and accessories to be provided by others may require additional engineering for structural framing and supports within modular partitions. Submit documentation of all items to be mounted to or embedded in modular partitions for manufacturer review and approval.
2. Do not proceed with procurement or fabrication without modular partition manufacturer’s review and approval
J. Electrical and Communications Access: 1 inch (25 mm) to 3 inches (75 mm) clear wall cavity for accessible from either side of partition by removable face tiles.
K. Provide back boxes, supports, and conduit as required to accommodate data, security and communications indicated on shop drawings. Modular partition manufacturer to provide continuous 1 inch (25 mm) open cavity vertically and horizontally between all frames.
L. Modular partition manufacture shall allow for adaptability and retrofitting of hardware for future division of partitions, tiles, or supports to the greatest extent practical.
2.3 MODULAR PARTITION FRAMING
A. Framing for Solid Partitions
1. Material: Aluminum extrusions, 6063T6 aluminum alloy, thickness engineered to meet performance requirements specified above.
2. Vertical Support Spacing: 6 inch minimum to 48 inch maximum.
3. Ceiling Track: Continuous, with intermittent breaks for pass through of building services or structural components.
4. Floor Track: Modular with wall frames inclusive of carpet grippers or floor tape (non-seismic) or continuous with floor anchor attachment (seismic) stopped at doorways and pass-throughs.
5. Bracing: as required to meet structural performance.
6. Fasteners: Zinc Plated Steel Type F Screws unless otherwise indicated on engineered shop drawings.
B. Framing for Glazed Partitions: Same as solid panel framing with customized spacing as shown on the Drawings.
Maximum spacing 60 inches.
C. Frame Bases
1. Provide frame bases with provisions for 1-1/2-inch height adjustment to accommodate floor slab variances.
2. Provide a leveling mechanism for making fine adjustment in height over adjustment range of the product.
2.4 GLASS AND GLAZING
A. Tempered glass minimum thickness 1/4 inch to ASTM C1048, Kind FT (fully tempered), Condition A (uncoated), Type 1, Class 1 (transparent), Quality q3.
2.5 DOORS AND DOOR HARDWARE
A. Aluminum and Glass Doors: See Door Schedule.
Conrad B. Duberstein U.S. Courthouse 10 22 19-6
B. Wood Doors: Conform to the requirements of Section 081416, "Wood Doors."
C. Door Hardware: All frames shall be prepped for their corresponding concealed and exposed door hardware.
Conform to the requirements of Section 087100.
2.6 DOOR FRAMES
A. Butt Hinge Frames: Manufacturer's standard aluminum frame single door, factory milled to receive hardware. Door frames capable of reconfiguration without part replacement or damage to wall components.
1. Frame Finish: Powder coated, color as selected by the Architect.
2. Door Module Size: As scheduled.
a. Finished door width is equal to module width less 3 inches.
3. Configuration: Header, jambs and pivot hardware. Single door frame width not to exceed 51 inch wide module.
4. Hardware Reinforcement: milled, reinforce, drill and tap frames at factory to receive specified hardware in accordance with the contract hardware schedule and templates.
5. Frame Height: Jambs over length 2 inches, for field cutting to suit opening height for proper alignment with adjacent frames.
6. Frame Preparation: Factory milled frame with hinge locations and sizes as determined and set by manufacturer; including factory installed steel backer plates for four (4) hinges (2 pair):
a. Hinges: 4-1/2 x 4 Stanley BB1409 fastened with 10-24 flat head machine screws.
b. For C.O.M. doors, conform to modular partition manufacturer's standard size, hole pattern and fastener type for hinges, levers or pulls to be supplied by others.
7. Electrical Requirements
a. Security System Components: Coordinated hardware requirements and prep work for security system components (supplied by others including but not limited to: electronic strikes, Magnetic locks, electrified locksets, hinges, request to exit buttons, motion sensor rex, door position contacts).
8. Factory notched and drilled jambs for ceiling track and manufacturer’s standard header attachment.
9. Extrusion Profile: Rectilinear profile to match any adjacent unitized glass frames.
10. Seals: Manufacturer's standard.
2.7 ACCESSORIES
A. Connections and Supports: Manufacturer's standard connections and supports that connect and release from floor and ceiling without damage using carpet grippers and ceiling track clips, with exception of the following conditions:
bulkhead (drywall ceiling), seismic conditions, electrical or service feeds, physical connections to base building (where required).
B. Panel Joint Closure: Manufacturer's standard, capable of closing up to a 1 inch gap between aluminum partitions and base building elements.
C. Trim: Continuous and modular, factory finished, snap on type; field cuttable for variations in floor and ceiling levels.
1. Base Trim Profiles: Recessed; removable to access leveling mechanisms.
Conrad B. Duberstein U.S. Courthouse 10 22 19-7
2. Ceiling Trim Profile: Recessed; adjustable to accommodate up to a 1/2 inch gap between aluminum partitions and base building elements.
3. Wall Trim Profile: Recessed; adjustable to accommodate up to a 1/2 inch up to 1 inch gap between aluminum partitions and base building elements.
4. Tile to Tile Profile: As detailed.
5. Colors: As selected by Architect from manufacturer's full range.
D. Brackets
1. Manufacturer's brackets, supports and accessories for complete installation of system's furniture components, architectural millwork, audio visual equipment, and paper accessories.
2. Provide bracket design to enable other system furniture to mount to modular partitions, on or off module.
2.8 FABRICATION
A. Modular Tiles: Unless otherwise inducated on shop drawings, factory assembled frames with 1 inch insulation, base track and levellers; face mounted tiles installed to frames on site.
B. Components
1. Fabricate components for installation with concealed fastening devices and pressurefit members that will not damage ceiling or floor coverings. Exceptions: Drywall ceiling, seismic applications and doors against base building require screw holes in base building for proper fastening.
2. Fabricate for installation with manufacturer’s standard seals at floor and other locations where partition assemblies abut fixed construction and for installation of sound attenuation insulation in partition cavities.
2.9 FINISHES
A. TBD.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine the areas and conditions where aluminum partition system is to be installed and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected by the Contractor in a manner acceptable to the Architect.
3.2 INSTALLATION
A. Install partitions after floor coverings and suspended drywall ceilings have been installed. Coordinate partition work with work of other trades which are affected by partition installation. Avoid damage to installed work.
B. Repair damaged or defaced work or replace with new work, as acceptable to Architect. Completely refinish defaced partition components with factory-finished materials or replace defaced components.
C. Furnish, drill for and install anchoring devices required, and secure partitions to floor, ceiling and walls, using concealed fasteners.
D. Install partitions rigid, level, plumb and in alignment, with components secure together, in accordance with manufacturer's instructions.
Conrad B. Duberstein U.S. Courthouse 10 22 19-8
E. Provide through posts to ceiling, or other concealed supports as required to ensure lateral stability of partition runs.
F. Install continuous and positive seal to prevent light and sound transmission at partition contacts with floor, ceiling, wall and other abutting surfaces.
3.3 DEMONSTRATION
A. Engage a factory-authorized service representative to demonstrate and train Owner's maintenance personnel to adjust, operate, and maintain demountable partitions.
END OF SECTION 10 22 19
Bankruptcy & Probation Consolidation Johnson Street Scope TURNSTILES Conrad B. Duberstein U.S. Courthouse 11 14 13-1
SECTION 11 14 13 TURNSTILES
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
A. Work of this Section, as shown or specified, shall be in accordance with the requirements of the Contract Documents.
1.2 BUY AMERICAN REQUIREMENTS
A. The Contractor shall adhere to any and all requirements of FAR Subpart 25.2, also known as the “Buy American Act”, and other federal trade agreements as applicable to this specific Contract.
B. Additional information on the Buy American requirements can be found at the Federal Acquisition Regulation website (http://www.acquisition.gov/far/).
1.3 SECTION INCLUDES
A. The Work of this Section includes all labor, materials, equipment, and services necessary to complete the pedestrian control equipment as shown on the drawings and/or specified herein.
1.4 RELATED SECTIONS
A. Electrical - Division 26.
1.5 QUALITY ASSURANCE
A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.
1.6 SUBMITTALS
A. Product Data – Submit:
1. Materials list of items proposed to be provided under this Section.
2. Manufacturer’s specifications and other data needed to prove compliance with the specified requirements.
B. Shop Drawings: Provide in sufficient detail to show fabrication, installation, anchorage, and interface of the work of this Section with the work of adjacent trades.
C. Manufacturer’s recommended installation procedures.
1.7 PRODUCT HANDLING
A. Protection: Use all means necessary to protect the materials of this Section before, during, and after installation, and to protect the installed work and materials of all other trades.
B. Replacements: In the event of damage, immediately make all repairs and replacements necessary.
Conrad B. Duberstein U.S. Courthouse 11 14 13-2
1.8 WARRANTY
A. Warranty turnstile against defects in materials and installation for a period of 3 years.
PART 2 PRODUCTS
2.1 MANUFACTURER
A. Turnstile shall be ______ turnstile unit made by _____, or approved equal.
A. Basis-of-Design Product: Subject to compliance with requirements, provide Boon Edam; Speedlane Lifeline Swing Type, with 56" high tempered glass panels, or approved equal.
B. General: Provide turnstiles consisting of operator and controller housed in cabinet enclosure with restrictive barrier arms. Device shall be activated by a signal from optical access control device.
1. Turnstiles shall meet ADA (Americans with Disabilities Act) requirements.
2. Turnstiles shall be CSA/ UL 325 Certified. (Must provide Certificates.)
3. Drive Mechanism
a. Passage barrier arms electronically controlled in both directions, via direct drive intelligent positioning (DDIP) induction sensor control motor.
b. The opening and closing speeds of the barriers are adjustable.
c. Safety photocell prevents the barriers from closing upon an obstruction. Should the normal barrier operation be stopped by an obstruction, the controlling logic detects an abnormal condition and generates an alarm.
4. Method of Operation: On receiving a signal from the access control system, or remote control device, the barriers will open. If an unauthorized person tries to tailgate or attempts to enter from the opposite direction, the system detects the unauthorized passage and activates the built-in alarm system.
a. The turnstiles shall, without significant modification, accept mode selection from a remote source. In addition to these functions, turnstiles shall have automatic resetting of alarms and shall be capable of providing remote access to authorized persons not in possession of a valid access card.
5. LED Indicator Light: 2" diameter LED display light flush mounted within the turnstile top or front face. The
Green badge symbol is continuously illuminated indicating passage is available. Upon authorization a Green Arrow will illuminate in the direction of passage authorization while in the opposite direction a Red Cross symbol will illuminate to indicate the unit is not available for use or is already in use.
6. Power Failure: In the event of a power failure the unit will be totally de-energized and the arms will fail open.
7. Fire Alarm: Input facility is available for voltage free contact supplied by others to effect fail state.
8. Power Supply: 120V AC 60Hz (50Hz available). The circuit is fed via a remote mounted step down transformer supplied with the unit.
9. Power Rating:
a. Stand by or passage use: 120VA.
b. Alarm condition including barrier movement: 140VA.
a.
Conrad B. Duberstein U.S. Courthouse 11 14 13-3
10. Logic Voltage: 24V DC.
11. Installation Details: The turnstile pedestals are delivered as fully assembled units.
C. Card Reader Mounting: Integration of Access Control Readers into turnstile top.
1. Process is achieved using manufacturer's standard 4" x 9" card reader inlay with "present card symbol." Inlay to include LED indicator light pictogram flush mounted into the turnstile lid.
D. Push Button Control
1. Simple console to control OptiStile barrier release.
2. Remote console to specific requirements.
E. Additional Interface: RS 485 Serial Interface
F. Traffic Flow Control
1. LED Way Mode Indicator - Switching Red cross and Green arrow to indicate the unit is available for use.
2. Remote switching of unit for Traffic Flow.
G. Provide manual release device and signage indicated such.
2.2 CONSTRUCTION
A. Casing: Manufactured from #4 brushed stainless steel.
B. Door Wing: Manufactured of 10mm flat, transparent tempared glass.
C. Top Plate: Manufactured from black tempered glass in a stainless steel casing.
2.3 EQUIPMENT
A. Drive System: Electromechanical drive system specially designed for the Speedlane mounted inside the cabinet(s) together with all of the controls. The drive system may allow for bi-directional or one way traffic.
(Requires 110-240 VAC, 1 Phase, 13 A service from below)
B. Locking Device: The locking device is activated in the closed position and will withstand up to 120Nm pushing force.
C. Power Loss: In the event of power loss, the Speedlane Swing barriers can open manually for egress.
D. Controls: Factory installed, purpose built microcontroller platform with embedded custom software.
E. Power Saving Mode / Sleep mode: The Speedlane Swing will go into sleep or power saving mode after pre-set time, wake-up detection by sensors in the leading face.
F. Inputs: The Speedlane Swing can accomodate up to 6 programmable inputs plus a dedicated input for fire alarm.
G. Outputs: The Speedlane Swing has 6 programmable outputs (Contact State is Normally Open) provided by Boon Edam.
Conrad B. Duberstein U.S. Courthouse 11 14 13-4
H. Sensors: The Speedlane Swing has 14 standard sensors; 10 that span the top inside of the cabinet to detect individiuals in the field of travel and two each at entry and exit of the cabinet at a mid and low height.
I. Jump Over Sensors: The Speedlane Swing has sensors located on the top of the cabinets to detect individauls attempting to go over the cabinet without entering the field of travel.
J. BoonTouch: Universal control panel that can operate up to six different security access solutions from a reception or security desk.
K. Low Object Sensors: Low object sensors shall be installed on the inside plinths of the cabinets to detect objects or individuals that remain in the field of travel but cannot be detected by the top sensors nor have reached the sensors at the exit of the lane. (e.g. Service animals, roller bags, etc.)
2.4 SECURITY EQUIPMENT
A. Actuation: Barrier actuation by card reader under top plate, max dimensions L x W x H: 130x55x50mm (5 7/64x2 11/64x1 31/32 inch).
Although tied into the Speedlane, actuation devices are not by Boon Edam.
2.2 TURNSTILE SYSTEM COMPONENTS
A. Unit Dimensions
1. Casework Length: 60" with rounded ends
2. Casework Height: 37-1/2".
3. Casework Width: 6".
B. Drive: Motorized
C. Function: The turnstiles shall include the following operating modes as standard:
1. Purely Optical (Always Open) - The barrier arms are not used, and alarms will signal unauthorized access attempts or tailgating.
2. Full Time Barrier (Normally Closed) – The barriers remain closed until a valid card is presented. Tailgaters and unauthorized entries are signaled by an alarm tone. If an unauthorized card is presented, the lanes will sound an alarm and the barrier arms will remain closed to prevent the user from proceeding further without intervention by a guard.
3. Pop-Out (Normally Open) – The barrier arms remain retracted unless there is an invalid transaction attempted.
The arms never pop out for free exit transactions. Tailgaters are still singled out with an alarm condition, but will not cause the arms to close.
2.3 FINISH MATERIALS
A. See Drawings.
Conrad B. Duberstein U.S. Courthouse 11 14 13-5
PART 3 EXECUTION
3.1 INSPECTION
A. Examine the areas and conditions where the pedestrian control equipment is to be installed and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work.
3.2 INSTALLATION
A. Coordinate as required with other trades to assure proper and adequate provision in the work of those trades for interface with the work of this Section.
B. Install the work of this Section in strict accordance with the original design, the approved Shop Drawings, pertinent requirements of governmental agencies having jurisdiction, and the manufacturer’s recommended installation procedures.
C. Electrical work shall be performed in accordance with the National Electrical Code.
END OF SECTION