This document is a Scope of Work for a federal construction contract opportunity to replace the main boilers at the Albany VAMC hospital. The project includes replacing three 900 HP dual fuel steam boilers from 1978 with temporary 1,000 BHP dual fuel steam boilers and a newer 400 HP fire-tube steam boiler. The work will be completed in three phases: 1) Replace electrical equipment and install new switchgear, 2) Install the temporary boilers and associated infrastructure, and 3) Remove the old boilers and install the new boilers. The contractor must use the Autodesk Build Construction cloud platform for project management and collaboration. The project must be substantially complete within 730 calendar days of the notice to proceed. The contracting agency is the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 2.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--528A8-17-805 REPLACE MAIN BOILERS, newest first.
File Type Posted
36C24224B0047 0006.docx DOCX document
36C24224B0047 0005.docx DOCX document
2024-09-09 Walk Through Sign in Sheet .pdf PDF
36C24224B0047 0004.docx DOCX document
E-501 Boiler Plant Pre-Purchase One-Line Diagram.pdf PDF
Boiler Plant - Electrcial Purchase.png PNG image
261219 Pad mounted Liquid Filled Medium Voltage Transformers.pdf PDF
262300 Switchgear.pdf PDF
260511ReqForElecInstall.pdf PDF
36C24224B0047 0003.docx DOCX document
260573 Overcurrent Protective Device Coordination Study.pdf PDF
263623 Automatic Transfer Switch.pdf PDF
261316 Medium Voltage Fusible Interrupter Switches.pdf PDF
36C24224B0047 0002.docx DOCX document
2024-08-23 Walk Through Sign in Sheet .pdf PDF
36C24224B0047 0001.docx DOCX document
9- Albany Plumbing - stamped.pdf PDF
4- Albany Structural - stamped.pdf PDF
36C24224B0047_1.docx DOCX document
8- Albany Fire Protection - Stamped.pdf PDF
3A- Albany Architectural - stamped.pdf PDF
WD Albany NY20240002 07-12-2024.docx DOCX document
10- Albany Specs.pdf PDF
3C- Albany Architectural - stamped.pdf PDF
3B- Albany Architectural - stamped.pdf PDF
6B- Albany Mechanical - stamped.pdf PDF
7- Albany Electrical - stamped.pdf PDF
6A- Albany Mechanical - stamped.pdf PDF
5- Albany Civil - stamped.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of Veterans Affairs

Replace Main Boilers, 528A8-17-805Project Name:

Project Address: Samuel S. Stratton VAMC

113 Holand Ave., Albany, New York 12208

SERVICE ALLEY

MAIN BOILER PLANT

CHILLER PLANT

CHP

SUMMER

BOILER

ARF

AHUS

TANK VAULT

ROOF

GROUND

BUILDING

GROUND FLOOR

EQUIP SHED

100% CONSTRUCTION DOCUMENTS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990

200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768

100% CONSTRUCTION

DOCUMENTS

REPLACE MAIN BOILERS 528A8-17-805

Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208

06/05/2024

105 Central Street Stoneham, MA 02180 P: 781-275-6050

C U se rs

\h a u n g \D o c u m e n ts

\A lb a n y_ B o ile r_ M e c h

E le ct ri c a l U p g ra d e

V h a u n g

G H

V P

.r v t

/7

/2

:3

:3

P M

GI-001

COVER PAGE

HL HA

AREA OF WORK

Revisions: Date:

DRAWING INDEX

DRAWING

NUMBER

DRAWING TITLE

INCLUDED

IN 90%

DRAWING

NUMBER

DRAWING TITLE

INCLUDED

IN 90%

DRAWING

NUMBER

DRAWING TITLE

INCLUDED

IN 90%

GI-001 COVER PAGE X MH-201

MECHANICAL - PHASE 2 - SUB-BASEMENT NEW

WORK PLAN

X

EPD-512

ELECTRICAL - PHASE 1 - CHILLER PLANT ONE-LINE DIAGRAM -

DEMOLITION

X

GI-002 DRAWING INDEX X MH-202

MECHANICAL - PHASE 2- BASEMENT NEW WORK

PLAN

X

EPD-520

ELECTRICAL- PHASE 2 - BOILER PLANT ONE-LINE DIAGRAM -

DEMOLITION

X

GI-003 GENERAL NOTES ABBREVIATIONS AND SYMBOLS X MH-203 MECHANICAL - PHASE 2- LEVEL 1 NEW WORK PLAN X

EPD-530

ELECTRICAL - PHASE 3 - BOILER PLANT ONE-LINE DIAGRAM -

DEMOLITION

X

GI-004 MECHANICAL - EXISTING CONDITION - PHOTOS X MH-204 MECHANICAL - PHASE 2- ROOF NEW WORK PLAN X

EPD-531

ELECTRICAL - PHASE 3 - BOILER PLANT ONE-LINE DIAGRAM

-TEMPORARY BOILERS DEMOLITION

X

GI-005 CONSTRUCTION PHASING PLAN AND SHUT DOWN REQUIREMENTS X MH-300 MECHANICAL - PHASE 3-RIGGING PLAN X

EPSD-101

ELECTRICAL PHASE 1 - SITE PLAN - CHILLER PLANT AND BOILER

PLANT SERVICE UPGRADE -DEMOLITION

X

GI-006 CONSTRUCTION PHASING PLAN AND SHUT DOWN REQUIREMENTS X MH-301

MECHANICAL - PHASE 3- SUB-BASEMENT NEW

WORK PLAN

X

EL-201

ELECTRICAL - PHASE 2 - SUB-BASEMENT LIGHTING NEW WORK

PLAN

X

MH-301A BOILER CONTROL ROOM - PHASE 3-NEW WORK X EL-202 ELECTRICAL - PHASE 2 - BASEMENT LIGHTING NEW WORK PLAN X

AG-001 ARCHITECTURAL GENERAL NOTES, ABBREVIATIONS, AND SYMBOLS X MH-302

MECHANICAL - PHASE 3- BASEMENT NEW WORK

PLAN

X

EL-301

ELECTRICAL - PHASE 3 - SUB-BASEMENT LIGHTING NEW WORK

PLAN

X

AD-201 ARCHITECTURAL PHASE 2 - SUB-BASEMENT DEMOLITION PLAN X MH-303 MECHANICAL - PHASE 3- LEVEL 1 NEW WORK PLAN X EL-302 ELECTRICAL - PHASE 3 - BASEMENT LIGHTING NEW WORK PLAN X

AD-301 ARCHITECTURAL PHASE 3 - SUB-BASEMENT DEMOLITION PLAN X MH-304 MECHANICAL - PHASE 3- ROOF NEW WORK PLAN X EP-100 ELECTRICAL - BOILER PLANT CONTROL ROOM NEW WORK X

AD-302 ARCHITECTURAL PHASE 3 - BASEMENT DEMOLITION PLAN X MH-401 MECHANICAL PHASE 2 - SECTION AND ISO VIEWS X EP-101 ELECTRICAL - PHASE 1 - SUB-BASEMENT NEW WORK PLAN X

AD-303 ARCHITECTURAL PHASE 3 - ROOF DEMOLITION PLAN X MH-402 MECHANICAL PHASE 2 - SECTION AND ISO VIEWS X EP-102 ELECTRICAL - PHASE 1 - BASEMENT NEW WORK PLANS X

AE-201 ARCHITECTURAL PHASE 2 - SUB-BASEMENT NEW WORK PLAN X MH-403 MECHANICAL PHASE 3 - SECTION AND ISO VIEWS X

EP-103

ELECTRICAL - PHASE 1 - OVERALL SUB-BASEMENT POWER NEW

WORK PLAN

X

AE-301

ARCHITECTURAL PHASE 3 - SUB-BASEMENT NEW WORK PLAN AND

CONTROL ROOM RCP

X MH-404 MECHANICAL PHASE 3 - SECTION AND ISO VIEWS

X

EP-201

ELECTRICAL - PHASE 2 - SUB-BASEMENT POWER NEW WORK

PLAN

X

AE-302 ARCHITECTURAL PHASE 3 - BASEMENT NEW WORK PLAN X MH-501 MECHANICAL PHASE 2 - PART PLANS X EP-202 ELECTRICAL - PHASE 2 - BASEMENT POWER NEW WORK PLAN X

AE-303 ARCHITECTURAL PHASE 3 - ROOF NEW WORK PLAN X MH-502 MECHANICAL PHASE 3 - PART PLANS X EP-301 ELECTRICAL - PHASE 3 - BASEMENT POWER NEW WORK PLAN X

AI-101 ARCHITECTURAL PHASE 3 - NEW WORK SECTIONS X MID-101 STEAM RISER DIAGRAM - PHASE 1 - DEMOLITION X EP-302 ELECTRICAL - PHASE 3 - BASEMENT POWER NEW WORK PLAN X

AI-102 ARCHITECTURAL PHASE 3 - NEW WORK SECTIONS AND DETAILS X MID-102

CONDENSATE RISER DIAGRAM - PHASE 1 -

DEMOLITION

X

EP-303 ELECTRICAL - PHASE 3 - ROOF POWER NEW WORK PLAN X

AI-103

ARCHITECTURAL PHASE 2 - NEW TEMPORARY DUST BARRIER

ENCLOSURE

X MID-201 STEAM RISER DIAGRAM - PHASE 2 - DEMOLITION

X

EP-510

ELECTRICAL - PHASE 1 - BOILER PLANT ONE-LINE DIAGRAM -

TEMPORARY BOILERS

X

AI-104 ARCHITECTURAL PHASE 3 - WALL SECTIONS X MID-202

CONDENSATE RISER DIAGRAM - PHASE 2 -

DEMOLITION

X

EP-511

ELECTRICAL - PHASE 1 - BOILER PLANT ONE-LINE DIAGRAM -

NEW WORK

X

AI-201 ARCHITECTURAL PHASE 3 - ROOF PENETRATION DETAILS X MID-301 STEAM RISER DIAGRAM - PHASE 3 - DEMOLITION X

EP-512

ELECTRICAL - PHASE 1 - CHILLER PLANT ONE-LINE DIAGRAM -

TEMPORARY POWER

X

AI-202 ARCHITECTURAL PHASE 3 - LOUVER/WALL DETAILS X MID-302

CONDENSATE RISER DIAGRAM - PHASE 3 -

DEMOLITION

X

EP-513

ELECTRICAL - PHASE 1 - CHILLER PLANT ONE-LINE DIAGRAM -

NEW WORK

X

AI-203 ARCHITECTURAL PHASE 3 - SUSPENDED CEILING DETAILS X MI-101 STEAM RISER DIAGRAM - PHASE 1 - NEW WORK X

EP-520

ELECTRICAL - PHASE 2 - BOILER PLANT ONE-LINE DIAGRAM -

NEW WORK

X

AI-204 ARCHITECTURAL PHASE 3 - BREECH DETAILS X MI-102

CONDENSATE RISER DIAGRAM - PHASE 1 - NEW

WORK

X

EP-531

ELECTRICAL - PHASE 3 - CHILLER PLANT ONE-LINE DIAGRAM -

NEW WORK

X

AF-101 ARCHITECTURAL PHASE 3 - ROOM FINISHES X MI-201 STEAM RISER DIAGRAM - PHASE 2 - NEW WORK X

EP-532

BOILER PLANT - PHASE 3 - BOILER PLANT ONE-LINE DIAGRAM -

NEW WORK

X

AF-102 ARCHITECTURAL PHASE 3 - ROOM FINISHES X MI-202

CONDENSATE RISER DIAGRAM - PHASE 2 - NEW

WORK

X

E-301 ELECTRICAL - DETAILS X

AF-103 ARCHITECTURAL PHASE 3 - WALL AND CEILING REPAIRS X MI-301 STEAM RISER DIAGRAM - PHASE 3 - NEW WORK X E-302 ELECTRICAL - DETAILS X

MI-302

CONDENSATE RISER DIAGRAM - PHASE 3 - NEW

WORK

X

E-401 ELECTRICAL - SCHEDULES X

SG-001 STRUTURAL GENERAL NOTES X MI-303 OTHER RISER DIAGRAM - PHASE 3 - NEW WORK X E-402 ELECTRICAL - PANEL SCHEDULES X

SD-201 STRUCTURAL PHASE 2 - SUB-BASEMENT DEMOLITION PLAN X MI-401 MECHANICAL DETAILS X E-403 ELECTRICAL - PANEL SCHEDULES X

SD-301 STRUCTURAL PHASE 3 - SUB-BASEMENT DEMOLITION PLAN X MI-402 MECHANICAL DETAILS X

SD-302 STRUCTURAL PHASE 3 - BASEMENT DEMOLITION PLAN X MI-403 MECHANICAL DETAILS X FA-000 FIRE ALARM - LEGEND, DETAILS AND RISER DIAGRAM

SF-201 STRUCTURAL PHASE 2 - SUB-BASEMENT NEW WORK PLAN X MI-404 MECHANICAL DETAILS X FA-201 FIRE ALARM - SUB-BASEMENT NEW WORK PLAN

SF-301 STRUCTURAL PHASE 3 - SUB-BASEMENT NEW WORK PLAN X MI-405 TEMPORARY BOILER DETAILS X FA-202 FIRE ALARM - BASEMENT NEW WORK PLAN

SF-302 STRUCTURAL PHASE 3 - BASEMENT NEW WORK PLAN X MI-406 TEMPORARY BOILER PID X FAD-201 FIRE ALARM - SUB-BASEMENT DEMOLITION PLAN

SF-401 STRUCTURAL SECTIONS X MI-407

TEMPORARY BOILER PLATFORM AND TRAILER

STAIR DETAILS

X

FAD-202 FIRE ALARM - BASEMENT DEMOLITION PLAN

SF-501 STRUCTURAL PHASE 2 - SUB-BASEMENT SEISMIC BRACING PLAN X MI-501 MECHANICAL SCHEDULES X

SF-502 STRUCTURAL PHASE 2 - BASEMENT SEISMIC BRACING PLAN X MI-502 MECHANICAL SCHEDULES X FX-000 FIRE PROTECTION LEGEND X

SF-503 STRUCTURAL PHASE 3 - SUB-BASEMENT SEISMIC BRACING PLAN X MI-503 MECHANICAL SCHEDULES X FD-201 FIRE PROTECTION BASEMENT FLOOR DEMOLITION PLAN X

SF-504 STRUCTURAL PHASE 3 - BASEMENT SEISMIC BRACING PLAN X MI-504 MECHANICAL SCHEDULES X FX-201 FIRE PROTECTION NEW WORK PART PLANS X

SF-601 STRUCTURAL DETAILS X MI-601 MECHANICAL CONTROLS X FX-600 FIRE PROTECTION DETAILS X

SF-602 STRUCTURAL SEISMIC DETAILS X MI-602 MECHANICAL CONTROLS X FX-601 FIRE PROTECTION DETAILS X

MI-603 MECHANICAL CONTROLS X

CI-101 CIVIL LEGEND, ABBREVIATIONS, AND GENERAL NOTES X MI-604 MECHANICAL CONTROLS X P-000 PLUMBING LEGEND X

CD-101 DEMOLITION PLAN X MI-605 MECHANICAL CONTROLS X P-201 PLUMBING PHASE 2 - SITE PLAN X

CS-101 SITE PLAN X MI-606 MECHANICAL CONTROLS X PD-201 PLUMBING PHASE 2 - BASEMENT DEMOLITION PLAN X

CG-101 GRADING PLAN X MI-607 MECHANICAL CONTROLS X PP-201U PLUMBING PHASE 2 - SUB BASEMENT UNDERSLAB PLAN X

CP-101 PAVING PLAN X PP-201 PLUMBING PHASE 2 - SUB BASEMENT PLAN X

CU-101 UTILITY PLAN X E-000

ELECTRICAL - LEGEND & ABBREVIATIONS

X

PP-202

PLUMBING PHASE 2 - SUB BASEMENT PLAN TEMPORARY BOILER

LOCATION

X

CJ-101 UTILITY PROFILE X ESP-101

ELECTRICAL - PHASE 1 - SITE PLAN - CHILLER PLANT

AND BOILER PLANT SERVICE UPGRADE - NEW WORK

X

PP-203 PLUMBING PHASE 2 - BASEMENT FLOOR PLAN X

CK-101 CIVIL DETAILS X ESP-102

ELECTRICAL - PHASE 1 - SITE PLAN - TEMPORARY

BOILERS

X

PD-301U

PLUMBING PHASE 3 - SUB BASEMENT UNDERSLAB DEMOLITION

PLAN

X

CK-102 CIVIL DETAILS X ESP-103 ELECTRICAL - PHASE 1 - SITE DETAILS X PD-301 PLUMBING PHASE 3 - SUB BASEMENT DEMOLITION PLAN X

ESP-104

ELECTRICAL - PHASE 1 - TEMPORARY BOILER

CONTROL ROOM

X

PD-302

PLUMBING PHASE 3 - SUB BASEMENT DEMOLITION PLAN

TEMPORARY BOILER LOCATION

X

MS-200 TEMPORARY BOILER, TRAILER AND UTILITIES LOCATION PLAN X ELD-201

ELECTRICAL - PHASE 2 - SUB-BASEMENT LIGHTING

DEMOLITION PLAN

X

PP-301U PLUMBING PHASE 3 - SUB BASEMENT UNDERSLAB PLAN X

MS-201 TEMPORARY BOILER, TRAILER AND UTILITIES LOCATION PLAN X ELD-202

ELECTRICAL - PHASE 2 - BASEMENT LIGHTING

DEMOLITION PLAN

X

PP-301 PLUMBING PHASE 3 - SUB BASEMENT PLAN X

MD-101 MECHANICAL - PHASE 1 - SUB-BASEMENT DEMOLITION PLAN X ELD-301

ELECTRICAL - PHASE 3 - SUB-BASEMENT LIGHTING

DEMOLITION PLAN

X

PP-302 PLUMBING PHASE 3 - BASEMENT FLOOR PLAN X

MD-103 MECHANICAL - PHASE 1 - LEVEL 1 DEMOLITION PLAN X ELD-302

ELECTRICAL - PHASE 3 - BASEMENT LIGHTING

DEMOLITION PLAN

X

PP-303 PLUMBING PHASE 3 - ROOF PLAN X

MD-201 MECHANICAL - PHASE 2 - SUB-BASEMENT DEMOLITION PLAN X EPD-100

ELECTRICAL - BOILER PLANT CONTROL ROOM

DEMOLITION

X

P-501 PLUMBING EXISTING WATER HEATERS RISER DIAGRAM X

MD-202 MECHANICAL - PHASE 2 - BASEMENT DEMOLITION PLAN X EPD-101

ELECTRICAL - BOILER PLANT - PHASE 1 -

SUB-BASEMENT DEMOLITION

X P-502

PLUMBING NEW STEAM WATER HEATERS RISER DIAGRAM AND

WATER HEATER DETAIL

X

MD-301 MECHANICAL - PHASE 3 - SUB-BASEMENT DEMOLITION PLAN X EPD-201

ELECTRICAL - PHASE 2 - SUB-BASEMENT POWER

DEMOLITION PLAN

X P-601 PLUMBING DETAILS X

MD-301A BOILER CONTROL ROOM - PHASE 3-DEMOLITION X EPD-202

ELECTRICAL - PHASE 2 - BASEMENT POWER

DEMOLITION PLAN

X P-602 PLUMBING DETAILS X

MD-302 MECHANICAL - PHASE 3 - BASEMENT DEMOLITION PLAN X EPD-301

ELECTRICAL - PHASE 3 - SUB-BASEMENT POWER

DEMOLITION PLAN

X P-701 PLUMBING SCHEDULES X

MD-303 MECHANICAL - PHASE 3 - LEVEL 1 DEMOLITION PLAN X EPD-302

ELECTRICAL - PHASE 3 - BASEMENT POWER

DEMOLITION PLAN

X

MD-304 MECHANICAL - PHASE 3 - ROOF DEMOLITION PLAN

X

EPD-303

ELECTRICAL - PHASE 3 - ROOF POWER DEMOLITION

PLAN

X

MH-103 MECHANICAL - PHASE 1- LEVEL 1 NEW WORK PLAN

X

EPD-511

ELECTRICAL - PHASE 1 - BOILER PLANT ONE-LINE

DIAGRAM - DEMOLITION

X

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990

200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768

100% CONSTRUCTION

DOCUMENTS

REPLACE MAIN BOILERS 528A8-17-805

Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208

06/05/2024

105 Central Street Stoneham, MA 02180 P: 781-275-6050

C U se rs

\h a u n g \D o c u m e n ts

\A lb a n y_ B o ile r_ M e c h

E le ct ri c a l U p g ra d e

V h a u n g

G H

V P

.r v t

/7

/2

:3

:3

P M

GI-002

DRAWING INDEX

HL HARevisions: Date:

DETAIL NUMBER

DRAWING NUMBER WHERE SHOWN

SECTION LETTER

DRAWING NUMBER WHERE DRAWN

POWER REQUIRED EQUIPMENT ABBREVIATION

EQUIPMENT NUMBER

BUILDING NO. WHERE EQUIPMENT IS LOCATED.

NON POWER REQUIRED EQUIPMENT ABBREVIATION

EQUIPMENT NUMBER

BUILDING NO. WHERE EQUIPMENT IS LOCATED.

FUEL OIL RETURN

FUEL OIL SUPPLYFOS

FOR

BOILER FEEDWATERBF

COLD (CITY) WATERCW

SOFT WATERSW

1. THE FIRST FIGURE OF DUCT SIZE INDICATES DIMENSION OF FACE SHOWN

OR INDICATED. DUCT SIZES ARE NET INSIDE DIMENSIONS.

2. FOR TYPICAL STEAM AND WATER PIPING CONNECTIONS TO EQUIPMENT,

SEE STANDARD EQUIPMENT DETAILS.

3. WATER PIPE CONNECTIONS TO AIR HEATING AND COOLING COILS SHALL

BE MADE TO PROVIDE COUNTER FLOW BETWEEN WATER AND AIR.

4. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS FOR EXACT

LOCATIONS OF CEILING DIFFUSERS, REGISTERS, AND GRILLES.

5. STEAM HEADER SET PRESSURE: 120 PSIG

6. ALTITUDE-BOILER ROOM FLOOR: 190 FT ABOVE SEA LEVEL

7. SEISMIC PROVISIONS REQUIRED - REFER TO STRUCTURAL DWGS FOR

MECHANIC PIPING SEISMIC BRACING REQUIREMENTS AND EQUIPMENT

ANCHORAGE REQUIREMENTS.

8. ALL PRESSURES LISTED ARE GAGE PRESSURE UNLESS OTHERWISE

NOTED

9. PIPING EXPANSION DELEGATED DESIGN SUBMITTAL. MECHANICAL

CONTRACTOR SHALL PROVIDE A DELEGATED DESIGN SUBMITTAL FOR

STEAM PIPING EXPANSION INCLUDING CONDENSATE; CALCULATIONS,

LOADS, FORCES, PIPE STRESSES, ANCHOR DESIGN, GUIDE LOCATIONS

AND EXPANSION LOOP & JOINTS. ALL CALCULATIONS SHALL BE STAMPED

AND SIGNED BY A STRUCTURAL ENGINEER REGISTERED IN STATE OF

NEW YORK. CONTRACTOR SHALL PROVIDE ALL MATERIALS, EQUIPMENT

REQUIRED FOR EXPANSION PROVISIONS.

10. PROVIDE REQUIRED VALVES AND PORTS PER THE LATEST BEI STANDARD

AND OPERATIONAL TESTING.

2 HR FIRE RATED WALL

F

AC

1-24

1S-34

CC

HOT WATER RETURN

QUICK-COUPLE HOSE CONNECTOR

GATE VALVE WITH GLOBE-VALVED BYPASS

PLUG VALVE

CONTROL VALVE (CV) - FLOAT-OPERATED

PRESSURE REDUCING VALVE (PRV)

WATER LEVEL CONTROLLER

FLOW METER

HOT WATER SUPPLY

FUSIBLE FIRE SAFETY VALVE

INVERTED BUCKET TRAP SET INCLUDING

PIPING ACCESSORIES SEE DETAIL

FLOAT AND THERMOSTATIC TRAP SET

INCLUDING PIPING ACCESSORIES SEE DETAIL

THERMOSTATIC TRAP SET INCLUDING

PIPING ACCESSORIES SEE DETAIL

THERMOSTATIC AIR VENT

LC

M

H4

H7

A

ABBREVIATIONS ABBREVIATIONS

LIMIT OF DEMOLITION

(WALL TYPE)

(WALL TYPE)

DN

DN

UP

UP

SUPPLY DUCT (UP & DOWN)

EXHAUST DUCT (UP & DOWN)

EXHAUST OR RETURN CEILING REGISTER OR GRILLE

EXHAUST OR RETURN BOTTOM REGISTER OR GRILLE

EXHAUST OR RETURN REGISTER OR TOP GRILLE

CONNECT NEW DUCT TO EXISTING DUCT

LINEAR SLOT DIFFUSER

BACK DRAFT DAMPER

BDD

10x8

STANDARD RADIUS ELBOW (LONG RADIUS)

NEW DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)

EXISTING DUCT TO REMAIN

FIRE DAMPER

FD

EXISTING DUCT TO BE REMOVED

HIGH PRESSURE STEAM CONDENSATE RETURN

HIGH PRESSURE STEAM (60 PSIG AND ABOVE)

HOT WATER HEATING SUPPLY

CONDENSATE PUMPED RETURN

LOW PRESSURE STEAM CONDENSATE RETURN

LOW PRESSURE STEAM (15 PSIG AND BELOW)

MEDIUM PRESSURE STEAM CONDENSATE RETURN

MEDIUM PRESSURE STEAM (16 PSIG THRU 59 PSIG)

VENT LINE

REFRIGERANT SUCTION

REFRIGERANT HOT GAS

REFRIGERANT LIQUID

CHILLED WATER SUPPLY

CHILLED WATER RETURN

DRAIN LINE

MAKE-UP WATER

HOT WATER HEATING RETURN

HPS

HPR

MPS

MPR

LPS

LPR

PR

HWS

HWR

V

CHR

RL

RS

RHG

CHS

MW

D

X EXISTING PIPE TO BE REMOVED

PIPING SYMBOLS

HWR

DIRECTION OF FLOW

SIDE CONNECTION

BOTTOM CONNECTION, 45° OR 90°

TOP CONNECTION, 45° OR 90°

UNION

RISE OR DROP IN PIPE

CAPPED OUTLET

PRESSURE GAGE

THERMOMETER

PIPE UP

PIPE DOWN

AUTOMATIC AIR VENT

AV

MANUAL AIR VENTMV

GENERAL PIPING SYMBOLS

BALL VALVE

GATE VALVE WITH 3/4" HOSE ADAPTER

CHECK VALVE

ANGLE GLOBE VALVE

BUTTERFLY VALVE

MODULATING CONTROL VALVE

TWO POSITION CONTROL VALVE

THREE-WAY MODULATING CONTROL VALVE

AUTOMATIC BALANCING CONTROL VALVE

PRESSURE SAFETY VALVE

GATE VALVE - THREADED/FLANGED

GLOBE VALVE - THREADED/FLANGED

PRESSURE REGULATING VALVE

THREE-WAY TWO POSITION CONTROL VALVE

WYE STRAINER (WITH BALL VALVE & HOSE CONNECTION)

FLEXIBLE CONNECTION

WATER BALANCE DEVICE

MODULATING CONTROL BUTTERFLY VALVE

CIRCUIT SETTER VALVE

WYE STRAINER WITH VALVED DRAIN AND QUICK-COUPLE

HOSE CONNECTOR

VALVE SYMBOLSGENERAL NOTES

HWS

DUCTWORK SYMBOLS

DRAWING SYMBOLS

A/E ARCHITECT / ENGINEER

AC AIR CONDITIONER

ACCU AIR-COOLED CONDENSING UNIT

ACD AUTOMATIC CONTROL DAMPER,

MODULATING

ACD-TP AUTOMATIC CONTROL DAMPER,

TWO POSITION

AD ACCESS DOOR

AF AFTER FILTER

AFCV AIR FLOW CONTROL VALVE

AFF ABOVE FINISHED FLOOR

AFMS AIR FLOW MEASURING STATION

AFW AIR FOIL WHEEL (FAN)

AHU AIR-HANDLING UNIT

AMP AMPERE

AP ACCESS PANEL

APD AIR PRESSURE DROP

AQST AQUASTAT

ARI AIR CONDITIONING AND

REFRIGERATION INSTITUTE AS AIR

SEPARATOR

ASHRAE AMERICAN SOCIETY OF HEATING

REFRIGERATION AIR CONDITIONING

ENGINEERS

BD BUTTERFLY DAMPER

BDD BACKDRAFT DAMPER

BHP BRAKE HORSEPOWER

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNIT PER HOUR

CAV CONSTANT AIR VOLUME

CD CEILING DIFFUSER

CFM CUBIC FEET PER MINUTE

CO CARBON MONOXIDE SENSOR

CO2 CARBON DIOXIDE

COP COEFFICIENT OF PERFORMANCE

CV CONSTANT VOLUME

D DAMPER - AUTOMATIC

DB DECIBELS

DDC DIRECT DIGITAL CONTROLS

DEG DEGREE

EA EXHAUST AIR

EF EXHAUST FAN

EX EXISTING

F FAHRENHEIT

FC FLEXIBLE CONNECTION

FD FIRE DAMPER

FM FLOW METER

FPM FEET PER MINUTE

FS FLOW SWITCH

FT FEET

FT WC FEET OF WATER COLUMN

GAL GALLONS

GPM GALLONS PER MINUTE

HOA HAND/OFF/AUTOMATIC

HP HORSEPOWER

HPDT HIGH PRESSURE DRIP TRAP

HPR HIGH PRESSURE RETURN (STEAM

CONDENSATE)

HPS HIGH PRESSURE SUPPLY (STEAM)

HW HOT WATER

HWR HEATING HOT WATER RETURN

HWS HEATING HOT WATER SUPPLY

HZ HERTZ

I/O INPUT/OUTPUT

IAQ INDOOR AIR QUALITY

IBT INVERTED BUCKET TRAP

ICF IN-LINE CENTRIFUGAL FAN

ID INSIDE DIAMETER

IN INCHES

IN WC INCH WATER COLUMN

IN-LB INCH-POUND

J INTENTIALLY LEFT BLANK

KW KILOWATT

KWH KILOWATT HOUR

LBS/HR POUNDS PER HOUR

LF LINEAR FOOT (FEET)

LPR LOW PRESSURE RETURN (STEAM

CONDENSATE)

MAX MAXIMUM

MBH 1,000 BTUH

MCA MINIMUM BRANCH CIRCUIT

AMPACITY

MHP MOTOR HORSEPOWER

MIN MINIMUM

MOV MOTOR OPERATED VALVE

MPR MEDIUM PRESSURE RETURN

(STEAM CONDENSATE)

MPS MEDIUM PRESSURE STEAM

MTD MEAN TEMPERATURE

DIFFERENCE

MVD MANUAL VOLUME DAMPER

NA NOT APPLICABLE

NC NOISE CRITERIA

NC NORMALLY CLOSED

NO NORMALLY OPEN

NOAA NATIONAL OCEANIC &

ATMOSPHERIC ADMINISTRATION

NOM NOMINAL

NPLV NON-STANDARD PART LOAD VALUE

NTS NOT TO SCALE

OA OUTSIDE AIR

OAD OUTDOOR AIR DAMPER

OAG OUTSIDE AIR GRILLE

OAI OUTSIDE AIR INTAKE

OD OUTSIDE DIAMETER

OSD OPEN SIGHT DRAIN

PD PRESSURE DROP

PG PRESSURE GAGE

PPM PARTS PER MILLION

PSI POUNDS PER SQUARE INCH

PSIG POUNDS PER SQUARE INCH GAGE

PSV PRESSURE SAFETY VALVE

REA RELIEF AIR

RELAD RELIEF AIR DAMPER

RHG REFRIGERANT HOT GAS

RL REFRIGERANT LIQUID LINE

RLA RUN LOAD AMPERE

RPM REVOLUTIONS PER MINUTE

RS REFRIGERANT SUCTION

RV RELIEF VALVE

SA SUPPLY AIR

SAD SOUND ATTENUATING DEVICE

SAT SUPPLY AIR TEMPERATURE

SCFM STANDARD CUBIC FEET PER

MINUTE

SD SMOKE DETECTOR

SD SUPPLY AIR DIFFUSER

SDPR SMOKE DAMPER

SEN SENSIBLE HEAT

SI SQUARE INCHES

SP STATIC PRESSURE

SPS STATIC PRESSURE SENSOR

SQ FT SQUARE FOOT (FEET)

SS STAINLESS STEEL

ST STEAM TRAP

T&PCV TEMPERATURE AND PRESSURE

CONTROL VALVE

TAB TESTING, ADJUSTING, BALANCE

TSP TOTAL STATIC PRESSURE

TSTAT THERMOSTAT

UH UNIT HEATER

V VALVE

VAV VARIABLE AIR VOLUME

VD VOLUME DAMPER

VFD VARIABLE FREQUENCY DRIVE

VI VIBRATION ISOLATOR

VPS VARIABLE PRIMARY SYSTEM

VSD VARIABLE SPEED DRIVE

W WATTS

SW SOFT WATER

VTR VENT THRU ROOF

CW COLD (CITY) WATER

DPS DIFFERENTIAL PRESSURE SENSOR

DIA DIAMETER

BF BOILER FEED

BF-1 BOILER FEED 1

BF-2 BOILER FEED 2

GV GATE VALVE

SV STEAM SAFETY RELIEF VALVE

XR EXISTING TO RE-LOCATE

XM EXISTING TO REMAIN

X EXISTING TO REMOVE

FOS FUEL OIL SUPPLY

FOR FUEL OIL RETURN

DR DIESEL RETURN

DS DIESEL SUPPLY

CTPD CONDENSATE TANK PUMP DISCHARGE

CTPS CONDENSATE TANK PUMP SUCTION

FOM FUEL OIL METER

WM WATER METER

SM STEAM METER

OFL OVERFLOW

PR PUMPED CONDENSATE RETURN

CONTROLS SYMBOLS

EPT ELECTRONIC TO PNEUMATIC TRANSDUCER

AT CARBON DIOXIDE TRANSMITTER

CARBON MONOXIDE TRANSMITTER

CO2

AT

CO

LTCP LOCAL TEMPERATURE CONTROL PANEL

HVAC HVAC CONTROL PANEL

ECC

INTEGRATE CONTROL POINT ON REMOTE GRAPHICS

WORKSTATION AT ENERGY CONTROL CENTER

TC

TEMPERATURE CONTROLLER. SEE SEQUENCE OF

OPERATION

VSMC VARIABLE SPEED MOTOR CONTROLLER

PC

PRESSURE CONTROLLER. SEE SEQUENCE OF

OPERATION

SC SPEED CONTROLLER. SEE SEQUENCE OF OPERATION

FC FLOW CONTROLLER. SEE SEQUENCE OF OPERATION

PSH PRESSURE SWITCH HIGH

FSH FLOW SWITCH HIGH

PSL PRESSURE SWITCH LOW

FSL FLOW SWITCH LOW

CONTROLS SYMBOLS

T ROOM THERMOSTAT/TRANSMITTER - WALL MOUNT

TT TEMPERATURE TRANSMITTER

M ROOM HUMIDISTAT (MOISTURE)/TRANSMITTER - WALL MOUNT

PT PRESSURE TRANSMITTER

TT TEMPERATURE TRANSMITTER, AVERAGING ELEMENT

FT FLOW TRANSMITTER

IT CURRENT TRANSMITTER

CT CONDUCTIVITY TRANSMITTER

SPS STATIC PRESSURE SENSOR

SD SMOKE DETECTOR

PDT PRESSURE DIFFERENTIAL TRANSMITTER

TSL TEMPERATURE SWITCH, LOW (FREEZESTAT)

HS HAND SWITCH (HAND-OFF-AUTO SWITCH)

ZC VALVE OR DAMPER POSITION CONTROLLER

LC LEVEL CONTROLLER

LT LEVEL TRANSMITTER

PDS PRESSURE DIFFERENTIAL SWITCH

TSH TEMPERATURE SWITCH, HIGH (FREEZESTAT)

LENGTH IN DUCT WHEN SPACE PERMITS.)

A

TEMPERATURE SENSING ELEMENT FOR

TRANSMITTING TEMPERATURE TO EMCS

(PROVIDE 12 INCHES [200mm] MINIMUM

SENSOR WITH AVERAGING ELEMENT TO TRANSMIT

TEMPERATURE TO EMCS

MOTOR STARTER

M ELECTRIC OPERATED CONTROL DAMPER/OR VALVE

LS LEVEL SWITCH

ESV EMERGENCY SHUTOFF VALVE

DT DRAFT GAUGE

DS DRAFT HIGH PRESSURE SWITCH

FS FLAME STENGTH

O2 OXYGEN CONTENT TRANSMITTER

SST START/STOP

DI DIGITAL INPUT

DO DIGITAL OUTPUT

AI ANALOG INPUT

AO ANALOG OUTPUT

CT CONDUCTIVITY TRANSMITTER

SCV STEAM CONTROL VALVE

CD CONTROL PANEL

TAV

S

EMERGENCY SWITCH

FIRE RATING SYMBOL

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990

200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768

100% CONSTRUCTION

DOCUMENTS

REPLACE MAIN BOILERS 528A8-17-805

Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208

06/05/2024

105 Central Street Stoneham, MA 02180 P: 781-275-6050

C U se rs

\h a u n g \D o c u m e n ts

\A lb a n y_ B o ile r_ M e c h

E le ct ri c a l U p g ra d e

V h a u n g

G H

V P

.r v t

/7

/2

:3

:3

P M

GI-003

GENERAL NOTESS, ABBREVIATIONS, AND

SYMBOLS

HL HARevisions: Date:

UP

DN

DN

DN

DN

DN

COGEN

ENCLSOURE

2 1

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990

200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768

100% CONSTRUCTION

DOCUMENTS

REPLACE MAIN BOILERS 528A8-17-805

Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208

06/05/2024

105 Central Street Stoneham, MA 02180 P: 781-275-6050

C U se rs

\h a u n g \D o c u m e n ts

\A lb a n y_ B o ile r_ M e c h

E le ct ri c a l U p g ra d e

V h a u n g

G H

V P

.r v t

/7

/2

:3

:3

P M

GI-004

MECHANICAL - EXISTING CONDITIONS -

PHOTOS

HL HA

1/16" = 1'-0"

MECHANICAL - SUB-BASEMENT EXISTING CONDITION

1/16" = 1'-0"

MECHANICAL - BASEMENT EXISTING CONDITION

1/16" = 1'-0"

MECHANICAL - ROOF EXISTING CONDITION

PHOTO 1: EXISTING PLUMBING EQUIPMENT TO REMAIN

PHOTO 2: EXISTING FO#6 TO BE DEMOLISHED

PHOTO 3: EXISTING CONDENSATE TANK TO BE DEMOLISHED

PHOTO 4: EXISTING FEEDWATER PUMPS TO BE DEMOLISHED

PHOTO 5: EXISTING CONDENSATE PUMPS TO BE DEMOLISHED

PHOTO 6: EXISTING WINTER BOILERS TO BE REPLACED

PHOTO 6: EXISTING SUMMER BOILER TO BE DEMOLISHED

PHOTO 8: EXISTING STEAM HEADER BOILER TO BE REPLACED

PHOTO 1: SECTION OF WALL TO BE OPEN

FOR RIGGING (LOOK FROM INSIDE)

PHOTO 2: SECTION OF WALL TO BE OPEN

FOR RIGGING (LOOK FROM OUTSIDE)

PHOTO 3: EXISTING DA TANK TO BE REPLACED

PHOTO 4: EXISTING DA TANK VENT TO BE REPLACED

PHOTO 5: EXISTING BOILER ECONOMIZER TO BE

DEMOLISHED

PHOTO 6: EXISTING OVERHEAD PIPING

PHOTO 1: EXISTING VENTILATION HOODS TO BE REPLACE WITH NEW

EXHAUST FANS

PHOTO 2: EXISTING EXHAUST FANS TO BE DEMOLISHED

PHOTO 3: ROOF LAYOUT

SUB-BASEMENT

BASEMENT

ROOF

Revisions: Date:

PHASE 1

TASK

STEAM

SHUTDOWN

ELECTRIC

SHUTDOWN

OTHER

SHUTDOWN

NOTES

PREPARE FOR EQUIPMENT INSTALLATION

PREPARE SITE FOR EQUIPMENT

INSTALLATION.

NO

INSTALL EROSION CONTROL.

SAW-CUT AND REMOVE PAVEMENT AND SIDEWALKS.

EXCAVATE AND DISPOSE OF EXCESS SOIL, STOCKPILE SOIL NEEDED FOR BACKFILLING.

INSTALL ELECTRICAL VAULTS.

INSTALL DRAIN PIPING.

INSTALL EQUIPMENT PAD FOR NEW TRANSFORMERS AND 15kV PRIMARY SWITCHES.

INSTALL UNDERGROUND CONDUIT SYSTEM BETWEEN NEW 15kV PRIMARY SWITCHES AND NEW PAD-MOUNTED

TRANSFORMERS.

INSTALL NEW DUCTBANK SYSTEM FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW 15kV PRIMARY SWITCHES.

BACKFILL SOIL AND INSTALL PAVEMENT PATCH AND SIDEWALKS.

INSTALL FENCE AND GATES.

INSTALL TOPSOIL, GRASS SEED, AND GRAVEL.

BOILER PLANT:

PREPARE FOR INSTALLATION OF NEW

INTERIOR EQUIPMENT

YES

INSTALL STANDBY EMERGENCY DISTRIBUTION BOARD DP-52D19 FED FROM EXISTING PARALLEL GENERATOR

DISTRIBUTION BOARD.

RE-FEED EXISTING PANEL '14-HCC-IL-LS' FROM NEW STANDBY EMERGENCY DISTRIBUTION BOARD 'DP-52D19'.

INSTALL TEMPORARY AUTOMATIC TRANSFER SWITCH U2-ATS-TEMP AND NEW STANDBY EMERGENCY DISTRIBUTION

BOARD 'CP-EDP2'.

INSTALL TEMPORARY BOILERS AND ASSOCIATED CONTROL ROOM PANEL.

INSTALL TEMPORARY POWER TO EXISTING BOILER PLANT MCC FROM EXISTING CHILLER PLANT DISTRIBUTION BOARD

'CSB'.

DEMOLISH EXISTING PAD-MOUNTED TRANSFORMERS AND 15kV SWITCHES.

INSTALL NEW BOILER PLANT PANELS 'BP-H4A', 'BP-H4B, 'BP-P2A', 'BP-P2B' AND RELATED TRANSFORMERS. PROVIDE TEMPORARY FEEDER FROM EXISTING BOILER PLANT MOTOR CONTROL CENTER TO ENABLE BOILER PLANT MECHANICAL EQUIPMENT REPLACEMENT TO COMMENCE PRIOR TO ARRIVAL OF NEW BOILER PLANT SWITCHGEAR.

NOTE: THE CHILLER PLANT SCOPE OF WORK INDICATED BELOW SHALL NOT COMMENCE UNTIL THE BOILER PLANT SERVICE UPGRADE IS 100% COMPLETE, TESTED AND ACCEPTED BY THE VAMC .

CHILLER PLANT:

PREPARE FOR INSTALLATION OF NEW

INTERIOR EQUIPMENT.

YES

REFEED CRITICAL CHILLER PLANT LOADS (HWP-7 & HWP-8) FROM NEW BOILER PLANT DISTRIBUTION SYSTEM.

REFEED EXISTING MOTOR CONTROL CENTER 'EMCC' FROM NEW BOILER PLANT DISTRIBUTION SYSTEM.

DEMOLISH EXISTING CHILLER ATS #1 AND ATS#2.

EQUIPMENT INSTALLATION

BOILER PLANT:

INSTALL EXTERIOR EQUIPMENT AND

RELATED FEEDERS.

YES

INSTALL NEW PAD-MOUNTED TRANSFORMERS.

INSTALL NEW 15kV PRIMARY SWITCHES.

REMOVE EXISTING 15kV FEEDER R639.

INSTALL NEW 15kV FEEDER R134 FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.

REMOVE EXISTING 15kV FEEDER R538.

INSTALL NEW 15kV FEEDER R235 FROM CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.

BOILER PLANT:

INSTALL INTERIOR EQUIPMENT YES INSTALL NEW SWITCHBOARD 'BP-SWBD' AND ASSOCIATED AUTOMATIC TRANSFER SWITCHES.

CHILLER PLANT:

INSTALL EXTERIOR EQUIPMENT AND

RELATED FEEDERS.

YES

INSTALL NEW PAD-MOUNTED TRANSFORMERS.

INSTALL NEW 15kV PRIMARY SWITCHES.

REMOVE EXISTING 15kV FEEDER R639.

INSTALL NEW 15kV FEEDER R639 FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.

REMOVE EXISTING 15kV FEEDER R538.

INSTALL NEW 15kV FEEDER R538 FROM CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.

CHILLER PLANT:

INSTALL INTERIOR EQUIPMENT

YES

INSTALL NEW SWITCHBOARD '52-SWBD'.

INSTALL NEW DISTRIBUTION BOARD '52-D4SB'.

COMMISSIONING AND TESTING

COMMISSIONING AND TESTING NO COMMISSION AND TESTING NEW EQUIPMENT AND ASSOCIATED FEEDERS.

REMOVAL OF EXISTING CHILLER PLANT SWITCHYARD EQUIPMENT.

REMOVE EXISTING CHILLER PLANT

SWITCHYARD EQUIPMENT

REMOVE EXISTING PAD-MOUNTED TRANSFORMERS

REMOVE EXISTING15kV SWITCHGEAR 'CHP'.

REMOVE EXISTING 5kV SWITCHGEAR.

REMOVE EXISTING SWITCHBOARD 'CSB'.

REMOVE FENCED ENCLOSURE AND PAD.

SECURE NEW CHILLER PLANT SWITCHYARD

INSTALL FENCE NO INSTALL FENCED ENCLOSURE AT NEW CHILLER PLANT EQUIPMENT YARD.

REMOVAL OF EXISTING HVAC EQUIPMENT IN CHILLER PLANT.

REMOVE EXISTING PRV-1 ENTIRELY NO NO

UNIT

HEATERS

PRV-1 SERVES HX-1 & 2, AND UNIT HEATER IN SIDE CHILLER ROOMS

REMOVE EXISTING HX-1& 2 ENTIRELY NO NO NO HX-1 & 2 ARE CURRENTLY NOT IN USE

REMOVE CONDENSATE PUMP CP-1

ENTIRELY

NO NO NO CP-1 IS CURRENTLY NOT IN USE. HAND CP-1 TO VA

REMOVE AND RECONNECT LPS/HPR LINES

SERVING UNIT HEATERS.

NO NO UNIT HEATER

RELOCATE 5"Ø HWS/HWR FROM COGEN NO NO YES COGEN HWS/R WORK WILL ONLY HAPPEN IN THE SUMMER. ALL CHILLER POWER WORK TO BE DONE OCT-MAR

REPLACE STEAM TRAPS ON EXISTING

PRV-2 & 3

YES NO NO SHORT TERAM

GENERAL NOTES:

1. CONTRACTOR TO COORDINATE ALL SHUTDOWNS REQUIREMENT IN WRITING WITH THE VA COR AT LEAST FOUR WEEKS IN ADVANCE.

2. THE CONSTRUCTION PHASING SEQUENCE IS MEANT AS A DESIGN INTENT. CONTRACTOR IS RESPONSIBLE FOR PROVIDING A DETAILED STEP BY STEP CONSTRUCTION PHASING

SEQUENCE AND SUBMIT TO THE VA COR AND A&E FOR APPROVAL.

3. IN CASE OF ANY DISCREPANCIES BETWEEN THE NARRATIVE BELOW, DRAWINGS OR SPECS, A RFI SHALL BE GENERATED BY THE CONTRACTOR TO THE DESIGN TEAM. THE NARRATIVE

BELOW MAY OR MAY NOT CONTAIN ALL THE DETAILS LISTED ELSEWHERE ON THE DRAWINGS/SPECS, REFER TO DRAWINGS/SPECS FOR MORE INFORMATION.

4. CONTRACTOR TO COORDINATE WITH LOCAL DIESEL DELIVERY COMPANIES TO ENSURE THAT FUEL DELIVERY TRACKS AREA AVAILABLE ON STANDBY TO ENSURE THAT FUEL OIL IS

AVAILABLE AT ALL TIMES TO FILL THE EXISTING GENERATOR BELLY TANKS DURING SHUTDOWNS.

5. DEDUCT ALTERNATES

5.1. #1: EXISTING 15KV FEEDERS R538 AND R639 FROM THE CAMPUS 15KV SWITCHGEAR TO EXISTING MANHOLE EMH-2 SHALL BE RETAINED FOR RE-USE. SPLICE THE EXISTING 15KV FEEDERS IN AN ABOVE GRADE ENCLOSURE AND EXTEND TO THE NEW 15KV SWITCHES IN 4”C(CONCRETE ENCASED DUCTBANK).

5.2. #2: EXISTING 15KV FEEDERS R538 AND R639 SHALL BE DISCONNECTED/REMOVED. RELATED CONDUIT SHALL BE RETAINED FOR RE-USE. PROVIDE NEW 4”C (CONCRETE ENCASED DUCTBANK) FROM EXISTING MANHOLE EMH-2 TO THE NEW PRIMARY SWITCHES. INSTALL NEW FEEDERS R538 AND R639 IN THE EXISTING/REWORKED DUCTBANK SYSTEM FROM THE

15KV CAMPUS SWITCHGEAR TO THE NEW PRIMARY SWITCHES.

PHASE 0 - MEDIUM VOLTAGE INFRASTRUCTURE UPGRADE

THE INTENT OF PHASE 0 IS TO INSTALL NEW TRANSFORMER AND 15kV PRIMARY SWITCHES FOR CHILLER PLANT.

PHASE 0 WORK INCLUDES:

1. INSTALL EQUIPMENT PADS FOR NEW TRANSFORMERS AND 15kV PRIMARY SWITCHES.

2. INSTALL UNDERGROUND CONDUIT SYSTEM BETWEEN NEW 15kV PRIMARY SWITCHES AND NEW PAD-MOUNTED TRANSFORMERS.

3. INSTALL NEW DUCTBANK SYSTEM FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW 15kV PRIMARY SWITCHES.

4. PROVIDE TEMPORARY POWER FOR EXISTING CHILLER PLANT PUMPS P7 AND P8.

5. INSTALL HOUSEKEEPING PADS FOR NEW SWITCHBOARD '52-CHP.

6. INSTALL SWITCHBOARD '52-SWBD.

7. INSTALL SECONDARY FEEDERS FROM PAD-MOUNTED TRANSFORMERS TO NEW SWITCHBOARD '52-SWBD'.

8. RE-FEED CHILLER #1 AND CHILLER #2 FROM NEW SWITCHBOARD '52-SWBD'.

9. RE-FEED EXISTING SWITCHBOARD '52-CHP' FROM NEW SWITCHBOARD '52'SWBD'.

10. INSTALL NEW DISTRIBUTION BOARD '52-D4SB' AND RELATED FEEDER.

11. RE-FEED EXISTING LOADS FROM EXISTING SWITCHBOARD '52-CHP' TO NEW DISTRIBUTION BOARD '52-D4SB'.

12. RE-FEED CHILLER #1 AND #2 TO NEW SWITCHBOARD '52-SWBD'.

13. REMOVE EXISTING PAD-MOUNTED TRANSFORMERS REMOVE EXISTING15kV SWITCHGEAR 'CHP'.

14. REMOVE EXISTING 5kV SWITCHGEAR.REMOVE EXISTING SWITCHBOARD 'CSB'.

15. REMOVE FENCED ENCLOSURE.

16. PROVIDE NEW FENCED ENCLOSURE FOR NEW OUTDOOR EQUIPMENT.

17. PROVIDE TEMPORARY FENCING AS NEEDED TO MAINTAIN SITE SECURITY.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990

200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768

100% CONSTRUCTION

DOCUMENTS

REPLACE MAIN BOILERS 528A8-17-805

Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208

06/05/2024

105 Central Street Stoneham, MA 02180 P: 781-275-6050

C U se rs

\h a u n g \D o c u m e n ts

\A lb a n y_ B o ile r_ M e c h

E le ct ri c a l U p g ra d e

V h a u n g

G H

V P

.r v t

/7

/2

:3

:3

P M

GI-005

CONSTRUCTION PHASING PLAN AND

SHUTDOWN REQUIREMENTS

ND HLRevisions: Date:

PHASE 2

TASK

STEAM

SHUTDOWN

ELECTRIC

SHUTDOWN

OTHER

SHUTDOWN

NOTES

TEMPORARY POWER

SETUP TEMPORARY POWER NO YES

"SEE

NOTES"

SETUP TEMPORARY POWER

1. INSTALL NEW DISTRIBUTION BOARD DP-14A-HCC'.

2. REMOVE EXISTING 200A BREAKER 52D19 IN GENERATOR PARALLELING SWITCHGEAR AND RELATED FEEDER

POWERING PANEL '14-L-LS'.

3. INSTALL NEW 1000A BREAKER 52D19 IN GENERATOR PARALLELING SWITCHGEAR.

4. INSTALL NEW FEEDER FROM BREAKER 52D19 TO NEW DISTRIBUTION BOARD 'DP-14A-HCC'.

5. RE-FEED EXISTING PANEL '14A-L-LS' FROM NEW DISTRIBUTION BOARD 'DP-14A-HCC'.

6. INSTALL NEW ATS-CP-EDP2 AND DISTRIBUTION BOARD 'CP-EDP2'.

7. INSTALL FEEDERS TO TEMPORARY BOILERS #1 AND #2.

8. INSTALL TRANSFORMER AND PANEL AT TEMPORARY BOILER CONTROL ROOM.

9. INSTALL NEW PANEL CP-ELP1 AND RELATED TRANSFORMER.

10. SETUP TEMPORARY FEEDER TO MAKEUP AIR UNIT

11. SETUP TEMPORARY FEEDERS TO DOMESTIC HOT WATER HEATERS

12. SETUP TEMPORARY FEEDERS TO SUMMER BOILER AND WINTER BOILER FUEL OIL PUMPS

13. SETUP TEMPORARY FEEDERS TO NEW CONDENSATE STORAGE TANK AND PUMPS

14. SETUP TEMPORARY FEEDERS TO NEW DOMESTIC HOT WATER HEATERS AND STEAM CONDENSATE PUMPS

15. SETUP 120V FEED TO EXISTING CONTROL ROOM

16. SETUP TEMPORARY FEEDS TO EXISTING COMPRESSORS

TEMPORARY PROTECTION FOR AIR COMPRESSORS

PROVIDE TEMPORARY PROTECTION FOR

AIR COMPRESSORS

NO NO NO PROVIDE TEMPORARY PARTITIONS. USE EXISTING FAN FOR EXHAUST

PROVIDE LEAD/LAG CONTROLS FOR

EXISTING COMPRESSORS

NO NO

REMOVAL OF EXISTING #6 DIESEL PUMPS

REMOVE # 6 FUEL OIL PUMPS/HEATERS NO NO NO CURRENTLY ABANDONED AND NOT IN USE

REMOVAL OF GAS CONNECTION TO #1 BOILER

DECOMMISSIONING BOILER B-1 AND

REMOVE NATURAL GAS BRANCH PIPING TO

BOILER B-11

NO NO YES

SHUTDOWN DOWN OF BOILER B-1

FOR FUTURE CONNECTION TO TEMPORARY BOILER. UTILIZE EXISTING ISOLATION VALVE TO BOILER #1 TO

ISOLATE NATURAL GAS

TEMPORARY BOILER HOOKUP

FUEL OIL NO NO NO

CROSS CONNECT SUMMER AND WINTER FUEL OIL PIPING TO ALLOW SUMMER BOILER FUEL OIL PUMPS TO

SERVE EXISTING BOILERS WHEN REPLACING WINTER BOILER FUEL OIL PUMPS.

INSTALL NEW WINTER FUEL OIL PUMPS AND EXTEND PIPING TO TEMPORARY BOILERS. PROVIDE TAPS AND

VALVE CONNECTIONS FOR NEW BOILERS INSTALLED AS PART OF PHASE 3.

NATURAL GAS NO NO NO EXTEND NATURAL GAS FROM BOILER #1 CONNECTION TO TEMPORARY BOILERS

COLD WATER NO NO YES

TAP INTO EXISTING COLD WATER SUPPLY IN CHILLER ROOM. EXTEND COLD WATER SUPPLY FROM EXISTING BACKFLOW PREVENTER IN CHILLER ROOM TO TEMPORARY BOILERS. THE CW SYSTEM SHUTDOWN WILL NEED TO BE TIMED WITH THE MAINTENANCE/TESTING OF EXISTING BACKFLOW PREVENTER. EXPECTED DURATION- 4

HOURS

EXTEND POWER TO TEMPORARY BOILERS NO NO NO NO MCC SHUTDOWN REQUIRED (ONLY INDIVIDUAL BREAKERS FEEDING EQUIPMENT AFFECTED)

STEAM YES NO NO

1. TAP 8"Ø PIPING FROM TEMPORARY BOILERS INTO EXISTING 8"Ø STEAM LINE LOCATED IN CHILLER PLANT.

2. PROVIDE 8"Ø HPS PIPING TO CROSS CONNECT EXISTING 8"Ø HPS LINE FROM CHILLER PLANT TO EXISTING

10"Ø HPS SERVING HOSPITAL.

3. CROSS CONNECT 6"Ø PIPING SERVING LAUNDRY TO EXISTING 6"Ø HPS SECONDARY HEADER.

4. CROSS CONNECT 4"Ø PIPING SERVING DA TANK PRV, MUA-1 PRV AND HPR HEATERS IN EXISTING 6"Ø

SECONDARY HEADER.

5. PROVIDE NEW DRIP TRAPS TO SECONDARY HEADER AND RUN TO EXISTING HPR LINE.

BOILER FEED (INSTALL NEW CONDENSATE

TANK)

YES NO NO

1. INSTALL NEW CONDENSATE RETURN TANK AND PUMPS IN PLACE OF OLD #6 DIESEL PUMPS.

2. TEMPORARILY RUN EXISTING BOILERS ON 100% MAKEUP. TEMPORARY MANAGEMENT OF CONDENSATE RETURN FROM HOSPITAL, BOILER PLANT, CHILLER PLANT SHALL BE PROVIDED BY THE CONTRACTOR IN COORDINATION WITH THE VA, INCLUDING BUT NOT LIMIT TO TEMPORARY DRAINAGE OF CONDENSATE AT ALL

SOURCES, AND EQUIPMENT LOCK OUT.

3. PROVIDE NEW CONDENSATE TANK HEADERS, LOW PRESSURE AND MEDIUM PRESSURE. CONNECT EXISTING

CONDENSATE RETURN LINES TO THE HEADERS RESPECTIVELY.

4. INSTALL NEW CONDENSATE PIPING SERVING TEMPORARY BOILERS, PROVIDE TAPS FOR FUTURE

CONNECTIONS TO NEW BOILERS AND FEED WATER PUMPS.

5. PROVIDE NEW MAKE-UP WATER FROM EXISTING WATER SOFTENER TO THE NEW TANK. PROVIDE A TEEs AND

VALVES FOR FUTURE CONNECTION TO NEW BLOWDOWN HEAT RECOVERY UNIT.

6. TEST NEW TANK AND PUMPS BY TEMPORARILY BYPASSING CONDENSATE PUMP DISCHARGE TO FLOOR DRAIN.

TEST AND OPERATE TEMPORARY BOILERS NO NO NO

1. TEST AND RUN ON 100% MAKEUP INITIALLY. BYPASS STEAM TO EXTERIOR DURING TESTING.

2. OPEN STEAM SUPPLY TO SYSTEM AND SLOWLY RETURN THE BOILER FEED BACK TO THE TEMPORAY BOILERS.

HOOK UP CONTROL ROOM

CW NO NO NO UTILIZE CW CONNECTION FOR TEMPORARY BOILERS

SEWER NO NO NA SEWER WILL BE PUMPED OUT ON A WEEKLY BASIS

ELECTRIC NO NO NO SEE TEMPORARY POWER SECTION. TEMPORARY POWER PROVIDED SO NO ASSOCIATED SHUTDOWN.

CENTRAL MONITORING (MED GAS, TANK

LEVELS, EMERGENCY GENERATOR, AIR

COMPRESSOR, GAS VALVES, DRYER,

FIRE/SECURITY MONITORING ....)

NO NO YES

ALL EQUIPMENT AND ALARMS IN BOILER PLAN TO BE MONITORED WILL BE MIRRORED TO THE CONTROLLERS IN THE TEMPORARY CONTROL ROOM . EXPECTED UNAVAILABILITY OF POINTS AT BMS- 4 HOURS. PROVIDE A NEW CONTROLLER INI CONTROL ROOM AND TIE TO ALC SYSTEM NETWORK FOR MONITORING AND ALARM

VA IT NO NO MINOR EXTENT ETHERNET CONNECTION FROM NETWORK SWITCH TO TEMPORARY CONTROL ROOM.

BMS NO NO MINOR

EXTEND DDC MONITORING FOR EXISTING AIR COMPRESSORS, GAS VALVE, DRYERS, FIRE/SECURITY

MONITORING. EXPECTED UNAVAILABILITY OF POINTS AT BMS- 4 HOURS

REMOVAL OF EXISTING CONDENSATE TANK AND PUMPS

REMOVE EXISTING CONDENSATE TANKS

AND PUMPS

NO NO NO REMOVAL TO ALLOW INSTALLATION OF NEW DHW HEATERS

REMOVAL OF EXISTING MUA-1 PRV AND REPLACEMENT OF HPS UNIT HEATERS

REPLACE EXISTING PRV SERVING MUA-1

AND REPLACE EXISTING HPS UNIT

HEATERS WITH LPS ONES

NO NO

YES,

SHUTDOWN

OF MUA-1

AND UNIT

HEATERS

OPEN WINDOWS FOR COMBUSTION AIR AND PROVIDE TEMPORARY HEAT IN EMERGENCY GENERATOR ROOM

AND SUMMER BOILER ROOM AS NEEDED

REMOVAL AND REPLACEMENT OF EXISTING FLASH TANK AND PIPING

REMOVE EXISTING FLASH TANK AND PIPING NO NO NO NEW FLASH TANK WILL BE INSTALLED.

INSTALL NEW DHW HEATERS

INSTALL NEW PRV AND HPS PIPING NO NO NO

CONNECT 6" HPS SERVING NEW PRV INTO EXISTING 6"HPS SECONDARY HEADER. PROVIDE TEE AND VALVE FOR FUTURE CONNECTION BACK TO PRIMARY HEADER. INSTALL NEW PRV NEAR THE DWHs

INSTALL NEW DHW HEATERS AND

CONDENSATE PUMPS

NO NO MINOR

CONNECT INTO EXISTING CW/HW PIPING. INSTALL NEW STEAM CONDENSATE PUMPS AND TIE CONNECTIONS TO NEW CONDENSATE TANK HEADER. MINOR SHUTDOWN OF EXISTING DHW SYSTEM- 2 -4 HOURS. COMMISSIONING

BY VA.

REMOVE EXISTING DHW HEATERS

REMOVE EXISTING DHW HEATERS NO NO NO

PROVIDE FREEZE PROTECTION IN BOILER ROOM AND BATHROOM

PROVIDE FREEZE PROTECTION IN BOILER

ROOM AND BATHROOM

NO NO NO PROVIDE STEAM HEATERS AS REQUIRED FOR TEMPORARY HEAT

PHASE 3

TASK

STEAM

SHUTDOWN

ELECTRIC

SHUTDOWN

OTHER

SHUTDOWN

NOTES

REMOVE EXISTING DA TANKS AND PUMPS

REMOVE EXISTING DA TANKS NO NO NO OPERATE EXISTING BOILERS AND TEMPORARY ON CONDENSATE STORAGE BYPASSING DA TANK CONNECTION

INSTALL NEW DA TANKS AND PUMPS

INSTALL NEW DA TANK AND PUMPS NO NO NO INSTALL IN PLACE OF EXISTING TANK

UPGRADE VENTILATION AND EXHAUST SYSTEM

REPLACE VFD OF EXISTING MUA-1.

EXISTING EXHAUST FANS AND INSTALL

NEW EXHAUST FANS ON ROOF

NO NO NO PROVIDE BMS HARDWIRED CONNECTIONS FOR CONENCTION TO NEW BOILERS

REMOVE SUMMER BOILER FUEL OIL PUMPS

REMOVE SUMMER BOILER PUMP NO NO NO REMOVE SUMMER BOILER FUEL OIL PUMPS AFTER THE DEMOLITION OF ALL EXISTING BOILERS.

REPLACE EXISTING DIESEL OIL PUMP MOTORS AND PROVIDE PIPING FOR STANDBY GENERATOR

REPLACE PUMP MOTORS IN THE DIESEL

PUMP IN TANK VAULT. UPGRADE DIESEL

CONTROL PANEL AS REQUIRED.

NO NO YES

DIESEL SYSTEM WILL BE SHUTDOWN FOR APPROXIMATELY 16 HOURS. EMERGENCY GENERATOR BELLY TANKS

WILL FILLED BY DIESEL TRUCK WHICH WILL BE MADE AVAILABLE WITHIN 30 MILES.

INSTALL NEW STANDBY GENERATOR AND APPURTENANCES

INSTALL NEW STANDBY GENERATOR,

LOUVERS, DAY TANK, DAMPERS, DIESEL

EXHAUST ETC

NO NO NO

CROSS CONNECT NEW GENERATOR TO

THE EXISTIING ELECTRICAL SYSTEM

NO YES NO

INTERCEPT EXISTING EMERGENCY FEED FROM THE EMRGENCY PARALLEL SWITCHBOARD. INTERCEPT NORMAL FEED FROM ATS-BREQ. PROVIDE NEW AUTOMATED TRANSFER SWITCH. EXPECTED SHUTDOWN 4-8 HOURS.

DEMOLISH EXISTING BOILER AND ANCILLARY EQUIPMENT

DEMOLISH EXISTING BOILERS, BLOWDOWN

TANK, PIPING, CONTROL SYSTEMS AS

CALLED ON DRAWINGS

NO NO NO

REMOVE EMERGENCY GAS SHUTOFF VALVE AND RELOCATE IT INSIDE THE PLANT

REMOVE EMERGENCY GAS SHUTOFF

VALVE AND RELOCATE IT INSIDE THE PLANT

NO NO

NATURAL

GAS

SHUTDOWN

EXPECTED SHUTDOWN- 8 HOURS. OPERATE TEMPORARY BOILERS ON FUEL OIL FROM PLANT DURING

RELOCATION

PAINT ALL SPECIFIED AREAS BEFORE NEW WORK BEGINS

PAINT ALL SPECIFIED AREAS BEFORE NEW

WORK BEGINS

NO NO NO

INSTALL NEW BOILERS AND EQUIPMENT

INSTALL NEW BOILERS AND EQUIPMENT AS

SHOWN ON PLANS

NO NO NO

INCLUDE ALL EQUIPMENT, PIPING, TIE-INS SHOWN ON PLANS. INTENT IS TO UPGRADE ELECTRIUCAL FEEDERS TO THE EXISTING MOTOR CONTROL CENTERS AS REQUIRED DURING DEMOLITION/CONSTRUCTION TO AVOID AN

ELECTRICAL SHUTDOWN WHEN THE TIME COMES TO HOOKUP NEW EQUIPMENT.

COMMISSION NEW BOILER PLANT

COMMISSION NEW BOILER PLANT NO NO NO

REMOVE TEMPORARY BOILERS

REMOVE TEMPORARY BOILERS AND

RESTORE SITE

NO NO NO

REMOVE EXISTING BOILER PLANT MCC

DEMOLISH EXISTING BOILER PLANT MCC.

REFEED BOILER PLANT PANELS 'BP--H4A', 'BP-H4B', BP-P2A', 'BP-P2B' AND RELATED TRANSFORMERS FROM NEW

BOILER PLANT SWITCHGEAR.

INSTALL CHILLER PLANT PERMANENT STANDBY POWER

INSTALL CHILLER PLANT PERMANENT

AUTOMATIC TRANSFER SWITCH.

YES

DISCONNECT TEMPORARY AUTOMATIC TRANSFER SWITCH 'U2-ATS-CP'.

INSTALL CHILLER PLANT PERMANENT AUTOMATIC TRANSFER SWITCH 'CP-ATS-EDP2'.

PROJECT CLOSEOUT

CLOSE OUT PROJECT PER VA

REQUIREMENTS

NO NO NO

GENERAL NOTES:

1. CONTRACTOR TO COORDINATE ALL SHUTDOWNS REQUIREMENT IN WRITING WITH THE VA COR AT LEAST FOUR WEEKS IN ADVANCE.

2. THE CONSTRUCTION PHASING SEQUENCE IS MEANT AS A DESIGN INTENT. CONTRACTOR IS RESPONSIBLE FOR PROVIDING A DETAILED STEP BY STEP CONSTRUCTION PHASING SEQUENCE AND SUBMIT

TO THE VA COR AND A&E FOR APPROVAL.

3. IN CASE OF ANY DISCREPANCIES BETWEEN THE NARRATIVE BELOW, DRAWINGS OR SPECS, A RFI SHALL BE GENERATED BY THE CONTRACTOR TO THE DESIGN TEAM. THE NARRATIVE BELOW MAY OR

MAY NOT CONTAIN ALL THE DETAILS LISTED ELSEWHERE ON THE DRAWINGS/SPECS, REFER TO DRAWINGS/SPECS FOR MORE INFORMATION.

4. CONTRACTOR TO COORDINATE WITH LOCAL DIESEL DELIVERY COMPANIES TO ENSURE THAT FUEL DELIVERY TRACKS AREA AVAILABLE ON STANDBY TO ENSURE THAT FUEL OIL IS AVAILABLE AT ALL

TIMES TO FILL THE EXISTING GENERATOR BELLY TANKS DURING SHUTDOWNS.

PHASE 2 - INSTALL TEMPORARY BOILERS

THE INTENT OF PHASE 2 IS TO INSTALL TEMPORARY BOILERS PRIOR TO DEMOLITION OF THE EXISTING BOILERS OR ANY PHASE 32 WORK SO THERE IS NO DISRUPTION TO FACILITY OPERATIONS.

THE BASIS OF DESIGN FOR THE TEMPORARY BOILERS IS POWERHOUSE. THE TEMPORARY BOILERS HAVE THE CAPACITY TO HANDLE THE FACILITY STEAM LOADS FOR BOTH WINTER AND SUMMER AS INDICATED ON THE DRAWINGS. EACH BOILER WILL HAVE THE CAPABILITY TO HAVE DUEL FUELS (NATURAL GAS AND #2 FUEL OIL) AND WILL HAVE A DA TANK, CHEMICAL SYSTEM AND OTHER ANCILLARY EQUIPMENT. PRESSURE RELIEF VALVE WILL BE INSTALLED ON 8” HPS IN CHILLER PLANT AND TIED INTO EXISTING 10” MAIN VENT STACK. PRESSURE RELIEF VALVE WILL BLOW OFF STEAM TO MAIN VENT

STACK DURING LOW SUMMER LOAD.

A CONTROL TRAILER WILL BE INSTALLED ADJACENT TO THE TEMPORARY BOILER TRAILERS. THE CONTROL TRAILER WILL CONTAIN SINK, CONTROLLERS, SCREENS AND A REST ROOM. THE REST ROOM AND

SINK WILL BE PUMPED OUT ON A WEEKLY BASIS.

PREPARATION WORK MUST BE CONDUCTED IN ORDER TO OPERATE THE TEMPORARY BOILERS. THE PREPARATION WORK INCLUDES:

1. UTILITY TIE-INS TO EXISTING FACILITY UTILITIES

2. MODIFICATION OF THE NATURAL GAS AUTOMATIC SHUT-OFF VALVE

3. REMOVE NATURAL GAS LINE TO BOILER #1.

4. INSTALL TEMPORARY NATURAL GAS SERVICE FOR TEMPORARY BOILERS.

5. INSTALL TEMPORARY WATER SERVICE FOR TEMPORARY BOILERS.

6. INSTALL NEW TEMPORARY MEDICAL GAS CABINETS AND ALARMS IN TEMPORARY CONTROL ROOM.

7. MODIFICATION OF THE STEAM HEADER PIPING IN THE BOILER PLANT.

8. MODIFICATION OF THE EXISTING CONDENSATE SYSTEM.

9. EXISTING DOMESTIC WATER HEATERS WILL BE REPLACED.

10. EXISTING AHU VFD WILL BE RELOCATED.

11. EXISTING COMPRESSORS WILL BE RETROFITTED WITH A LEAD/LAG CONTROLS. PRESSURE ALARM WILL BE EXTENDED TO THE TEMPORARY CONTROL ROOM.

12. EXISTING MAIN GAS VALVE ALARM WILL BE EXTENDED TO THE TEMPORARY CONTROL ROOM

13. EXISTING HIGH PRESSURE STEAM UNIT HEATERS WILL BE REPLACED.

14. EXISTING WINTER BOILER FUEL OIL PUMPS WILL BE REPLACED.

15. INSTALLATION OF PROTECTIVE PARTITIONS, A DUST BARRIER ENCLOSURE TO PROTECT EXISTING EQUIPMENT IN THE BOILER PLANT

THE UTILITIES INCLUDING NATURAL GAS, DIESEL FUEL OIL, CONDENSATE PIPING, ELECTRIC, DDC CONTROLS, AND WATER MUST BE CONNECTED TO THE TEMPORARY BOILERS. SHUTDOWNS WILL BE REQUIRED. IN ADDITION, THE STEAM PIPING FROM THE TEMPORARY BOILERS SHALL BE CONNECTED TO THE EXISTING STEAM HEADER VIA A CONNECTION POINT IN THE EXISTING CHILLER PLANT. THIS

CONNECTION POINT WILL PROVIDE STEAM TO THE FACILITY.

THE ELECTRIC FEEDS WILL BE FROM THE EXISTING PANELS AND SWITCHGEAR IN THE EXISTING BOILER PLANT. THE BUILDING AUTOMATION SYSTEM (BAS) AND OTHER COMMUNICATIONS WILL BE EXTENDED FROM THE EXISTING BOILER PLANT TO THE TEMPORARY BOILER CONTROL ROOM. ALL FUNCTIONS OF THE CURRENT CONTROL ROOM AND HOSPITAL CRITICAL MONITORING SYSTEMS (MEDICAL GASES, EMERGENCY GENERATOR STATUS, TANKS.) NEED TO BE REPLICATED TO THE TEMPORARY CONTROL ROOM.

THE NATURAL GAS MAIN LINE WILL REQUIRE MODIFICATION PRIOR TO PHASE 2 WORK. A TEE WILL HAVE TO BE INSTALLED IN THE MAIN LINE AND THE EXISTING MANUAL SHUT OFF VALVE WILL REQUIRE RELOCATION TO INSIDE THE BOILER PLANT. THE EXISTING PLANT WILL REQUIRE A SWITCH OVER TO DIESEL FUEL OIL WHILE THE NATURAL GAS LINE IS MODIFIED.

THE CONDENSATE SYSTEM WILL BE MODIFIED SO THE FACILITY CONDENSATE CAN BE TRANSFERRED TO THE TEMPORARY BOILERS. THE NEW CONDENSATE TANK WILL BE LOCATED AT THE EXISTING FUEL OIL #6 PUMPING AREA WITHIN THE BOILER PLANT. THE PIPING FROM THE NEW CONDENSATE TANK WILL BE PIPED TO THE TEMPORARY BOILERS WITH SEVERAL BRANCHES (VALVED AND CAPPED) FOR FUTURE CONNECTIONS TO BOILER FEED SYSTEM IN PHASE 2. EXISTING CONDENSATE TANK AND PUMPS WILL BE DEMOLISHED AFTER NEW CONDENSATE TANK, PUMPS AND PIPING ARE INSTALLED AND

COMMISSIONED.

THE FOLLOWING PIPE MODIFICATIONS WILL NEED TO BE MADE PRIOR TO PHASE 2 INCLUDING STEAM CONNECTION IN THE CHILLER ROOM TO TEMPORARY BOILER, MODIFYING THE CONNECTION TO HOSPITAL STEAM BRANCH, MODIFYING THE CONNECTION TO LAUNDRY STEAM BRANCH, AND MODIFYING THE 4” CONNECTION TO DA TANK PRV. SIMILARLY, CONNECTIONS TO CONDENSATE RETURN LINES FROM HOSPITAL, MEDIUM PRESSURE DRIPS WILL REQUIRE MODIFICATION. THE STEAM PIPING CONNECTIONS FROM THE TEMPORARY BOILERS TO THE HOSPITAL AND LAUNDRY BRANCHES WILL HAVE A TEE WITH SHUTOFF VALVES SO ONCE THE TEMPORARY BOILERS ARE OPERATING, THE EXISTING BOILERS CAN BE ISOLATED.

ONCE ALL THE UTILITIES HAVE BEEN TIED IN, THE TEMPORARY BOILERS WILL BE COMMISSIONED. THE TEMPORARY BOILERS MUST OPERATE FOR TWO WEEKS AFTER COMMISSIONING TO ENSURE THE

BOILERS ARE OPERATING WITHOUT ISSUES BEFORE THE EXISTING BOILERS ARE DEMOLISHED.

EXISTING DOMESTIC WATER HEATERS WILL BE REPLACED WITH NEW IN THIS PHASE. PROVIDE NEW PRV AND CONNECT TO 6” HPS SECONDARY HEADER TO PROVIDE LOW PRESSURE STEAM FOR NEW

DWHS.

EXISTING AHU VFD WILL BE RELOCATED. ALSO EXISTING AIR COMPRESSORS WILL BE PROVIDED WITH THE DDC MONITORING AT THE TEMPORARY CONTROL ROOM.

REPLACE EXISTING HIGH PRESSURE STEAM UNIT HEATER WITH LOW PRESSURE. REPLACE PRV SERVING MUA-1 WITH HIGHER CAPACITY TO PROVIDE LOW PRESSURE STEAM FOR EXISTING MUA-1 AND NEW

UNIT HEATERS.

CROSS-CONNECT EXISTING SUMMER BOILER FUEL PIPING AND WINTER BOILER FUEL PIPING TO ALLOW SUMMER BOILER PUMP TO SERVE EXISTING AND TEMPORARY BOILERS DURING REPLACEMENT OF

WINTER BOILER PUMPS.

LASTLY, PROTECTIVE PARTITIONS, A DUST BARRIER ENCLOSURE WILL BE INSTALLED TO PROTECT EXISTING EQUIPMENT IN THE PLANT THAT ARE NOT SLATED FOR DEMOLITION SO THAT BOILER PLANT

PERSONNEL CAN SERVICE THIS EQUIPMENT DURING CONSTRUCTION.

PHASE 3: (NEW WORK)

PHASE 3 CANNOT COMMENCE UNTIL PHASE 2 WORK HAS BEEN COMPLETED AND ACCEPTED BY THE VA. THE GC WILL RECEIVE A NOTICE TO PROCEED TO PHASE 3 ONCE PHASE 2 WORK IS ACCEPTED BY

THE VA.

THIS PHASE INCLUDES THE DEMOLITION OF EXISTING EQUIPMENT NOT DEMOLISHED DURING PHASE 2 AND INCLUDES THE INSTALLATION OF NEW BOILERS, WATER HEATERS, AND RELATED EQUIPMENT. A NEW STANDBY GENERATOR WILL ALSO BE INSTALLED DURING PHASE 3. THE EXISTING CHIMNEY WILL BE REUSED.

THE FOLLOWING EXISTING EQUIPMENT IS TO BE REMOVED FROM THE BOILER PLANT DURING PHASE 3:

1. (3) EXITING 1000 HP WATER TUBE BOILERS WITH ECONOMIZERS

2. (1) 400 HP SUMMER FIRETUBE BOILER

3. DEAERATOR TANK AND PUMPS

4. BLOWDOWN TANK

5. DIESEL FUEL OIL PUMPS (SERVING 400 HP SUMMER BOILER)

6. DIESEL FUEL OIL PUMPS (SERVING EMERGENCY GENERATORS)

7. CHEMICAL FEED SYSTEM

8. STEAM HEADER PIPING

9. NATURAL GAS METER

10. ADVANCED STEAM METERS

11. CIRCULAR CHART RECORDERS, CONTROLLERS LOCATED IN THE CONTROL ROOM

12. EXISTING WATER HEATERS (AFTER INSTALLATION OF NEW WATER HEATERS)

THE FOLLOWING DEMOLITION WORK IN THE EXISTING INTERIOR SPACE WILL ALSO TAKE PLACE DURING PHASE 3:

1. GENERATOR ROOM: DEMOLISH PORTIONS OF EAST AND WEST WALLS FOR RIGGING AND NEW AIR INTAKE LOUVERS

2. BOILER ROOM: DEMOLISH THE EXISTING WINDOW AND PORTION OF WEST WALL AND SOME RAILING AT THE CATWALK BELOW THE EXISTING WINDOW FOR NEW BOILER RIGGING WORK.

3. CONTROL ROOM: DEMOLISH THE EXISTING CEILING AND LIGHTING

4. ROOF: COORDINATE WITH MEP FOR REMOVING THE FANS, VENT PIPING, DOMESTIC WATER HEATERS AND STACKS, AND ROOF PENETRATION WORK

ONCE THE EQUIPMENT IS DEMOLISHED AND PRIOR TO RIGGING IN THE NEW BOILERS AND RELATED EQUIPMENT, THE PLANT INSIDE WALLS SHALL BE PAINTED AND SECTIONS OF MASONRY REPOINTED.

AFTER PAINTING AND REPOINTING, THE BOILERS AND RELATED EQUIPMENT CAN BE INSTALLED. IN ORDER TO RIG IN THE NEW EQUIPMENT, CERTAIN SECTIONS OF THE EXISTING MASONRY WALLS AND WINDOWS IN THE BOILER PLANT WILL REQUIRE MODIFICATION SO THE NEW BOILERS CAN BE RIGGED INTO THE BUILDING. EXISTING UTILITIES ON THE WALL WILL HAVE TO BE RELOCATED. ONCE THE NEW BOILERS HAVE BEEN RIGGED INTO THE BOILER PLANT, THE WALL OPENING SHALL BE CLOSED WITH NEW AIR INTAKE LOUVER.

PATCHING THE ROOF OF THE ROOM OPENING FROM DEMOLITION WORK WHERE IS NOT USED FOR INSTALLATION OF NEW PIPING AND NEW STACKS. TEHER ARE SOME NEW ARCHITECTURAL WORK IN THE UPGRADE CONTROL ROOM INCLUDING THE NEW CEILING OF A SUSPENDED TILE SYSTEM, NEW ROOF DECKING AS WELL AS MEP WORK. ANOTHER NEW WORK WILL BE REQUIRED AT THE EXISTING OPENING BETWEEN MECHANIAL ROOM AND CHIMNEY. A NEW BREECHING OF 3-DUCT SYSTEM WILL REPLACE THE EXISTING SINGLE DUCT. SOME OF NEW WORK WILL BE SCHEDULED IN THIS AREA INCLUDING, NEW

STRUCTURAL FRAMING OPENING TO PROTECT THE NEW DUCTS, A NEW ACCESS PANEL AND WALL INFILL.

THE CATWALKS WILL BE INSTALLED AFTER THE BOILERS ARE IN PLACE.

IT SHOULD BE NOTED WHILE THE DIESEL FUEL OIL PUMPS SERVING EMERGENCY GENERATOR ARE BEING REMOVED, PROVISIONS MUST BE MADE TO PROVIDE FUEL OIL TO THE EXISTING EMERGENCY GENERATOR FUEL OIL USING BELLY TANKS. THE CONTRACTOR WILL CONTRACT WITH A FUEL OIL PUMPING COMPANY LOCATED WITHIN A 30 MILE RADIUS TO ENSURE FUEL OIL IS READILY AVAILABLE.

ONCE THE NEW BOILER PLANT AND RELATED SYSTEM ARE OPERATING, THE SYSTEMS SHALL BE COMMISSIONED.