S02 - 640-381.MVW.6.2011.2011.MOUNTAIN_VIEW_CENTER.PIPING_DIAGRAMS_MECH.MH7.01.pdf
PDF 135 KB Posted
- Attached to
- Y1DA--640-20-107 MV-HR BMS HVAC CONST
- Solicitation number
- 36C26120B0013
About this file
This document includes a piping diagram for a mechanical system and information on a related federal contract opportunity for HVAC construction. The piping diagram shows the layout of piping, valves, controls and other components for a boiler system serving air handling units. It includes notes specifying installation requirements to ensure proper function and maintenance access.
The federal contract opportunity is a solicitation by the Department of Veterans Affairs to provide HVAC construction services. The notice states the original RFP is now being conducted as an IFB with the new solicitation number provided. Interested parties are directed to the SAM website for full details on requirements and response timing. The work involves HVAC construction at the Mountain View VA Medical Center.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CD
T
T
AS-1
B-1
ON ROOF
S
ET
ET-1
1 BOILER PIPING DIAGRAM
NO SCALE
CF-1
HWP-2
SECONDARY
F M
HWP-1
PRIMARY
STRAINER (TYP)
FLEX CONN. (TYP)
RELIEF VALVE DRAIN TO
NEAREST EQPT. DRAIN (TYP)
12" MINIMUM SEPARATION
2" HWS
2" HWR
2" HWR
2" HWS
GAS TRAIN INCLUDING
ISOLATION VALVE AND GAS
PRESSURE REGULATOR
INSTALLED AT EYE LEVEL.
FLOOR DRAIN.
TO EQUIPMENT.
TEMPERATURE SENSOR LOCATIONS.
REFER TO CONTROL DRAWINGS FOR WATER FLOW SWITCHES,
DRAIN ALL LOW POINTS OF SYSTEM AND RISERS TO NEAREST
NO DANGER OF SCALDING ATTENDANTS.
THE DISCHARGE FROM SAFETY RELIEF VALVES SHALL POSE
ALL THERMOMETERS AND PRESSURE GAUGES SHALL BE
HEATING WATER SYSTEM TO ELIMINATE ANY TRAPPED AIR.
INSTALL AUTOMATIC VENTING AT HIGH POINTS IN THE
PROVIDE ELBOW SUPPORT AT ALL PIPE CONNECTIONS
6.
7.
3.
4.
5.
1.
2.
NC
NC
NC
DRAIN
2" HWS 2" HWS
2" HWR
GENERAL DETAIL NOTES
BFP
HOSE BIBB
1"
1"
TO VAV BOXES
TO ROOF RECEPTOR
(SEE PLMB PLAN)
ACID NEUTRALIZATION
KIT
CONDENSATE
DRAIN (TYP)
2" HWS
SHELL DRAIN VALVE AND CONDENSATE DRAIN TRAP TO
BE PROVIDED TO DRAIN FREELY BY GRAVITY TO
APPROPRIATE DISCHARGE LOCATION.
INSTALL ALL SYSTEM COMPONENTS IN SUCH A MANNER
TO ALLOW REMOVAL OF BOILER PANELS FOR
EQUIPMENT MAINTENANCE.
THE FOLLOWING ITEMS ARE TO BE INSTALLED AND MAY
BE SHIPPED LOOSE BY BOILER MFR:
* RELIEF VALVE
* LOW WATER CUT-OFF SWITCH
* AQUASTAT
PIPING DIAGRAM IS SPECIFIC TO BASIS OF DESIGN MFR.
PROVIDE INSTALLATION MEETING MFR'S. INSTALLATION
DIAGRAM AND INSTALLATION REQUIREMENTS.
SEE PLANS FOR ADDITIONAL ROUTING AND PIPE SIZES.
8.
9.
10.
11.
PUMP WITH VFD
TEMPERATURE
SENSOR (TYP)
FLOW METER
(TYP)
CHEMICAL POT FEEDER
24" MAXIUMUM SEPARATION
4" BYPASS LEG
TO AHU-1
ISOLATION VALVE (TYP)
PRESSURE GAGE (TYP)
TEMP GAGE (TYP)
TEMP./PRESS. TEST FITTING (TYP)
FLOW SWITCH (TYP)
BOILER ISOLATION VALVE (24V)(TYP)
PRV: SET
AT 12 PSIG
RV: SET AT 45 PSIG
(FIELD ADJUSTED)
SAME SIZE AS RV
OUTLETTO EQUIPMENT
DRAIN
EXTENT OF PIPING UNDER
PLUMBING SECTION
1" COLD WATER
(REFER TO PLUMBING
DRAWINGS)
Office of Construction and Facilities Management
N
E N G I N E E R I N G
I N T E R F A C E
TEL
FAX
PROJECT:
CONTACT:
www.interfaceengineering.com
717 Market Street
Suite 500
San Francisco, CA 94103
415.489.7240
415.489.7289
Date Signed: ----
EFORP
DERET
SI
GE
R
R E
E
NI
GN
E
LA
NOISS
CA L I FO
RN
I AS TA T E OF
Exp. 06-30-2012
No. M29691
M
E C H A N IC A L
G E
OR
GE
L . ARELLA
N O
C o p yr ig h t
S te in b e rg
A rc h it e c ts
A ll R ig h ts
R e s e rv e d
T h e s e
P la n s a n d o r S p e c if ic a ti o n s a re in te n d e d fo r th e s o le b e n e fi t o f S te in b e rg
A rc h it e c ts c lie n t a n d m a y n o t b e u s e d re u s e d ,c o p ie d ,o r re p ro d u c e d in a n y fo rm w it h o u t th e e x p re s s w ri tt e n c o n s e n t o f S te in b e rg
A rc h it e c ts
George Arellano
2010-0410
DATEREV ISSUE
ARCHITECT
PROJECT #:
DATE:
SCALE:
CLIENT
Steinberg Architects 98 Battery Street, Suite 300 San Francisco, CA 94111
02.09.2011 100% Schematic Design
03.16.2011 100% Design Development
05.02.2011 90% Construction Documents
05.31.2011 100% Construction Documents
/2
/2
:2
:2
A
M C
R e v it L o c a l\
-0
V a P a lo
A lt o
\V A
P a lo
A lt o
J o n e s B ld g
E
B v
.r v t
1776 OLD MIDDLEFIELD
ROAD, MOUNTAIN VIEW, CA
94043
MH7.01
VAPAHCS Mountain View Center - #640-381
PIPING DIAGRAMS -
MECHANICAL
10037.00 5.31.2011
VA Palo Alto Health Care System 3801 Miranda Ave. Building 6, C360 Palo Alto, CA 94304
100%
CONSTRUCTION
DOCUMENTS
File details come from the government source that posted it. Updated .