Amendment 00004 RFI Answers.docx

DOCX document 18 KB Posted

Attached to
Y1DZ--NRM - CONSTR PROJ - 630-26-102 Design Build HVAC Bldgs. 4 and 5
Solicitation number
36C24226R0034
Issued by

About this file

This document is Amendment 00004 to a Request for Information (RFI) containing clarifications and responses for a design-build HVAC upgrade project (Project 630-26-102) at a Veterans Affairs facility. The amendment addresses critical technical specifications for equipment to be served by optional standby power, including two of three 4160V, 3-phase, 60 Hz chillers (100 FLA amps each, 668.1 kW per chiller), two 460V, 3-phase, 60 Hz chilled water pumps (200 HP, 234A), two 460V, 3-phase, 60 Hz condenser water pumps (150 HP, 170A), and six to eight cooling tower cells with dual 10 HP motors each. A new 480V emergency switchgear with transformer capacity and four spare buckets will be designed by an electrical engineer to support these systems.

The amendment clarifies that four exhaust fans are required for the Electrical Switchgear Area and five for the Chiller Plant (with two currently operational), both requiring BMS system connection and temperature-activated operation at 80 degrees Fahrenheit. The new optional standby power switchboard will not be connected to the existing emergency generator feed, with that wiring work scheduled under a separate project. CAD drawings remain unavailable but will be requested from the A-E firm. The response deadline for this amendment remains May 6, 2026, at 3:00 PM Eastern time, with the RFI submission deadline of April 29, 2026.

View the file

Other files

File Type Posted
36C24226R0034 0005.docx DOCX document
36C24226R0034 0004.docx DOCX document
36C24226R0034 0003.docx DOCX document
S02 Mech_CD Drawing.pdf PDF
S02 Mechanical Print Chiller Plant Drawing.pdf PDF
S02 Elec CD Drawing.pdf PDF
S02 Architectural Drawing.pdf PDF
Amendment 00003 RFI Answers.docx DOCX document
36C24226R0034 0002.docx DOCX document
VA Privacy Training Document.pdf PDF
36C24226R0034 0001.pdf PDF
013200 Construction Documentation Design Build HVAC Bldgs. 4 and 5.1.docx DOCX document
WD NY20250003 Mod 17 12122025.1.pdf PDF
S02 Participation Goals for Minorities and Females 2.1.pdf PDF
01 35 26 Safety Requirements Design Build HVAC Bldgs. 4 and 5.1.docx DOCX document
01 00 00 General Requirements Design Build HVAC Bldgs. 4 and 5.1.docx DOCX document
S02 FAR DEVIATION FEB 2025 NOTICE 2.1.docx DOCX document
S02 AUTODESK Contractors Access Instructions 1.1.pdf PDF
S02 LIQUIDATED DAMAGES FORMULATION MEMO 2.1.docx DOCX document
S02 SAFETY AND ENVIRONMENTAL RECORD 2.1.docx DOCX document
36C24226R0034_1.1.docx DOCX document
S02 52.225-2 BUY AMERICAN CERTIFICATE 2.1.docx DOCX document
S02 LIMITATION ON SUBCONTRACTING 2.1.docx DOCX document
S02 INSTRUCTIONS TO BIDDERS REGARDING TAX EXEMPTION IN NY 2.1.docx DOCX document
S02 Privacy Training for Personnel without Access to VA Computer 1.1.pdf PDF
SCA Wagw No 2015 4187 Rev 34 12032025.1.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 00004 Proj: 630-26-102 Proj Title: design Build HVAC Bldgs. 4 and 5

38. It is our understanding that the new optional stand-by power switchboard serving chilled water plant equipment will not be connected to the existing emergency generator feed. The wiring between the existing generator and the new optional stand-by power switchboard will be done under a separate project and not part of this project. Please confirm.

Ans: Confirmed. New 480V switchgear will need to be connected to new emergency panel but not wired to existing generator feed.

39. Can we please get the CAD drawings?

Ans: CAD Drawings are currently unavailable. They will be requested from the A-E. Can’t the .pdfs supplied be converted to AutoCAD?

40. I wanted to follow up on our site visit yesterday as it was discussed by the COR that there would be more of a clarification on the amount of exhaust fans and a more clear scope of work as they wanted to keep the playing field fair?

Ans: Four exhaust fans for only the Electrical Switchgear Area. Exhaust fans and fresh air intake louvers need to be connected to the BMS system. Inspect/repair/replace any defective fan. For the Chiller Plant, five exhaust fans are needed. There are only two operational fans now. Fans need to operate when the temperature reaches 80 deg F in the area.

New emergency switchgear including transformer with the capacity to run the following equipment below and provide 4 spare buckets (480V.) Electrical engineer to design.

From RFI Answers #2 Please provide a list, and/or confirm items scheduled to be served from optional standby power.

Ans: 2 chillers, 2 condenser water pumps, 2 chilled water pumps, 6-8 Cooling tower cells with fans will be needed to run simultaneously.

(2) of (4) Chillers – please confirm which Chillers / confirm electrical characteristics, (FLA, MOP, voltage, phase)

Ans: 2 of 3 Chillers will need to run. 4160V, 3 phase, 60 Hz 100 FLA amps for the motors. 668.1 kW per chiller for “Job kW.”

Chilled water pumps – please confirm which pumps, and associated electrical characteristics, (HP, voltage, phase)

Ans: 2 of the existing four pumps will need to run with the chillers. They are 460V, 3 phase 60 Hz 200 hp motors. The Amps on the nameplate is listed at 234A.

Cooling Tower – please confirm arrangement, (e.g. how many cells / how many cooling tower fans). Provide electrical characteristics, (HP, voltage, phase)

Ans: 6-8 Cooling tower cells. Each cell has (2) 10HP 460V 3 phase 60hz motors.

Cooling Tower pumps / condenser water pumps – please confirm which pumps and associated electrical characteristics, (HP, voltage, phase)

Ans: 2 of the existing four pumps will need to run with the chillers They are 460V, 3 phase 60 Hz 150 hp motors. The Amps on the nameplate is listed at 170A.