Hybrid OR RFIs Amendment 003.xlsx

XLSX spreadsheet 51 KB Posted

Attached to
Z1DA-- Renovate OR for Hybrid Installation
Solicitation number
36C26126R0009
Issued by

About this file

This file is a Request for Information (RFI) Amendment containing 138 numbered questions and responses related to solicitation 36C26126R0009 for renovating operating rooms at the VA Northern California Health System in Mather, California for hybrid surgical installation. The RFI addresses clarifications on technical specifications, design requirements, contractor responsibilities, and administrative submission requirements for a complex healthcare renovation project involving both permanent OR renovations and temporary surgical trailers.

Key scope clarifications include: wall type specifications (S-6 wall details, fire-rated partitions), security systems (C-Cure 9000 access control with VA certifications), fire extinguisher cabinet requirements (semi-recessed cabinets in operating rooms with VA to determine extinguisher type), structural steel certification requirements (AISC certification waivable with third-party inspection or 5+ years erector experience), modular ceiling systems (SLD Technology Airframe systems with contractor-coordinated MEP connections), and temporary trailer setup and commissioning (contractor responsible for delivery, setup, connections, testing, and certification at contractor cost). The contractor must provide detailed phased construction plans, coordinate with equipment vendors (Stryker booms, Olympus equipment, Swiss Log pneumatic tube systems, Avigilon cameras), manage ICRA barrier containment, and ensure all systems (HVAC, electrical, plumbing, medical gas, safety, communications) meet applicable standards prior to clinical use. Administrative requirements include separate price breakdowns for trailer and renovation scopes, emailed proposals with specific subject lines, 8.5x11-inch paper (11x17-inch permitted for schedules), and key personnel with 3 similar-magnitude projects ($10-20+ million) completed within the past 10 years. RFI due date is January 15, 2026, with proposals due February 12, 2026. The second site visit is scheduled for February 4, 2026.

View the file

Other files

File Type Posted
36C26126R0009 0007.docx DOCX document
36C26126R0009 0007.docx DOCX document
Wage Determination CA20260007 01.23.2026.pdf PDF
36C26126R0009 0006.docx DOCX document
36C26126R0009 0005.docx DOCX document
Site Walk 02.04.26.pdf PDF
Attachment RFI 55 - VA Mather Fire Alarm_AS-BUILT 8-27-2020.pdf PDF
Attachment RFI No. 56.docx DOCX document
Attachmetn RFI 115B - Hybrid Drawings 5-4-15.pdf PDF
Attachment RFI 168A -0062457 T0240DXWM VA 1248 NAS Submittal.pdf PDF
36C26126R0009 0005.docx DOCX document
Attachment RFI 115 A - 700000162 L_Pre-Install CHR F-GenChromoViewVPAUDM_EN.pdf PDF
Attachment RFI 168B 20MFAI560 AIR FILTER HEPA 24 X 24 X 12 AstroCel III_prod_mark_sheet_AFP 1 405F.pdf PDF
Attachment 169B EP.401T.pdf PDF
Attachment 171 M-001T.pdf PDF
36C26126R0009 0004.docx DOCX document
ATTACH RFI No.116 SLDAirFrame_ShopDrawings.pdf PDF
Attachment RFI 150 Physics Report.pdf PDF
Attachment RFI No. 123 Spanos Group_ VA Mather Pneumatic Tube System_ FINAL As-Built Set for VA_ 8.18.2023.pdf PDF
Attachment RFI No. 139.docx DOCX document
36C26126R0009 0003.docx DOCX document
Attachment RFI No. 17.docx DOCX document
Attachment RFI 104.pdf PDF
Attachment RFI 135 OR Laydown Area.pdf PDF
Attachment RFI No. 009.pdf PDF
Attachment RFI NO. 15.docx DOCX document
Attachment RFI 76-78 Electrical Gear Locations.pdf PDF
36C26126R0009 0002.docx DOCX document
IMG_5182.JPG JPG image
IMG_5191.JPG JPG image
IMG_5260.JPG JPG image
IMG_5187.JPG JPG image
IMG_E5223.JPG JPG image
IMG_E5224.JPG JPG image
IMG_E5225.JPG JPG image
IMG_5250.JPG JPG image
IMG_5254 .JPG JPG image
Site Visit Log 36C26126R0009.pdf PDF
IMG_5186.JPG JPG image
IMG_5252.JPG JPG image
IMG_5256.JPG JPG image
Attachment G - Supplemental Price Breakdown.xlsx XLSX spreadsheet
612A4-25-004_VA_TRAILER_DRAWINGS_Bid Set_09-30-2025.pdf PDF
Attachment B - EMR Sheet.docx DOCX document
Attachment D - Construction Experience Project Data Sheet.pdf PDF
Attachment E - Past Performance Questionnaire.docx DOCX document
Specifcations 612A4-25-004_VA_Hybrid-OR and Trailer 10.23.2025.pdf PDF
852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING-CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION.docx DOCX document
Wage Determination CA20250007 09.26.2025.pdf PDF
36C26126R0009 Solicitation.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

RFIRFI QuestionRFI Response
1RFI 1) On Sheet A-201, there is a wall type S-6 to be installed. Currently, there is no detail for a wall type S-6. Please clarify the following:S-6 shall match S-8 non-rated wall type but use a small 6-inch stud.
1) Detail for wall type S-6.
2RFI 2) On Sheet ALS-201, there are adjacent bolded areas to the Renovate OR scope of work. Currently, at the Patient Care Suite and the adjacent corridors, it is indicated that smoke partition (non-rated), 2 hr. fire barrier, 2 hr. fire/smoke barrier, 1 hr. fire barrier, and 1 hr. fire/smoke barrier wall types are to be installed. Currently, at the Elevator Lobby, it is indicated that a 2-hr. fire barrier partition wall type to be installed. Currently, at Rooms 2A519, 2A521, and 2A523, it is indicated that a 1 hr. fire barrier partition wall type to be installed.a) Replacement of drywall to achieve 1 hr. fire smoke rating up to bottom of deck may be required. Additional studs may be required to extend wall to deck. Based on visual assessment, parts of these walls are not rated. Existing studs and utilities are to remain. All existing and new penetrations to be fire/smoke sealed.

3 RFI 3: Please confirm whether the requirement for AISC Certified Fabricator and AISC Certified Erector can be waived for this project? If a waiver is possible, please advise on the conditions or acceptable alternatives required for compliance. The AISC certification for fabricators can be waived provided all QA requirements in section N6 of AISC 360 are carried out by a third-party inspector in the shop. This requirement is waived if the shop itself is certified. It's important the owner and contractor understand the additional inspection requirements when comparing steel bids between certified and non-certified fabricators. The AISC certification for erectors can be waived provided the erector has 5+ years of experience in similar sized projects.

4Do you have clarification on the security systems specified for this project?Per T401 - keynote 7; access control system exists and C-Cure 9000.
Upon review of the contract documents, we do not see any indication of a specific security system manufacturer or platform being specified. The lack of clarity regarding brand or system type may create issues, as certain systems require specific manufacturer certifications for installation. Our current understanding is that the scope appears to include security system cabling only. Please confirm the following:1 - C-Cure 9000 Existing
2 - Certifications per VA Specifications
3 - Provide and install devices as noted on sheets T203, T304. Coordinate
requirements with door hardware schedule.
1. Whether any specific security system brand or platform is specified for this project
2. Whether there is certification requirements associated with the security system
3. Whether our scope is limited to cabling only, or if there are any security systems, devices, or equipment that we are required to provide and/or install Clarification is requested so we can confirm scope and ensure proper compliance.
The project specifications call for fully recessed fire extinguisher cabinets. Based on the wall depth shown on the plans and the larger size of the required cabinets needed to accommodate the water mist fire extinguishers, fully recessed cabinets will not fit within the (2) fire-rated wall locations at Operating Rooms #4 and #5. There is also NO specification for the Fire Extinguishers.1. The operating rooms shall receive a semi-recessed wall cabinet. If the wall is rated, an alcove is required per details 06 & 07 on AE-304. The Fire Extinguisher to be
5purchased for the Operating Room shall balance infection control and the NFPA standards. Per the NFPA 16.10.14 a Clean Agent or water mist-type fire extinguisher,
must be provided in operating rooms. Operating rooms are considered to have Class A,B & C type fires due to presence of medical gases (Class B) and energized
electrical equipment (Class C) inside the room. There are only two types of extinguishers considered clean agents. (1) The carbon dioxide extinguisher cannot be used
on human tissue. (2) The water-mist extinguisher is not approved for class B "medical gas" related fires. Therefore, the A/E cannot make a recommendation for the Fire
extinguisher to be purchased and it will need to be determine by the VA which clean agent extinguisher is best in the Operating rooms. VA to determine if the contractor
is to provide the fire extinguisher or just the cabinet.
2. FEC shown in corridors shall be semi-recessed into any non-rated wall. If the wall is rated, an alcove is required per details 06 & 07 on AE-304. Per the VA TIL Fire
Protection Design Manual, the Fire Extinguisher type will need to meet Class A,B,C requirements and be 2-1/2 gallons. VA to determine if the contractor is to provide
the fire extinguisher or just the cabinet and recommend the specific type.

6 Per door schedule on Sheet AE-331, door 2A-232 calls for hardware set SH-3G which is for a single door, but is this door is paired opening? Please advise. Similarly, door schedule on Sheet AE-710T, door T1-004 calls for hardware set SH-3H which is for a single door, and this door is a paired opening? See Attachment RFI No. 6

7The project specifications require the use of an AISC-certified steel subcontractor. We are requesting clarification on whether a steelDuplicate question please see RFI 3 above.
subcontractor holding Los Angeles City Certification may be accepted in lieu of AISC certification?
The Los Angeles City Certification meets or exceeds AISC quality control and safety standards. Please advise if this certification would be acceptable for this project, or if AISC certification is strictly required.
8Opening 2A229B is currently assigned Hardware Group 7B-1. This hardware group is not configured to accommodate an automatic operator. However, drawing A2.01 indicates HW (Hands-Free Wall Actuator for an Auto Operator) at this opening. This appears to conflict with the assigned hardware group.Door 2A229B will require a hand wave auto operator
Revised Hardware 7B-1 shall include: See Attachment RFI NO. 8
assigned group hardware.
Please confirm the following:
Whether Opening 2A229B is intended to be provided with an automatic operator
If an automatic operator is required, please provide the correct hardware requirements and the revised hardware group applicable to this opening Clarification is requested to ensure proper coordination and compliance with the contract documents.

9 We are working on the bid for the Mather project Bathroom/Laundry Accessories and have noticed that the items listed in the table below do not appear in the drawings. Also, for the Toilet Tissue Dispensers (VC), the layout plan on sheet AE-322 labels the tag as B6, while the mounting diagram on the same sheet labels it as B5. Please see attachment RFI No. 9

10Please clarify if a CIVIL set of plans is available or will be provided in the future for the TEMPORARY SURGICAL TRAILERS area whereVA to provide Civil Plans for the space
this work is to occur? Please clarify if a set of complete AS-BUILT plans are available for the TEMPORARY
SURGICAL TRAILERS area where this work is to occur?
11Please clarify if the lockers shown on plan sheets AE202 & AE203 in both the Female & Male Staff Locker Rooms are to be furnished and installed by the GC? If they are to be furnished and installed by the GC, can a specification section be provided for them?Refer to locker schedule on AE-324 and equipment list on
QH-102, lockers are VA provided and VA installed.
12Please clarify if any sort of appliances (Medical Type) will be needed to be furnished and installed by the GCs? There are no spec sections for these, and it is hard to tell from the drawings if anything is required, especially in regard to Medical Refrigerators?All equipment found in the drawings is labeled with a JSN number that refers to its identification in the equipment lists on QH-102 and QH-103. This equipment list identifies who will provide and install the equipment and provides a description of such equipment. No additional specs will be provided by A/E. If specs are required for installation, requests must be made to the VA facility.

13 Please clarify if any sort of LEED or Green Point Commissioning will be required for this project? We could not find anything regarding these in the specifications A/E is not aware of any LEED or Green Point Commissioning required. VA will be providing CX services as required. All sustainability requirements are described in the spec sections for each item as needed.

14 We are requesting more information regarding the temporary trailers, specifically we request the trailer manufacturer’s contact information plus data that they can provide such as Overall length, Width, and height, the weight per module, weight when fully outfitted, VA Engineering: Please refer to the trailer drawings available on the SAMS.gov website: 612A4-25-004_VA_TRAILER_DRAWINGS_Bid Set_09-30-2025.pdf. All dimensions are indicated as shown in the drawings

15 Can the VA supply information regarding approved haul routes and/or crane access zones, if needed? See Attachment RFI No. 15 VA Engineering: Trailers will be stored on the Mather Campus.

Address: 10535 Hospital Way, Mather, CA 95655.

Due to their size, moving these trailers must be scheduled after regular operating hours.

16After the project is completed, will these trailers be removed entirely or relocated back on campus, returned to vendor?VA Engineering: Trailers to remain in place.
17Can you provide a map or description of the location where the VA owned temp OR trailers are being stored onsite?See red boxes on attachment RFI No. 17
18Per Spec Section 01 45 29, the description section (Para 1.1), states the following: This section specifies materials testing activities and inspection services required during project construction to be provided by a Testing Laboratory retained by the General Contractor or Department of Veterans Affairs.” Typically, on VA projects the GC is responsible for carrying these costs by hiring companies such as MatriScope rather than the owner. Please advise on whether special inspection costs will be carried out by the GC or Dept of VA.VA Engineering: Materials testing activities and inspection services required during project construction shall be performed by a Testing Laboratory retained by the General Contractor and paid for by the General Contractor.
19It appears that Temp. Surgical Trailer Drawings do not include a specification book. Will a specification book be provided for the scope associated with theThe specifications are shared with the Hybrid OR project book.
temporary surgical trailers?
20Referring to the Temp. Surgical Trailer Drawings, AE-400T and AE-702 detail 2 call out for scuppers and down spouts, it appears the drawings do not showSince these are temporary trailers it is the intent of the A/E that downspouts are not connected to any drain system and will flow on to
the down spouts connect to a (E) drain system. Please confirm if the new downspouts will be connected to a storm drain system. Please provide detailsthe existing pavement.
connect to a (E) storm drain system. Please confirm if the new downspouts will be connected
Please provide details if the new down spouts are to be connected to a storm drain system.
21Please confirm if the Clean Utility room 2A-245 is to receive new motorized blackout shades.AESUS Response 01/08/2026:
Reference AE-202/08.Per drawings, A/E confirms motorized blackout shades at the following locations:
The RCP (AC-201) does not show Clean Utility room to receive shades.2A-240
Areas to receive new motorized blackout shades:2A-241
- Anesthesia Chief Office 2A-2402A-242
- HAC 2A-2412A-243
- Frozen Sections 2A-2422A-245
- Computer work Area 2A-243VA to confirm
Please confirm location of new shades is correct.
22Please clarify “Timer Controls: Clock timer, programmable” Reference Section 12 24 21 page 3 in the specifications please confirm what the mentioned timerA timer would provide control to the facility to automatically operate the shades at a given time.
is meant to do.For instance, every day when the sun goes down and the glare from sun into the window would warrant closing the shade. Confirm with
VA facility if such controls are required on the remote control device.
23Amendment 0001 indicates there should be an OR Interior Video included with Encl 2. We do not find this video included with the amendment. Please advise.The video would not post, we posted the pictures which were derived from the video.
24Block 13 on the SF1442 indicates sealed offers in original and 1 copy are due at the place specified in Item 8. Under Instructions to Offerors, Item 3.a. (RFP Page 9) states that offers shall be emailed to charee.harris@va.gov. Please confirm that offers are only to be emailed, and that hard copies are not required.Proposals will be email only to charee.harris@va.gov at the date and time specified.
Hard copies are NOT required.
25Reference Instructions to Offerors on RFP Page 9: Item 3.a. states, “The subject line of the email must cite RFP: 36C26126R0009.” However, Item 3.d. states, “Offerors MUST mark the subject line of the email as 36C26126R0009 Renovate OR for Hybrid Installation Technical Proposal and 36C26126R0009 Renovate OR for Hybrid Installation Price Proposal.” Please clarify the required subject line for emailed offers (Item 3.a or 3.d).There are two binders, one will be marked 36C26126R0009 Renovate OR Hybrid Technical and the other Renovate OR Hybrid Price

26 Reference Instructions to Offerors on RFP Page 9: Item 3.d. states, “Offerors MUST mark the subject line of the email as 36C26126R0009 Renovate OR for Hybrid Installation Technical Proposal and 36C26126R0009 Renovate OR for Hybrid Installation Price Proposal.” If we are able to submit both the Technical and Price proposals in one email, please confirm the subject line may read, “36C26126R0009 Renovate OR for Hybrid Installation Technical and Price Proposal”. IT can be one email marked as stated, provided it is less than 10MB in size due to email file size constraints in the VA.

27 Reference Instructions to Offerors: Item 6.d. on RFP Page 10 indicates that proposals shall be prepared on 8.5 x 11-inch paper. This item also states the schedule sheet may be larger for legibility. Please confirm the schedule may be 11 x 17-inch page size. Yes, the schedule may go on 11x17 size paper for legibility.

28 Reference Instructions to Offerors: Item 6.f. on RFP Page 10 states that each volume will contain a Table of Contents. It also states that Tab indexing will be used to identify Sections as appropriate. Including a Table of Contents and an Index seems redundant. Please confirm a Table of Contents meets the requirements for a Tab Index. The table of contents will suffice, provided there are indicators where each segment starts. For examples resumes page XX to XX.

29 Reference Instructions to Offerors: Item 7.c. defines similar magnitude, when referred to in the evaluation factors, as projects that were valued between $10,000,000 and $20,000,000. Will projects greater than $20,000,000 be considered relevant as it pertains to similar magnitude? Yes, projects greater than $20 million are acceptable for similar magnitude. Just can’t go lower, for example here is a $100,000.00 project would be unacceptable.

30 Reference Instructions to Offerors: Item 7.e. states that the Superintendent must not perform other duties or responsibilities, (i.e., safety officer, quality control officer, job site or home office project manager) during the project duration. However, Section 01 45 00 para 3.4.B states that the CQC System Manager is assigned as CQC System Manager but has duties as project superintendent in addition to quality control. Please confirm the Superintendent and CQC System Manager roles cannot be filled by the same person. In this instance the QC manager and superintendent will be separate individuals, however, the QCmanager is not required to be on site at all times.

31 Reference Instructions to Offerors: Section 01 45 00 para 3.4.B states that the CQC System Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 5 years construction experience on construction similar to the scope of this Contract. Will the Government allow 10 years of construction experience on construction similar to the scope of this Contract, in lieu of a degree in engineering, architecture, or construction management? Yes, 10 years of construction experience will suffice in lieu of the referenced degrees.

32 Reference Instructions to Offerors: Section 01 45 00 para 3.4.C discusses (specialty) CQC Personnel and states that these individuals are directly employed by the General Contractor and cannot be employed by a supplier or subcontractor on this project. In addition, it states that these individuals have no other duties other than quality control. On past projects it has been acceptable and cost-effective to allow subcontractors to provide specialized CQC personnel in their respective disciplines, who also have other duties (ex., electrical subcontractor foreman acting as the electrical CQC). Requiring the General Contractor to direct hire these CQC personnel who have no other duties will result in elevated costs to the Government. Will the Government allow these CQC personnel to be employed by a subcontractor and have other duties so long as they are provided sufficient time to perform their CQC duties? In this instance the QC manager and superintendent will be separate individuals, however, the QCmanager is not required to be on site at all times. The individual is also one of the key personnel for proposal evaluation.

TRACKING

33 Reference Instructions to Offerors: Item 7.f.i. (RFP Page 11) indicates that a letter of intent is required for current employees. However, 7.f.ii. states, “***Letters of Commitment/Intent are only required for those personnel being hired specifically for this project and are not current employees. A letter is not required for current employees.” Similarly, in Section M, under Factor II (RFP Page 69) it states that the offeror shall state in their proposal that the individual is a current employee of the prime contractor or provide a letter of commitment… Please confirm a letter of commitment/intent is not required for current employees. Letter of intent/commitment is not required for current employees. Only those who will be hired specifically for this project will require a letter of intent/commitment.

34 Section M, under Factor II (RFP Page 69) states that the offeror shall state in their proposal that the individual is a current employee of the prime contractor or provide a letter of commitment stating the proposed individual will become an employee of the prime contractor prior to award. Please confirm this should state the proposed individual will become an employee upon award (not prior to award). Upon Award is Acceptable

35 Reference Instructions to Offerors: Item 7.g. on RFP Page 11 indicates for joint ventures that a copy of the executed joint venture agreement shall be included in the proposal. Please confirm that the joint venture agreement does not count against the page limitations. The joint venture agreement does not count on page limitations and may be a separate attachment.

36 Attachment G – Supplemental Price Breakdown is organized by high-level systems rather than CSI Divisions, which are more customary and in alignment with the specifications and our estimating systems. As this worksheet indicates “May be edited as needed”, may we modify this sheet to reflect the CSI Divisions of work? This would provide more valuable breakdown information for the Government and would be a lot less cumbersome to fill out. Yes, you may edit and/or modify as you so choose.

37 RFP Page 14 under Joint Ventures it states, “**If there is a Joint Venture, we will allow the extra pages for this information it shall be referenced as an attachment”. Please clarify the information that is being referenced here, is this referring to the Joint Venture Agreement? The Joint Venture agreement may be an attachment.

38 Under Instructions to Offerors it states that a cover is required for both Technical and Price volumes. Please confirm the cover does not count against the page limitations The cover is not a part of the page count.

39FAR 52.228-1 is included in the RFP and indicates the amount of the bid guarantee shall be 100 percent of the bid price or 20,000,000.00, whichever is less. Shouldn’t this be 20 percent of the bid price or $3,000,000.00, whichever is less?Correct FAR 52.228-1 shall read the amount of the bid shall be 20 percent of the bid price of $3,000,000.00 whichever is less.
40Reference Attachment C – Key Personnel Evaluation: Near the top of the first page in blue it indicates we are to demonstrate experience for “Elevator Design Project Manager, Elevator Project Superintendent, Elevator Project Engineer, Elevator Safety Officer, and Elevator QC Manager”. These positions do not align with RFP instructions for Key Personnel and appear to be remnants from a different project. Please confirm these positions are not applicable to this Hybrid OR project and confirm we may delete this statement from Attachment C.The key personnel shall be the personnel stated in the instructions as follows:
1. Project Manager
2. Project Superintendent
3. Safety Officer
4. Quality Control
41Be as specific as possible: Reference Section M: Under Factor II Key Personnel (RFP Page 69) the second-to-last paragraph indicates that to be considered acceptable or higher on this factor, the offeror must provide project personnel who have 3 projects of similar size and scope. Attachment C (Key Personnel Evaluation) asks for a list of projects that were completed by the key personnel within the past six years (note that the RFP does not list this requirement). Projects that meet the RFP definition of similar size and scope do not come along frequently for SDVOSB contractors. Will the Government please allow key personnel to list project experience that occurred more than six years ago?Yes, this can be extended to 10 years.
42Reference Section M, Factor III on Page 69: This paragraph indicates a high-level milestone plan which ‘clearly demonstrates how the two tasks will be accomplished in the same space during the 500-day time period.’ Please clarify which two tasks the VA is referring to that will be accomplished in the same space.The two tasks consist of trailer work site preparation and set-up of temporary surgical trailers, and the renovation work inside the operating room section of the hospital.
43The RFP includes a document titled “Attachment D – Construction Experience Project Data Sheet”. This document includes multiple Exhibits including:Only the solicitation attachments required. The two items referenced as a and b in the sheet Construction experience are not required as the information is available elsewhere in the solicitation and would be considered a duplicate effort. Required solicitation attachments are as follows: Attachment A RFI, Attachment B EMR Sheet, Attachment C Key Personnel, Attach D Construction Experience, Attachment E Past Performance, Attach G Supplemental Price Breakdown.
a. Exhibit “C” Team Composition and Management. Please confirm Exhibit “C” is not required.
b. Exhibit “D” Safety Data Sheet. Please confirm Exhibit "D” is not required.

44 Will the Government please issue Attachment D (Construction Experience Project Data Sheet) in Word format so it can be completed legibly (ex., without trying to fit a ‘detailed’ project description into the small box provided)? RFI 44 attachment

45 Be as specific as possible: Reference Section M, Factor V on RFP Page 69: This paragraph states that for purposes of this evaluation, recency is defined as active or completed efforts performed within the past three (3) to five (5) years from the issuance date of this solicitation. Will projects active or completed more recently than three (3) years from the issuance date of this solicitation be acceptable? If the project is active it shall be at least 60% complete based on the invoices paid to date. If a project is more recent and complete it can be accepted.

46Reference Section M, Factor V on RFP Page 69: This paragraph states that a relevancy determination will be made for each of the three submitted contracts. Would a Hybrid OR renovation project for the VA that had a value of less than $10 million be considered relevant?Less than $10M would not be relevant, as it is considered a much smaller project.
47Reference Drawing EP.401T: We understand the contractor is responsible for providing and coordinating any required temporary electrical services and outage planning. However, the documents do not define a board-specific temporary power/bypass method or acceptable outage window for installing the 1200A breaker in NSH1001A. Please advise.ZONA Electrical Response (01/19/26) – Temporary power requirements, infrastructure and outage windows will require discussion/coordination with VA Mather Facilities. VA to provide feedback and schedule meeting as needed.

48 Reference Drawing EP.401T: While the bus tap installation is clearly contractor scope, the documents do not define how power to EHS/ESH1001A or downstream loads are to be maintained during the tap installation. Please advise and clarify outage allowances, temporary feeds, and VA-provided coordination. ZONA Electrical Response (01/19/26) – Temporary power requirements, infrastructure and outage windows will require discussion/coordination with VA Mather Facilities. VA to provide feedback and schedule meeting with design team as needed.

49 Please provide the Camera requirements and/or desired camera manufacturer/model number for the cameras shown on drawing T-304 Level 2 Video Surveillance RCP. Specification 282300 Video Surveillance appears to be pretty old referencing Analog video throughout VA Engineering: For indoor applications, the preferred camera is the Avigilon 5.0C-H6M-D2-IR Unity H6 Mini Dome Indoor Camera 5MP with the in-ceiling mounting adapter (H6M-MT-DCIL1) if applicable. For any outdoor applications, the Unity H6A Dual Head Camera 4K (16.0C-H6ADH-DO1-IR) with appropriate exterior wall/corner/pole mounts(WLMT-1021/CRNMT-1001/PLMT-1001) and pendant adapter (NPTA-1201).

50 13.Please provide existing Camera System Software manufacturer/model number to be added with the new cameras found on drawing T-304. VA Engineering: We are currently transitioning to the Avigilon Unity Enterprise Edition on-premise video platform and will be fully integrated by the performance period of this contract. The contract was just awarded on January 2nd.

51 14.Please verify that the existing Camera System Software has a current valid Software Service Agreement with the manufacturer. If not, please provide the existing Camera System serial number. VA Engineering: We are currently transitioning to the Avigilon Unity Enterprise Edition on-premise video platform and will be fully integrated by the performance period of this contract. The contract was just awarded on January 2nd.

52 Please verify that there is an existing Camera System Server Storage available for the added new cameras found on drawing T-304. If not, please provide the Server Storage requirements and/or desired manufacturer/model number. Specification 282300 Video Surveillance appears to be pretty old referencing Analog video throughout. VA Engineering: There will be some additional capacity available. However, we would prefer the contractor provide two Avigilon ENVR2 Plus appliances 8TB (ENVR2-PLUS-8P8) with eight Avigilon Unity Video 8 Enterprise Edition licenses for each unit (16 total). The appliances will be placed in the nearest data closet on appropriate server rack-type shelving. The Avigilon Rack Mount kit is not required.

53 Please verify that there is an existing PoE Network Switch available in IDF 2A112 for the added new cameras found on drawing T-304. If not, please provide the PoE Network Switch requirements and/or desired manufacturer/model number. Specification 282300 Video Surveillance appears to be pretty old referencing Analog video throughout. VA Engineering: The contractor will be responsible to provide a separate patch panel specifically for the camera ethernet cables. The cameras cables will be pulled to and terminated on the previously mentioned patch panel by the contractor. The appliances noted previously have on-board PoE and any other PoE switches in the closet would be provided by the government.

54Please verify that there is no Specification 285231 Emergency Call System required for the 2nd Floor Renovation or Temporary Trailers.The specification section does not apply to this project.
55Please provide us with a built for fire alarm system to know the location of all devices for us to provide any temporary raceway in case this will be affected by demolition work. Also, please provide us the contact information for the company maintaining or supervising the (E) FA system to know if there are available zones for (N) Devices that may be required.
56Please provide us information on (E) Buss Duct (Manufacturer/serial or model no./Rating/Buss type (Aluminum or Copper/amperes/Voltages/Phases)
57Since there is work regarding the existing Pneumatic Tube System, would it be possible to get the as-built plans for it ?VA will provide as-builts.
58In the solicitation statement of work, programming and controls: Johnson Controls is called out for programming and controls system for the project. Is the VA open to otherour existing system is Johnson Controls. Jonson Controls is our preferred vendor for programming and controls systems. This choice is made to ensure consistency, avoid potential confusion, and facilitate easier maintenance and future compatibility of parts and systems
vendors to perform this scope of work, as in Siemens.
59Please clarify regarding the camera system addition/changes for this project. Is the requirement only to provide/install the cameras and cat6 cables to the data room where a VA provide switch is located? Would the VA IT personnel be responsible for connecting to the networks which, programming, and any necessary video server hardware and software requirement?VA Engineering: The contractor is obligated to furnish and install the Avigilon cameras and
appliances along with the ethernet cabling including termination to a separate patch panel in
the designated data closet. The software integration and programming of cameras will be handled by the government.
60Please clarify if other vendors can be used for HVAC Controls besides Johnson Controls for this project? From what we understand they are the current vendor.Correct, Johnson controls is the the system/vendor on station.
61Please clarify if there is any Commercial Kitchen Equipment required on this project ?No commercial Kitchen equipment is part of this project.
62Please provide the Camera requirements and/or desired camera manufacturer/model number for the cameras shown on drawing T-304 Leve 2 Video Surveillance RCP. SpecificationFor indoor applications, the preferred camera is the Avigilon 5.0C-H6M-D2-IR Unity H6 Mini dome Indoor Camera 5MP with the In-ceiling
282300 Video Surveillance appears to be pretty old referencing Analog video throughout.mounting adapter (H6M-MT-DCIL1) if applicable. For any outdoor applications the unity H6A Dual Head Camera 4K. (16.0C-H6ADH-D01-IR)
with appropriate exterior wall/corner/pole mounts(WLMT-1021/CRNMT-1001/PLMT-1001) and pendant adapter (NPTA-1201)

63 For the Temporary Trailers Project, sheet AE-201T shows callouts for FRP at some locations. Can you please confirm whether the FRP is intended to continue throughout the Clean Supply Room and the Corridor, or if it is only required at the specific wall locations identified by the callouts? and pendant adapter (NPTA-1201).

64For the demo/temp ICRA barrier plan (AD-101), can you clarify where the temp barrier layout is actually shown and installed for this project? We see the keyThe entire area of work needs to be contained with ICRA barriers as shown by the dashed lines with ICRA wall
indicates a thicker dashed line for the temp barriers. Is the temp barrier the dashed line surrounding the entire area of work or is it just the ICRA vestibule areas?types A and C called out. ICRA wall types can be found on sheet AD-103. Where dashed lines are shown on top of
existing walls, refer to ICRA wall type C, to extend existing walls up to the deck. Where new ICRA barriers are
required to be built as new walls to contain the area of construction, provide ICRA wall type A. All temporary
construction barriers are to be 1 hour fire rated. Contractor can propose alternative ICRA barriers such as STARC
walls upon VA approval. However, all existing walls used to contain the construction area must be extended to the
deck as shown in wall type C on sheet AD-103. The entire area of construction must be contained by ICRA barriers
that are sealed for fire, smoke, dust, and noise.
65Male & Female Staff Lockers / RR Showers – Is it ok to use Schluter Kerdi Waterproof Fabric at shower walls and floors? If so, are we thin setting tile over the Kerdi FabricAESUS takes no exception to the use of the Schluter Kerdi Waterproof System. Confirm with VA for approval. Center drain is shown ond etail 01/AE-324.
(TCNA W244C-25 ) or installing a full mortar bed with lath prior to installed the Kerdi Fabric (TCNA W231/W241-25). Will the shower floors b recessed for a full mortar bedNo floor recess required. Float surrounding floor in bathroom area per details 01-02 on AE-324.
sloped to drain. The schluter Kerdi waterproof fabric system requires us to use the Schluter Center Drain. Please adivse if the Schluter Kerdi waterproof system is ok to use.
66What TCNA installation number should we bid with for the wall tile outside of the showers? TCNA W243-25?Tile setting per specification 09 30 13.
67Are the floors on Level 2 to receive Lightweight concrete? If not please identify the floor substrateRefer to structural keynotes on S-201 and details on S-401.
68At the Scrub Sinks, it calls for CWT-1 at the back wall. How high should the tile be installed?Refer to general remarks on finish schedule on AI.02
69Please clarify what type of Grout is to be used – Standard Cementitious or Epoxy?Refer to 09 30 13 specification for grout types at specific locations.
70The specifications call for Schluter Jolly trim at all exposed edges at wall tile. Please clarify if this correct?Correct FAR 52.228-1 shall read the amount of the bid shall be 20 percent of the bid price of $3,000,000.00 whichever is less.
71Please clarify if this project will require a liquid waterproof membrane on the restroom floors? If so that would include installing the membrane up the walls 4-6 inchesLiquid waterproofing membrane not allowed per detail 03/AE-324. Floor sheet waterproofing membrane to be continued up walls 6 inches. Ensure
overlap with wall sheet membrane per detail 03/AE-324. For sheet membrane requirements refer to specification 09 30 13.
72VA Engineering: “One Bid”. Fill out 2 Price Breakdown worksheet. One for Temporary trailers and one for 2nd floor renovation. Separate Attachment G is required to facilitate a faster payment process and to avoid confusion.VA Engineering: “One Bid”. Fill out 2 Price Breakdown worksheet. One for Temporary trailers and for 2nd floor renovation.

73 Are there any detail drawings available for the SLD ceilings in the operating room? Drawing EL101 keynotes state 'coordinate with vendor and installation guides.' Please confirm if additional details will be provided. A/E Response: Please coordinate with VA Mather for supplemental information regarding SLD ceilings.

75What lighting controls manufacturer should be used in the operating room? Please confirm the specified vendor or acceptable manufacturers.Please coordinate with VA Mather for acceptable lighting control vendors.
76Drawing EP.601 shows a new feeder connecting to panel SH11A feeding panel SH22A. Where is panel SH11A located? Is it on the 1st floor?A/E Response: Located on 1st Floor, Electrical Closet 1A129. Refer to attached pdf E1.0 (see attachment for 76-78 RFI)
77Drawing EP.601 shows a new feeder connecting to panel SL11A feeding panel SL22A. Where is panel SL11A located? Is it on the 1st floor?Located on 1st Floor, Electrical Closet 1A129. Refer to attached pdf E1.0.
78Drawing EP.601 shows a new feeder connecting to CRIT DB QHD1001A. Where is this distribution board located?A/E Response: Panel QH21A shall be fed from (E) QH12C, located on 1st Floor, Electrical Closet 1A216. Refer to attached pdf E1.0. Panel no longer being fed from (E) QHD1001A.
79Drawing EP.601 shows the feeder connecting panel NH22A to an existing bus duct. Where is this bus duct located?A/E Response: (E) Normal bus duct shown on 2/EP101.
80There is a note on P-101 that states to relocate any water lines over a server room, but the plans do not provide routing or sizing or number of pipes existing. Are there as-builts that can be provided that would allow plumbers to quantify in their bid? Please advise.VA to supply as-builts.

VA Engineering: Existing is 2” air vent pipe. No need to relocate.

81M-802 Mechanical Controls shows the controls as Johnson Controls. Is it the intent of the hospital to continue using Johnson Controls?Yes
82Keynote 4 on M-102 states for Mechanical Contractor to connect duct to prefabricated ceiling system. Who is responsible for the installation of SLD Ceiling System?Typically the GC.
83Keynote 4 on M-102 states that there are ceiling system drawings by SLD. Please provide these drawings.Refer to architectural plans (AE-2XX) for proposed SLD reflected ceiling plans. Also, preliminary SLD drawings were provided in the bid package. SLD is the sole-source provider on this project. Contractor to coordinate with SLD and provide final shop drawings.
84General Note H on M-102 states that there is phasing for this project. Does the owner have a document showing the phasing plan, or is this going to be provided by the awarded GC?Final phasing plan is developed by GC. Refer to various phasing notes throughout plans.
85Please confirm facility to put the HHW S/R into a “no flow” condition to facilitate line freeze of (E) HHW S/R lines.Major system interruptions must be requested in writing at least three weeks prior to the intended date. Approval must be obtained from the VA Utility Shutdown Committee before the utility shutdown is performed. Additionally, a Method of Procedure (MOP) must be submitted to the VA Utility Shutdown Committee for review and approval prior to the shutdown.
86Please provide (E) material types for the HHW S/R systems requiring a tie in.Existing heating hot water piping is black iron, with limited runouts of Type L copper.
87Please confirm fixture P-519 is a single fixture and not two individual fixtures.P-519 is a single basin surgical scrub sink. A two-basin sink installation is also acceptable.
88Please provide trapeze detail for pipe installation.Detail may be provided
89Please confirm facility responsible for isolation and back feed for medical gas system during installation of new isolation ball valves.Isolate medical gas at shaft (note 6), in coordination with facility. The need for back feed is not anticipated.
90Please confirm end of (E) medical gas systems to be capped off before grid line T7.Medical gas must be isolated at shaft (note 6), new isolation valves installed, and ZVB & NCP demolished, before service installed to ZVBs (note 5) serving area plan south.
91Please confirm fixture to be either P-519 (P-101 & P-102) or P-520 (P-502).Intent is P-5019, single basin surgical scrub sink.
92Can you provide a construction schedule?Construction schedule to be provided by the selected General Contractor as a submittal.
93Please provide hanger, supports and roof supports for temp trailer pipe connections.
94Please provide fist floor plans for areas where plumbing will be preformed.Refer to first floor layout shown on M-101.
95Please provide phasing plan for first floor plumbing demolition and installation.Final phasing plan is developed by selected General Contractor. Refer to various phasing notes throughout plans.
96Please provide logistics and any infectious control requirements for first floor plumbing.ICR items to be provided by owner.
97Please provide details for pipe penetrations through walls, floors ceilings.Refer to UL details in architectural plans.
98Please provide details for pipe penetrations through fire rated walls, floors ceilings.Refer to UL details in architectural plans.
99Please detail on prefabricated ceiling system and med gas connections to it.Refer to SLD preliminary shop drawings.
100Please provide connection how new medical gas alarm panel is to tie into the system and monitor the medical gas system.Remote sensors are installed downstream of ZVB to monitor pressures. Existing area alarm panels in area tie-back to master alarm panel (central plant). New area alarm panels to utilize this wiring homerun.
101Please confirm detail 8/M-503 does not apply to this project.Confirmed. Does not apply.
102Please confirm Door 2A-230A and 2A-230B should be fire rated as no one has an aluminum fire rated slider that I am aware of. If this is in fact to be fire rated please advise on manufacturer and model number desired.Yes, the door is required to be fire-rated. Specialized fire-resistant glass is required. If the manufacturer requires a steel frame in place of aluminum to achieve the rating, AESUS takes no exception.

103 The spec does not indicate integral blinds for GL-3, under the glass type for window BL2 it indicates integral blinds (Ref Det A3.33/06). This detail cannot be located. Should this lead lined glass have integral blinds? Should all GL-3 glass have integral blinds or is it isolated to just the glass at BL2. Window BL2-01 at the Hybrid OR Control Room is both lead lined with lead glass and contains integral blinds. See below for integral blind detail integrated into the lead lined window detail 14/AE-333, which will required integral blinds between two panes of glass, only one of which will need to be lead glass. See revised detail attached

104 The project is within an active healthcare facility; however no language assigns iCRA or OSHPD Inception control responsibilities to the structured cabling contractor. Please confirm: The low voltage/structured cabling contactor is NOT responsible for ICRA planning or classification, Temporary barriers or containment, negative air machines or HEPA filtration. Confirmed - All ICRA and OSHPD compliance measures are by the General Contractor or others, and LVC will work within established controls. See updated ICRA requirements as Attachment RFI 104.

105 There are several references to demolition and cutover in the T-Sheets or the provided drawings, but no detail or sequence of events. Please confirm: The low voltage cabling contractor is to Install all new cabling while existing active cabling is still in place then perform a patching cutover and demo "old Cables". If the above sequence is correct, pleas provide as-builts for cables to be demoed, or an approximate quantity of cables. Confirm there is no demo or cutover SOW for the temp trailers. If there is request to provide details please. Area is being remodeled entirely – all existing cabling to be demo. Contractor to confirm all existing cabling with GC and owner prior to removal. Confirmed – no demo or cutover for the temp trailer scope.

106Please confirm if the LVC provides and install all copper and fiber optic patch cords. Please confirm LVC provides and installs all patch cords at both ends of every cable installed. LVC provides all patch cords at both ends of every cable installs, but only installs the patch panel side. Please provide lengths and colors for work station and TR.Confirmed – the LV contractor to provide patch cords (copper/fiber) for both ends and only install patch cords at the TR side.
It is the responsibility of the LV contractor to determine lengths and quantities, color blue.
107Level 02 IDF 2A112 - Confirm this rack and room in general are existing and are to be re-used.Confirmed – equipment racks are existing and are to be used.
108Division 271500 - Is there a preferred cable manufacturer for horizontal cabling?Berk—Tek / Ortronics is the existing preferred solution.
109Situation: RCP Drawing AC-201 shows room 2A-241 getting ACT-02 and the Room Finish Schedule on Drawing AI.02 calls out GYPBD-2 and doesn’t call out the ACT-2. Which governs, the RCP or the Room Finish schedule?AESUS Response: Housekeeping Closet Room 2A-241 to receive ACT-2.

110 Situation: RCP Drawing AC-201 shows Female Staff Lockers as Room # 2A-008 and the Room Finish Schedule on Drawing AI-02 is calling it Room 2A-106B. Which governs, the RCP or the room finish schedule? AESUS Response: Female Staff Lockers rooms to be number 2A-106B.

111 Trailer vendor shop drawings (Gerling, Sheets V-T01 thru V-T05) as well as Hybrid OR vendor (Philips, Sheets V-001 thru V-009) have been included within the bidding documents. These sheets indicate that they are “FOR REFERENCE ONLY USED FOR BASIS OF DESIGN.” In regards to the GC’s scope of work required to be performed for this project, please confirm that the trailers are to arrive fully furnished so that all GC needs to make necessary connections at the stub-out locations for Med-gas, plumbing, power, IT. For example, on Sheet V-T01 we consider that the items drawn as a dashed line like (2) exterior doors and the (2) storage rooms sink are to be coordinated and installed by GC, but all the other items like the walls, support structures for lights/booms, LED lights within the trailer will be provided by Gerling. Also, we are assuming that these trailers will already be roofed as Sheet AE-400T does not indicate roofing to be installed by GC for the trailers. VA Engineering: The trailers are to arrive fully furnished and ready for connection, except for specific items indicated on the Gerling list for Trailer set up. Refer to the Gerling “Trailer Install Onsite at VA” documentation. Stryker and Olympus will install the booms and equipment inside the trailers.

The General Contractor (GC) is responsible for the delivery, setup, construction, and connection of the trailers, including all required stub-outs for Med-gas, plumbing, power, and IT systems, to ensure the trailers are fully operational for clinical use. The costs associated with trailer setup, commissioning, testing, and certification shall be borne by the GC. This includes coordinating with Gerling, Stryker and Olympus for installation requirements and engaging third-party inspectors to verify that all systems—HVAC, electrical, plumbing, medical gas, safety, and communications—are fully functional and compliant prior to use. The trailers must be installed, set up, certified, and fully operational on-site prior to the start of renovation activities in the second-floor OR areas. The GC shall develop a detailed phased construction plan that minimizes operational disruptions, maintains VA scheduling requirements, and ensures the continuous operation of interim surgical facilities. All commissioning activities shall be conducted in coordination with certified third-party inspectors and relevant authorities. The GC is responsible for ensuring that all systems meet applicable safety, building, and clinical standards. Refer to the Gerling “Trailer Install Onsite at VA” document for guidance. The GC shall coordinate with Gerling regarding trailer setup and installation requirements. Point of contact: Kevin Robinson. Tel: 740 965-2888. The cost of trailer commissioning shall be the responsibility of the GC.

112 Attachment D - Construction Experience Project Data Sheet includes various Exhibits that reference NAVFAC/USACE. This is not a Navy project will the VA be providing and updated Attachment D that References VA projects. Updated attachment D is attached in Word Format. See Attachment RFI 112

113 Sheet AE-202 note 17 of “612A4-25-004 _VA_Hybrid-OR_DRAWINGS_Bid Set_09-30-2025” states general contractor to coordinate roof work with COR and existing warranty information. The plans do not show any work at the roof. The only roof work is for the new temporary structure. Please confirm no work at the existing building roof. Confirmed, the OR portion of the scope does not have “roof work”. However, the trailer set of drawings does include roof work and this note applies.

114 Note 5 of the New Ceiling Mounted Booms by Stryker on sheet AE-204 of “612A4-25-004 _VA_Hybrid-OR_DRAWINGS_Bid Set_09-30-2025” states the outlets called out on the plans are not correct and do not meet VA Design Guide requirements. Please provide update plans that show work required to make this work be compliant with VA Design Guidelines. VA Engineering: Project was designed based on 2018 guidelines. No new drawing will be provided. Provide outlets per called out in the drawing.

115Sheets AE-204, AE-206, and AE-207 all discuss the general contractor’s responsibility to furnish/install structural supports and related plates for the Stryker Booms. The plans do not include details showing the required plates and their connection to the Stryker booms. Please provide details showing the plate and required connection to both the Stryker Booms for the light booms, equipment booms, and Anesthesia BoomsStryker drawings to be provided by the VA for both existing and new booms.

This is the start of the file's text. The full file is on GovTribe.