Text version
7-1-AE-101
B
C
D
E
F
G
A
2 1
7-1-AE-901
19'-1 1/8"
8' -7
7/
8"
2' -1
1/
2" 8'
-4
/4
7'-0 1/8" 5'-0 5/8"
C
ADA
R 2'-9"
7/
8"
7'-5 3/8" 6"
34 43
ADA
R 2'-9"
7-1-AE-901
7-1-AE-901 2
TOILET, MALE
A
A
C1
A
B
C1
18A
HALL
18B
TOILET, FEMALE
18A
7-1-AE-901 10
OFFICE
OFFICE
1A
OFFICE
2A
OFFICE
EMERGENCY
MANAGEMENT
ELEC. CLOSET
OI&T
MECH. RM.
ACCESS
SAFETY &
OCCUPATIONAL
HEALTH
EQUIPMENT RM.
CORRIDOR
C101
OFFICE
3A
INDUSTRIAL
HYGIENIST
CORRIDOR
C101
OFFICE
OFFICE
5A
STORAGE
BREAK ROOM
HAC
TOILET, MALE
TOILET, FEMALE
CALL CENTER
CORRIDOR
C101
MECH. RM.
ACCESS
OFFICE
MULTI-PURPOSE
RM.
CORRIDOR
CORRIDOR
OFFICE
OFFICE
OFFICE
OFFICE
OFFICE
SAFETY &
OCCUPATIONAL
HEALTH MGR.
CALL CENTER
OFFICE
6A
OFFICE
7A
CALL CENTER
OI&T
1B
ELEC. CLOSET
OI&T
MECH. RM.
ACCESS
SAFETY &
OCCUPATIONAL
HEALTH
CORRIDOR
C101
OFFICE
CHASE
CH-1
A B
STRUCTURE ABOVE
HEAD SLIP
CONNECTOR
FINISHED CEILING
ACOUSTIC BATTS
3 5/8" METAL STUDS
@ (16" O.C.)
1 LAYER 5/8" ABUSE-
RESISTANT GWB
EA. SIDE
PAF (.145) @ (32" O.C.)
TRACK - T&B
STRUCTURE ABOVE
HEAD SLIP
CONNECTOR
FINISHED CEILING
ACOUSTIC BATTS
EXISTING 4" METAL
STUDS @ (16" O.C.)
1 LAYER 5/8" ABUSE-
RESISTANT GWB
EA. SIDE
PAF (.145) @ (32" O.C.)
TRACK - T&B
C1
STRUCTURE ABOVE
FIRE RATED SEALANT,
EA. SIDE, T&B
HEAD SLIP
CONNECTOR
FINISHED CEILING
ACOUSTIC BATTS
3 5/8" METAL STUDS
@ (16" O.C.)
1 LAYER 5/8" ABUSE-
RESISTANT GWB
EA. SIDE
PAF (.145) @ (32" O.C.)
TRACK - T&B
EXISTING GWB
1 HOUR FIRE BARRIER
UL 263 DESIGN U419
6" ABOVE
FINISHED CEILING
BID ALTERNATE
A. DEDUCT ALT #1: ALL WORK IN BASE BID WITH THE FOLLOWING EXCEPTIONS / DEDUCTIONS:
1. WORK IN JOHN COCHRAN BUILDING 7 DELETE
DOUBLE MTL STUD
HEADER W/ TRACK
5/8" GWB
H.M. DOOR FRAME
W/ DOOR PER SCHEDULE
SEALANT, ALL SIDES
CONTINOUS - TYP.
PHASE GENERAL NOTES
1. REFER TO SHEET 7-1-AD-101.
th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
1 2 3 4 5 6 7 8 9
A
B
C
D
E
F
VA FORM 08-6231
ARCHITECTS Drawing Title Project Title
Location
Date Checked Drawn
Project Number
Building Number
Drawing Number
CONSULTANTS
Dwg: Of:
657-18-110CORRECT WORKPLACE & LIFE SAFETY
ISSUES, ABATE ASBESTOS, & IMPROVE
WAYFINDING
SEPTEMBER 12, 2018
Building Name
JOHN COCHRAN DIVISION -
Revisions: Date:
3705 North 200th Street Elkhorn, Nebraska 68022
(402) 291-6941
15 Sunnen Drive Suite 104 St. Louis, MO 64143
(314) 645-1132
8802 South 135th Street, Suite 100 Omaha, NE 68138
(402) 861-4445
LESS THAN 10% SPRINKLED
DEDUCT ALTERNATE #1
VETERANS
HEALTH
ADMINISTRATION
BID DOCUMENTS
Stamp
/1
/2
:4 :5
P
M
7-1-AE-101
ARCHITECTURAL RENOVATION PLAN, DETAILS & NOTES- LEVEL 1
JOHN COCHRAN VA MEDICAL CENTER, ST. LOUIS, MO
JJG/TJF
BUILDING 7
AHT
1/8" = 1'-0"1
LEVEL 01 - ARCHITECTURAL RENOVATION PLAN
TRUE
RENOVATION GENERAL NOTES
1 REFER TO GENERAL ARCHITECTURAL NOTES ON SHEET G-002 FOR ADDITIONAL ITEMS NOT COVERED BY THESE NOTES.
2 REFER TO HA – DRAWINGS AND REPORTS ON FILE WITH VA STLHCS – ENGINEERING FOR KNOWN EXTENTS OF HAZARDOUS
MATERIALS IN PROJECT AREA.
3 REFER TO ARCHITECTURAL DEMO PLANS FOR EXTENTS OF DEMOLITION WORK IN PROJECT AREA.
4 REFER TO ROOM FINISH SCHEDULE FOR FINISHES.
5 REFER TO MECHANICAL DWGS FOR RELATED MECHANICAL REMODELING.
6 REFER TO ELECTRICAL DWGS FOR RELATED ELECTRICAL REMODELING.
7 REFER TO FIRE PROTECTION DWGS FOR RELATED FIRE PROTECTION REMODELING.
8 FILL ALL LOCATIONS WHERE MASONRY WALLS HAVE BEEN REMOVED.
9 PATCH TO MATCH EXISTING WHERE DAMAGED BY DEMOLITION.
10 REINSTALL SIGNAGE IN ORIGINAL LOCATION OR WHERE DIRECTED BY COR.
11 REINSTALL PICTURES/ARTWORK IN ORIGINAL LOCATION OR WHERE DIRECTED BY COR.
12 REINSTALL HANDRAILS AND CORNER GUARDS. PATCH TO MATCH EXISTING WHERE REQUIRED DUE TO REMODELING.
13 DEMOLITION WASTE TO BE REMOVED TO DUMPSTER.
14 DISRUPTIVE ACTIVITIES IN OCCUPIED SPACES TO BE LIMITED AS DIRECTED BY COR. COORDINATE WELL IN ADVANCE WITH COR PRIOR
TO BEGINNING WORK.
15 REFER TO AI-100-SERIES DRAWINGS FOR FURNITURE AND EQUIPMENT.
16 REFER TO AE-100-SERIES DRAWINGS FOR DIMENSIONS AND NOTES FOR NEW CONSTRUCTION.
17 EXISTING EXTERIOR WALL SURFACES VARY IN DEPTH: CONTR TO LAY OUT AND INSTALL NEW EXTERIOR WALLS TO PROVIDE FINISH FACE OF WALL WITHOUT ENCROACHING ON FINISH CLEAR ROOM DIMENSIONS SHOWN ON ENLARGED FLOOR PLAN.
18 NO WOOD BLOCKING ALLOWED.
19 ALL WALLS AND CHASES TO BE INSULATED - SEE WALL TYPES AND ARCHITECTURAL GENERAL NOTES.
20 CONTRACTOR TO VERIFY LOCATION OF EXISTING PIPING AND RELATED ITEMS PRIOR TO START OF WORK. COORDINATE ALL EXISTING AND NEW MECHANICAL AND ELECTRICAL WORK TO FIT WITHIN WALLS AND CHASES SHOWN; WHERE EXISTING OR NEW MECHANICAL AND ELECTRICAL WORK FALLS OUTSIDE OF THE PROVIDED WALLS AND CHASES, THE CONTRACTOR SHALL NOTIFY THE COR FOR
REVISIONS TO THE LAYOUT OF WALLS OR CHASE AT NO ADDITIONAL COST TO THE OWNER.
21 DEMO WORK AND NEW WORK INDICATE APPROXIMATE AREA TO BE REMOVED. CONTRACTOR TO FIELD VERIFY ACTUAL AREA TO BE REMOVED - REMOVAL EXTENTS MAY DEPEND ON LOCATION OF AND DIRECTION OF SUSPENDED ACOUSTICAL CEILING GRID MAIN-TEE.
CONTRACTOR TO COORDINATE WORK AREA WITH MEP DRAWINGS FOR FULL SCOPE OF WORK. CONTRACTOR IS RESPONSIBLE FOR
WORK AS NECESSARY, FIELD VERIFY.
22 MAINTAIN ALL EXISTING FIRE RATINGS. FIELD VERIFY.
23 WORK AREA SHOWN DOES NOT DISTINGUISH BETWEEN PHASES BUT ONLY SHOWS AREA TO BE REMOVED AND REINSTALLED.
CONTRACTOR IS RESPONSIBLE FOR IDENTIFYING PHASING OF WORK; SOME PORTIONS OF WORK SHOWN MIGHT OCCUR IN MULTIPLE
PHASES. SEE PHASING REQUIREMENTS ON SHEET GI-002 AND GC-100.
24 REMOVE AND REINSTALL ALL ITEMS LOCATED IN CEILING (LIGHTS, DIFFUSERS, SPRINKLER HEADS, EXIT SIGNS, SIGNS, FANS, AHU, ALARMS, ANTENNAS, OCCUPANCY SENSORS, SPEAKERS, NURSE CALL, CODE LIGHTS, EMERGENCY SHOWER, CAMERA, CURTAIN TRACK, PATIENT LIFT OR ACCESS HATCHES, ETC.) AS REQUIRED. ALL ITEMS MAY NOT BE INDICATED ON DRAWINGS. FIELD VERIFY FOR
FULL SCOPE OF WORK.
25 ANY CONTRACTOR DISTURBED FINISHES MUST BE RESTORED TO MATCH THE EXISTING FINISH. COORDINATE WITH VA TO MATCH
EXISTING FINISHES.
26 COVER AND PROTECT ALL VA EQUIPMENT AND FURNITURE SO THAT THE FUNCTION AND APPEARANCE IS NOT AFFECTED BY CONSTRUCTION, THE CONTRACTOR, THEIR EQUIPMENT, MATERIALS, OR ANY INVOLVED ACTIONS.
27 A 1 HR MINIMUM FIRE-RATED SEPARATION IS REQUIRED BETWEEN ALL OCCUPIED SPACE AND CONSTRUCTION AREAS. THIS
PROTECTION INCLUDES ANY EXISTING PENETRATIONS AND OPENINGS.
28 PATCH FLOOR SLABS AT PENETRATIONS AND OPENINGS RESULTING FROM REMOVAL OF PIPING AS NECESSARY TO MAINTAIN
EXISTING FIRE SEPARATION AND FINISH.
29 AT PIPING AND EQUIPMENT REMOVAL LOCATIONS PATCH TO MATCH ADJACENT EXISTING FLOOR, WALLS, & CEILINGS.
30 PATCH PARTITION WALLS AND FILL/PATCH OPENINGS RESULTING FROM REMOVAL OF PIPING. MATCH EXISTING WALL CONDITION (FINISH, PAINT COLOR, WALL MOUNTED EQUIPMENT AND ACCESSORIES, ETC.) TYP. WALL CONDITION: GWB OR PLASTER. SEE MEP DRAWINGS FOR FULL EXTENT OF WORK. REMOVE, REPLACE, PATCH AND REPAIR WALL TO THE EXTENT NECESSARY TO COMPLETE WORK AND MEET THE REQUIRED STANDARDS FOR VA CONSTRUCTION. COORDINATE REMOVAL AND REINSTALLATION OF WALL MOUNTED EQUIPMENT, ETC. FIELD VERIFY. MAINTAIN EXISTING FIRE RATINGS. VERIFY EXISTING CONDITIONS WITH COR DURING
PRE-CONSTRUCTION WALK THRU, ADDITIONAL COSTS WILL NOT BE ALLOWED.
31 PATCH PARTITION WALLS AT NEW PENETRATIONS RESULTING FROM INSTALLATION OF NEW PIPING. SEAL AGAINST NEW PIPING TO MATCH EXISTING WALL CONDITION. MATCH EXISTING WALL CONDITION (FINISH, PAINT COLOR, WALL MOUNTED EQUIPMENT AND ACCESSORIES, ETC.) TYP. WALL CONDITION: GWB OR PLASTER. SEE MEP DRAWINGS FOR FULL EXTENT OF WORK. REMOVE, REPLACE, PATCH AND REPAIR WALL TO THE EXTENT NECESSARY TO COMPLETE WORK AND MEET THE REQUIRED STANDARDS FOR VA CONSTRUCTION. COORDINATE REMOVAL AND REINSTALLATION OF WALL MOUNTED EQUIPMENT, ETC. FIELD VERIFY. MAINTAIN EXISTING FIRE RATINGS. VERIFY EXISTING CONDITIONS WITH COR DURING PRE-CONSTRUCTION WALK THRU, ADDITIONAL COSTS WILL
NOT BE ALLOWED.
1/4" = 1'-0"2
PARTIAL LEVEL 01 ARCHITECTURAL RENOVATION PLAN
RENOVATION KEYNOTES
29 REFER TO ASBESTOS ABATEMENT DRAWINGS FOR ADDITIONAL
INFORMATION RELATED TO EXISTING FLOORING AND/OR CEILING
REMOVAL THIS ROOM.
30 REMOVE & REPLACE ACCESS HATCH-SEE SHEET AE-500 FOR DETAILS.
31 SEE AF-100 SERIES SHEETS FOR NEW TOILET ACCESSORIES
LOCATIONS, SCHEDULE AND MOUNTING HEIGHTS.
32 NEW 5/8” TYPE “X” MR GWB OVER EXISTING LT. GA. METAL STUD
FRAMING.
33 6” LT. GA. METAL CEILING JOISTS W/ TWO LAYERS 5/8” TYPE “X” MR GWB
CEILING.
34 LT. GA. METAL STUD PARTITION FRAMING TO BOTTOM OF LT. GA.
CEILING JOISTS W/ ONE LAYER 5/8” TYPE “X” MR GWB EACH SIDE.
35 6” MTL STUD WALL MATCH ADJ. WALL STUD HEIGHT WITH 1 LAYER 5/8”
TYPE “X” MOISTURE-MOLD RESISTANT GWB EA SIDE.
36 CEILING-HUNG METAL TOILET PARTITION.
37 FURR OUT EXTERIOR WALLS WITH EXTRUDED INSULATION BEHIND
METAL STUDS WITH BATT INSULATION, VAPOR BARRIER, AND DRYWALL
SHEATHING.
38 LIMITS OF FUTURE OCCUPANCY SHELL SPACE.
39 EXISTING CHASE WALL TO REMAIN.
40 PATCH FLOOR AND WALLS WHERE RADIATORS AND CONVECTORS
WERE REMOVED.
RENOVATION KEYNOTES
18 WINDOW POCKET - SEE WALL SECTIONS & REFLECTED CEILING PLAN.
19 WIRE STORAGE SHELVING; SEE EQUIPMENT SCHEDULE.
20 SEE AF-100 SERIES SHEETS FOR FLOOR FINISHES.
21 CONTRACTOR AND MATERIAL INGRESS/EGRESS PATH.
22 ANTE CHAMBER W/ STICKY WALK-OFF MAT – SEE DEMOLITION & NEW
FLOOR PLAN GENERAL NOTES.
23 TEMPORARY CONSTRUCTION BARRIER - SEE DEMOLITION & NEW
FLOOR PLAN GENERAL NOTES.
24 THRU-WALL PENETRATION W/ 2-HOUR RATED FIRE DAMPER;
COORDINATE SIZE/LOCATION W/ MECH; PROVIDE & INSTALL
FIRE-RATED ASS'Y TO CLOSE OPENING & MAINTAIN FIRE RATING
DURING CONSTRUCTION PRIOR TO COMPLETION OF FIRE DAMPER.
25 ALUMINUM-CLAD INSULATED EXTERIOR WALL PANELS AND FRAMING
OVER FACE OF BUILDING. SEE AE-200 SERIES SHEETS FOR
ELEVATIONS AND DETAILS.
26 EXISTING HEAD WALL TO REMAIN. CONSTRUCT NEW CEILING/GRID UP
TO EXISTING HEAD WALL.
27 PROCEDURE AREA SUBJECT TO SPECIAL REQUIREMENTS FOR WORK
IN STERILE AREAS. REFER TO VA GUIDELINES. SEE ASBESTOS AND
MECHANICAL DRAWINGS FOR ADDITIONAL INFORMATION.
28 WORK AT THIS LOCATION REQUIRES REMOVAL OF EXISTING WALL
CONDITION, FIELD VERIFY. MATCH EXISTING WALL CONDITION (FINISH,
PAINT COLOR, BASE, WALL COVERING, WALL-MOUNTED EQUIPMENT
AND ACCESSORIES, ETC.). TYP. WALL CONSTRUCTION: MR GWB,
PAINTED, WITH VINYL BASE. SEE MEP DRAWINGS FOR FULL EXTENT OF
WORK. REMOVE, REPLACE, PATCH AND REPAIR WALL TO THE EXTENT
NECESSARY TO COMPLETE WORK AND MEET THE STANDARDS FOR VA
CONSTRUCTION. COORDINATE REMOVAL AND REINSTALLATION OF
WALL MOUNTED EQUIPMENT, CASEWORK, ETC. FIELD VERIFY. AREA
SHOWN IS AN APPROXIMATE AREA TO BE REMOVED. MAINTAIN
EXISTING FIRE RATINGS. VERIFY EXISTING CONDITIONS DURING
PRE-CONSTRUCTION WALK-THROUGH WITH COR. ADDITIONAL COSTS
WILL NOT BE ALLOWED.
RENOVATION KEYNOTES
1 STERILE STORAGE AREA SUBJECT TO SPECIAL REQUIREMENTS. REFER
TO VA GUIDELINES.
2 CLEAN ROOM AREA SUBJECT TO SPECIAL REQUIREMENTS. REFER TO
VA GUIDELINES.
3 SEE ROOM FINISH SCHEDULE ON AF-100 SERIES SHEETS FOR
FINISHES.
4 PATCH EXISTING WALL W/ FINISHES TO MATCH EXISTING.
5 REPAIR EXISTING CEILING AFTER INSTALLATION OF NEW HVAC
EQUIPMENT -SEE REFLECTED CEILING PLAN.
6 NEW 2-HR-RATED SHAFT WALL FROM FLOOR TO STRUCT. ABOVE; W/
90-MIN. RATED ACCESS PANEL; COORDINATE W/ MECH FOR ACCESS
PANEL LOCATION. COORDINATE EXTENTS OF SHAFT ENCLOSURE
W/MEP DRAWINGS.
7 THRU-FLOOR PENETRATION W/ 2-HOUR RATED FIRE DAMPER;
COORDINATE SIZE/LOCATION W/ MECH; PROVIDE & INSTALL
FIRE-RATED ASS'Y TO CLOSE OPENING & MAINTAIN FIRE RATING
DURING CONSTRUCTION PRIOR TO COMPLETION OF FIRE DAMPER.
8 1-HOUR RATED WALL - SEE WALL TYPES (TYP).
9 PAINT EXISTING WALLS: PATCH, SAND, SMOOTH AND PREPARE
SURFACE OF EXIST WALL FOR NEW FINISH.
10 INSTALL CORNER GUARDS; SEE ARCHITECTURAL FINISH PLAN
AF-100-SERIES SHEETS FOR DETAILS.
11 PATCH TO MATCH EXISTING FINISH AS REQ'D. DUE TO REMODELING.
12 TEMPORARY CONSTRUCTION PARTITION - REMOVE AFTER
COMPLETION OF REFINISHING; PATCH TO MATCH ANY DAMAGE TO
EXISTING/NEW FINISHES.
13 MAINTAIN PATH FOR EGRESS DURING CONSTRUCTION.
14 AREA FOR NEW OWNER-PROVIDED/OWNER-INSTALLED
CABINET/EQUIPMENT; SEE FINISH PLAN & EQUIPMENT SCHEDULE.
15 NEW FIRE EXTINGUISHER CABINET (FEC); SEE SHEET AE-500 FOR
DETAILS.
16 EXISTING FEC.
17 NEW WD DOOR/HM FRAME; SEE DOOR SCHEDULE.
1 1/2" = 1'-0"3 Wall Types
X X XDOOR SCHEDULE
DOOR NO.
SIZE
FINISH
FRAME
HARDWARE COMMENTSWIDTH HEIGHT
FRAME
MATERIAL FRAME TYPE
18 3'-0" 7'-0" P-8 HOLLOW
METAL
1 HW1 Deduct Alternate #1 - No Work Bldg. 7 - PAINT COLOR TO MATCH EXISTING HOLLOW METAL FRAMES IN ADJACENT
CORRIDOR
18A 3'-0" 7'-0" P-8 HOLLOW
METAL
1 HW1 Deduct Alternate #1 - No Work Bldg. 7 - PAINT COLOR TO MATCH EXISTING HOLLOW METAL FRAMES IN ADJACENT
CORRIDOR
3" = 1'-0"5
DOOR 18 & 18A HEADER DETAIL
atast Text Box Add Sanitary Napkin Dispensers - Womens Tlts 19-02-25 atast Text Box 32 REFER TO SHEETS 7-1-AE-901 FOR TOILET ACCESSORY AND EQUIPMENT LOCATIONS; REFER TO SHEET 1-AE-601 FURNITURE, EQUIPMENT & ACCESSORIES SCHEDULE AND SPECIFICATIONS FOR TOILET ACCESSORIES AND EQUIPMENT atast Text Box atast Polygon atast Text Box atast Polygon atast Rectangle atast Rectangle atast Rectangle atast Rectangle
| Sheets |
| 7-1-AE-101 - ARCHITECTURAL RENOVATION PLAN, DETAILS & NOTES- LEVEL 1 |
File details come from the government source that posted it.