District Veterans Contracting Inc.pdf

PDF 156 KB Posted

Attached to
C1NB--Cooling Tower Replacement Project 595-11-135 Federal contract opportunity
Solicitation number
36C24420R0014
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

This document outlines a federal contract opportunity for cooling tower replacement services. The Lebanon VA Medical Center is seeking a design-build contractor team through a two-phase solicitation to complete design and construction of a cooling tower renovation project with an anticipated budget between $2,000,000 and $5,000,000. Only Service-Disabled Veteran Owned Small Businesses will be considered in phase one. The selected offerors will then submit proposals for phase two. The project delivery period is 455 calendar days from notice to proceed. The contracting agency is the Department of Veterans Affairs VHA VISN 4. The NAICS code is 238220 for plumbing, heating, and air conditioning contractors, with a size standard of $15 million. The solicitation is scheduled for release on or around February 21, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to C1NB--Cooling Tower Replacement Project 595-11-135, newest first.
File Type Posted
EXHIBIT B - Past Performance Relevancy Questionnaire REV.docx DOCX document
36C24420R0014 A0004.pdf PDF
Full Set - Drawings Chiller.pdf PDF
Qs and As A0004.pdf PDF
36C24420R0014 A0004_1.docx DOCX document
36C24420R0014 A0003.pdf PDF
RLS Construction Group LLC.pdf PDF
36C24420R0014 A0003_1.docx DOCX document
SAW Contracting Inc.pdf PDF
AEONRG LLC.pdf PDF
36C24420R0014-A0002000.docx DOCX document
36C24420R0014-A0002001.pdf PDF
36C24420R0014-A0001001.docx DOCX document
36C24420R0014-A0001002.pdf PDF
36C24420R0014-018.docx DOCX document
36C24420R0014-017.docx DOCX document
36C24420R0014-015.pdf PDF
36C24420R0014-020.docx DOCX document
36C24420R0014-021.docx DOCX document
36C24420R0014-014.pdf PDF
36C24420R0014-013.pdf PDF
36C24420R0014-012.docx DOCX document
36C24420R0014-023.docx DOCX document
36C24420R0014-016.docx DOCX document
36C24420R0014-019.docx DOCX document
36C24420R0014-022.docx DOCX document
36C24420R0014-011.docx DOCX document
36C24420R0014-001.docx DOCX document
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REMARKS:

R ECORD OF ATTENDANCE

Solicitation/Contract No. 3 6C24420R0014 DATE: 5/13/20 TIME: 1 PM

Project Title: C ooling Tower Replacement Project 595-20-135

TYPE OF MEETING

Training ( ) Bid Opening

Negotiation Conference Pre-Performance Conference

Pre-proposal/Pre-bid site visit Business Strategy Panel

Pre-proposal/Pre-bid conference Pre-Final Inspection

Progress Meeting Final Inspection

Source Selection Evaluation Meeting Other:

NAME ORGANIZATION P HONE NUMBER EMAIL

ADDRESS

Jeffrey Zbezinski RPO East NCO4 Contracting Officer

878-271-6636 Jeffrey Zbezinski

Rachel Gross District Veterans

Contracting

301-525-7966 rgross@districtvetcon.com

Peter Porretta Lighthouse

Architecture

215-732-6883 peter@lighthousedesign.com

Joseph McGillian Paradigm

Consulting Engineers

610-624-1240 joemcgillian@pcemep.com

Jeff Dolan Dolan Mechanical 856-629-9331 jdolan@dolanmechanical.com

Brian Pedersen Lebanon VA Med, Center 717.514.6065 Brian.Pedersen3@va.gov

Contracting Officer not present, the engineering walk-through/tour confirmed discussions did not make changes to the requirement or the specifications; this can only done by a written amendment to solicitation.

mailto:rgross@districtvetcon.com mailto:peter@lighthousedesign.com mailto:joemcgillian@pcemep.com mailto:jdolan@dolanmechanical.com

2020-05-22T13:14:47-0400
Jeffrey Zbezinski 551812

File details come from the government source that posted it. Updated .