This document provides details regarding an upcoming federal contract opportunity for cooling tower replacement services at the Lebanon VA Medical Center. The project involves design and construction services for replacement of the facility's cooling towers and is anticipated to be awarded as a best value, two-phase design-build contract between $2-5 million. Only firms certified as 100% Service Disabled Veteran Owned Small Businesses will be eligible to participate in phase one of the competition. Phase one proposals will be evaluated to determine which offerors qualify for phase two. The solicitation is expected to be released on or around February 21, 2020 with a 455 calendar day period of performance. The primary agency is the Department of Veterans Affairs Veterans Health Administration VISN 4.

View the file

Other files for this federal contract opportunity

Other files attached to C1NB--Cooling Tower Replacement Project 595-11-135, newest first.
File Type Posted
36C24420R0014 A0004.pdf PDF
Full Set - Drawings Chiller.pdf PDF
36C24420R0014 A0004_1.docx DOCX document
Qs and As A0004.pdf PDF
36C24420R0014 A0003.pdf PDF
RLS Construction Group LLC.pdf PDF
District Veterans Contracting Inc.pdf PDF
AEONRG LLC.pdf PDF
36C24420R0014 A0003_1.docx DOCX document
SAW Contracting Inc.pdf PDF
36C24420R0014-A0002000.docx DOCX document
36C24420R0014-A0002001.pdf PDF
36C24420R0014-A0001001.docx DOCX document
36C24420R0014-A0001002.pdf PDF
36C24420R0014-018.docx DOCX document
36C24420R0014-017.docx DOCX document
36C24420R0014-015.pdf PDF
36C24420R0014-020.docx DOCX document
36C24420R0014-021.docx DOCX document
36C24420R0014-014.pdf PDF
36C24420R0014-013.pdf PDF
36C24420R0014-012.docx DOCX document
36C24420R0014-022.docx DOCX document
36C24420R0014-023.docx DOCX document
36C24420R0014-016.docx DOCX document
36C24420R0014-019.docx DOCX document
36C24420R0014-011.docx DOCX document
36C24420R0014-001.docx DOCX document
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART 1: Prepare no more than three (3) Part 1 forms: (Phase I).

Provide the following information requested in this format for each of the projects/contracts being described. Projects may be on going and cannot have been completed any later than five (5) years prior to the solicitation issue date. Provide frank, concise comments regarding YOUR PERFORMANCE on the contracts you identify. no more than (3) pages per project.

A. Offeror (Your) Name (Company/Division):

B. Project/Contract Title:

C. Contract Specifics:

1. Description of Effort as Prime or _Subcontractor

2. Contract Number

3. Original Contract $ Value Current/Final Contract $ Value

4. If amounts in 3 above are different, provide a brief description of the reason:

5. Completion Date:

1. Original Date:

2. Current Schedule: _____________________

3. Estimate/Final Completion Date:

4. Primary cause for Contract Modifications

D. Provide detailed description of the work performed under the contract and describe why you believe the work is very relevant, relevant or semi-relevant to this solicited project. (Use as much space as necessary)

In addition, address the following

1. Describe the specific elements of the work performed by your firm.

2. Indicate what elements of work were performed by your major subcontractors and indicate if those same subcontractors will be used on this project. Should you intend to use these same subcontractors, please list their company names and described their principal areas of work that they will perform.

3. Address any technical areas about this project you consider uniquely relevant to this solicitation.

E. Point of Contact for Owner/Government agency Contracting Officer and or inspector (COR / COTR); include a current phone number and email address for each.

Part 2, Additional offeror information required.

A. Name subcontractors and/or Teaming Partners to be utilized on this contract. Multiple subcontractors may be named for the same discipline but are limited to a maximum of three (3) subcontractors per discipline. As a minimum, provide the name(s) of subcontractors to be utilized in the following areas:

(Specialty Trades will address their specific trade for any major subcontractor or Teaming partner – list below is not all inclusive or may not apply)

a. Specialty Trades:

i. Existing Conditions

ii. Concrete

iii. Masonry

iv. Metals

v. Wood, Plastics and Composites

vi. Thermal and Moisture Protection

vii. Openings

viii. Finishes

ix. Specialties

x. Equipment

xi. Furnishings

xii. Conveying Equipment

xiii. Fire Suppression

xiv. Plumbing

xv. Heating, Ventilating and Air Conditioning

xvi. Electrical

xvii. Electrical Safety and Security

xviii. Earthworks

xix. Exterior Improvements

xx. Utilities

{MUST BE PROJECT SPECIFIC}