This document is a Request for Proposal (RFP) for replacing the primary boilers serving the Albany VAMC main hospital. The key details are:
The project includes construction services to replace three 900 HP dual fuel fired steam water-tube boilers with two temporary 1,000 BHP dual fuel steam boilers. A newer 400 HP fire-tube steam boiler is anticipated to remain in service until the temporary boilers are operating. The goal is to improve the boiler plant reliability and efficiency. The project will be completed in three phases: 1) Replace electrical equipment and install new switchgear, 2) Install the temporary boilers, and 3) Remove the 900 HP boilers and install the new boilers. The contractor will be required to use the Autodesk Build construction management platform and have all submittals approved prior to mobilization. The work must be substantially complete within 730 calendar days after the notice to proceed.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
04-01-23
26 05 11 - 1
SECTION 26 05 11
REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section applies to all sections of Division 26.
B. Manufacturer shall provide electrical equipment, materials, related components and accessories in accordance with the specifications and drawings.
1.2 MINIMUM REQUIREMENTS
A. Reference to the International Building Code (IBC), Underwriters
Laboratories, Inc. (UL), and National Fire Protection Association
(NFPA) codes are minimum required standards.
B. Drawings and specification sections shall govern in cases where requirements exceed the ones required in the above standards.
1.3 TEST STANDARDS
A. Materials and equipment shall be listed, labeled or certified by a
Nationally Recognized Testing Laboratory (NRTL) to meet Underwriters
Laboratories, Inc., standards where test standards have been established. Materials and equipment not listed by UL Standards will be accepted providing that materials and equipment is listed, labeled, and certified to meet safety requirements of a NRTL. Materials and equipment that no NRTL lists, labels, and certifies, will be considered if inspected or tested in accordance with national industrial standards, such as ANSI, NEMA, or NETA. Evidence of compliance shall include certified test reports and shop drawings.
B. Definitions:
1. Listed: Material or equipment included in a list published by an organization that:
a. Is acceptable to the Authority Having Jurisdiction (AHJ) and concerned with evaluation of products or services.
b. Is published by a nationally recognized laboratory which makes periodic inspection of production of such equipment.
c. States that such equipment meets nationally recognized standards or has been tested and found safe for use in a specified manner.
2. Labeled: Material or equipment is labeled when:
a. It embodies a valid label, symbol, or other identifying mark of a nationally recognized testing laboratory such as Underwriters
Laboratories, Inc.
26 05 11 - 2
b. The laboratory makes periodic inspections of the production of such equipment.
c. The labeling indicates compliance with nationally recognized standards or tests to determine safe use in a specified manner.
3. Certified: Material or equipment is certified when:
a. It has been tested and validated by a NRTL to meet nationally recognized standards or to be safe for use in a specified manner.
b. It is periodically inspected by a NRTL.
c. It bears a label, tag, or other record of certification.
4. Nationally Recognized Testing Laboratory (NRTL): laboratory which is approved, in accordance with OSHA regulations, by the Secretary of Labor.
5. Provide: The term “provide” denotes “furnish, install and connect”.
1.4 QUALIFICATIONS (MANUFACTURERS, PRODUCTS AND SERVICES)
A. Manufacturer’s Qualifications: The manufacturer shall regularly and presently produce, as one of the manufacturer's principal products, the equipment and material specified for this project, and shall have manufactured the item for at least three years.
B. Product Qualification:
1. Product shall have been in satisfactory operation, on three installations of similar size and type as this project, and for a minimum of three years.
2. The Government reserves the right to require the manufacturer to submit a list of installations where the products have been in operation before approval.
C. Service Qualifications: There shall be a permanent service organization maintained or trained by the manufacturer which will render service to this installation within four (4) hours of receipt of notification that service is needed. Submit name and address of service organizations.
1.5 APPLICABLE PUBLICATION
A. Applicable publications listed in all sections of Division 26 are the latest issues, unless otherwise noted.
B. Products specified in all sections of Division 26 shall comply with the applicable publications listed in each section.
1.6 MANUFACTURED PRODUCTS
A. Materials and equipment furnished shall be of current production by manufacturers regularly engaged in the manufacture of such items, and
26 05 11 - 3 for which replacement parts shall be available. Materials and equipment furnished shall be new, and shall have superior quality and freshness.
B. When more than one unit of the same class of equipment is required, such units shall be the product of a single manufacturer.
C. Equipment Assemblies and Components:
1. Components of an assembled unit need not be products of the same manufacturer.
2. Manufacturers of equipment assemblies, which include components made by others, shall assume complete responsibility for the final assembled unit.
3. Components shall be compatible with each other and with the total assembly for the intended service.
4. Parts which are similar shall be the product of a single manufacturer.
D. Factory wiring shall be identified on the equipment, and shown on all wiring diagrams.
E. When Factory Tests are specified, Factory Tests shall be performed in the factory by the equipment manufacturer, and witnessed by the Design
Engineer. Additionally, the manufacturer shall comply with the following requirements:
1. The Government shall have the option of witnessing factory tests.
The manufacturer shall notify the Government, through the Resident
Engineer/COR, a minimum of thirty (30) days prior to the manufacturer’s performing of the factory tests.
2. When factory tests are successful, manufacturer shall furnish four
(4) copies of the equipment manufacturer’s certified test report to the Resident Engineer fourteen (14) days prior to shipment of the equipment, and not more than ninety (90) days after completion of the factory tests.
3. When factory tests are not successful, factory tests shall be repeated in the factory by the equipment manufacturer, and witnessed by the Design Engineer. The manufacturer shall be liable for additional expenses for the Government to witness factory re-testing.
1.7 VARIATIONS FROM CONTRACT REQUIREMENTS
A. Where the Government requests variations from the contract requirements, the manufacturer shall provide additional materials, 26 05 11 - 4 equipment, related components and accessories to satisfy these variations. If the manufacturer requests variations from the contract requirements, manufacturer shall be liable for all additional costs and expenses.
1.8 MATERIALS AND EQUIPMENT PROTECTION
A. Materials and Equipment shall be protected during shipment against physical damage, dirt, moisture, cold and rain:
1. 2. Damaged equipment shall be, as determined by the Resident
Engineer, replaced or repaired.
3. Painted surfaces shall be protected with removable factory installed heavy kraft paper, sheet vinyl or equal.
4. Damaged paint on equipment and materials shall be refinished with the same quality of paint and workmanship as used by the manufacturer so repaired areas are not obvious.
1.9 WORK PERFORMANCE
A. Not Used
1.10 EQUIPMENT INSTALLATION AND REQUIREMENTS
A. Not Used.
1.11 EQUIPMENT IDENTIFICATION
A. In addition to the requirements of the latest NEC, install an identification sign which clearly indicates information required for use and maintenance of items such individual breakers and controllers in switchgear and other significant equipment.
B. Nameplates shall be laminated black phenolic resin with a white core with engraved lettering, a minimum of 6 mm (1/4 inch) high. Secure nameplates with screws. Nameplates that are furnished by manufacturer as a standard catalog item, or where other method of identification is herein specified, are exceptions.
C. Install adhesive arc flash warning labels on all equipment as required by the latest NFPA 70E.
1.12 SUBMITTALS
A. Submit six copies to Resident Engineer/COR in accordance with Section
01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. The Government's approval shall be obtained for all equipment and material before delivery to the job site. The Government prohibits delivery, storage or installation of equipment or material which has not been approved through the submittal process.
26 05 11 - 5
C. All submittals shall include descriptive literature, catalog cuts, shop drawings, and other data necessary for the Government to ascertain that the proposed equipment and materials comply with specification requirements. Catalog cuts submitted for approval shall be legible and clearly identify equipment being submitted.
D. Submittals for individual systems and equipment assemblies which consist of more than one item or component shall be made for the system or assembly as a whole. Partial submittals will not be considered for approval.
1. Mark the submittals, "SUBMITTED UNDER SPECIFICATION
SECTION__________________".
2. Submittals shall be marked to show specification reference including the section and paragraph numbers.
3. Submit each section separately.
E. The submittals shall include the following:
1. Information that confirms compliance with contract requirements.
Include the manufacturer's name, model or catalog numbers, catalog information, technical data sheets, shop drawings, pictures, nameplate data and test reports as required.
3. Elementary and interconnection wiring diagrams for communication and signal systems, control system and equipment assemblies. All terminal points and wiring shall be identified on wiring diagrams.
4. Parts list to include replacement parts and part numbers recommended by the equipment manufacturer, and quantity of parts.
F. Maintenance and Operation Manuals:
1. Submit as required for systems and equipment specified in the technical sections. Furnish four copies, bound in hardback binders, (manufacturer's standard binders) or an approved equivalent. Furnish one complete manual as specified in the technical section but in no case later than prior to performance of systems or equipment test, and furnish the remaining manuals prior to contract completion.
2. Inscribe the following identification on the cover: the words
"MAINTENANCE AND OPERATION MANUAL," the name and location of the system, equipment, building, name of the manufacturer, and contract number. Include in the manual the names, addresses, and telephone numbers of the local representatives for the system or equipment.
3. Provide a "Table of Contents" and assemble the manual to conform to the table of contents, with tab sheets placed before instructions
26 05 11 - 6 covering the subject. The instructions shall be legible and easily read, with large sheets of drawings folded in.
4. The manuals shall include:
a. Internal and interconnecting wiring and control diagrams with data to explain detailed operation and control of the equipment.
b. A control sequence describing start-up, operation, and shutdown.
c. Description of the function of each principal item of equipment.
d. Installation and maintenance instructions.
e. Safety precautions.
f. Diagrams and illustrations.
g. Testing methods.
h. Performance data.
i. Lubrication schedule including type, grade, temperature range, and frequency.
j. Pictorial "exploded" parts list with part numbers. Emphasis shall be placed on the use of special tools and instruments. The list shall indicate sources of supply, recommended spare parts, and name of servicing organization.
k. List qualified permanent servicing organizations for support of the equipment, including addresses and certified qualifications.
1.13 SINGULAR NUMBER
A. Where any device or part of equipment is referred to in these specifications in the singular number (e.g., "the switch"), this reference shall be deemed to apply to as many such devices as are required to complete the installation as shown on the drawings.
1.15 WARRANTY
A. Workmanship, labor, equipment, materials, related components and accessories shall be free from defects, and shall remain so for a period of one year from the date of project acceptance by the
Government
1.16 TRAINING
A. Training shall be provided to designated Government personnel for particular equipment or system as required in each associated specification section.
B. Manufacturer shall furnish the services of factory certified and experienced instructors to provide full instruction in the adjustment, operation, and maintenance of the specified equipment and system.
Instruction shall also include safety requirements.
26 05 11 - 7
C. Manufacturer shall develop a training schedule, and submit training schedule to Resident Engineer for review and approval at least thirty
(30) days prior to the scheduled training.