This document is a Standard Form 1449 Solicitation/Contract/Order for Commercial Products and Commercial Services (RFQ) for fire protection testing, inspection, maintenance, and repair services at the VA Sierra Nevada Healthcare System. The solicitation (36C26126Q0018) is a 100% Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside with a $25 million size standard for the NAICS code 561621. The contract period includes a base year from 10-07-2025 to 10-06-2026, with four potential option years extending through 10-06-2030.

Key details include a site visit scheduled for 09/16/2025 at 08:00am PST, quote submissions due by 09/26/2025 at 11:00am PDT, and requirements for comprehensive fire protection system services at the Reno, NV facility. The contractor must perform testing, inspection, maintenance, and repair of various fire protection systems including sprinklers, suppression systems, fire pumps, dampers, and standpipes, adhering to specific Joint Commission and National Fire Protection Association (NFPA) standards. Offerors must be verified SDVOSB at the time of quote submission and maintain certification throughout contract performance, with failure to do so resulting in exclusion from evaluation.

View the file

Other files

File Type Posted
36C26126Q0018 0002.docx DOCX document
Floor Plans - Fire and Smoke Dampers - Working.pdf PDF
Reno VAMC-Building 1 Section C - Damper Inspection Report 2024.pdf PDF
975 Kirman Pre action 5 yr 7-20.pdf PDF
ANNUAL FWP 231130.pdf PDF
Semi-annual FM200 4-28-2025.pdf PDF
Reno VAMC-Area G - Damper Inspection Report 2025.pdf PDF
975 Kirman Ave. Reno Nv FSD 1.30.24.pdf PDF
VA Bldg. 12 Preaction 10-22-2024.pdf PDF
Reno VAMC-Building 1D - Damper Inspection Report 2025.pdf PDF
Semi-annual Ansul Testing Canteen 05-15-24.pdf PDF
QTRLY flow and tamper blank document.xlsx XLSX spreadsheet
Area D Fire Damper Inspection.xlsx XLSX spreadsheet
Semi-annual Ansul Testing NFS 05-15-24.pdf PDF
VA Bldg. 12 Preaction 1-6-2025.pdf PDF
36C26126Q0018 0001.docx DOCX document
2- Floor Plans - Fire and Smoke Dampers Bldg 1 1A 1D 5 6 10 12.pdf PDF
VA Bldg. 12 Preaction 4-28-2025.pdf PDF
Reno VAMC-Building 5 Section K - Damper Inspection Report 2024.pdf PDF
Attachment 1 - Drawings.pdf PDF
Reno VAMC-Building 12 - Damper Inspection Report 2025.pdf PDF
Bldg Sprinkler Inspections.pdf PDF
Reno VAMC-Building 6 - Damper Inspection Report 2025.pdf PDF
VA FSD Inspection Bldg 10 FD 5B-Fail 5.9.24.pdf PDF
Semi-annual FM200 10-22-2024.pdf PDF
Site Visit Information.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C26126Q0018

PAGE 1 OF

1. REQUISITION NO.

2. CONTRACT NO.

3. AWARD/EFFECTIVE DATE

4. ORDER NO.

5. SOLICITATION NUMBER

6. SOLICITATION ISSUE DATE

a. NAME

b. TELEPHONE NO. (No Collect Calls)

8. OFFER DUE

DATE/LOCAL

TIME

9. ISSUED BY

CODE

10. THIS ACQUISITION IS

UNRESTRICTED OR

SET ASIDE:

% FOR:

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

8(A)

NAICS:

SIZE STANDARD:

11. DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS

13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ

IFB

RFP

15. DELIVER TO

CODE

16. ADMINISTERED BY

CODE

17a. CONTRACTOR/OFFEROR

CODE

FACILITY CODE

18a.

PAYMENT WILL BE MADE BY

CODE

TELEPHONE NO.

UEI:

EFT:

PHONE:

FAX:

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED

SEE

ADDENDUM

19.

20.

21.

22.

23.

24.

ITEM NO.

SCHEDULE OF SUPPLIES/SERVICES

QUANTITY

UNIT

UNIT PRICE

AMOUNT

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26.

TOTAL AWARD AMOUNT (For Govt. Use Only) 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

ARE

ARE NOT ATTACHED.

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

ARE

ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________

29. AWARD OF CONTRACT: REF. ___________________________________ OFFER

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND

DATED ________________________________. YOUR OFFER ON SOLICITATION

DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY

(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE

ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED

SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) 30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED

AUTHORIZED FOR LOCAL REPRODUCTION

(REV. NOV 2021)

PREVIOUS EDITION IS NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.212

7. FOR SOLICITATION

INFORMATION CALL:

STANDARD FORM 1449

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL

PRODUCTS AND COMMERCIAL SERVICES

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

36C26126Q0018 09-09-2025 Jill Williams 702-001-5380 09-26-2025 11:00am

PDT

00261 Department of Veterans Affairs Network Contracting Office 21 VA Southern Nevada Healthcare System

X X Y 561621 $25 Million N/A X See Delivery Schedule

00261 Department of Veterans Affairs Network Contracting Office 21 Southern Nevada Healthcare System

Department of Veterans Affairs Financial Services Center P.O. Box 149971 Austin TX 78714-9971 See CONTINUATION Page Fire Protection Testing, Inspection, Maintenance and Repair IAW the Performance Work Statement.

ALL

QUESTIONS MUST BE SUBMITTED WITHIN 5 DAYS of RFQ CLOSE.

This is a 100% SDVOSB set-aside. Offerors must be verified at the time of quote submission and shall continue to be registered until time of award, during performance, and through final payment of any contract resulting from this solicitation. Failure to submit SDVOSB certification AND completion of VAAR Clause 852.219-75 will result in being excluded from evaluations and ineligible for award.

Site Visit Information:

Date of Site Visit: 09/16/2025 at 08:00am PST Additional Details located in Attachment 1 of this document.

See CONTINUATION Page X X Table of Contents

SECTION A1
A.1 SF 1449 SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES1
SECTION B - CONTINUATION OF SF 1449 BLOCKS4
B.1 CONTRACT ADMINISTRATION DATA4
B.2 IT CONTRACT SECURITY5
B.3 PRICE/COST SCHEDULE15
ITEM INFORMATION15
SECTION C - CONTRACT CLAUSES30
C.1 52.212-4 CONTRACT TERMS AND CONDITIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2023)30
C.2 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)35
C.3 52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)36
C.4 SUPPLEMENTAL INSURANCE REQUIREMENTS36
C.5 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)37
C.6 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION)40
C.7 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)41
C.8 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)42
C.9 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)43
C.10 52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (JAN 2025) (DEVIATION FEB 2025)43
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS52
SECTION E - SOLICITATION PROVISIONS53
E.1 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (SEP 2023)53
E.2 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)57
E.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)57
E.4 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)60
E.5 52.233-2 SERVICE OF PROTEST (SEP 2006)61
E.6 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)62
E.7 52.237-1 SITE VISIT (APR 1984)62
E.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)62
E.9 52.212-2 EVALUATION—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (NOV 2021)63
ADDENDUM to FAR 52.212-1 INSTRUCTIONS TO OFFERORS—COMMERCIAL ITEMS64
ADDENDUM to FAR 52.212-2 EVALUATION—COMMERCIAL ITEMS (OCT 2014)66
E.10 52.212-3 OFFEROR REPRESENTATIONS AND CERTIFICATIONS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (MAY 2024) (DEVIATION FEB 2025)68

SECTION B - CONTINUATION OF SF 1449 BLOCKS

B.1 CONTRACT ADMINISTRATION DATA

1. Contract Administration: All contract administration matters will be handled by the following individuals:

a. CONTRACTOR:

b. GOVERNMENT: Contracting Officer 36C261 Department of Veterans Affairs Network Contracting Office 21 VA Southern Nevada Healthcare System

2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:

[X]
52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or
[]
52.232-36, Payment by Third Party

3. INVOICES: Invoices shall be submitted in arrears:

a. Quarterly[]
b. Semi-Annually[]
c. Other[X] Monthly, in Arrears

4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.

All invoicing will be conducted through Tungsten

B.2 IT CONTRACT SECURITY

VA INFORMATION AND INFORMATION SYSTEM SECURITY/PRIVACY

1. GENERAL

Contractors, contractor personnel, subcontractors, and subcontractor personnel shall be subject to the same Federal laws, regulations, standards, and VA Directives and Handbooks as VA and VA personnel regarding information and information system security.

2. ACCESS TO VA INFORMATION AND VA INFORMATION SYSTEMS

a. A contractor/subcontractor shall request logical (technical) or physical access to VA information and VA information systems for their employees, subcontractors, and affiliates only to the extent necessary to perform the services specified in the contract, agreement, or task order.

b. All contractors, subcontractors, and third-party servicers and associates working with VA information are subject to the same investigative requirements as those of VA appointees or employees who have access to the same types of information. The level and process of background security investigations for contractors must be in accordance with VA Directive and Handbook 0710, Personnel Suitability and Security Program. The Office for Operations, Security, and Preparedness is responsible for these policies and procedures.

c. Contract personnel who require access to national security programs must have a valid security clearance. National Industrial Security Program (NISP) was established by Executive Order 12829 to ensure that cleared U.S. defense industry contract personnel safeguard the classified information in their possession while performing work on contracts, programs, bids, or research and development efforts. The Department of Veterans Affairs does not have a Memorandum of Agreement with Defense Security Service (DSS). Verification of a Security Clearance must be processed through the Special Security Officer located in the Planning and National Security Service within the Office of Operations, Security, and Preparedness.

d. Custom software development and outsourced operations must be located in the U.S. to the maximum extent practical. If such services are proposed to be performed abroad and are not disallowed by other VA policy or mandates, the contractor/subcontractor must state where all non-U.S. services are provided and detail a security plan, deemed to be acceptable by VA, specifically to address mitigation of the resulting problems of communication, control, data protection, and so forth. Location within the U.S. may be an evaluation factor.

e. The contractor or subcontractor must notify the Contracting Officer immediately when an employee working on a VA system or with access to VA information is reassigned or leaves the contractor or subcontractor's employ. The Contracting Officer must also be notified immediately by the contractor or subcontractor prior to an unfriendly termination.

3. VA INFORMATION CUSTODIAL LANGUAGE

a. Information made available to the contractor or subcontractor by VA for the performance or administration of this contract or information developed by the contractor/subcontractor in performance or administration of the contract shall be used only for those purposes and shall not be used in any other way without the prior written agreement of the VA. This clause expressly limits the contractor/subcontractor's rights to use data as described in Rights in Data - General, FAR 52.227-14(d) (1).

b. VA information should not be co-mingled, if possible, with any other data on the contractors/subcontractor's information systems or media storage systems in order to ensure VA requirements related to data protection and media sanitization can be met. If co-mingling must be allowed to meet the requirements of the business need, the contractor must ensure that VA's information is returned to the VA or destroyed in accordance with VA's sanitization requirements. VA reserves the right to conduct on site inspections of contractor and subcontractor IT resources to ensure data security controls, separation of data and job duties, and destruction/media sanitization procedures are in compliance with VA directive requirements.

c. Prior to termination or completion of this contract, contractor/ subcontractor must not destroy information received from VA, or gathered/ created by the contractor in the course of performing this contract without prior written approval by the VA. Any data destruction done on behalf of VA by a contractor/subcontractor must be done in accordance with National Archives and Records Administration (NARA) requirements as outlined in VA Directive 6300, Records and Information Management and its Handbook 6300.1 Records Management Procedures, applicable VA Records Control Schedules, and VA Handbook 6500.1, Electronic Media Sanitization. Self-certification by the contractor that the data destruction requirements above have been met must be sent to the VA Contracting Officer within 30 days of termination of the contract.

d. The contractor/subcontractor must receive, gather, store, back up, maintain, use, disclose and dispose of VA information only in compliance with the terms of the contract and applicable Federal and VA information confidentiality and security laws, regulations and policies. If Federal or VA information confidentiality and security laws, regulations and policies become applicable to the VA information or information systems after execution of the contract, or if NIST issues or updates applicable FIPS or Special Publications (SP) after execution of this contract, the parties agree to negotiate in good faith to implement the information confidentiality and security laws, regulations and policies in this contract.

e. The contractor/subcontractor shall not make copies of VA information except as authorized and necessary to perform the terms of the agreement or to preserve electronic information stored on contractor/subcontractor electronic storage media for restoration in case any electronic equipment or data used by the contractor/subcontractor needs to be restored to an operating state. If copies are made for restoration purposes, after the restoration is complete, the copies must be appropriately destroyed.

f. If VA determines that the contractor has violated any of the information confidentiality, privacy, and security provisions of the contract, it shall be sufficient grounds for VA to withhold payment to the contractor or third party or terminate the contract for default or terminate for cause under Federal Acquisition Regulation (FAR) part 12.

g. If a VHA contract is terminated for cause, the associated BAA must also be terminated and appropriate actions taken in accordance with VHA Handbook 1600.01, Business Associate Agreements. Absent an agreement to use or disclose protected health information, there is no business associate relationship.

h. The contractor/subcontractor must store, transport, or transmit VA sensitive information in an encrypted form, using VA-approved encryption tools that are, at a minimum, FIPS 140-2 validated.

i. The contractor/subcontractor's firewall and Web services security controls, if applicable, shall meet or exceed VA's minimum requirements. VA Configuration Guidelines are available upon request.

j. Except for uses and disclosures of VA information authorized by this contract for performance of the contract, the contractor/subcontractor may use and disclose VA information only in two other situations: (i) in response to a qualifying order of a court of competent jurisdiction, or (ii) with VA's prior written approval. The contractor/subcontractor must refer all requests for, demands for production of, or inquiries about, VA information and information systems to the VA contracting officer for response.

k. Notwithstanding the provision above, the contractor/subcontractor shall not release VA records protected by Title 38 U.S.C. 5705, confidentiality of medical quality assurance records and/or Title 38 U.S.C. 7332, confidentiality of certain health records pertaining to drug addiction, sickle cell anemia, alcoholism or alcohol abuse, or infection with human immunodeficiency virus. If the contractor/subcontractor is in receipt of a court order or other requests for the above mentioned information, that contractor/subcontractor shall immediately refer such court orders or other requests to the VA contracting officer for response.

l. For service that involves the storage, generating, transmitting, or exchanging of VA sensitive information but does not require C&A or an MOU-ISA for system interconnection, the contractor/subcontractor must complete a Contractor Security Control Assessment (CSCA) on a yearly basis and provide it to the COR.

4. INFORMATION SYSTEM DESIGN AND DEVELOPMENT

a. Information systems that are designed or developed for or on behalf of VA at non-VA facilities shall comply with all VA directives developed in accordance with FISMA, HIPAA, NIST, and related VA security and privacy control requirements for Federal information systems. This includes standards for the protection of electronic PHI, outlined in 45 C.F.R. Part 164, Subpart C, information and system security categorization level designations in accordance with FIPS 199 and FIPS 200 with implementation of all baseline security controls commensurate with the FIPS 199 system security categorization (reference Appendix D of VA Handbook 6500, VA Information Security Program). During the development cycle a Privacy Impact Assessment (PIA) must be completed, provided to the COR, and approved by the VA Privacy Service in accordance with Directive 6507, VA Privacy Impact Assessment.

b. The contractor/subcontractor shall certify to the COR that applications are fully functional and operate correctly as intended on systems using the VA Federal Desktop Core Configuration (FDCC), and the common security configuration guidelines provided by NIST or the VA. This includes Internet Explorer 7 configured to operate on Windows XP and Vista (in Protected Mode on Vista) and future versions, as required.

c. The standard installation, operation, maintenance, updating, and patching of software shall not alter the configuration settings from the VA approved and FDCC configuration. Information technology staff must also use the Windows Installer Service for installation to the default "program files" directory and silently install and uninstall.

d. Applications designed for normal end users shall run in the standard user context without elevated system administration privileges.

e. The security controls must be designed, developed, approved by VA, and implemented in accordance with the provisions of VA security system development life cycle as outlined in NIST Special Publication 800-37, Guide for Applying the Risk Management Framework to Federal Information Systems, VA Handbook 6500, Information Security Program and VA Handbook 6500.5, Incorporating Security and Privacy in System Development Lifecycle.

f. The contractor/subcontractor is required to design, develop, or operate a System of Records Notice (SOR) on individuals to accomplish an agency function subject to the Privacy Act of 1974, (as amended), Public Law 93-579, December 31, 1974 (5 U.S.C. 552a) and applicable agency regulations. Violation of the Privacy Act may involve the imposition of criminal and civil penalties.

g. The contractor/subcontractor agrees to:

(1) Comply with the Privacy Act of 1974 (the Act) and the agency rules and regulations issued under the Act in the design, development, or operation of any system of records on individuals to accomplish an agency function when the contract specifically identifies:

(a) The Systems of Records (SOR); and

(b) The design, development, or operation work that the contractor/ subcontractor is to perform;

(1) Include the Privacy Act notification contained in this contract in every solicitation and resulting subcontract and in every subcontract awarded without a solicitation, when the work statement in the proposed subcontract requires the redesign, development, or operation of a SOR on individuals that is subject to the Privacy Act; and

(2) Include this Privacy Act clause, including this subparagraph (3), in all subcontracts awarded under this contract which requires the design, development, or operation of such a SOR.

h. In the event of violations of the Act, a civil action may be brought against the agency involved when the violation concerns the design, development, or operation of a SOR on individuals to accomplish an agency function, and criminal penalties may be imposed upon the officers or employees of the agency when the violation concerns the operation of a SOR on individuals to accomplish an agency function. For purposes of the Act, when the contract is for the operation of a SOR on individuals to accomplish an agency function, the contractor/subcontractor is considered to be an employee of the agency.

(1) "Operation of a System of Records" means performance of any of the activities associated with maintaining the SOR, including the collection, use, maintenance, and dissemination of records.

(2) "Record" means any item, collection, or grouping of information about an individual that is maintained by an agency, including, but not limited to, education, financial transactions, medical history, and criminal or employment history and contains the person's name, or identifying number, symbol, or any other identifying particular assigned to the individual, such as a fingerprint or voiceprint, or a photograph.

(3) "System of Records" means a group of any records under the control of any agency from which information is retrieved by the name of the individual or by some identifying number, symbol, or other identifying particular assigned to the individual.

i. The vendor shall ensure the security of all procured or developed systems and technologies, including their subcomponents (hereinafter referred to as "Systems"), throughout the life of this contract and any extension, warranty, or maintenance periods. This includes, but is not limited to workarounds, patches, hotfixes, upgrades, and any physical components (hereafter referred to as Security Fixes) which may be necessary to fix all security vulnerabilities published or known to the vendor anywhere in the Systems, including Operating Systems and firmware. The vendor shall ensure that Security Fixes shall not negatively impact the Systems.

j. The vendor shall notify VA within 24 hours of the discovery or disclosure of successful exploits of the vulnerability which can compromise the security of the Systems (including the confidentiality or integrity of its data and operations, or the availability of the system). Such issues shall be remediated as quickly as is practical, but in no event longer than 10 days.

k. When the Security Fixes involve installing third party patches (such as Microsoft OS patches or Adobe Acrobat), the vendor will provide written notice to the VA that the patch has been validated as not affecting the Systems within 10 working days. When the vendor is responsible for operations or maintenance of the Systems, they shall apply the Security Fixes within 30 days.

l. All other vulnerabilities shall be remediated as specified in this paragraph in a timely manner based on risk, but within 60 days of discovery or disclosure. Exceptions to this paragraph (e.g. for the convenience of VA) shall only be granted with approval of the contracting officer and the VA Assistant Secretary for Office of Information and Technology.

5. INFORMATION SYSTEM HOSTING, OPERATION, MAINTENANCE, OR USE

a. For information systems that are hosted, operated, maintained, or used on behalf of VA at non-VA facilities, contractors/subcontractors are fully responsible and accountable for ensuring compliance with all HIPAA, Privacy Act, FISMA, NIST, FIPS, and VA security and privacy directives and handbooks. This includes conducting compliant risk assessments, routine vulnerablity scanning, system patching and change management procedures, and the completion of an acceptable contingency plan for each system. The contractor's security control procedures must be equivalent, to those procedures used to secure VA systems. A Privacy Impact Assessment (PIA) must also be provided to the COR and approved by VA Privacy Service prior to operational approval. All external Internet connections to VA's network involving VA information must be reviewed and approved by VA prior to implementation.

b. Adequate security controls for collecting, processing, transmitting, and storing of Personally Identifiable Information (PII), as determined by the VA Privacy Service, must be in place, tested, and approved by VA prior to hosting, operation, maintenance, or use of the information system, or systems by or on behalf of VA. These security controls are to be assessed and stated within the PIA and if these controls are determined not to be in place, or inadequate, a Plan of Action and Milestones (POA&M) must be submitted and approved prior to the collection of PII.

c. Outsourcing (contractor facility, contractor equipment or contractor staff) of systems or network operations, telecommunications services, or other managed services requires certification and accreditation (authorization) (C&A) of the contractor's systems in accordance with VA Handbook 6500.3, Certification and Accreditation and/or the VA OCS Certification Program Office. Government- owned (government facility or government equipment) contractor-operated systems, third party or business partner networks require memorandums of understanding and interconnection agreements (MOU-ISA) which detail what data types are shared, who has access, and the appropriate level of security controls for all systems connected to VA networks.

d. The contractor/subcontractor's system must adhere to all FISMA, FIPS, and NIST standards related to the annual FISMA security controls assessment and review and update the PIA. Any deficiencies noted during this assessment must be provided to the VA contracting officer and the ISO for entry into VA's POA&M management process. The contractor/subcontractor must use VA's POA&M process to document planned remedial actions to address any deficiencies in information security policies, procedures, and practices, and the completion of those activities. Security deficiencies must be corrected within the timeframes approved by the government. Contractor/subcontractor procedures are subject to periodic, unannounced assessments by VA officials, including the VA Office of Inspector General. The physical security aspects associated with contractor/ subcontractor activities must also be subject to such assessments. If major changes to the system occur that may affect the privacy or security of the data or the system, the C&A of the system may need to be reviewed, retested and re- authorized per VA Handbook 6500.3. This may require reviewing and updating all of the documentation (PIA, System Security Plan, Contingency Plan). The Certification Program Office can provide guidance on whether a new C&A would be necessary.

e. The contractor/subcontractor must conduct an annual self assessment on all systems and outsourced services as required. Both hard copy and electronic copies of the assessment must be provided to the COR. The government reserves the right to conduct such an assessment using government personnel or another contractor/subcontractor. The contractor/subcontractor must take appropriate and timely action (this can be specified in the contract) to correct or mitigate any weaknesses discovered during such testing, generally at no additional cost.

f. VA prohibits the installation and use of personally-owned or contractor/ subcontractor-owned equipment or software on VA's network. If non-VA owned equipment must be used to fulfill the requirements of a contract, it must be stated in the service agreement, SOW or contract. All of the security controls required for government furnished equipment (GFE) must be utilized in approved other equipment (OE) and must be funded by the owner of the equipment. All remote systems must be equipped with, and use, a VA-approved antivirus (AV) software and a personal (host-based or enclave based) firewall that is configured with a VA-approved configuration. Software must be kept current, including all critical updates and patches. Owners of approved OE are responsible for providing and maintaining the anti-viral software and the firewall on the non-VA owned OE.

g. All electronic storage media used on non-VA leased or non-VA owned IT equipment that is used to store, process, or access VA information must be handled in adherence with VA Handbook 6500.1, Electronic Media Sanitization upon: (i) completion or termination of the contract or (ii) disposal or return of the IT equipment by the contractor/subcontractor or any person acting on behalf of the contractor/subcontractor, whichever is earlier. Media (hard drives, optical disks, CDs, back-up tapes, etc.) used by the contractors/ subcontractors that contain VA information must be returned to the VA for sanitization or destruction or the contractor/subcontractor must self-certify that the media has been disposed of per 6500.1 requirements. This must be completed within 30 days of termination of the contract.

h. Bio-Medical devices and other equipment or systems containing media (hard drives, optical disks, etc.) with VA sensitive information must not be returned to the vendor at the end of lease, for trade-in, or other purposes. The options are:

(1) Vendor must accept the system without the drive;

(2) VA's initial medical device purchase includes a spare drive which must be installed in place of the original drive at time of turn-in; or

(3) VA must reimburse the company for media at a reasonable open market replacement cost at time of purchase.

(4) Due to the highly specialized and sometimes proprietary hardware and software associated with medical equipment/systems, if it is not possible for the VA to retain the hard drive, then;

(a) The equipment vendor must have an existing BAA if the device being traded in has sensitive information stored on it and hard drive(s) from the system are being returned physically intact; and

(b) Any fixed hard drive on the device must be non-destructively sanitized to the greatest extent possible without negatively impacting system operation. Selective clearing down to patient data folder level is recommended using VA approved and validated overwriting technologies/methods/tools. Applicable media sanitization specifications need to be pre-approved and described in the purchase order or contract.

(c) A statement needs to be signed by the Director (System Owner) that states that the drive could not be removed and that (a) and (b) controls above are in place and completed. The ISO needs to maintain the documentation.

6. SECURITY INCIDENT INVESTIGATION

a. The term "security incident" means an event that has, or could have, resulted in unauthorized access to, loss or damage to VA assets, or sensitive information, or an action that breaches VA security procedures. The contractor/ subcontractor shall immediately notify the COR and simultaneously, the designated ISO and Privacy Officer for the contract of any known or suspected security/privacy incidents, or any unauthorized disclosure of sensitive information, including that contained in system(s) to which the contractor/ subcontractor has access.

b. To the extent known by the contractor/subcontractor, the contractor/ subcontractor's notice to VA shall identify the information involved, the circumstances surrounding the incident (including to whom, how, when, and where the VA information or assets were placed at risk or compromised), and any other information that the contractor/subcontractor considers relevant.

c. With respect to unsecured protected health information, the business associate is deemed to have discovered a data breach when the business associate knew or should have known of a breach of such information. Upon discovery, the business associate must notify the covered entity of the breach. Notifications need to be made in accordance with the executed business associate agreement.

d. In instances of theft or break-in or other criminal activity, the contractor/subcontractor must concurrently report the incident to the appropriate law enforcement entity (or entities) of jurisdiction, including the VA OIG and Security and Law Enforcement. The contractor, its employees, and its subcontractors and their employees shall cooperate with VA and any law enforcement authority responsible for the investigation and prosecution of any possible criminal law violation(s) associated with any incident. The contractor/subcontractor shall cooperate with VA in any civil litigation to recover VA information, obtain monetary or other compensation from a third party for damages arising from any incident, or obtain injunctive relief against any third party arising from, or related to, the incident.

7. LIQUIDATED DAMAGES FOR DATA BREACH

a. Consistent with the requirements of 38 U.S.C. 5725, a contract may require access to sensitive personal information. If so, the contractor is liable to VA for liquidated damages in the event of a data breach or privacy incident involving any SPI the contractor/subcontractor processes or maintains under this contract.

b. The contractor/subcontractor shall provide notice to VA of a "security incident" as set forth in the Security Incident Investigation section above. Upon such notification, VA must secure from a non-Department entity or the VA Office of Inspector General an independent risk analysis of the data breach to determine the level of risk associated with the data breach for the potential misuse of any sensitive personal information involved in the data breach. The term 'data breach' means the loss, theft, or other unauthorized access, or any access other than that incidental to the scope of employment, to data containing sensitive personal information, in electronic or printed form, that results in the potential compromise of the confidentiality or integrity of the data. Contractor shall fully cooperate with the entity performing the risk analysis. Failure to cooperate may be deemed a material breach and grounds for contract termination.

c. Each risk analysis shall address all relevant information concerning the data breach, including the following:

(1) Nature of the event (loss, theft, unauthorized access);

(2) Description of the event, including:

(a) date of occurrence;

(b) data elements involved, including any PII, such as full name, social security number, date of birth, home address, account number, disability code;

(3) Number of individuals affected or potentially affected;

(4) Names of individuals or groups affected or potentially affected;

(5) Ease of logical data access to the lost, stolen or improperly accessed data in light of the degree of protection for the data, e.g., unencrypted, plain text;

(6) Amount of time the data has been out of VA control;

(7) The likelihood that the sensitive personal information will or has been compromised (made accessible to and usable by unauthorized persons);

(8) Known misuses of data containing sensitive personal information, if any;

(9) Assessment of the potential harm to the affected individuals;

(10) Data breach analysis as outlined in 6500.2 Handbook, Management of Security and Privacy Incidents, as appropriate; and

(11) Whether credit protection services may assist record subjects in avoiding or mitigating the results of identity theft based on the sensitive personal information that may have been compromised.

d. Based on the determinations of the independent risk analysis, the contractor shall be responsible for paying to the VA liquidated damages in the amount of $10,000.00 per affected individual to cover the cost of providing credit protection services to affected individuals consisting of the following:

(1) Notification;

(2) One year of credit monitoring services consisting of automatic daily monitoring of at least 3 relevant credit bureau reports;

(3) Data breach analysis;

(4) Fraud resolution services, including writing dispute letters, initiating fraud alerts and credit freezes, to assist affected individuals to bring matters to resolution;

(5) One year of identity theft insurance with $20,000.00 coverage at $0 deductible; and

(6) Necessary legal expenses the subjects may incur to repair falsified or damaged credit records, histories, or financial affairs.

8. SECURITY CONTROLS COMPLIANCE TESTING

On a periodic basis, VA, including the Office of Inspector General, reserves the right to evaluate any or all of the security controls and privacy practices implemented by the contractor under the clauses contained within the contract. With 10 working-day's notice, at the request of the government, the contractor must fully cooperate and assist in a government-sponsored security controls assessment at each location wherein VA information is processed or stored, or information systems are developed, operated, maintained, or used on behalf of VA, including those initiated by the Office of Inspector General. The government may conduct a security control assessment on shorter notice (to include unannounced assessments) as determined by VA in the event of a security incident or at any other time.

9. TRAINING

a. All contractor employees and subcontractor employees requiring access to VA information and VA information systems shall complete the following before being granted access to VA information and its systems:

(1) Sign and acknowledge (either manually or electronically) understanding of and responsibilities for compliance with the Contractor Rules of Behavior, Appendix E relating to access to VA information and information systems;

(2) Successfully complete the VA Cyber Security Awareness and Rules of Behavior training and annually complete required security training;

(3) Successfully complete the appropriate VA privacy training and annually complete required privacy training; and

(4) Successfully complete any additional cyber security or privacy training, as required for VA personnel with equivalent information system access [to be defined by the VA program official and provided to the contracting officer for inclusion in the solicitation document - e.g., any role-based information security training required in accordance with NIST Special Publication 800-16, Information Technology Security Training Requirements.]

b. The contractor shall provide to the contracting officer and/or the COR a copy of the training certificates and certification of signing the Contractor Rules of Behavior for each applicable employee within 1 week of the initiation of the contract and annually thereafter, as required.

c. Failure to complete the mandatory annual training and sign the Rules of Behavior annually, within the timeframe required, is grounds for suspension or termination of all physical or electronic access privileges and removal from work on the contract until such time as the training and documents are complete.

(End of Clause)

B.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
YR
__________________
__________________

FIRE PROTECTION SERVICE OF TESTING, INSPECTION, MAINTENANCE/REPAIR AND VASNHCS

Contract Period: Base POP Begin: 10-07-2025 POP End: 10-06-2026 PRINCIPAL NAICS CODE: 561621 - Security Systems Services (except Locksmiths) PRODUCT/SERVICE CODE: H212 - Equipment and Materials Testing - Fire Control Equipment

1.00
YR
__________________
__________________

OPTION YEAR 1: FIRE PROTECTION SERVICE OF TESTING, INSPECTION, MAINTENANCE/REPAIR AND VASNHCS Contract Period: Option 1 POP Begin: 10-07-2026 POP End: 10-06-2027

1.00
YR
__________________
__________________

OPTION YEAR 2: FIRE PROTECTION SERVICE OF TESTING, INSPECTION, MAINTENANCE/REPAIR AND VASNHCS Contract Period: Option 2 POP Begin: 10-07-2027 POP End: 10-06-2028

1.00
YR
__________________
__________________

OPTION YEAR 3: FIRE PROTECTION SERVICE OF TESTING, INSPECTION, MAINTENANCE/REPAIR AND VASNHCS Contract Period: Option 3 POP Begin: 10-07-2028 POP End: 10-06-2029

1.00
YR
__________________
__________________

OPTION YEAR 4: FIRE PROTECTION SERVICE OF TESTING, INSPECTION, MAINTENANCE/REPAIR AND VASNHCS Contract Period: Option 4 POP Begin: 10-07-2029 POP End: 10-06-2030

GRAND TOTAL
__________________

36C26126Q0018

Page 1 of Page 1 of

PERFORMANCE WORK STATEMENT

654-26-1-6093-0004 FIRE PROTECTION SYSTEM SERVICE

VA SIERRA NEVADA HEALTH CARE SYSTEM

General Information

1. General: This is a services contract for the maintenance, repair, testing, and inspection for the Fire Protection System at VA Sierra Nevada Health Care System (VASNHCS). The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the contractor who, in turn is responsible to the Government.

1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the maintenance, repair, testing, and inspection for the Fire Protection System as defined in this Performance Work Statement (PWS) except for those items specified as government furnished property and services. The contractor shall perform to the standards in this contract.

1.2 Background: VASNHCS has a requirement to ensure the fire protection system (suppression, sprinklers, dampers, wet & dry standpipes, fire pumps, etc.,) are properly maintained, tested, inspected, and repaired per The Joint Commission (TJC) EC.02.03.05 and LS.02.01.35, National Fire Protection Association (NFPA) 25, NFPA 12A, NFPA 13, NFPA 72, NFPA 80, NFPA 90A, NFPA 96, NFPA 101, NFPA 105, and per state and federal requirements.

1.3 Objectives: Ensure that the fire protection system at VASNHCS is properly maintained, tested, inspected, and repaired per the requirements listed in 1.2 Background.

1.4 Scope of work:

1. General

a. Period of performance: Base plus four option years

b. Location: VASNHCS, 975 Kirman Ave, Reno, NV 89502

c. Work hours:

i. Normal work hours for contractor work shall be performed Monday thru Friday, 0800 – 1600 excluding federal holidays.

ii. All testing and inspections (Paragraph 1.4. Sec 6 (Inspection/Testing required)) that may affect patient care will be conducted outside normal working hours to mitigate any impacts to patient care. Such as: semi-annual Ansul testing, damper inspections, standpipe testing/inspections. This will be noted in this PWS. The contractor will include the price in the contract.

iii. Any repairs, maintenance, or overtime work (to include testing/inspection) not noted in this PWS will require a quote/proposal (provided at no charge to the government) and must be approved by the contracting officer (CO), contracting officer’s representative (COR), or designated representative prior to any work commencing (with either a purchase order or modification to the contract).

iv. The contractor shall supply 24 hour/7 day a week service for immediate service for emergency repairs or maintenance, if required and requested. A separate line item will be included in this contract to cover any emergency repairs or maintenance. Additional funding (with CO approval and modification) may be added to the contract if needed, or if the funds are not used, the amount will be deobligated with a modification to the contract.

v. Note: If the government requests any type of quote or proposal to assess any repair, testing, inspection, maintenance, etc., this will be provided at no cost to the government.

d. Contractors are requested and highly encouraged to conduct a site visit to the hospital to have a complete understanding of what this contract entails.

e. The contractor, without additional expense to the Government, shall obtain all licenses, permits, and insurance required to perform the work in this contract and shall comply with all current, applicable federal, state, and local laws, to include the ability to perform all inspections, testing, maintenance, and repairs with a State of Nevada license. Evidence of insurance, licenses, and permits shall be provided to the CO and COR before work commences.

i. Inspection, testing, maintenance, and repair service shall be provided by qualified personnel (NFPA 25, Section 3.3.24 and 4.1.1.2). Qualified personnel shall be competent and capable persons shown to have met the requirements and training for this field and area of inspection, testing, maintenance, and repairs (NFPA 25, Section 3.3.34).

2. The contractor shall ensure that their personnel comply with all VASNHCS policies to include, but is not limited to:

a. Parking in the appropriate/authorized spaces, with special consideration to ensure that they are not parking in veteran/patient spaces. (Parking is only available on the 2nd deck of the two-story parking garage off Belli Drive, the four-story parking garage south of the two-story parking garage, or on the streets surrounding the hospital). Temporary parking may be allowed near the Pipe Shop to load and unload material, equipment, etc.

b. Tobacco, vaping, or smoking are not authorized on any part of the hospital property.

c. Contractor employees must check-in with the VASNHCS Police every day (during the duration of the service) to receive a visitor badge (which is only good for 24 hours).

d. If the contractor(s) are not feeling well, has been around someone who has tested positive for COVID within the seven days prior to service, or is awaiting a COVID test result, immediately contact the COR to reschedule the work.

e. VASNHCS may demand that the contractor remove any person(s) who pose a threat to the health, safety, or security of the hospital, employees, or patients.

3. Codes and standards:

a. The publications listed below form a part of this contract. The fire protection system testing, inspection, maintenance, and repairs shall meet the requirements of the most current and latest (Note: The “Current Edition #” may not be current, pending any exercise of option year): code editions published, all manufacturer guidelines, The Joint Commission, Veteran’s Affairs Directives/Memorandums, State of Nevada, and industry standards as applicable, and in the case of conflicting standards, the most stringent shall apply. All documentation shall include information as required per The Joint Commission and NFPA requirements.

i. The Joint Commission EC.02.03.05, EP’s 11, 12, 13, 14, 18, and 28 (documentation).

ii. NFPA 25 – Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems. Current Edition 2023.

iii. NFPA 12A – Standard on Halon 1301 Fire Extinguishing Systems. Current Edition 2025.

iv. NFPA 13 – Standard for the Installation of Sprinkler Systems. Current Edition 2025.

v. NFPA 72 – National Fire Alarm and Signaling Code. Current Edition 2025 (OI&T area only)

vi. NFPA 80 – Standard for Fire Doors and Other Opening Protectives. Current Edition 2025.

vii. NFPA 90A – Standard for the Installation of Air-conditioning and Ventilating Systems. Current Edition 2024.

viii. NFPA 96 – Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations. Current Edition 2024.

ix. NFPA 105 – Standard for Smoke Door Assemblies and Other Opening Protectives. Current Edition 2025.

b. All testing, inspections, maintenance, and repairs will adhere to and meet the dates per TJC requirements. Not meeting these requirements will impact the VA’s Joint Commission accreditation, and this cannot happen.

4. Service:

a. All preventive maintenance (PM), testing, and inspections shall follow the frequency requirement noted below in section 5. Unless specifically noted by the COR, the contractor must comply with the schedule to ensure compliance per TJC and NFPA requirements.

i. All contractor work shall be escorted by a VASNHCS staff member to the appropriate location of service. All PMs, testing, and inspection shall be scheduled at least 30 days prior to the service.

ii. A proposal or quote will be submitted by the contractor to correct any deficiency found during an inspection and testing. Note: The government shall not be charged for any assessment of the deficiency.

iii. Items may include (but is not limited to):

1. Replace, repair, move, or test fire sprinkler heads, piping/water systems (such as standpipes), suppression systems (Ansul, FM200/Novec, Preaction, etc.), fire pumps/connections, dampers, add glycol to the system, etc.

b. If there is a maintenance/repair issue for the fire protection system at VASNHCS and is separate from the PM testing/inspection requirements, a proposal or quote will be submitted by the contractor. The contractor shall come onsite to assess the issue (at no cost to the government) and provide a proposal/quote for the repair or maintenance.

i. Items may include (but is not limited to):

1. Leaks in the water line (suppression, fire sprinkler, etc.,), fire pump or connection repair, backflow repair, standpipes, any dry/wet chemical systems, or any equipment related to the Life Safety Code.

c. Proposal/Quote: The proposal/quote (provided at no charge to the government) will be submitted to the COR or designated representative for review and may be paid with a government purchase card or through a modification to the contract. At no time will any work be done without a purchase order or modification to the contract.

5. Frequency requirement (for PM’s, testing, and inspection): (Note: all dates will comply with VASNHCS’s last documented test, inspection, and/or maintenance date completed.)

a. Quarterly

i. Four times per year: +/- 10 days from the last completed. (i.e., January 15, April 15, July 15, October 15. No sooner than the 6th day of the month and no later than the 25th day of the month listed above as an example.)

b. Semi-annual (every six months)

i. Twice a year: +/- 20 days from the last completed. (i.e., October 15, 2025, April 15, 2026). No sooner than the 20 days prior to and no later than 20 days after the day of the month listed above as an example.)

c. Annual

i. Once per year: +/- 30 days from the last completed. (i.e., April 15, 2025. No sooner than the 30 days prior to and no later than 30 days after April 15, 2026.)

d. Tri-annual (36 month)

i. Every three years: +/- 45 days from the last completed. (i.e., April 15, 2025. No sooner than the 45 days prior to and no later than 45 days after April 15, 2028)

e. Four, five, and six years

i. Every four, five, or six years: +/- 45 days from the last completed. (i.e., April 15, 2025. No sooner than 45 days prior to and no later than 45 days after April 15, 2029, April 15, 2030, or April 15, 2031, respectively.)

6. Inspection/Testing required (note: the frequency requirement (section 5)) all testing/inspections must be followed, unless otherwise noted or unforeseen circumstances arise that is out of all parties control.

a. EC.02.03.05/EP 13: Ansul System

i. One building/Two locations:

1. Nutrition and Food Service (Bldg 1/C2338)

2. Canteen (Bldg 1/C1321)

ii. Semi-annual (to be conducted after hours 1630-2000 (estimated))

iii. May and November

b.