This document outlines specifications for electrical infrastructure upgrades at the Chalmers P. Wylie VA Ambulatory Care Center in Columbus, Ohio. Key requirements include upgrading electrical systems, materials, and equipment in accordance with NFPA and OSHA standards. Manufacturers must be regularly engaged in producing listed, labeled, or certified products. Products must have a service organization that can respond within four hours. The contractor must protect materials and equipment, perform work with de-energized circuits where possible, and complete factory and site testing, including four copies of test reports. The specifications cover minimum qualifications, applicable publications, manufactured products, work performance, and variations from contract requirements.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
757-21-701 | EHRM Infrastructure Upgrades - Tier 2 Chalmers P. Wylie VA Ambulatory Care Center – Columbus, OH Final Bid Documents Specifications Volume 2 June 2, 2023
Specifications Sign and Seal:
Ohio Architectural Registration No: 1716896
Specifications Sign and Seal:
Ohio Engineer (Fire Protection) Registration No: PE 85383
Specifications Sign and Seal:
Ohio Engineer Registration No: E-85534
Specifications Sign and Seal: Registered Communications Distribution Designer Registration No: BICSIID # 270641
A | 4425 East Agave Road Phoenix, AZ 85044 P | 602.584.5010 E | howdy@spur-design.com W | spur-design.com mailto:howdy@spur-design.com
EHRM Infrastructure Upgrades, Tier 2 – Columbus, OH
VA 757-22-705
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 1
AIR TERMINAL UNITS
SECTION 23 36 00
AIR TERMINAL UNITS
PART 1 - GENERAL
1.1 DESCRIPTION
Air terminal units, air flow control valves.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.
B. Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
C. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and
EQUIPMENT.
F. Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC.
E. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
D. Section 23 31 00, HVAC DUCTS and CASINGS.
1.3 QUALITY ASSURANCE
Refer to Article, QUALITY ASSURANCE, in Section 23 05 11, COMMON WORK
RESULTS FOR.
1.4 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, and SAMPLES.
B. Manufacturer's Literature and Data:
1. Air Terminal Units: Submit test data.
2. Air flow control valves.
C. Samples: Provide one typical air terminal unit for approval by the
Resident Engineer. This unit will be returned to the Contractor after all similar units have been shipped and deemed acceptable at the job site.
D. Certificates:
1. Compliance with Article, QUALITY ASSURANCE.
2. Compliance with specified standards.
E. Operation and Maintenance Manuals: Submit in accordance with paragraph, INSTRUCTIONS, in Section 01 00 00, GENERAL REQUIREMENTS.
1.5 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 2
AIR TERMINAL UNITS
B. Air Conditioning, Heating, and Refrigeration Institute (ARI/AHRI):
880-2017........... Performance Rating of Air Terminals
C. American Society for Testing and Materials (ASTM):
C665-2017.......... Standard Specification for Mineral-Fiber
Blanket Thermal Insulation for Light Frame
Construction and Manufactured Housing
D. National Fire Protection Association (NFPA):
90A-2021........... Standard for the Installation of Air
Conditioning and Ventilating Systems
E. Underwriters Laboratories, Inc. (UL):
181-2013........... Factory-Made Air Ducts and Air Connectors
1.6 GUARANTY
In accordance with the GENERAL CONDITIONS
PART 2 - PRODUCTS
2.1 GENERAL
A. Coils:
1. All Air-Handling Units: Provide aluminum fins and copper coils for all hot water reheat coils.
2. Water Heating Coils:
a. ARI certified, continuous plate or spiral fin type, leak tested at 2070 kPa (300 PSI).
b. Capacity: As indicated, based on scheduled entering water temperature.
c. Headers: Copper or Brass.
d. Fins: Aluminum, maximum 315 fins per meter (8 fins per inch).
e. Tubes: Copper, arrange for counter-flow of heating water.
f. Water Flow Rate: Minimum 0.032 Liters/second (0.5 GPM).
g. Provide vent and drain connection at high and low point, respectively of each coil.
h. Coils shall be guaranteed to drain.
3. Electric Heating Coils:
a. ARI certified, spiral fin type.
b. Capacity: As indicated, based on scheduled data.
c. Coil: Enclosed copper tube, aluminum finned element of coiled nickel-chrome resistance wire centered in tubes and embedded in
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 3
AIR TERMINAL UNITS
refractory material. Exposed helical coil of nickel-chrome resistance wire with refractory ceramic support bushings will not be allowed.
B. Labeling: Control box shall be clearly marked with an identification label that lists such information as nominal CFM, maximum and minimum factory-set airflow limits, coil type and coil connection orientation, where applicable.
C. Factory calibrate air terminal units to air flow rate indicated. All settings including maximum and minimum air flow shall be field adjustable.
D. Dampers with internal air volume control: See section 23 31 00 HVAC
DUCTS and CASINGS.
E. Terminal Sound Attenuators: See Section 23 31 00 HVAC DUCTS and
CASINGS.
2.2 AIR TERMINAL UNITS (BOXES)
A. General: Factory built, pressure independent units, factory set-field adjustable air flow rate, suitable for single duct applications. Use of dual-duct air terminal units is not permitted. Clearly show on each unit the unit number and factory set air volumes corresponding to the contract drawings. Section 23 05 93, TESTING, ADJUSTING, and BALANCING
FOR HVAC work assumes factory set air volumes. Coordinate flow controller sequence and damper operation details with the drawings and
Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC. All air terminal units shall be brand new products of the same manufacturer.
B. Capacity and Performance: The Maximum Capacity of a single terminal unit shall not exceed 566 Liters/second (1,200 CFM) with the exception of operating rooms and Cystoscopy rooms, which shall be served by a single air terminal unit at a maximum of 1,250 Liters/second (3,000
CFM).
C. Sound Power Levels:
Acoustic performance of the air terminal units shall be based on the design noise levels for the spaces stipulated in Section 23 05 41
(Noise and Vibration Control for HVAC Piping and Equipment. Terminal sound attenuators shall be provided, as required, to meet the intent of the design.
D. Casing: Unit casing shall be constructed of galvanized steel no lighter than 0.85 mm (22 Gauge). Air terminal units serving the operating
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 4
AIR TERMINAL UNITS
rooms and Cystoscopy rooms shall be fabricated without lining. Provide hanger brackets for attachment of supports.
1. Lining material: Suitable to provide required acoustic performance, thermal insulation and prevent sweating. Meet the requirements of
NFPA 90A and comply with UL 181 for erosion as well as ASTMC 665 antimicrobial requirements. Insulation shall consist of 13 mm (1/2
IN) thick non-porous foil faced rigid fiberglass insulation of 4-lb/cu.ft, secured by full length galvanized steel z-strips which enclose and seal all edges. Tape and adhesives shall not be used.
Materials shall be non-friable and with surfaces, including all edges, fully encapsulated and faced with perforated metal or coated so that the air stream will not detach material. No lining material is permitted in the boxes serving operating rooms and Cystoscopy rooms.
2. Access panels (or doors): Provide panels large enough for inspection, adjustment and maintenance without disconnecting ducts, and for cleaning heating coils attached to unit, even if there are no moving parts. Panels shall be insulated to same standards as the rest of the casing and shall be secured and gasketed airtight. It shall require no tool other than a screwdriver to remove.
3. Total leakage from casing: Not to exceed 2 percent of the nominal capacity of the unit when subjected to a static pressure of 750 Pa
(3 inch WG), with all outlets sealed shut and inlets fully open.
4. Octopus connector: Factory installed, lined air distribution terminal. Provide where flexible duct connections are shown on the drawings connected directly to terminals. Provide butterfly-balancing damper, with locking means in connectors with more than one outlet. Octopus connectors and flexible connectors are not permitted in the Surgical Suite.
E. Construct dampers and other internal devices of corrosion resisting materials which do not require lubrication or other periodic maintenance.
1. Damper Leakage: Not greater than 2 percent of maximum rated capacity, when closed against inlet static pressure of 1 kPa (4 inch
WG).
F. Provide multi-point velocity pressure sensors with external pressure taps.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 5
AIR TERMINAL UNITS
1. Provide direct reading air flow rate table pasted to box.
G. Provide static pressure tubes.
H. Externally powered DDC variable air volume controller and damper actuator to be furnished under Section 23 09 23, DIRECT-DIGITAL CONTROL
SYSTEM FOR HVAC for factory mounting on air terminal units. The DDC controller shall be electrically actuated.
I. Fan powered terminal units:
1. General: The fan will be in a series configuration inside the unit casing.
2. Fan assembly: Forward curved centrifugal direct drive blower with adjustable speed controller.
a. Motor: Integral thermal overload protection.
1) 115 V single phase.
208/240 V single phase.
277 V single phase.
b. Motor assembly: Completely isolated from cabinet with rubber vibration mounts.
3. Wiring: Factory mounted and wire controls. Mount electrical components NEMA-1 control box with removable cover. Incorporate single point electrical connection to power source. Provide terminal strip in control box for field wiring of power source.
Provide factory wired non-fused disconnect switch on each terminal unit.
4. Provide 1-inch thick throwaway filter in the return air inlet.
2.3 AIR FLOW CONTROL VALVE (AFCV)
A. Airflow control device shall be a venturi valve type air flow control valve.
B. Pressure independent over a 150 Pa-750 Pa (0.6 inch WG – 3.0 inch WG) drop across valve.
C. Volume control accurate to plus or minus 5% of airflow over an airflow turndown range of 16 to 1. No minimum entrance or exit duct diameters shall be required to ensure accuracy or pressure independence.
D. Response time to change in command signal and duct static pressure within three seconds.
E. 16 gauge spun aluminum valve body and control device with continuous welded seam and 316 stainless steel shaft and shaft support brackets.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 6
AIR TERMINAL UNITS
Pressure independent springs shall be stainless steel. Shaft bearing surfaces shall be Teflon or polyester.
F. 316 stainless steel continuous welded seam valve body, control device, shaft, shaft support bracket, pivot arm and internal mounting link.
The control device shall have a baked on corrosion resistant phenolic coating. The shaft shall have a Teflon coating and all shaft bearing surfaces shall be made of Teflon. The pressure independent springs shall be made of stainless steel.
G. The airflow device shall have no exposed aluminum or stainless steel components. The shaft support brackets, pivot arm, internal mounting link, and pressure independent springs shall have a baked-on corrosion resistant phenolic coating. Internal nuts, bolts, and rivets shall be titanium or phenolic coated stainless steel.
H. Constant volume units:
1. Actuator to be factory mounted to the valve.
2. Closed loop control of airflow by way of flow feedback signal with less than 1 second response time.
3. Shaft positioned using direct potentiometer measurement to produce a linear factory calibrated feedback.
4. The maximum and minimum airflows shall be as scheduled.
I. Variable volume units:
1. Actuator to be factory mounted to the valve.
2. Closed loop control of airflow by way of flow feedback signal with less than 1 second response time.
3. Shaft positioned using direct potentiometer measurement to produce a linear factory calibrated feedback.
J. Certification:
1. Control device: factory calibrated to airflows detailed on plans using NIST traceable air stations and instrumentation having a combined accuracy of plus or minus 1% of signal over the entire range of measurement.
2. Electronic airflow control devices: further calibrated and their accuracy verified to plus or minus 5% of signal at a minimum of eight different airflows across the full operating range of the device.
3. All airflow control devices: individually marked with device specific, factory calibration data to include: tag number, serial
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 36 00 - 7
AIR TERMINAL UNITS
number, model number, eight point characterization information (for electronic devices), and quality control inspection numbers.
K. Airflow measuring devices and airflow control devices that are not venturi valves (e.g., Pitot tube, flow cross, air bar, orifice ring, vortex shedder, etc.) are acceptable, provided the following conditions are met:
1. They meet the performance and construction characteristics stated throughout this section of the specification.
2. Suppliers of airflow control devices or airflow measuring devices requiring minimum duct diameters: provide revised duct layouts showing the required straight duct runs upstream and downstream of these devices.
3. Supplier of the airflow control system: submit coordination drawings reflecting these changes and include static pressure loss calculations as part of submittal.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Work shall be installed as shown and according to the manufacturer’s diagrams and recommendations.
B. Handle and install units in accordance with manufacturer's written instructions.
C. Support units rigidly so they remain stationary at all times.
Cross-bracing or other means of stiffening shall be provided as necessary. Method of support shall be such that distortion and malfunction of units cannot occur.
D. Locate air terminal units to provide a straight section of inlet duct for proper functioning of volume controls. See VA Standard Detail.
3.2 OPERATIONAL TEST
Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
- - - E N D - - -
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 1
AIR OUTLETS AND INLETS
SECTION 23 37 00
AIR OUTLETS AND INLETS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Roof Curbs
B. Air Outlets and Inlets: Diffusers, Registers, and Grilles.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.
B. Section 23 05 11, COMMON WORK RESULTS FOR HVAC and STEAM GENERATION.
C. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and
EQUIPMENT.
D. Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC.
1.3 QUALITY ASSURANCE
A. Refer to Article, QUALITY ASSURANCE, in Section 23 05 11, COMMON WORK
RESULTS FOR HVAC.
B. Fire Safety Code: Comply with NFPA 90A.
1.4 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, and SAMPLES.
B. Manufacturer's Literature and Data:
1. Air intake/exhaust hoods.
2. Diffusers, registers, grilles and accessories.
C. Coordination Drawings: Refer to article, SUBMITTALS, in Section 23 05
11, COMMON WORK RESULTS FOR HVAC.
extent referenced. The publications are referenced in the text by the
B. Air Diffusion Council Test Code
1062 GRD-2015...... Certification, Rating, and Test Manual, 4th
Edition
C. American Society of Civil Engineers (ASCE):
ASCE 7-2022........ Minimum Design Loads for Buildings and Other
Structures.
D. American Society for Testing and Materials (ASTM):
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 2
AIR OUTLETS AND INLETS
A167-1999.......... Standard Specification for Stainless and
Heat Resisting Chromium-Nickel Steel Plate, Sheet, and Strip
B209-2021.......... Standard Specification for Aluminum and
Aluminum Alloy Sheet and Plate
E. National Fire Protection Association (NFPA):
F. Underwriters Laboratories, Inc. (UL):
181-2013........... Factory-Made Air Ducts and Air Connectors
PART 2 - PRODUCTS
2.1 GRAVITY INTAKE/EXHAUST VENTILATORS (ROOF MOUNTED)
A. Aluminum, ASTM B209, louvered, spun, or fabricated using panel sections with roll-formed edges, 13 mm (1/2 inch) mesh aluminum welded wire bird screen, with gravity or motorized dampers where shown, accessible interior, designed for wind velocity specified in Paragraph 3.3.
1. Spun Intake/Exhaust Ventilators: Spun aluminum structural components shall be constructed of minimum 1.3 mm (16 Gauge) marine alloy aluminum, bolted to a rigid aluminum support structure. The aluminum base shall have continuously welded curb cap corners for maximum leak protection. The spun aluminum baffle shall have a rolled bead for added strength.
2. Louvered Intake/Exhaust Hoods: Louvered hood constructed from 0.081
Gauge extruded aluminum tiers welded to a minimum 3.3 mm (8 Gauge) aluminum support structure. The aluminum hood shall be constructed of a minimum 0.064 marine alloy aluminum and provided with a layer of anti-condensate coating. The aluminum base shall have continuously welded curb cap corners for maximum leak protection.
3. Low Silhouette Intake/Exhaust Ventilator: The unit shall be of bolted and welded construction utilizing corrosion resistant fasteners. The aluminum hood shall be constructed of minimum 1.60 mm
(14 Gauge) marine alloy aluminum, bolted to a minimum 3.25 mm (8
Gauge) aluminum support structure. The aluminum base shall have continuously welded curb cap corners for maximum leak protection.
Birdscreen constructed of 13 mm (1/2 inch) mesh shall be mounted across the relief opening.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 3
AIR OUTLETS AND INLETS
B. See ventilator schedule on the drawings. Sizes shown on the drawings designate throat size. Area of ventilator perimeter opening shall be not less than the throat area.
C. Dampers for Gravity Ventilators without Duct Connection: Construct damper of the same material as the ventilator and of the design to completely close opening or remain wide open. Hold damper in closed position by a brass chain and catch. Extend chains 300 mm (12 inches) below and engage catch when damper is closed.
D. See paragraph 3.3 for Intake/Exhaust exposed to high wind velocities.
E. Provide Roof Curb by unit manufacturer. Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC for additional requirements.
2.2 EQUIPMENT SUPPORTS
Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
2.3 AIR OUTLETS AND INLETS
A. Materials:
1. Steel or aluminum. Provide manufacturer's standard gasket.
2. Exposed Fastenings: The same material as the respective inlet or outlet. Fasteners for aluminum may be stainless steel.
3. Contractor shall review all ceiling drawings and details and provide all ceiling mounted devices with appropriate dimensions and trim for the specific locations.
B. Performance Test Data: In accordance with Air Diffusion Council Code
1062GRD. Refer to Section 23 05 41, NOISE and VIBRATION CONTROL FOR
HVAC PIPING and EQUIPMENT for NC criteria.
C. Air Supply Outlets:
1. Ceiling Diffusers: Suitable for surface mounting, exposed T-bar or special tile ceilings, off-white finish, square or round neck connection as shown on the drawings. Provide plaster frame for units in plaster ceilings.
a. Square, louver, fully adjustable pattern: Round neck, surface mounting unless shown otherwise on the drawings. Provide equalizing or control grid and volume control damper.
b. Louver face type: Square or rectangular, removable core for 1, 2, 3, or 4 way directional pattern. Provide equalizing or control grid and opposed blade damper.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 4
AIR OUTLETS AND INLETS
c. Perforated face type: Manual adjustment for one-, two-, three-, or four-way horizontal air distribution pattern without change of air volume or pressure. Provide equalizing or control grid and opposed blade over overlapping blade damper. Perforated face diffusers for VAV systems shall have the pattern controller on the inner face, rather than in the neck and designed to discharge air horizontally at the ceiling maintaining a Coanda effect.
d. Slot diffuser/plenum:
1) Diffuser: Frame and support bars shall be constructed of heavy gauge extruded aluminum. Form slots or use adjustable pattern controllers, to provide stable, horizontal air flow pattern over a wide range of operating conditions.
2) Galvanized steel boot lined with 13 mm (1/2 inch) thick fiberglass conforming to NFPA 90A and complying with UL 181 for erosion. The internal lining shall be factory-fabricated, anti-microbial, and non-friable.
3) Provide inlet connection diameter equal to duct diameter shown on drawings or provide transition coupling if necessary. Inlet duct and plenum size shall be as recommended by the manufacturer.
4) Maximum pressure drop at design flow rate: 37 Pa
(0.15 inch W.G.)
2. Linear Bar Grilles and Diffusers: Extruded aluminum, manufacturer's standard finish, and positive holding concealed fasteners.
a. Margin Frame: Flat, 20 mm (3/4 inch) wide.
b. Bars: Minimum 5 mm (3/16 inch) wide by 20 mm (3/4 inch) deep, zero deflection unless otherwise shown. Bar spacing shall be a minimum of 3 mm (1/8 inch) on center. Reinforce bars on 450 mm
(18 inch) center for sidewall units and on 150 mm (6 inch) center for units installed in floor or sills.
c. Provide opposed blade damper and equalizing or control grid where shown.
3. Operating Room Air Distribution Devices:
a. Devices shall consist of a non-aspirating perforated panel center air supply providing downward airflow over the operating table and fixed nonadjustable multiple slot perimeter panels surrounding the operating table area to provide an air curtain
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 5
AIR OUTLETS AND INLETS
which shall be projected outward from the operating table area at not less than a five degree angle nor more than a 15 degree angle. Velocity of air distribution at operating table height shall not exceed 12 m/min (40 feet per minute) for the center supply or 15 m/min (50 feet per minute) for the air curtain.
Perforated pressure plates shall be provided over the perimeter and center air distribution faces to equalize pressure and airflow throughout the system.
b. All components of the system inside the operating room shall be fabricated of 1.0 mm (20 Gauge) thick 18-8 stainless steel (ASTM
A167), No. 4 finish, and outside the operating room shall be of the manufacturer’s standard aluminum finish. All distribution components and pressure plates shall be attached to the face panels at both the perimeter and center. The face panels shall be retained with 1/4 turn fasteners. Plenums shall be supplied by the manufacturer and shall be sized to permit them to be easily wiped out by hand with germicidal solution for sterilization purposes and all horizontal corners of the plenums shall have a minimum radius of 20 mm (3/4 inch). Connecting elbows shall be radialized and be sized to permit manual sterilization of the plenums.
4. Supply Registers: Double deflection type with horizontal face bars and opposed blade damper with removable key operator.
a. Margin: Flat, 30 mm (1-1/4 inches) wide.
b. Bar spacing: 20 mm (3/4 inch) maximum.
c. Finish: Off white baked enamel for ceiling mounted units. Wall units shall have a prime coat for field painting, or shall be extruded with manufacturer's standard finish.
5. Supply Grilles: Same as registers but without the opposed blade damper.
6. Drum Louvers: Aluminum construction, drum louver, with pivoted blades and rotating drum to adjust length of throw and direction.
a. Register shall have integral; face adjustable, opposed blade damper constructed of heavy gauge steel. Damper shall be operable from the face of the register. Units shall be nozzle type with adjustable discharge pattern.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 6
AIR OUTLETS AND INLETS
7. Jet Diffusers: Aluminum construction (nozzle and frame) suitable for wall or ceiling mounting or direct mounting on ducts.
D. Return and Exhaust Registers and Grilles: Provide opposed blade damper without removable key operator for registers.
1. Finish: Off-white baked enamel for ceiling mounted units. Wall units shall have a prime coat for field painting, or shall be extruded aluminum with manufacturer's standard aluminum finish.
2. Standard Type: Fixed horizontal face bars set at 30 to 45 degrees, approximately 30 mm (1-1/4 inch) margin.
3. Perforated Face Type: To match supply units.
4. Grid Core Type: 13 mm by 13 mm (1/2 inch by 1/2 inch) core with 30 mm (1-1/4 inch) margin.
5. Linear Type: To match supply units.
6. Door Grilles: Are furnished with the doors.
7. Egg Crate Grilles: Aluminum or Painted Steel 1/2 by 1/2 by 1/2 inch grid providing 90% free area.
a. Heavy extruded aluminum frame shall have countersunk screw mounting. Unless otherwise indicated, register blades and frame shall have factory applied white finish.
b. Grille shall be suitable for duct or surface mounting as indicated on drawings. All necessary appurtenances shall be provided to allow for mounting.
E. Supply Registers in Psychiatric Rooms: Supply air registers shall be security type, steel with perforated faceplate, flat surface margin, extension sleeve, opposed blade damper and back mounting flanges.
Faceplate shall be 5 mm (3/16 inch) (minimum) with 5x5 mm holes on 7 mm (3/16 by 3/16 inch holes on 9/32 inch) spacing and a minimum free area of 45 percent. Wall sleeve shall be 5 mm (3/16 inch) thick
(minimum).
F. Air Inlet Registers in Psychiatric Rooms: Return, exhaust, transfer and relief air registers shall be security type, steel with perforated faceplate, flat surface margin, wall sleeve, opposed blade damper and back mounting flanges. Faceplate shall be 5 mm (3/16 inch) (minimum) with 5x5 mm holes on 7 mm (3/16 by 3/16 inch holes on 9/32 inch) spacing and a minimum free area of 45 percent. Wall sleeve shall be 5 mm (3/16 inch) thick (minimum).
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 7
AIR OUTLETS AND INLETS
G. Acoustic Transfer Grille: Aluminum, suitable for partition or wall mounting.
2.4 WIRE MESH GRILLE
A. Fabricate grille with 2 x 2 mesh 13 mm (1/2 inch) galvanized steel or aluminum hardware cloth in a spot welded galvanized steel frame with approximately 40 mm (1-1/2 inch) margin.
B. Use grilles where shown in unfinished areas such as mechanical rooms.
2.5 FILTER RETURN/EXHAUST GRILLE
A. Provide grille with in stream 1-inch deep MERV 4 filter and removable face.
1. Finish: Off-white baked enamel for ceiling mounted units. Wall units shall have a prime coat for field painting, or shall be extruded aluminum with manufacturer's standard aluminum finish. Stainless
Steel shall be No. 4 finish.
2. Standard Type: Fixed horizontal face bars set at 30 to 45 degrees, approximately 30 mm (1-1/4 inch) margin.
3. Steel, Aluminum, or Stainless steel as scheduled.
4. Standard face connected to a mounting frame with space for a throwaway filter. Hold face closed by a locking screw. Provide retaining clips to hold filter in place. Provide fiberglass throwaway filter.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Comply with provisions of Section 23 05 11, COMMON WORK RESULTS FOR
HVAC AND STEAM GENERATION, particularly regarding coordination with other trades and work in existing buildings.
B. Protection and Cleaning: Protect equipment and materials against physical damage. Place equipment in first class operating condition, or return to source of supply for repair or replacement, as determined by
Resident Engineer. Protect equipment during construction against entry of foreign matter to the inside and clean both inside and outside before operation and painting.
3.2 INTAKE/ EXHAUST HOODS EXPOSED TO WIND VELOCITY
Provide additional support and bracing to all exposed ductwork installed on the roof or outside the building to withstand wind velocity of 145 km/h
(90 mph).
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 37 00 - 8
AIR OUTLETS AND INLETS
3.3 TESTING, ADJUSTING AND BALANCING (TAB)
Refer to Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC.
3.4 OPERATING AND PERFORMANCE TESTS
Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-1
DECENTRALIZED UNITARY HVAC EQUIPMENT
SECTION 23 81 00
DECENTRALIZED UNITARY HVAC EQUIPMENT
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies split-systems air conditioners.
B. Definitions:
1. Energy Efficiency Ratio (EER): The ratio of net cooling capacity is
Btu/h to total rate of electricity input in watts under designated operating conditions (Btu hour/Watt).
2. Seasonal Energy Efficiency Ratio (EER): The ratio of the total cooling output of an air conditioner during its normal annual usage period for cooling in Btu/h divided by total electric energy input in watts during the same period (Btu hour/Watt).
3. Unitary: A Unitary Air Conditioner consists of one or more factory-made assemblies which normally include an evaporator or cooling coil, a compressor and condenser combination, and may include a heating function as well.
4. Where such equipment is provided in more than one assembly the separated assemblies are to be designed to be used together and the requirements of rating are based upon use of matched assemblies.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES
B. Section 23 05 11, COMMON WORK RESULTS FOR HVAC
C. Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC and STEAM
GENERATION EQUIPMENT
D. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and
EQUIPMENT.
E. Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC
F. Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS.
G. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
H. Section 23 23 00, REFRIGERANT PIPING.
I. Section 23 31 00, HVAC DUCTS and CASINGS.
J. Section 23 82 16, AIR COILS
K. Section 28 31 00, FIRE DETECTION and ALARM.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-2
DECENTRALIZED UNITARY HVAC EQUIPMENT
1.3 QUALITY ASSURANCE
A. Refer to specification Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
B. Safety Standards: ASHRAE Standard 15, Safety Code for Mechanical
Refrigeration.
1.4 SUBMITTALS
A. Submit in accordance with specification Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, and SAMPLES
B. Manufacturer’s literature and data:
1. Sufficient information, including capacities, pressure drops, and piping connections clearly presented, shall be included to determine compliance with drawings and specifications for units noted below:
a. Unitary air conditioners:
1) Split systems
2. Unit Dimensions required clearances, operating weights accessories and start-up instructions.
3. Electrical requirements, wiring diagrams, interlocking and control wiring showing factory installed and portions to be field installed.
4. Mounting and flashing of the roof curb to the roofing structure with coordinating requirements for the roof membrane system.
C. Certification: Submit proof of specified ARI Certification.
D. Performance Rating: Submit catalog selection data showing equipment ratings and compliance with required sensible-to-heat-ratio, energy efficiency ratio (EER), and coefficient of performance (COP).
E. Operating and Maintenance Manual: Submit three copies of Operating and
Maintenance manual to Resident Engineer three weeks prior to final inspection.
F. Completed System Readiness Checklists provided by the Commissioning
Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS.
extent referenced. The publications are referenced in the text by the
B. Air-Conditioning, Heating, and Refrigeration Institute (AHRI):
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-3
DECENTRALIZED UNITARY HVAC EQUIPMENT
210/240-2017............Performance Rating of Unitary Air-Conditioning and Air-Source Heat Pump Equipment
270-2015................Sound Rating of Outdoor Unitary Equipment
310/380-2017............Standard for Packaged Terminal Air-Conditioners and Heat Pumps (CSA-C744-04)
340/360-2015............Performance Rating of Commercial and Industrial
Unitary Air-Conditioning and Heat Pump
Equipment
520-2004................Performance Rating of Positive Displacement
Condensing Units
C. Air Movement and Control Association (AMCA):
210-2016................Laboratory Methods of Testing Fans for
Aerodynamic Performance Rating (ANSI)
410-1996................Recommended Safety Practices for Users and
Installers of Industrial and Commercial Fans
D. American National Standards Institute (ANSI):
S12.51-2017.............Acoustics - Determination of Sound Power Levels of Noise Sources Using Sound Pressure -
Precision Method for Reverberation Rooms (same as ISO 3741:1999)
E. American Society of Civil Engineers (ASCE)
ASCE 7-2017.............Minimum Design Loads for Buildings and Other
Structures
F. American Society of Heating, Refrigerating, and Air-Conditioning
Engineers (ASHRAE):
Handbook 2016...........HVAC Systems and Equipment
15-2019.................Safety Standard for Refrigeration Systems
(ANSI)
62.1-2016...............Ventilation for Acceptable Indoor Air Quality
(ANSI)
G. American Society of Testing and Materials (ASTM):
B117-2018...............Standard Practice for Operating Salt Spray
(Fog) Apparatus
H. Federal Specifications (Fed. Spec.):
A-A-50502-2009.......... Air conditioner (Unitary Heat Pump) Air to Air
(3000-300,000 Btu)
I. Military Specifications (Mil. Specs.):
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-4
DECENTRALIZED UNITARY HVAC EQUIPMENT
MIL-PRF-26915D..........Primer Coating, for Steel Surfaces
J. National Electrical Manufacturer's Association (NEMA):
ICS 1-2005..............Industrial Controls and Systems: General
Requirements
MG 1-2019...............Motors and Generators (ANSI)
K. National Fire Protection Association (NFPA) Publications:
90A-2021................Standard for the Installation of Air-
Conditioning and Ventilating Systems
PART 2 - PRODUCTS
2.1 UNITARY AIR CONDITIONERS - GENERAL
A. Applicable ARI Standards:
1. Cooling Capacity 39.6 kW (135,000 Btu/h) and More: AHRI 340/ 360.
2. Cooling Capacity Less Than 39.6 kW (135,000 Btu/h): AHRI 210/240.
Units shall be listed in the ARI Directory of Certified Unitary Air-
Conditioners.
B. Performance Rating: Cooling capacity of units shall meet the sensible heat and total heat requirements shown in the contract documents. In selecting unit size, make true allowance for "sensible to total heat ratio" to satisfy required sensible cooling capacity.
C. Machinery Guards: Provide guards as shown in AMCA 410 for belts, chains, couplings, pulleys, sheaves, shafts, gears and other moving parts regardless of height above the floor. Drive guards may be excluded where motors and drives are inside factory fabricated casings.
D. Corrosion Prevention: Unless specified otherwise, equipment fabricated from ferrous metals that do not have a zinc coating or a duplex coating of zinc and paint shall be treated for prevention of rust with a factory coating or paint system that will withstand 125 hours in a salt-spray fog test, except that equipment located outdoors shall be tested for 500 hours. The salt-spray fog test shall be in accordance with ASTM B117 using a 20 percent sodium chloride solution. Immediately after completion of the test, the coating shall show no signs of blistering, wrinkling or cracking, no loss of adhesion, and the specimen shall show no signs of rust beyond 3 mm (1/8-inch) on both sides from the scratch mark. Refer to Drawings and Section 23 82 16, AIR COILS, for additional coil requirements.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-5
DECENTRALIZED UNITARY HVAC EQUIPMENT
2.3 SPLIT-SYSTEM AIR CONDITIONERS
A. Description: Factory assembled and tested, wall-mounted unit, with an air-cooled remote condensing unit, and field-installed refrigeration piping.
B. Wall-Mounting, Evaporator-Fan Components:
1. Cabinet: Enameled steel with removable panels on front and ends in color selected by Architect, and discharge drain pans with drain connection.
2. Airstream Surfaces: Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1. Drain Pan and Drain
Connection: Comply with ASHRAE 62.1-2007.
4. Refrigerant Coil: Copper tube, with mechanically bonded aluminum fins, complying with AHRI 210/240, and with thermal-expansion valve.
a. Mount coil assembly over stainless-steel drain pan complying with
ASHRAE 62.1 and having a condensate pump unit with integral float switch, pump-motor assembly, and condensate reservoir.
5. Fan: Direct drive, centrifugal fan.
6. Fan Motors: Comply with requirements in Section 23 05 12, GENERAL
MOTOR REQUIREMENTS FOR HVAC and STEAM GENERATION EQUIPMENT for multi-tapped, multi-speed motors with internal thermal protection and permanent lubrication.
7. Filters: Disposable, with MERV rating of 7 or higher according to
ASHRAE 52.2.
C. Air-Cooled, Compressor-Condenser Components:
1. Casing: Steel, finished with baked enamel in color selected by
Architect, with removable panels for access to controls, weep holes for water drainage, and mounting holes in base. Service valves, fittings, and gage ports shall be brass and located outside of the casing.
2. Compressor: Hermetically sealed scroll with crankcase heater and mounted on vibration isolation. Compressor motor shall have thermal- and current-sensitive overload devices, start capacitor, relay, and contactor.
3. Compressor motor with manual-reset, high-pressure switch and automatic-reset, low-pressure switch.
4. Refrigerant: R-410A unless otherwise indicated.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-6
DECENTRALIZED UNITARY HVAC EQUIPMENT
5. Refrigerant Coil: Copper tube, with mechanically bonded aluminum fins, complying with AHRI 210/240, and with liquid subcooler.
6. Fan: Aluminum, propeller type, directly connected to motor.
7. Motor: Permanently lubricated, with integral thermal-overload protection.
8. Low Ambient Kit: Permit operation down to minus 18 deg C (0 deg F).
9. Mounting Base: Polyethylene.
10. Minimum Energy Efficiency: Comply with ASHRAE/IESNA 90.1 "Energy
Standard for Buildings except Low-Rise Residential Buildings."
PART 3 EXECUTION
3.1 INSTALLATION
C. Install wind restraints according to manufacturer's written instructions. Wind restrained vibration isolation roof-curb rails are specified in Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC
PIPING and EQUIPMENT.
D. Install units level and plumb maintaining manufacturer’s recommended clearances and tolerances.
E. Install water-cooled units with thermometer and pressure gage at the water supply and return connection.
F. Install vibration spring isolators under base of self-contained unit, with minimum static deflection of 25 mm (1 inch) unless otherwise indicated. Refer to Section 23 05 41, NOISE and VIBRATION CONTROL FOR
HVAC PIPING and EQUIPMENT
G. Install ground-mounting, compressor-condenser components on 100 mm (4-inch) thick, reinforced concrete base; 100 mm (4 inches) larger on each side than unit. Concrete, reinforcement, and formwork are specified in
Section 03 30 00, CAST-IN-PLACE CONCRETE. Coordinate anchor installation with concrete base.
H. Install ground-mounting, compressor-condenser components on polyethylene mounting base.
I. Install roof-mounting compressor-condenser components on equipment supports specified in Section 07 72 00, ROOF ACCESSORIES. Anchor units to supports with removable, cadmium-plated fasteners.
J. Install compressor-condenser components on restrained, spring isolators with a minimum static deflection of 25 mm (1 inch) unless otherwise indicated. Refer to Section 23 05 41, NOISE and VIBRATION CONTROL FOR
HVAC PIPING and EQUIPMENT.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-7
DECENTRALIZED UNITARY HVAC EQUIPMENT
K. Install and connect precharged refrigerant tubing to component's quick-connect fittings. Install tubing to allow access to unit.
L. Install wall sleeves in finished wall assembly and weatherproof.
Install and anchor wall sleeves to withstand, without damage seismic forces as required by code.
3.2 CONNECTIONS
A. Verify condensate drainage requirements.
B. Install piping adjacent to units to allow service and maintenance.
C. Install normal-weight, 20.7-MPa (3000-psi), compressive strength (28-day) concrete mix inside roof curb, 100 mm (4 inches) thick.
D. Ground equipment and install power wiring, switches, and controls for split systems.
E. Connect refrigerant piping to coils with shutoff valves on the suction and liquid lines at the coil and a union or flange at each connection at the coil and condenser.
F. Install ducts to the units with flexible duct connections.
G. Connect piping with shutoff duty valves on the supply and return side of the coil and unions at all connections and with a throttling valve on the return piping near the coil.
H. Connect piping with shutoff duty valves on the supply and return side of the water-cooled condenser and unions at all connections and with a throttling valve on the return piping near the condenser
I. Connect piping with shutoff duty valves and unions on the steam supply and condensate side of the steam coil. On the condensate line near the coil provide a strainer, trap and shutoff valve.
3.3 FIELD QUALITY CONTROL
A. Perform tests and inspections and prepare test reports.
B. Tests and Inspections: After installing units and after electrical circuitry has been energized, test units for compliance with requirements. Inspect for and remove shipping bolts, blocks, and tie-down straps. After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. Remove and replace malfunctioning units and retest as specified above.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
238100-8
DECENTRALIZED UNITARY HVAC EQUIPMENT
3.4 STARTUP AND TESTING
A. The Commissioning Agent will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the Resident Engineer and Commissioning Agent. Provide a minimum of 7 days prior notice.
B. Provide services of manufacturer’s technical representative for four hours to instruct VA personnel in operation and maintenance of units.
3.5 COMMISSIONING
A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the
System Readiness Checklist provided by the Commissioning Agent.
B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00 –
COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.
3.6 DEMONSTRATION AND TRAINING
A. Provide services of manufacturer’s technical representative for four hours to instruct VA personnel in operation and maintenance of units.
B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS.
---END---
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 81 23 - 1
COMPUTER-ROOM AIR-CONDITIONERS
SECTION 23 81 23
COMPUTER-ROOM AIR-CONDITIONERS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies process cooling split systems air conditioning unit.
B. Definitions:
1. Energy Efficiency Ratio (EER): A ratio calculated by dividing the cooling capacity in Btuh by the power input in watts at any given set of rating conditions, expressed in Watts (Btu/h) per watt.
2. Coefficient of Performance (COP): A ratio calculated by dividing the change in heating or cooling capacity (Btu/h) to the energy consumed by the system (kW), expressed in Btu/kWh.
3. Unitary (AHRI): Consists of one or more factory-made assemblies, which normally include an evaporator or cooling coil, a compressor and condenser combination, and may include a heating function.
4. CRAC Units: Computer Room Air Conditioning Units.
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.
C. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS.
D. Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
E. Section 23 05 12, GENERAL MOTOR REQUIREMENTS FOR HVAC and STEAM
GENERATION EQUIPMENT.
F. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and
EQUIPMENT.
G. Section 23 05 93: TESTING, ADJUSTING, and BALANCING FOR HVAC.
H. Section 23 08 00 – COMMISSIONING OF HVAC SYSTEMS.
I. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
J. Section 23 21 13, HYDRONIC PIPING
K. Section 23 22 13, STEAM and CONDENSATE HEATING PIPING.
L. Section 23 21 23, HYDRONIC PUMPS and Section 23 22 23, STEAM CONDENSATE
PUMPS.
M. Section 23 22 13, STEAM and CONDENSATE HEATING PIPING.
N. Section 23 23 00, REFRIGERANT PIPING.
O. Section 23 31 00, HVAC DUCTS and CASINGS.
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 81 23 - 2
COMPUTER-ROOM AIR-CONDITIONERS
1.3 QUALITY ASSURANCE
Refer to specification Section 23 05 11, COMMON WORK RESULTS FOR HVAC.
1.4 SUBMITTALS
A. Submit in accordance with specification Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, and SAMPLES.
B. Manufacturer’s Literature and Data rated capacities (at design indoor and outdoor conditions), EER/COP, operating characteristics, required specialties and accessories. Submit published catalog selection data showing equipment ratings and compliance with required sensible ratio.
1. Indoor Air Conditioning Unit
2. Glycol Pump Package
3. Dry Cooler
4. Air Cooled Condensing Unit
C. Submit detailed equipment assemblies with dimensions, operating weights, required clearances.
D. Submit wiring diagrams for power, alarm and controls.
E. Certification: Submit, simultaneously with shop drawings, a proof of certification:
F. Completed System Readiness Checklists provided by the Commissioning
Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00 COMMISSIONING OF HVAC SYSTEMS.
1.5 GUARANTEE
The unit shall be guaranteed against all mechanical defects in material, parts or workmanship and shall be repaired or replaced at the
Contractor's expense within the period of one year from final acceptance. Contractor shall adhere to a four-hour service response time to troubles during the guarantee period.
1.6 APPLICABLE PUBLICATIONS
extent referenced. The publications are referenced in the text by the
B. Air Conditioning, Heating, and Refrigeration Institute (ARI/AHRI):
210/240-2023....... Performance Rating of Unitary Air-Conditioning and Air-Source Heat Pump Equipment
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 81 23 - 3
COMPUTER-ROOM AIR-CONDITIONERS
340/360-2022....... Performance Rating of Commercial and Industrial
Unitary Air-Conditioning and Heat Pump
Equipment
410-2011........... Standard for Forced-Circulation Air-Heating and
Air-Cooling Coils
460-2005........... Performance Rating of Remote Mechanical-Draft
Air-Cooled Refrigerant Condensers
520-2004........... Performance Rating of Positive Displacement
Condensing Units
DCPP-2008.......... Directory of Certified Product Performance -
Applied Directory of Certified Products
C. Air Movement and Control Association (AMCA):
210-2016........... Laboratory Methods of Testing Fans for
Aerodynamic Performance Rating
410-1996........... Recommended Safety Practices for Users and
Installers of Industrial and Commercial Fans
D. American Society of Heating, Refrigerating and Air-Conditioning Engineers
(ASHRAE):
Handbook-2020...... HVAC Systems and Equipment
Handbook-2022...... Refrigeration
15-2019............ Safety Standard for Refrigeration Systems
(ANSI)
52.1-1992.......... Gravimetric and Dust-Spot Procedures for
Testing Air-Cleaning Devices Used in General
Ventilation for Removing Particulate Matter
62.1-2019.......... Ventilation for Acceptable Indoor Air Quality
(ANSI)
90.1-2020.......... Energy Standard for Buildings except Low-Rise
Residential Buildings (ANSI Approved; IESNA Co-
Sponsored)
E. American Society for Testing and Materials (ASTM):
B117-2019.......... Standard Practice for Operating Salt Spray
(Fog) Apparatus
F. Federal Specifications:
00-A-374C-1995..... Air Conditioners with Remote Condensing Units or Remote Air cooled and Water-Cooled Condenser
Chalmers P. Wylie Veterans Outpatient Clinic – Columbus, OH
Final Bid Documents
10-01-22
23 81 23 - 4
COMPUTER-ROOM AIR-CONDITIONERS
Units, Unitary
TT-C-490D-2021..... Cleaning Methods for Ferrous Surfaces and
Pretreatments for Organic Coatings
G. National Electrical Manufacturers Association (NEMA):
MG 1-2017.......... Motors and Generators (ANSI)
H. National Fire Protection Association (NFPA):
70-2020............ National Electrical Code (NEC)
PART 2 - PRODUCTS
2.1 FLOOR-MOUNTED UNITS 28 KW (8 TONS) AND LARGER
A. Description: Packaged, factory assembled, prewired, and prepiped;
consisting of cabinet, fans, filters, humidifier, and controls.
B. Cabinet and Frame: Welded steel, braced for rigidity, and supporting compressors and other mechanical equipment and fittings.
C. Doors and Access Panels: Galvanized steel with polyurethane gaskets, hinges, and concealed fastening devices.
D. Insulation: Thermally and acoustically insulate cabinet interior with -
25-mm (1-inch) thick 24 kg/m3 (1.5 lb /ft3) high-density mineral fiber duct liner coated on airstream side.
E. Finish of Interior Surfaces: Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1.
F. Finish of Exterior Surfaces: Baked-on, textured vinyl enamel; color as…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .