About this file

This document provides details for a solicitation notice for construction services for the Bankruptcy and Probation Courts Consolidation Project at the Conrad B. Duberstein U.S. Courthouse. The General Services Administration (GSA), Northeast and Caribbean Region, Public Buildings Service is seeking proposals for general construction services. The project is located at the Conrad B. Duberstein Courthouse in Brooklyn, New York. This is a total small business set-aside with a NAICS code of 236220 and size standard of $39.5 million average annual receipts. Interested offerors should review all attached solicitation files, which include some sensitive but unclassified documents requiring access through beta.sam.gov. A pre-proposal conference and site visit will be held on December 19, 2019 at 9:00 AM EST at the project location. Proposals are due based on the date specified in the solicitation. Offerors must register in the System for Award Management and submit four paper copies and one electronic copy of their proposal.

View the file

Other files

File Type Posted
Additional Responses for RFIs 1-24-2020.pdf PDF
Solicitation Amendment 2 -SF30.pdf PDF
Duberstein GC Bid Sheets_Rev 2.xlsx XLSX spreadsheet
GSA 012700 Unit Prices FY15 Update Oct. 1 2014.pdf PDF
01 COBie Quick Reference Guide.pdf PDF
RFI Responses Duberstein.pdf PDF
Copy of Specifications Addendum 1.pdf PDF
07 COBie Playbook Training.pdf PDF
Door Hardware Photos2.jpg JPG image
Door Hardware Photos1.jpg JPG image
Copy of Narrative Addendum 1.pdf PDF
02b COBie Requirements Specification.pdf PDF
Door Hardware Photos3.jpg JPG image
Narrative Addendum 1 rev 20-0114.pdf PDF
03b COBie Sample - As-Built Workbook.xlsx XLSX spreadsheet
Solicitation Amendment 1 -SF30.pdf PDF
00 COBie Playbook - READ ME FIRST.pdf PDF
Duberstein GC Bid Sheets_Rev 1.xlsx XLSX spreadsheet
Asset ImpExp Template-simple 7-22-16 (with RKT Edits 6-27-17).xlsx XLSX spreadsheet
06 Quick Start Guide - Definitions.pdf PDF
05 Responsibility Matrix.xlsx XLSX spreadsheet
GSA 012700 Unit Prices FY15 Update Oct. 1, 2014.pdf PDF
SF 1442 Form.pdf PDF
Duberstein Courts Consolidation - Prebid Agenda 2019 12 19.pdf PDF
Walkthrough Sign in 2019 12 19.pdf PDF
Attachment A4 - Past Performance Questionnaire.docx DOCX document
GC Reps&Certs sep19 (1).docx DOCX document
Attachment A1 - Experience Summary Table.docx DOCX document
GSA_Form_527.pdf PDF
Conrad B. Duberstein U.S. Courthouse GC Agreement 2019 12 12.pdf PDF
Wage Determination 2019 12 11.pdf PDF
SF 1442 Form.pdf PDF
Attachment A3 - Sample Key Personnel Resume Format (1).pdf PDF
Conrad B. Duberstein U.S. Courthouse GC Solicitation 2019 12 12.pdf PDF
Duberstein GC SOW - Final (2019.11.18).pdf PDF
GC Bid Sheets.xlsx XLSX spreadsheet
SF24-16d (1).pdf PDF
Attachment A2 - Project Fact Sheet.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COBie Information Delivery Plan (IDP) Template

Project: Sample Building Renovation Version: Number Prepared for: Client Prepared by: Name Transmittal Date: Month DD, Year

TABLE OF CONTENTS

1.Project Information4
2.Version Control5
3.Project Roles & Responsiblities5
3.1.COBie Responsibility Matrix (Detailed)6
3.2.COBie QC Manager6
3.2.1.Duties:6
3.3.Proficiencies:6
4.Software7
5.Deliverables & Due Dates7
5.1.Mobilization Submittal Details7
6.Asset Types in Scope8
6.1.Classification Systems Clarifications8
7.Quality Control8
8.Process Description/ Workflows Diagram9
9.Documents9
9.1.Documents Types in Scope:9
9.2.Document Naming:9
9.3.Electronic Submittal Specifics10
9.3.1.As-Installed Equipment Capture10

1. Project Information

GSA Contract Number:

Task Order Number:

Project Name:

Location:

COBie Version:

Facility Name(s):

Facility Name
Facility Category Code

Submitted By:

Name

Company

Phone

Email

2.

Version Control Prior to making changes to the processes, people or products (tools) involved in the COBie IDP, the IDP must be updated to reflect the changes, re-submitted for review and approved before changes are instated. All changes submitted from the previous COBie IDP version should be made in blue to make them stand out.

Date Submitted
Date Approved
Version Number
Reason for Submission of New Version

← Older - Newer →

3. Project Roles & Responsiblities

Role
Contact Name
Organization
E-Mail
Phone
General Responsibilities

COBie QC Manager (Primary)

COBie QC Manager (Secondary)

Project Manager(s)

Discipline Lead - Electric

Discipline Lead – Mech.

Discipline Lead – Plumb.

Add Other Project Roles..

3.1. COBie Responsibility Matrix (Detailed)

· See appendix A - Provide detailed COBie responsibility matrix (.xlsx template included) as appendix A.

3.2. COBie QC Manager

The COBie Quality Control (QC) Manager shall be responsible for overseeing overall implementation of COBie IDP and will coordinate the extraction, collection, collating, testing, and delivery of all COBie-specified deliverables.

3.2.1. Duties:

· Preparation, approval and implementation of COBie Information Delivery Plan

· Preparation, review, and approval of all COBie-specific submittals

· Preparation, review, and approval of all COBie-formatted submittals

· Documentation and submission of current COBie collection processes

· Documentation, execution, and submission of streamlined COBie collection processes

· Identification, designation, and documentation of all COBie data collection personnel

· Coordination of all COBie data collection personnel to ensure accurate data merging

· Provision of COBie technical expertise to all COBie data collection personnel

· Carry out and lead monthly COBie progress meetings

· Identification, selection, and operation of all applicable COBie-supporting software

· Provision of computer hardware necessary to run all BIM/COBie software programs needed

· Submission of request for equipment photographs, Documentation of Response

· If approved, preparation, review, and approval of equipment photographs

· Submission of request for electronic O&M manuals, Documentation of Response

· If approved, preparation, review, and approval of electronic O&M manuals

· Submission of request for electronic information delivery media and encryption specification

· Preparation, review, and approval of all electronic media, as specified

· Encryption of all electronic media, as specified

3.3. Proficiencies:

· Microsoft Excel

· Use of multi-sheet Excel Workbooks

· Use of Excel Filtering/Sorting Capabilities

· PDF reader and editing tools

· Use of PDF reader comment tools

· Use of PDF Markup/ editing tools

· BIM Software used on this project

· Ability to create and edit BIM model content

· Ability to locate and edit BIM data required by COBie

· COBie Export Tool

· Ability to successfully export BIM data in correct format to a COBie spreadsheet

4. Software

Product Name
Used For
Autodesk Revit 2018
Design Authoring
COBie Extension
Exporting COBie Data from Revit…

COBie Toolkit

Fill in additional…

5. Deliverables & Due Dates COBie deliverables shall be produced directly from native Building Information Modeling (or other) Design Software tool whenever practical COBie deliverables shall be produced directly from native Building Information Modeling (or other) Design Software tool whenever practical Legend:

R = Required S = Suggested

Estimated Completion Date:
COBie File (.xlsx)

(PBS P100 - 1.10.2.5)

COBie Data File QC Report 013600.2.02.B.2 COBie Documents File 013600.2.02.B.3 Installed equipment Photos 013600.2.02.B.3

Mobilization Submittal

R
R
R

30% Fiscal Completion

S
S
S
S

60% Fiscal Completion

R
R
R
R

90% Fiscal Completion

R
R
R
R

Beneficial Occupancy

R
R
R
R

Fiscal Completion

R
R
R
R

Project Closeout/ As-Builts

R
R
R
R

5.1. Mobilization Submittal Details

A Construction Mobilization model will be prepared to provide the outline of facility assets needed to support the capture of COBie data through the construction phase. The number of assets COBie Mobilization Submittal should match the number of assets in the Project Closeout COBie submittal with the exception of assets that may have been changed through RFI’s or Architectural Supplementary Instructions (ASI’s). Change

6. Asset Types in Scope List of asset types in scope included in Appendix B. (This list should be provided by the Owner and ideally would be developed with the help of their facilities management staff)

6.1. Classification Systems Clarifications

Get clarification from the owner on which classification system(s) they prefer to use. If no clarification given, the default classification system used in the U.S. version of COBie is Omniclass.

Default Classification System
Over Ride Classification System
COBie.Contact.Category
Omniclass Table 34
COBie.Facility.Category
Omniclass Table 11
COBie.Space.Category
Omniclass Table 13
Facility.Type.Category
Omniclass Table 23
GSA Asset ID
Facility.System.Category
Omniclass Table 21

If any custom classification system is used, include the system as an appendix or an attachment.

7. Quality Control Quality Control checks should be performed prior to all COBie submissions. COBie deliverable shall be tested using an automated QC tool such as COBie Tool Kit (or approved substitute). Resulting QC reports should be included with respective COBie submission. The content of each COBie file shall be evaluated based on the requirement that “the data on drawing schedules match the data in the COBie file” and that the data is populated and formatted in compliance with the COBie standard.

8. Process Description/ Workflows Diagram Give a detailed description of the processes that will be used to export, collect, populate and validate (QC) COBie data. A workflow diagram should be included for a deeper understanding of COBie workflows. COBie deliverables shall be produced directly from native BIM authoring tool whenever practical. If manual spreadsheet data population is opted for, it must be demonstrated that information is tied back to the BIM via a unique element ID.

9. Documents The majority of the information contained in O&M manuals is required to be provided prior to the end of the project as standard submittals. The objective of creating COBie O&M submittals is to capture these standard submittal documents electronically to allow the information to be re-used in whatever format that is required on this project.

9.1. Documents Types in Scope:

Submittal Types to Include in COBie

✓
Design Reports
✓
Design Review Comments
✓
Contract Drawings
✓
Contract Specifications
✓
Contract Amendments
✓
Contract Modifications
✓
Manufacturer’s Product Data
✓
Manufacturer Certifications
✓
Manufacturer Instructions
✓
Manufacturer PM Schedules
✓
Manufacturer Warranty Certificates
✓
Fabrication Drawings
✓
Sample Image
✓
Installed Equipment Photo
✓
Test Reports
✓
Consumables - Equipment
✓
Consumables – Facility
✓
Start-Up Procedures
✓
Shut-Down Procedures
✓
Normal Operating Instructions
✓
Emergency Operating Instructions
✓
System Flow Diagrams
✓
Draft Property Transfer Report
✗
Add additional items as applicable…

9.2. Document Naming:

The COBie QC Manager will use the following naming convention for all COBie submittal files when documenting the location in the COBie Submittal Template (or create a similar, logical document naming standard):

COBie.TypeName + Submittal Type + version

In the following example, separate files are provided for each submittal type:

· Pump-Type1-ProductData-v01

· Pump-Type1-InstallationInstructions-v01

· Pump-Type1-WarrantyCertificate-v01

9.3. Electronic Submittal Specifics

Submittal files are to be provided electronically, in PDF format, by individual manufacture product family. Contractors should use original manufacturer PDF’s that are text searchable for COBie submittal documents. Scanned copies of faxed documents of manufacturer’s files or fabricator’s drawings are not permitted. COBie submittal documents may be electronically marked to indicate the selections or options chosen for a given product. Annotations of deviations or optional selections appearing outside the submittal documents, shall be included in the body of the PDF file. All PDF’s will be down-sized to “Standard” quality to ensure minimum file size.

The location of these files is to be provided in the COBie.Document.Directory. Submittals that have not been approved or acknowledged shall not be included in any COBie submissions. COBie QC Manager will ensure that each PDF provided is limited to a single manufacturer’s product type. If submittals exist that do refer to multiple manufacturers product types, there are two options:

Option 1. Split Manufacturer’s files In this option, the COBie QC Manager is responsible to split files containing multiple types of COBie submittal documents into individual files corresponding to each different type of submittal.

Option 2. Bookmark Manufacturer’s files In this option, the COBie QC Manager is responsible to create internal bookmarks within a single COBie submittal document. To ensure that these bookmarks may be used by applications consuming this information it is recommended that the bookmark be one single concatenated word without any punctuation or spaces.[footnoteRef:0] [0: The Adobe document “Parameters for Opening PDF Files” dated April 2007 indicates that the way that these book marks can be identified is using the full name of the file, followed by a hashtag, followed by the name of the bookmark. The example, as it applies to our COBie files is: “Object-SubmittalType-VersionXX #WarrantyCertificate”]

Once the COBie Submittal document has been created, it should be moved to a specific subdirectory called “documents”.

9.3.1. As-Installed Equipment Capture

· The production and updating of installed equipment lists will be coordinated with the designated subcontractors. To produce a monthly roll-up of all equipment that appears on drawings schedules. Each COBie-specific file will include JPEG files for each piece of installed equipment.

31-Jan-19DRAFT - COBie Information Delivery Plan Template image1.png