This is a Request for Information (RFI) form for VA Project 612A4-25-004, "Renovate OR for Hybrid Installation," under Solicitation No. 36C26126R0009. The RFI was submitted on January 5, 2026, and sent to Charee Harris at charee.harris@va.gov. The inquiry pertains to Specification Section 08 71 00 (door hardware) and references Drawings AE-331 and AE-710T.
The contractor requested clarification on hardware set specifications for two paired door openings that were incorrectly scheduled for single-door hardware sets. Specifically, door 2A-232 on Sheet AE-331 was assigned hardware set SH-3G, and door T1-004 on Sheet AE-710T was assigned hardware set SH-3H, both intended for single doors despite being paired openings. AESUS Design Group responded on January 6, 2026, providing corrected hardware specifications for both doors. Door 2A-232 (Interior Unequal Double Door) requires five hinges, a full mortise hinge, flush bolt, dust-proof strike, storeroom lock, interchangeable core, coordinator, two surface closers, armor plate, astragal, adhesive gasketing, alarm contacts, and a card reader. Door T1-004 (Exterior Double Door) requires similar components plus a door operator and actuators, rain guard, door bottoms, and a threshold for outswing configuration.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION (RFI) FORM
Contractor Name:
Address:
Phone and Email:
Send to: charee.harris@va.gov
RFI
PROJECT NO.: 612A4-25-004 RFI NO.: 001
PROJECT NAME: Renovate OR for
Hybrid Installation
DATE REQUESTED: 1/5/2026
SOLICITATION
NO.:
36C26126R0009 REFERENCE: n/a
DRAWING: AE-331 & AE-710T SPECIFICATION
SECTION:
08 71 00
DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED
Be as specific as possible:
Per door schedule on Sheet AE-331, door 2A-232 calls for hardware set SH-3G which is for a single door, but this door is a paired opening? Please advise.
Similarly, door schedule on Sheet AE-710T, door T1-004 calls for hardware set SH-3H which is for a single door, and this door is a paired opening?
Please advise which hardware set should be use for these openings.
PROJECT MANAGER’S RESPONSE
TRACKING NO.: AMENDMENT NO.:
VA PROJECT ENGINEER/MANAGER: DATE:
Door 2A-232: Interior Unequal Double Door 5 Hinge USA TA2314 1 Hinge, Full Mortise USA TA2314 QC 1 Flush Bolt 2848 / 2948 1 Dust Proof Strike (L04021) 570 1 Storeroom Lock (F07) AUR 8805FL Temp Core 1 Interchangeable Core 33600006N 1 Coordinator 2600 Series 2 Surface closer C02011 R/PR3511 2 Armor Plate, Fire Rated K1050 F 24" high CSK BEV 1 Astragal (by door manufacturer) 1 Adhesive Gasketing S88BL PE 2 alarm contact (by Div 28) Card Reader (by Div 28)
Door TI-004: Exterior Double Door 5 Hinge USA TA2314 1 Hinge, Full Mortise USA TA2314 QC 1 Flush Bolt 2848 / 2948 1 Dust Proof Strike (L04021) 570 1 Storeroom Lock (F07) AUR 8805FL Temp Core 1 Interchangeable Core 33600006N 1 Coordinator 2600 Series 2 Surface closer C02021 R/PR3511 1 Astragal (by door manufacturer) 1 Adhesive Gasketing S88BL PE 2 alarm contact (by Div 28) 1 door operator & actuators (by section 08 71 13) Card Reader (by Div 28) Rain guard 346C 2 Door bottom 420APKL 57mm threshold (outswing door)
AESUS Design Group Response 01/06/2026