QTRLY flow and tamper blank document.xlsx

XLSX spreadsheet 31 KB Posted

Attached to
H212--Fire Protection Testing, Inspection, and Maintenance/Repair
Solicitation number
36C26126Q0018
Issued by

About this file

This document is a Quarterly Fire Water Flow Devices Test form for the Reno VA Medical Center (VAMC) located at 975 Kirman Ave, 89502. The comprehensive inspection checklist follows NFPA 25-2020 standards and requires detailed testing of fire protection water flow devices across multiple building floors and areas, including stairwells, service elevators, and various building sections.

The inspection protocol involves specific steps such as notifying Biomedical Engineering and Boiler Plant operators, verifying fire alarm system status, measuring water pressure before and after flow testing, checking waterflow devices for physical condition, examining tamper switches, and assessing gauge operability. The document covers 67 specific inspection points across different building floors and areas, with instructions to document pressure readings, restoration times, and pass/fail conditions for each location. Any negative or failing results require follow-up work orders for corrective action and retesting. The inspection is to be conducted by Kyle Lawrence, with coordination recommended to minimize unnecessary fire pump activation.

View the file

Other files

File Type Posted
36C26126Q0018 0002.docx DOCX document
Floor Plans - Fire and Smoke Dampers - Working.pdf PDF
Reno VAMC-Building 1 Section C - Damper Inspection Report 2024.pdf PDF
975 Kirman Pre action 5 yr 7-20.pdf PDF
ANNUAL FWP 231130.pdf PDF
Semi-annual FM200 4-28-2025.pdf PDF
Reno VAMC-Area G - Damper Inspection Report 2025.pdf PDF
975 Kirman Ave. Reno Nv FSD 1.30.24.pdf PDF
VA Bldg. 12 Preaction 10-22-2024.pdf PDF
Reno VAMC-Building 1D - Damper Inspection Report 2025.pdf PDF
Semi-annual Ansul Testing Canteen 05-15-24.pdf PDF
Area D Fire Damper Inspection.xlsx XLSX spreadsheet
Semi-annual Ansul Testing NFS 05-15-24.pdf PDF
VA Bldg. 12 Preaction 1-6-2025.pdf PDF
36C26126Q0018 0001.docx DOCX document
2- Floor Plans - Fire and Smoke Dampers Bldg 1 1A 1D 5 6 10 12.pdf PDF
VA Bldg. 12 Preaction 4-28-2025.pdf PDF
Reno VAMC-Building 5 Section K - Damper Inspection Report 2024.pdf PDF
Attachment 1 - Drawings.pdf PDF
Reno VAMC-Building 12 - Damper Inspection Report 2025.pdf PDF
Bldg Sprinkler Inspections.pdf PDF
Reno VAMC-Building 6 - Damper Inspection Report 2025.pdf PDF
VA FSD Inspection Bldg 10 FD 5B-Fail 5.9.24.pdf PDF
Semi-annual FM200 10-22-2024.pdf PDF
Site Visit Information.docx DOCX document
36C26126Q0018.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QFW-Flow

EC.02.03.05 EP 2ATTACHMENT B1
QUARTERLY FIRE WATER FLOW DEVICES TESTNFPA 25-2020: 5.3.3.1, 13.2.4.3.2, 5.3.3.2, 13.2.4.4.2SOP PLB 405
QUARTERLY FIRE WATER DEVICES INSPECTIONNFPA 25-2020: 5.2.4, 13.2.4.3.1, 13.2.4.4.1, 13.2.5.1.1, 13.2.6.1
Site:RENO VAMC. 975 Kirman Ave. 89502
EE:
WO#
Inspector:Kyle Lawrence
Date:
Note: Make every attempt to coordinate with BioMed to complete during the FW alarm testing
and during the weekly fire pump run to mitigate unneeded running of the fire pump.
1. Notify the following of the test.
a. Bio Medical Engineering 3929Rich Chriss
b. Boiler Plant x1287Operator
c. Supervisor
2. Verify the fire alarm system is in test.Yes: Continue.No: StopInitialsKHL
3. Record the pressure indicated by the supply water gauge in the (Pressure Before) column below.
4. Open valve to test position.
5. After the flow has stabilized, record the flowing pressure indicated by the water supply gauge in the
(Flow Pressure) column below.
6. Slowly close the test valve. Note: Do not shock system. Record the time taken for the supply water pressure to return to the static (nonflowing) pressure.
Record the pressure in the (Pressure After) column. Record time in the (Restore Time ) column. Verify waterflow device. Record Pass or Fail in Pass/Fail Column.
If No Gauge (NG), verify waterflow device. Record Pass or Fail in Pass/Fail Column.
7. Verify Waterflow Device is free of physical damage and annotate condition. G=Good or P=Poor in Physical Condition (Waterflow Device) column below.
8. Verify Tamper Switch is not physically damaged and annotate condition. G=Good or P=Poor in Physical Condition (Tamper Switch) column below.
9. Verify Gauge is operable and not physically damaged and annotate condition. G=Good or P=Poor in Physical Condition (Gauge) column below.
10. Secure fire pump by depressing the stop button.
11. Test jockey pump to verify readiness condition.InitialsKHL
12. Inform Bio Medical Engineering, Boiler Plant and Supervisor when Complete.InitialsKHL
13. Negative (P or Fail) results are to be followed up with work orders for corrective action and retested.
IDBuildingFloorAreaReference AreaPressure BeforeFlow PressurePressure AfterRestore Time-SecPhysical ConditionPass FailWork OrderRepair DatePass Fail
Waterflow DeviceTamper SwitchGauge
115NorthStair
214NorthStair
313NorthStair
412NorthStair
511NorthStair
61PenthouseCenterStair
716CenterStair
815CenterStair
915Center EastC5330
IDBuildingFloorAreaReference AreaPressure BeforeFlow PressurePressure AfterRestore Time-SecPhysical ConditionPass FailWork OrderRepair DatePass Fail
Waterflow DeviceTamper SwitchGauge
1014CenterStair
1114Center EastC4331A
1213CenterStair
1313Center EastC3332
1412CenterStair
1512Center EastC2331A
1611CenterStair (1)
1711CenterStair (2)
181BasementCenter EastC0330
191BasementCenter EastC0339
201A3NorthStair
211A3NorthStair-Pent
221A2NorthStair
231A1NorthStair
241DBasementEast StairsBD-101
251D1EastG1541
2651EastEast
2752EastEast
281D2EastG2530
291D3EastG3540
301D4East3D-102
311D5EastG5545
321D5EastG5545
331D3WestG3651A
341D3MRI WestStair
351D2MRI WestStair
361D2WestG2652
371D1MRI WestStair
381D1MRI WestStair-ER
391DBasementMRI WestStair L Hatch
401DBasementMRI WestG0700
411D1WestG1646
421D1PT/OTOSA G1575
IDBuildingFloorAreaReference AreaPressure BeforeFlow PressurePressure AfterRestore Time-SecPhysical ConditionPass FailWork OrderRepair DatePass Fail
Waterflow DeviceTamper SwitchGauge
4312PenthouseNorthStair
44126NorthStair
45125NorthStair
46124NorthStair
47123NorthStair
48122NorthStair
49121NorthStair
5012BasementNorthOS B0100
51126SouthStair
52125SouthStair
53124SouthStair
54123SouthStair
55122SouthStair
56121SouthStair
5712Gen Bldg.SouthBGEN1
58121Service ElevatorB1260******************************CappedOff**************************************************
59121Service ElevatorB1260******************************CappedOff**************************************************
60122Service ElevatorB2260
61101Top of RampHatch
62101WestOSA L1832
63101EastOSA L1862
6410BasementIRML0878
6561EastStair
6662EastStair
6771RecordsN227
NGNo Gauge
COMMENTS:
Building 15 demo'd February 2019. No longer in service. Removed ID #'s 68-71.
**Flow ID # 61. Verify Waterflow Alarm Device Pass or Fail

File details come from the government source that posted it. Updated .