2- Albany General - stamped.pdf
PDF 10 MB Posted
- Attached to
- Z1DA--528A8-17-805 REPLACE MAIN BOILERS Federal contract opportunity
- Solicitation number
- 36C24224B0047
About this file
This document is a Scope of Work for a federal construction contract opportunity to replace the main boilers at the Albany VAMC hospital. The project includes replacing three 900 HP dual fuel steam boilers from 1978 with temporary 1,000 BHP dual fuel steam boilers and a newer 400 HP fire-tube steam boiler. The work will be completed in three phases: 1) Replace electrical equipment and install new switchgear, 2) Install the temporary boilers and associated infrastructure, and 3) Remove the old boilers and install the new boilers. The contractor must use the Autodesk Build Construction cloud platform for project management and collaboration. The project must be substantially complete within 730 calendar days of the notice to proceed. The contracting agency is the Department of Veterans Affairs, Veterans Health Administration, Veterans Integrated Service Network 2.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Veterans Affairs
Replace Main Boilers, 528A8-17-805Project Name:
Project Address: Samuel S. Stratton VAMC
113 Holand Ave., Albany, New York 12208
SERVICE ALLEY
MAIN BOILER PLANT
CHILLER PLANT
CHP
SUMMER
BOILER
ARF
AHUS
TANK VAULT
ROOF
GROUND
BUILDING
GROUND FLOOR
EQUIP SHED
100% CONSTRUCTION DOCUMENTS
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768
100% CONSTRUCTION
DOCUMENTS
REPLACE MAIN BOILERS 528A8-17-805
Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208
06/05/2024
105 Central Street Stoneham, MA 02180 P: 781-275-6050
C U se rs
\h a u n g \D o c u m e n ts
\A lb a n y_ B o ile r_ M e c h
E le ct ri c a l U p g ra d e
V h a u n g
G H
V P
.r v t
/7
/2
:3
:3
P M
GI-001
COVER PAGE
HL HA
AREA OF WORK
Revisions: Date:
DRAWING INDEX
DRAWING
NUMBER
DRAWING TITLE
INCLUDED
IN 90%
DRAWING
NUMBER
DRAWING TITLE
INCLUDED
IN 90%
DRAWING
NUMBER
DRAWING TITLE
INCLUDED
IN 90%
GI-001 COVER PAGE X MH-201
MECHANICAL - PHASE 2 - SUB-BASEMENT NEW
WORK PLAN
X
EPD-512
ELECTRICAL - PHASE 1 - CHILLER PLANT ONE-LINE DIAGRAM -
DEMOLITION
X
GI-002 DRAWING INDEX X MH-202
MECHANICAL - PHASE 2- BASEMENT NEW WORK
PLAN
X
EPD-520
ELECTRICAL- PHASE 2 - BOILER PLANT ONE-LINE DIAGRAM -
DEMOLITION
X
GI-003 GENERAL NOTES ABBREVIATIONS AND SYMBOLS X MH-203 MECHANICAL - PHASE 2- LEVEL 1 NEW WORK PLAN X
EPD-530
ELECTRICAL - PHASE 3 - BOILER PLANT ONE-LINE DIAGRAM -
DEMOLITION
X
GI-004 MECHANICAL - EXISTING CONDITION - PHOTOS X MH-204 MECHANICAL - PHASE 2- ROOF NEW WORK PLAN X
EPD-531
ELECTRICAL - PHASE 3 - BOILER PLANT ONE-LINE DIAGRAM
-TEMPORARY BOILERS DEMOLITION
X
GI-005 CONSTRUCTION PHASING PLAN AND SHUT DOWN REQUIREMENTS X MH-300 MECHANICAL - PHASE 3-RIGGING PLAN X
EPSD-101
ELECTRICAL PHASE 1 - SITE PLAN - CHILLER PLANT AND BOILER
PLANT SERVICE UPGRADE -DEMOLITION
X
GI-006 CONSTRUCTION PHASING PLAN AND SHUT DOWN REQUIREMENTS X MH-301
MECHANICAL - PHASE 3- SUB-BASEMENT NEW
WORK PLAN
X
EL-201
ELECTRICAL - PHASE 2 - SUB-BASEMENT LIGHTING NEW WORK
PLAN
X
MH-301A BOILER CONTROL ROOM - PHASE 3-NEW WORK X EL-202 ELECTRICAL - PHASE 2 - BASEMENT LIGHTING NEW WORK PLAN X
AG-001 ARCHITECTURAL GENERAL NOTES, ABBREVIATIONS, AND SYMBOLS X MH-302
MECHANICAL - PHASE 3- BASEMENT NEW WORK
PLAN
X
EL-301
ELECTRICAL - PHASE 3 - SUB-BASEMENT LIGHTING NEW WORK
PLAN
X
AD-201 ARCHITECTURAL PHASE 2 - SUB-BASEMENT DEMOLITION PLAN X MH-303 MECHANICAL - PHASE 3- LEVEL 1 NEW WORK PLAN X EL-302 ELECTRICAL - PHASE 3 - BASEMENT LIGHTING NEW WORK PLAN X
AD-301 ARCHITECTURAL PHASE 3 - SUB-BASEMENT DEMOLITION PLAN X MH-304 MECHANICAL - PHASE 3- ROOF NEW WORK PLAN X EP-100 ELECTRICAL - BOILER PLANT CONTROL ROOM NEW WORK X
AD-302 ARCHITECTURAL PHASE 3 - BASEMENT DEMOLITION PLAN X MH-401 MECHANICAL PHASE 2 - SECTION AND ISO VIEWS X EP-101 ELECTRICAL - PHASE 1 - SUB-BASEMENT NEW WORK PLAN X
AD-303 ARCHITECTURAL PHASE 3 - ROOF DEMOLITION PLAN X MH-402 MECHANICAL PHASE 2 - SECTION AND ISO VIEWS X EP-102 ELECTRICAL - PHASE 1 - BASEMENT NEW WORK PLANS X
AE-201 ARCHITECTURAL PHASE 2 - SUB-BASEMENT NEW WORK PLAN X MH-403 MECHANICAL PHASE 3 - SECTION AND ISO VIEWS X
EP-103
ELECTRICAL - PHASE 1 - OVERALL SUB-BASEMENT POWER NEW
WORK PLAN
X
AE-301
ARCHITECTURAL PHASE 3 - SUB-BASEMENT NEW WORK PLAN AND
CONTROL ROOM RCP
X MH-404 MECHANICAL PHASE 3 - SECTION AND ISO VIEWS
X
EP-201
ELECTRICAL - PHASE 2 - SUB-BASEMENT POWER NEW WORK
PLAN
X
AE-302 ARCHITECTURAL PHASE 3 - BASEMENT NEW WORK PLAN X MH-501 MECHANICAL PHASE 2 - PART PLANS X EP-202 ELECTRICAL - PHASE 2 - BASEMENT POWER NEW WORK PLAN X
AE-303 ARCHITECTURAL PHASE 3 - ROOF NEW WORK PLAN X MH-502 MECHANICAL PHASE 3 - PART PLANS X EP-301 ELECTRICAL - PHASE 3 - BASEMENT POWER NEW WORK PLAN X
AI-101 ARCHITECTURAL PHASE 3 - NEW WORK SECTIONS X MID-101 STEAM RISER DIAGRAM - PHASE 1 - DEMOLITION X EP-302 ELECTRICAL - PHASE 3 - BASEMENT POWER NEW WORK PLAN X
AI-102 ARCHITECTURAL PHASE 3 - NEW WORK SECTIONS AND DETAILS X MID-102
CONDENSATE RISER DIAGRAM - PHASE 1 -
DEMOLITION
X
EP-303 ELECTRICAL - PHASE 3 - ROOF POWER NEW WORK PLAN X
AI-103
ARCHITECTURAL PHASE 2 - NEW TEMPORARY DUST BARRIER
ENCLOSURE
X MID-201 STEAM RISER DIAGRAM - PHASE 2 - DEMOLITION
X
EP-510
ELECTRICAL - PHASE 1 - BOILER PLANT ONE-LINE DIAGRAM -
TEMPORARY BOILERS
X
AI-104 ARCHITECTURAL PHASE 3 - WALL SECTIONS X MID-202
CONDENSATE RISER DIAGRAM - PHASE 2 -
DEMOLITION
X
EP-511
ELECTRICAL - PHASE 1 - BOILER PLANT ONE-LINE DIAGRAM -
NEW WORK
X
AI-201 ARCHITECTURAL PHASE 3 - ROOF PENETRATION DETAILS X MID-301 STEAM RISER DIAGRAM - PHASE 3 - DEMOLITION X
EP-512
ELECTRICAL - PHASE 1 - CHILLER PLANT ONE-LINE DIAGRAM -
TEMPORARY POWER
X
AI-202 ARCHITECTURAL PHASE 3 - LOUVER/WALL DETAILS X MID-302
CONDENSATE RISER DIAGRAM - PHASE 3 -
DEMOLITION
X
EP-513
ELECTRICAL - PHASE 1 - CHILLER PLANT ONE-LINE DIAGRAM -
NEW WORK
X
AI-203 ARCHITECTURAL PHASE 3 - SUSPENDED CEILING DETAILS X MI-101 STEAM RISER DIAGRAM - PHASE 1 - NEW WORK X
EP-520
ELECTRICAL - PHASE 2 - BOILER PLANT ONE-LINE DIAGRAM -
NEW WORK
X
AI-204 ARCHITECTURAL PHASE 3 - BREECH DETAILS X MI-102
CONDENSATE RISER DIAGRAM - PHASE 1 - NEW
WORK
X
EP-531
ELECTRICAL - PHASE 3 - CHILLER PLANT ONE-LINE DIAGRAM -
NEW WORK
X
AF-101 ARCHITECTURAL PHASE 3 - ROOM FINISHES X MI-201 STEAM RISER DIAGRAM - PHASE 2 - NEW WORK X
EP-532
BOILER PLANT - PHASE 3 - BOILER PLANT ONE-LINE DIAGRAM -
NEW WORK
X
AF-102 ARCHITECTURAL PHASE 3 - ROOM FINISHES X MI-202
CONDENSATE RISER DIAGRAM - PHASE 2 - NEW
WORK
X
E-301 ELECTRICAL - DETAILS X
AF-103 ARCHITECTURAL PHASE 3 - WALL AND CEILING REPAIRS X MI-301 STEAM RISER DIAGRAM - PHASE 3 - NEW WORK X E-302 ELECTRICAL - DETAILS X
MI-302
CONDENSATE RISER DIAGRAM - PHASE 3 - NEW
WORK
X
E-401 ELECTRICAL - SCHEDULES X
SG-001 STRUTURAL GENERAL NOTES X MI-303 OTHER RISER DIAGRAM - PHASE 3 - NEW WORK X E-402 ELECTRICAL - PANEL SCHEDULES X
SD-201 STRUCTURAL PHASE 2 - SUB-BASEMENT DEMOLITION PLAN X MI-401 MECHANICAL DETAILS X E-403 ELECTRICAL - PANEL SCHEDULES X
SD-301 STRUCTURAL PHASE 3 - SUB-BASEMENT DEMOLITION PLAN X MI-402 MECHANICAL DETAILS X
SD-302 STRUCTURAL PHASE 3 - BASEMENT DEMOLITION PLAN X MI-403 MECHANICAL DETAILS X FA-000 FIRE ALARM - LEGEND, DETAILS AND RISER DIAGRAM
SF-201 STRUCTURAL PHASE 2 - SUB-BASEMENT NEW WORK PLAN X MI-404 MECHANICAL DETAILS X FA-201 FIRE ALARM - SUB-BASEMENT NEW WORK PLAN
SF-301 STRUCTURAL PHASE 3 - SUB-BASEMENT NEW WORK PLAN X MI-405 TEMPORARY BOILER DETAILS X FA-202 FIRE ALARM - BASEMENT NEW WORK PLAN
SF-302 STRUCTURAL PHASE 3 - BASEMENT NEW WORK PLAN X MI-406 TEMPORARY BOILER PID X FAD-201 FIRE ALARM - SUB-BASEMENT DEMOLITION PLAN
SF-401 STRUCTURAL SECTIONS X MI-407
TEMPORARY BOILER PLATFORM AND TRAILER
STAIR DETAILS
X
FAD-202 FIRE ALARM - BASEMENT DEMOLITION PLAN
SF-501 STRUCTURAL PHASE 2 - SUB-BASEMENT SEISMIC BRACING PLAN X MI-501 MECHANICAL SCHEDULES X
SF-502 STRUCTURAL PHASE 2 - BASEMENT SEISMIC BRACING PLAN X MI-502 MECHANICAL SCHEDULES X FX-000 FIRE PROTECTION LEGEND X
SF-503 STRUCTURAL PHASE 3 - SUB-BASEMENT SEISMIC BRACING PLAN X MI-503 MECHANICAL SCHEDULES X FD-201 FIRE PROTECTION BASEMENT FLOOR DEMOLITION PLAN X
SF-504 STRUCTURAL PHASE 3 - BASEMENT SEISMIC BRACING PLAN X MI-504 MECHANICAL SCHEDULES X FX-201 FIRE PROTECTION NEW WORK PART PLANS X
SF-601 STRUCTURAL DETAILS X MI-601 MECHANICAL CONTROLS X FX-600 FIRE PROTECTION DETAILS X
SF-602 STRUCTURAL SEISMIC DETAILS X MI-602 MECHANICAL CONTROLS X FX-601 FIRE PROTECTION DETAILS X
MI-603 MECHANICAL CONTROLS X
CI-101 CIVIL LEGEND, ABBREVIATIONS, AND GENERAL NOTES X MI-604 MECHANICAL CONTROLS X P-000 PLUMBING LEGEND X
CD-101 DEMOLITION PLAN X MI-605 MECHANICAL CONTROLS X P-201 PLUMBING PHASE 2 - SITE PLAN X
CS-101 SITE PLAN X MI-606 MECHANICAL CONTROLS X PD-201 PLUMBING PHASE 2 - BASEMENT DEMOLITION PLAN X
CG-101 GRADING PLAN X MI-607 MECHANICAL CONTROLS X PP-201U PLUMBING PHASE 2 - SUB BASEMENT UNDERSLAB PLAN X
CP-101 PAVING PLAN X PP-201 PLUMBING PHASE 2 - SUB BASEMENT PLAN X
CU-101 UTILITY PLAN X E-000
ELECTRICAL - LEGEND & ABBREVIATIONS
X
PP-202
PLUMBING PHASE 2 - SUB BASEMENT PLAN TEMPORARY BOILER
LOCATION
X
CJ-101 UTILITY PROFILE X ESP-101
ELECTRICAL - PHASE 1 - SITE PLAN - CHILLER PLANT
AND BOILER PLANT SERVICE UPGRADE - NEW WORK
X
PP-203 PLUMBING PHASE 2 - BASEMENT FLOOR PLAN X
CK-101 CIVIL DETAILS X ESP-102
ELECTRICAL - PHASE 1 - SITE PLAN - TEMPORARY
BOILERS
X
PD-301U
PLUMBING PHASE 3 - SUB BASEMENT UNDERSLAB DEMOLITION
PLAN
X
CK-102 CIVIL DETAILS X ESP-103 ELECTRICAL - PHASE 1 - SITE DETAILS X PD-301 PLUMBING PHASE 3 - SUB BASEMENT DEMOLITION PLAN X
ESP-104
ELECTRICAL - PHASE 1 - TEMPORARY BOILER
CONTROL ROOM
X
PD-302
PLUMBING PHASE 3 - SUB BASEMENT DEMOLITION PLAN
TEMPORARY BOILER LOCATION
X
MS-200 TEMPORARY BOILER, TRAILER AND UTILITIES LOCATION PLAN X ELD-201
ELECTRICAL - PHASE 2 - SUB-BASEMENT LIGHTING
DEMOLITION PLAN
X
PP-301U PLUMBING PHASE 3 - SUB BASEMENT UNDERSLAB PLAN X
MS-201 TEMPORARY BOILER, TRAILER AND UTILITIES LOCATION PLAN X ELD-202
ELECTRICAL - PHASE 2 - BASEMENT LIGHTING
DEMOLITION PLAN
X
PP-301 PLUMBING PHASE 3 - SUB BASEMENT PLAN X
MD-101 MECHANICAL - PHASE 1 - SUB-BASEMENT DEMOLITION PLAN X ELD-301
ELECTRICAL - PHASE 3 - SUB-BASEMENT LIGHTING
DEMOLITION PLAN
X
PP-302 PLUMBING PHASE 3 - BASEMENT FLOOR PLAN X
MD-103 MECHANICAL - PHASE 1 - LEVEL 1 DEMOLITION PLAN X ELD-302
ELECTRICAL - PHASE 3 - BASEMENT LIGHTING
DEMOLITION PLAN
X
PP-303 PLUMBING PHASE 3 - ROOF PLAN X
MD-201 MECHANICAL - PHASE 2 - SUB-BASEMENT DEMOLITION PLAN X EPD-100
ELECTRICAL - BOILER PLANT CONTROL ROOM
DEMOLITION
X
P-501 PLUMBING EXISTING WATER HEATERS RISER DIAGRAM X
MD-202 MECHANICAL - PHASE 2 - BASEMENT DEMOLITION PLAN X EPD-101
ELECTRICAL - BOILER PLANT - PHASE 1 -
SUB-BASEMENT DEMOLITION
X P-502
PLUMBING NEW STEAM WATER HEATERS RISER DIAGRAM AND
WATER HEATER DETAIL
X
MD-301 MECHANICAL - PHASE 3 - SUB-BASEMENT DEMOLITION PLAN X EPD-201
ELECTRICAL - PHASE 2 - SUB-BASEMENT POWER
DEMOLITION PLAN
X P-601 PLUMBING DETAILS X
MD-301A BOILER CONTROL ROOM - PHASE 3-DEMOLITION X EPD-202
ELECTRICAL - PHASE 2 - BASEMENT POWER
DEMOLITION PLAN
X P-602 PLUMBING DETAILS X
MD-302 MECHANICAL - PHASE 3 - BASEMENT DEMOLITION PLAN X EPD-301
ELECTRICAL - PHASE 3 - SUB-BASEMENT POWER
DEMOLITION PLAN
X P-701 PLUMBING SCHEDULES X
MD-303 MECHANICAL - PHASE 3 - LEVEL 1 DEMOLITION PLAN X EPD-302
ELECTRICAL - PHASE 3 - BASEMENT POWER
DEMOLITION PLAN
X
MD-304 MECHANICAL - PHASE 3 - ROOF DEMOLITION PLAN
X
EPD-303
ELECTRICAL - PHASE 3 - ROOF POWER DEMOLITION
PLAN
X
MH-103 MECHANICAL - PHASE 1- LEVEL 1 NEW WORK PLAN
X
EPD-511
ELECTRICAL - PHASE 1 - BOILER PLANT ONE-LINE
DIAGRAM - DEMOLITION
X
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768
100% CONSTRUCTION
DOCUMENTS
REPLACE MAIN BOILERS 528A8-17-805
Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208
06/05/2024
105 Central Street Stoneham, MA 02180 P: 781-275-6050
C U se rs
\h a u n g \D o c u m e n ts
\A lb a n y_ B o ile r_ M e c h
E le ct ri c a l U p g ra d e
V h a u n g
G H
V P
.r v t
/7
/2
:3
:3
P M
GI-002
DRAWING INDEX
HL HARevisions: Date:
DETAIL NUMBER
DRAWING NUMBER WHERE SHOWN
SECTION LETTER
DRAWING NUMBER WHERE DRAWN
POWER REQUIRED EQUIPMENT ABBREVIATION
EQUIPMENT NUMBER
BUILDING NO. WHERE EQUIPMENT IS LOCATED.
NON POWER REQUIRED EQUIPMENT ABBREVIATION
EQUIPMENT NUMBER
BUILDING NO. WHERE EQUIPMENT IS LOCATED.
FUEL OIL RETURN
FUEL OIL SUPPLYFOS
FOR
BOILER FEEDWATERBF
COLD (CITY) WATERCW
SOFT WATERSW
1. THE FIRST FIGURE OF DUCT SIZE INDICATES DIMENSION OF FACE SHOWN
OR INDICATED. DUCT SIZES ARE NET INSIDE DIMENSIONS.
2. FOR TYPICAL STEAM AND WATER PIPING CONNECTIONS TO EQUIPMENT,
SEE STANDARD EQUIPMENT DETAILS.
3. WATER PIPE CONNECTIONS TO AIR HEATING AND COOLING COILS SHALL
BE MADE TO PROVIDE COUNTER FLOW BETWEEN WATER AND AIR.
4. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS FOR EXACT
LOCATIONS OF CEILING DIFFUSERS, REGISTERS, AND GRILLES.
5. STEAM HEADER SET PRESSURE: 120 PSIG
6. ALTITUDE-BOILER ROOM FLOOR: 190 FT ABOVE SEA LEVEL
7. SEISMIC PROVISIONS REQUIRED - REFER TO STRUCTURAL DWGS FOR
MECHANIC PIPING SEISMIC BRACING REQUIREMENTS AND EQUIPMENT
ANCHORAGE REQUIREMENTS.
8. ALL PRESSURES LISTED ARE GAGE PRESSURE UNLESS OTHERWISE
NOTED
9. PIPING EXPANSION DELEGATED DESIGN SUBMITTAL. MECHANICAL
CONTRACTOR SHALL PROVIDE A DELEGATED DESIGN SUBMITTAL FOR
STEAM PIPING EXPANSION INCLUDING CONDENSATE; CALCULATIONS,
LOADS, FORCES, PIPE STRESSES, ANCHOR DESIGN, GUIDE LOCATIONS
AND EXPANSION LOOP & JOINTS. ALL CALCULATIONS SHALL BE STAMPED
AND SIGNED BY A STRUCTURAL ENGINEER REGISTERED IN STATE OF
NEW YORK. CONTRACTOR SHALL PROVIDE ALL MATERIALS, EQUIPMENT
REQUIRED FOR EXPANSION PROVISIONS.
10. PROVIDE REQUIRED VALVES AND PORTS PER THE LATEST BEI STANDARD
AND OPERATIONAL TESTING.
2 HR FIRE RATED WALL
F
AC
1-24
1S-34
CC
HOT WATER RETURN
QUICK-COUPLE HOSE CONNECTOR
GATE VALVE WITH GLOBE-VALVED BYPASS
PLUG VALVE
CONTROL VALVE (CV) - FLOAT-OPERATED
PRESSURE REDUCING VALVE (PRV)
WATER LEVEL CONTROLLER
FLOW METER
HOT WATER SUPPLY
FUSIBLE FIRE SAFETY VALVE
INVERTED BUCKET TRAP SET INCLUDING
PIPING ACCESSORIES SEE DETAIL
FLOAT AND THERMOSTATIC TRAP SET
INCLUDING PIPING ACCESSORIES SEE DETAIL
THERMOSTATIC TRAP SET INCLUDING
PIPING ACCESSORIES SEE DETAIL
THERMOSTATIC AIR VENT
LC
M
H4
H7
A
ABBREVIATIONS ABBREVIATIONS
LIMIT OF DEMOLITION
(WALL TYPE)
(WALL TYPE)
DN
DN
UP
UP
SUPPLY DUCT (UP & DOWN)
EXHAUST DUCT (UP & DOWN)
EXHAUST OR RETURN CEILING REGISTER OR GRILLE
EXHAUST OR RETURN BOTTOM REGISTER OR GRILLE
EXHAUST OR RETURN REGISTER OR TOP GRILLE
CONNECT NEW DUCT TO EXISTING DUCT
LINEAR SLOT DIFFUSER
BACK DRAFT DAMPER
BDD
10x8
STANDARD RADIUS ELBOW (LONG RADIUS)
NEW DUCT (INSIDE DIMENSIONS: WIDTH x DEPTH)
EXISTING DUCT TO REMAIN
FIRE DAMPER
FD
EXISTING DUCT TO BE REMOVED
HIGH PRESSURE STEAM CONDENSATE RETURN
HIGH PRESSURE STEAM (60 PSIG AND ABOVE)
HOT WATER HEATING SUPPLY
CONDENSATE PUMPED RETURN
LOW PRESSURE STEAM CONDENSATE RETURN
LOW PRESSURE STEAM (15 PSIG AND BELOW)
MEDIUM PRESSURE STEAM CONDENSATE RETURN
MEDIUM PRESSURE STEAM (16 PSIG THRU 59 PSIG)
VENT LINE
REFRIGERANT SUCTION
REFRIGERANT HOT GAS
REFRIGERANT LIQUID
CHILLED WATER SUPPLY
CHILLED WATER RETURN
DRAIN LINE
MAKE-UP WATER
HOT WATER HEATING RETURN
HPS
HPR
MPS
MPR
LPS
LPR
PR
HWS
HWR
V
CHR
RL
RS
RHG
CHS
MW
D
X EXISTING PIPE TO BE REMOVED
PIPING SYMBOLS
HWR
DIRECTION OF FLOW
SIDE CONNECTION
BOTTOM CONNECTION, 45° OR 90°
TOP CONNECTION, 45° OR 90°
UNION
RISE OR DROP IN PIPE
CAPPED OUTLET
PRESSURE GAGE
THERMOMETER
PIPE UP
PIPE DOWN
AUTOMATIC AIR VENT
AV
MANUAL AIR VENTMV
GENERAL PIPING SYMBOLS
BALL VALVE
GATE VALVE WITH 3/4" HOSE ADAPTER
CHECK VALVE
ANGLE GLOBE VALVE
BUTTERFLY VALVE
MODULATING CONTROL VALVE
TWO POSITION CONTROL VALVE
THREE-WAY MODULATING CONTROL VALVE
AUTOMATIC BALANCING CONTROL VALVE
PRESSURE SAFETY VALVE
GATE VALVE - THREADED/FLANGED
GLOBE VALVE - THREADED/FLANGED
PRESSURE REGULATING VALVE
THREE-WAY TWO POSITION CONTROL VALVE
WYE STRAINER (WITH BALL VALVE & HOSE CONNECTION)
FLEXIBLE CONNECTION
WATER BALANCE DEVICE
MODULATING CONTROL BUTTERFLY VALVE
CIRCUIT SETTER VALVE
WYE STRAINER WITH VALVED DRAIN AND QUICK-COUPLE
HOSE CONNECTOR
VALVE SYMBOLSGENERAL NOTES
HWS
DUCTWORK SYMBOLS
DRAWING SYMBOLS
A/E ARCHITECT / ENGINEER
AC AIR CONDITIONER
ACCU AIR-COOLED CONDENSING UNIT
ACD AUTOMATIC CONTROL DAMPER,
MODULATING
ACD-TP AUTOMATIC CONTROL DAMPER,
TWO POSITION
AD ACCESS DOOR
AF AFTER FILTER
AFCV AIR FLOW CONTROL VALVE
AFF ABOVE FINISHED FLOOR
AFMS AIR FLOW MEASURING STATION
AFW AIR FOIL WHEEL (FAN)
AHU AIR-HANDLING UNIT
AMP AMPERE
AP ACCESS PANEL
APD AIR PRESSURE DROP
AQST AQUASTAT
ARI AIR CONDITIONING AND
REFRIGERATION INSTITUTE AS AIR
SEPARATOR
ASHRAE AMERICAN SOCIETY OF HEATING
REFRIGERATION AIR CONDITIONING
ENGINEERS
BD BUTTERFLY DAMPER
BDD BACKDRAFT DAMPER
BHP BRAKE HORSEPOWER
BTU BRITISH THERMAL UNIT
BTUH BRITISH THERMAL UNIT PER HOUR
CAV CONSTANT AIR VOLUME
CD CEILING DIFFUSER
CFM CUBIC FEET PER MINUTE
CO CARBON MONOXIDE SENSOR
CO2 CARBON DIOXIDE
COP COEFFICIENT OF PERFORMANCE
CV CONSTANT VOLUME
D DAMPER - AUTOMATIC
DB DECIBELS
DDC DIRECT DIGITAL CONTROLS
DEG DEGREE
EA EXHAUST AIR
EF EXHAUST FAN
EX EXISTING
F FAHRENHEIT
FC FLEXIBLE CONNECTION
FD FIRE DAMPER
FM FLOW METER
FPM FEET PER MINUTE
FS FLOW SWITCH
FT FEET
FT WC FEET OF WATER COLUMN
GAL GALLONS
GPM GALLONS PER MINUTE
HOA HAND/OFF/AUTOMATIC
HP HORSEPOWER
HPDT HIGH PRESSURE DRIP TRAP
HPR HIGH PRESSURE RETURN (STEAM
CONDENSATE)
HPS HIGH PRESSURE SUPPLY (STEAM)
HW HOT WATER
HWR HEATING HOT WATER RETURN
HWS HEATING HOT WATER SUPPLY
HZ HERTZ
I/O INPUT/OUTPUT
IAQ INDOOR AIR QUALITY
IBT INVERTED BUCKET TRAP
ICF IN-LINE CENTRIFUGAL FAN
ID INSIDE DIAMETER
IN INCHES
IN WC INCH WATER COLUMN
IN-LB INCH-POUND
J INTENTIALLY LEFT BLANK
KW KILOWATT
KWH KILOWATT HOUR
LBS/HR POUNDS PER HOUR
LF LINEAR FOOT (FEET)
LPR LOW PRESSURE RETURN (STEAM
CONDENSATE)
MAX MAXIMUM
MBH 1,000 BTUH
MCA MINIMUM BRANCH CIRCUIT
AMPACITY
MHP MOTOR HORSEPOWER
MIN MINIMUM
MOV MOTOR OPERATED VALVE
MPR MEDIUM PRESSURE RETURN
(STEAM CONDENSATE)
MPS MEDIUM PRESSURE STEAM
MTD MEAN TEMPERATURE
DIFFERENCE
MVD MANUAL VOLUME DAMPER
NA NOT APPLICABLE
NC NOISE CRITERIA
NC NORMALLY CLOSED
NO NORMALLY OPEN
NOAA NATIONAL OCEANIC &
ATMOSPHERIC ADMINISTRATION
NOM NOMINAL
NPLV NON-STANDARD PART LOAD VALUE
NTS NOT TO SCALE
OA OUTSIDE AIR
OAD OUTDOOR AIR DAMPER
OAG OUTSIDE AIR GRILLE
OAI OUTSIDE AIR INTAKE
OD OUTSIDE DIAMETER
OSD OPEN SIGHT DRAIN
PD PRESSURE DROP
PG PRESSURE GAGE
PPM PARTS PER MILLION
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH GAGE
PSV PRESSURE SAFETY VALVE
REA RELIEF AIR
RELAD RELIEF AIR DAMPER
RHG REFRIGERANT HOT GAS
RL REFRIGERANT LIQUID LINE
RLA RUN LOAD AMPERE
RPM REVOLUTIONS PER MINUTE
RS REFRIGERANT SUCTION
RV RELIEF VALVE
SA SUPPLY AIR
SAD SOUND ATTENUATING DEVICE
SAT SUPPLY AIR TEMPERATURE
SCFM STANDARD CUBIC FEET PER
MINUTE
SD SMOKE DETECTOR
SD SUPPLY AIR DIFFUSER
SDPR SMOKE DAMPER
SEN SENSIBLE HEAT
SI SQUARE INCHES
SP STATIC PRESSURE
SPS STATIC PRESSURE SENSOR
SQ FT SQUARE FOOT (FEET)
SS STAINLESS STEEL
ST STEAM TRAP
T&PCV TEMPERATURE AND PRESSURE
CONTROL VALVE
TAB TESTING, ADJUSTING, BALANCE
TSP TOTAL STATIC PRESSURE
TSTAT THERMOSTAT
UH UNIT HEATER
V VALVE
VAV VARIABLE AIR VOLUME
VD VOLUME DAMPER
VFD VARIABLE FREQUENCY DRIVE
VI VIBRATION ISOLATOR
VPS VARIABLE PRIMARY SYSTEM
VSD VARIABLE SPEED DRIVE
W WATTS
SW SOFT WATER
VTR VENT THRU ROOF
CW COLD (CITY) WATER
DPS DIFFERENTIAL PRESSURE SENSOR
DIA DIAMETER
BF BOILER FEED
BF-1 BOILER FEED 1
BF-2 BOILER FEED 2
GV GATE VALVE
SV STEAM SAFETY RELIEF VALVE
XR EXISTING TO RE-LOCATE
XM EXISTING TO REMAIN
X EXISTING TO REMOVE
FOS FUEL OIL SUPPLY
FOR FUEL OIL RETURN
DR DIESEL RETURN
DS DIESEL SUPPLY
CTPD CONDENSATE TANK PUMP DISCHARGE
CTPS CONDENSATE TANK PUMP SUCTION
FOM FUEL OIL METER
WM WATER METER
SM STEAM METER
OFL OVERFLOW
PR PUMPED CONDENSATE RETURN
CONTROLS SYMBOLS
EPT ELECTRONIC TO PNEUMATIC TRANSDUCER
AT CARBON DIOXIDE TRANSMITTER
CARBON MONOXIDE TRANSMITTER
CO2
AT
CO
LTCP LOCAL TEMPERATURE CONTROL PANEL
HVAC HVAC CONTROL PANEL
ECC
INTEGRATE CONTROL POINT ON REMOTE GRAPHICS
WORKSTATION AT ENERGY CONTROL CENTER
TC
TEMPERATURE CONTROLLER. SEE SEQUENCE OF
OPERATION
VSMC VARIABLE SPEED MOTOR CONTROLLER
PC
PRESSURE CONTROLLER. SEE SEQUENCE OF
OPERATION
SC SPEED CONTROLLER. SEE SEQUENCE OF OPERATION
FC FLOW CONTROLLER. SEE SEQUENCE OF OPERATION
PSH PRESSURE SWITCH HIGH
FSH FLOW SWITCH HIGH
PSL PRESSURE SWITCH LOW
FSL FLOW SWITCH LOW
CONTROLS SYMBOLS
T ROOM THERMOSTAT/TRANSMITTER - WALL MOUNT
TT TEMPERATURE TRANSMITTER
M ROOM HUMIDISTAT (MOISTURE)/TRANSMITTER - WALL MOUNT
PT PRESSURE TRANSMITTER
TT TEMPERATURE TRANSMITTER, AVERAGING ELEMENT
FT FLOW TRANSMITTER
IT CURRENT TRANSMITTER
CT CONDUCTIVITY TRANSMITTER
SPS STATIC PRESSURE SENSOR
SD SMOKE DETECTOR
PDT PRESSURE DIFFERENTIAL TRANSMITTER
TSL TEMPERATURE SWITCH, LOW (FREEZESTAT)
HS HAND SWITCH (HAND-OFF-AUTO SWITCH)
ZC VALVE OR DAMPER POSITION CONTROLLER
LC LEVEL CONTROLLER
LT LEVEL TRANSMITTER
PDS PRESSURE DIFFERENTIAL SWITCH
TSH TEMPERATURE SWITCH, HIGH (FREEZESTAT)
LENGTH IN DUCT WHEN SPACE PERMITS.)
A
TEMPERATURE SENSING ELEMENT FOR
TRANSMITTING TEMPERATURE TO EMCS
(PROVIDE 12 INCHES [200mm] MINIMUM
SENSOR WITH AVERAGING ELEMENT TO TRANSMIT
TEMPERATURE TO EMCS
MOTOR STARTER
M ELECTRIC OPERATED CONTROL DAMPER/OR VALVE
LS LEVEL SWITCH
ESV EMERGENCY SHUTOFF VALVE
DT DRAFT GAUGE
DS DRAFT HIGH PRESSURE SWITCH
FS FLAME STENGTH
O2 OXYGEN CONTENT TRANSMITTER
SST START/STOP
DI DIGITAL INPUT
DO DIGITAL OUTPUT
AI ANALOG INPUT
AO ANALOG OUTPUT
CT CONDUCTIVITY TRANSMITTER
SCV STEAM CONTROL VALVE
CD CONTROL PANEL
TAV
S
EMERGENCY SWITCH
FIRE RATING SYMBOL
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768
100% CONSTRUCTION
DOCUMENTS
REPLACE MAIN BOILERS 528A8-17-805
Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208
06/05/2024
105 Central Street Stoneham, MA 02180 P: 781-275-6050
C U se rs
\h a u n g \D o c u m e n ts
\A lb a n y_ B o ile r_ M e c h
E le ct ri c a l U p g ra d e
V h a u n g
G H
V P
.r v t
/7
/2
:3
:3
P M
GI-003
GENERAL NOTESS, ABBREVIATIONS, AND
SYMBOLS
HL HARevisions: Date:
UP
DN
DN
DN
DN
DN
COGEN
ENCLSOURE
2 1
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768
100% CONSTRUCTION
DOCUMENTS
REPLACE MAIN BOILERS 528A8-17-805
Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208
06/05/2024
105 Central Street Stoneham, MA 02180 P: 781-275-6050
C U se rs
\h a u n g \D o c u m e n ts
\A lb a n y_ B o ile r_ M e c h
E le ct ri c a l U p g ra d e
V h a u n g
G H
V P
.r v t
/7
/2
:3
:3
P M
GI-004
MECHANICAL - EXISTING CONDITIONS -
PHOTOS
HL HA
1/16" = 1'-0"
MECHANICAL - SUB-BASEMENT EXISTING CONDITION
1/16" = 1'-0"
MECHANICAL - BASEMENT EXISTING CONDITION
1/16" = 1'-0"
MECHANICAL - ROOF EXISTING CONDITION
PHOTO 1: EXISTING PLUMBING EQUIPMENT TO REMAIN
PHOTO 2: EXISTING FO#6 TO BE DEMOLISHED
PHOTO 3: EXISTING CONDENSATE TANK TO BE DEMOLISHED
PHOTO 4: EXISTING FEEDWATER PUMPS TO BE DEMOLISHED
PHOTO 5: EXISTING CONDENSATE PUMPS TO BE DEMOLISHED
PHOTO 6: EXISTING WINTER BOILERS TO BE REPLACED
PHOTO 6: EXISTING SUMMER BOILER TO BE DEMOLISHED
PHOTO 8: EXISTING STEAM HEADER BOILER TO BE REPLACED
PHOTO 1: SECTION OF WALL TO BE OPEN
FOR RIGGING (LOOK FROM INSIDE)
PHOTO 2: SECTION OF WALL TO BE OPEN
FOR RIGGING (LOOK FROM OUTSIDE)
PHOTO 3: EXISTING DA TANK TO BE REPLACED
PHOTO 4: EXISTING DA TANK VENT TO BE REPLACED
PHOTO 5: EXISTING BOILER ECONOMIZER TO BE
DEMOLISHED
PHOTO 6: EXISTING OVERHEAD PIPING
PHOTO 1: EXISTING VENTILATION HOODS TO BE REPLACE WITH NEW
EXHAUST FANS
PHOTO 2: EXISTING EXHAUST FANS TO BE DEMOLISHED
PHOTO 3: ROOF LAYOUT
SUB-BASEMENT
BASEMENT
ROOF
Revisions: Date:
PHASE 1
TASK
STEAM
SHUTDOWN
ELECTRIC
SHUTDOWN
OTHER
SHUTDOWN
NOTES
PREPARE FOR EQUIPMENT INSTALLATION
PREPARE SITE FOR EQUIPMENT
INSTALLATION.
NO
INSTALL EROSION CONTROL.
SAW-CUT AND REMOVE PAVEMENT AND SIDEWALKS.
EXCAVATE AND DISPOSE OF EXCESS SOIL, STOCKPILE SOIL NEEDED FOR BACKFILLING.
INSTALL ELECTRICAL VAULTS.
INSTALL DRAIN PIPING.
INSTALL EQUIPMENT PAD FOR NEW TRANSFORMERS AND 15kV PRIMARY SWITCHES.
INSTALL UNDERGROUND CONDUIT SYSTEM BETWEEN NEW 15kV PRIMARY SWITCHES AND NEW PAD-MOUNTED
TRANSFORMERS.
INSTALL NEW DUCTBANK SYSTEM FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW 15kV PRIMARY SWITCHES.
BACKFILL SOIL AND INSTALL PAVEMENT PATCH AND SIDEWALKS.
INSTALL FENCE AND GATES.
INSTALL TOPSOIL, GRASS SEED, AND GRAVEL.
BOILER PLANT:
PREPARE FOR INSTALLATION OF NEW
INTERIOR EQUIPMENT
YES
INSTALL STANDBY EMERGENCY DISTRIBUTION BOARD DP-52D19 FED FROM EXISTING PARALLEL GENERATOR
DISTRIBUTION BOARD.
RE-FEED EXISTING PANEL '14-HCC-IL-LS' FROM NEW STANDBY EMERGENCY DISTRIBUTION BOARD 'DP-52D19'.
INSTALL TEMPORARY AUTOMATIC TRANSFER SWITCH U2-ATS-TEMP AND NEW STANDBY EMERGENCY DISTRIBUTION
BOARD 'CP-EDP2'.
INSTALL TEMPORARY BOILERS AND ASSOCIATED CONTROL ROOM PANEL.
INSTALL TEMPORARY POWER TO EXISTING BOILER PLANT MCC FROM EXISTING CHILLER PLANT DISTRIBUTION BOARD
'CSB'.
DEMOLISH EXISTING PAD-MOUNTED TRANSFORMERS AND 15kV SWITCHES.
INSTALL NEW BOILER PLANT PANELS 'BP-H4A', 'BP-H4B, 'BP-P2A', 'BP-P2B' AND RELATED TRANSFORMERS. PROVIDE TEMPORARY FEEDER FROM EXISTING BOILER PLANT MOTOR CONTROL CENTER TO ENABLE BOILER PLANT MECHANICAL EQUIPMENT REPLACEMENT TO COMMENCE PRIOR TO ARRIVAL OF NEW BOILER PLANT SWITCHGEAR.
NOTE: THE CHILLER PLANT SCOPE OF WORK INDICATED BELOW SHALL NOT COMMENCE UNTIL THE BOILER PLANT SERVICE UPGRADE IS 100% COMPLETE, TESTED AND ACCEPTED BY THE VAMC .
CHILLER PLANT:
PREPARE FOR INSTALLATION OF NEW
INTERIOR EQUIPMENT.
YES
REFEED CRITICAL CHILLER PLANT LOADS (HWP-7 & HWP-8) FROM NEW BOILER PLANT DISTRIBUTION SYSTEM.
REFEED EXISTING MOTOR CONTROL CENTER 'EMCC' FROM NEW BOILER PLANT DISTRIBUTION SYSTEM.
DEMOLISH EXISTING CHILLER ATS #1 AND ATS#2.
EQUIPMENT INSTALLATION
BOILER PLANT:
INSTALL EXTERIOR EQUIPMENT AND
RELATED FEEDERS.
YES
INSTALL NEW PAD-MOUNTED TRANSFORMERS.
INSTALL NEW 15kV PRIMARY SWITCHES.
REMOVE EXISTING 15kV FEEDER R639.
INSTALL NEW 15kV FEEDER R134 FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.
REMOVE EXISTING 15kV FEEDER R538.
INSTALL NEW 15kV FEEDER R235 FROM CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.
BOILER PLANT:
INSTALL INTERIOR EQUIPMENT YES INSTALL NEW SWITCHBOARD 'BP-SWBD' AND ASSOCIATED AUTOMATIC TRANSFER SWITCHES.
CHILLER PLANT:
INSTALL EXTERIOR EQUIPMENT AND
RELATED FEEDERS.
YES
INSTALL NEW PAD-MOUNTED TRANSFORMERS.
INSTALL NEW 15kV PRIMARY SWITCHES.
REMOVE EXISTING 15kV FEEDER R639.
INSTALL NEW 15kV FEEDER R639 FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.
REMOVE EXISTING 15kV FEEDER R538.
INSTALL NEW 15kV FEEDER R538 FROM CAMPUS 15kV SWITCHGEAR TO NEW PRIMARY SWITCH.
CHILLER PLANT:
INSTALL INTERIOR EQUIPMENT
YES
INSTALL NEW SWITCHBOARD '52-SWBD'.
INSTALL NEW DISTRIBUTION BOARD '52-D4SB'.
COMMISSIONING AND TESTING
COMMISSIONING AND TESTING NO COMMISSION AND TESTING NEW EQUIPMENT AND ASSOCIATED FEEDERS.
REMOVAL OF EXISTING CHILLER PLANT SWITCHYARD EQUIPMENT.
REMOVE EXISTING CHILLER PLANT
SWITCHYARD EQUIPMENT
REMOVE EXISTING PAD-MOUNTED TRANSFORMERS
REMOVE EXISTING15kV SWITCHGEAR 'CHP'.
REMOVE EXISTING 5kV SWITCHGEAR.
REMOVE EXISTING SWITCHBOARD 'CSB'.
REMOVE FENCED ENCLOSURE AND PAD.
SECURE NEW CHILLER PLANT SWITCHYARD
INSTALL FENCE NO INSTALL FENCED ENCLOSURE AT NEW CHILLER PLANT EQUIPMENT YARD.
REMOVAL OF EXISTING HVAC EQUIPMENT IN CHILLER PLANT.
REMOVE EXISTING PRV-1 ENTIRELY NO NO
UNIT
HEATERS
PRV-1 SERVES HX-1 & 2, AND UNIT HEATER IN SIDE CHILLER ROOMS
REMOVE EXISTING HX-1& 2 ENTIRELY NO NO NO HX-1 & 2 ARE CURRENTLY NOT IN USE
REMOVE CONDENSATE PUMP CP-1
ENTIRELY
NO NO NO CP-1 IS CURRENTLY NOT IN USE. HAND CP-1 TO VA
REMOVE AND RECONNECT LPS/HPR LINES
SERVING UNIT HEATERS.
NO NO UNIT HEATER
RELOCATE 5"Ø HWS/HWR FROM COGEN NO NO YES COGEN HWS/R WORK WILL ONLY HAPPEN IN THE SUMMER. ALL CHILLER POWER WORK TO BE DONE OCT-MAR
REPLACE STEAM TRAPS ON EXISTING
PRV-2 & 3
YES NO NO SHORT TERAM
GENERAL NOTES:
1. CONTRACTOR TO COORDINATE ALL SHUTDOWNS REQUIREMENT IN WRITING WITH THE VA COR AT LEAST FOUR WEEKS IN ADVANCE.
2. THE CONSTRUCTION PHASING SEQUENCE IS MEANT AS A DESIGN INTENT. CONTRACTOR IS RESPONSIBLE FOR PROVIDING A DETAILED STEP BY STEP CONSTRUCTION PHASING
SEQUENCE AND SUBMIT TO THE VA COR AND A&E FOR APPROVAL.
3. IN CASE OF ANY DISCREPANCIES BETWEEN THE NARRATIVE BELOW, DRAWINGS OR SPECS, A RFI SHALL BE GENERATED BY THE CONTRACTOR TO THE DESIGN TEAM. THE NARRATIVE
BELOW MAY OR MAY NOT CONTAIN ALL THE DETAILS LISTED ELSEWHERE ON THE DRAWINGS/SPECS, REFER TO DRAWINGS/SPECS FOR MORE INFORMATION.
4. CONTRACTOR TO COORDINATE WITH LOCAL DIESEL DELIVERY COMPANIES TO ENSURE THAT FUEL DELIVERY TRACKS AREA AVAILABLE ON STANDBY TO ENSURE THAT FUEL OIL IS
AVAILABLE AT ALL TIMES TO FILL THE EXISTING GENERATOR BELLY TANKS DURING SHUTDOWNS.
5. DEDUCT ALTERNATES
5.1. #1: EXISTING 15KV FEEDERS R538 AND R639 FROM THE CAMPUS 15KV SWITCHGEAR TO EXISTING MANHOLE EMH-2 SHALL BE RETAINED FOR RE-USE. SPLICE THE EXISTING 15KV FEEDERS IN AN ABOVE GRADE ENCLOSURE AND EXTEND TO THE NEW 15KV SWITCHES IN 4”C(CONCRETE ENCASED DUCTBANK).
5.2. #2: EXISTING 15KV FEEDERS R538 AND R639 SHALL BE DISCONNECTED/REMOVED. RELATED CONDUIT SHALL BE RETAINED FOR RE-USE. PROVIDE NEW 4”C (CONCRETE ENCASED DUCTBANK) FROM EXISTING MANHOLE EMH-2 TO THE NEW PRIMARY SWITCHES. INSTALL NEW FEEDERS R538 AND R639 IN THE EXISTING/REWORKED DUCTBANK SYSTEM FROM THE
15KV CAMPUS SWITCHGEAR TO THE NEW PRIMARY SWITCHES.
PHASE 0 - MEDIUM VOLTAGE INFRASTRUCTURE UPGRADE
THE INTENT OF PHASE 0 IS TO INSTALL NEW TRANSFORMER AND 15kV PRIMARY SWITCHES FOR CHILLER PLANT.
PHASE 0 WORK INCLUDES:
1. INSTALL EQUIPMENT PADS FOR NEW TRANSFORMERS AND 15kV PRIMARY SWITCHES.
2. INSTALL UNDERGROUND CONDUIT SYSTEM BETWEEN NEW 15kV PRIMARY SWITCHES AND NEW PAD-MOUNTED TRANSFORMERS.
3. INSTALL NEW DUCTBANK SYSTEM FROM EXISTING CAMPUS 15kV SWITCHGEAR TO NEW 15kV PRIMARY SWITCHES.
4. PROVIDE TEMPORARY POWER FOR EXISTING CHILLER PLANT PUMPS P7 AND P8.
5. INSTALL HOUSEKEEPING PADS FOR NEW SWITCHBOARD '52-CHP.
6. INSTALL SWITCHBOARD '52-SWBD.
7. INSTALL SECONDARY FEEDERS FROM PAD-MOUNTED TRANSFORMERS TO NEW SWITCHBOARD '52-SWBD'.
8. RE-FEED CHILLER #1 AND CHILLER #2 FROM NEW SWITCHBOARD '52-SWBD'.
9. RE-FEED EXISTING SWITCHBOARD '52-CHP' FROM NEW SWITCHBOARD '52'SWBD'.
10. INSTALL NEW DISTRIBUTION BOARD '52-D4SB' AND RELATED FEEDER.
11. RE-FEED EXISTING LOADS FROM EXISTING SWITCHBOARD '52-CHP' TO NEW DISTRIBUTION BOARD '52-D4SB'.
12. RE-FEED CHILLER #1 AND #2 TO NEW SWITCHBOARD '52-SWBD'.
13. REMOVE EXISTING PAD-MOUNTED TRANSFORMERS REMOVE EXISTING15kV SWITCHGEAR 'CHP'.
14. REMOVE EXISTING 5kV SWITCHGEAR.REMOVE EXISTING SWITCHBOARD 'CSB'.
15. REMOVE FENCED ENCLOSURE.
16. PROVIDE NEW FENCED ENCLOSURE FOR NEW OUTDOOR EQUIPMENT.
17. PROVIDE TEMPORARY FENCING AS NEEDED TO MAINTAIN SITE SECURITY.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
248 Copeland Street Quincy, MA 02169 P: 617-481-6390 F: 617-687-5990
200 Brickstone Square Andover, MA 01810 P: 978-296-6227 F: 978-475-5768
100% CONSTRUCTION
DOCUMENTS
REPLACE MAIN BOILERS 528A8-17-805
Samuel S. Stratton VA Medical Center, 113 Holland Ave., Albany, New York 12208
06/05/2024
105 Central Street Stoneham, MA 02180 P: 781-275-6050
C U se rs
\h a u n g \D o c u m e n ts
\A lb a n y_ B o ile r_ M e c h
E le ct ri c a l U p g ra d e
V h a u n g
G H
V P
.r v t
/7
/2
:3
:3
P M
GI-005
CONSTRUCTION PHASING PLAN AND
SHUTDOWN REQUIREMENTS
ND HLRevisions: Date:
PHASE 2
TASK
STEAM
SHUTDOWN
ELECTRIC
SHUTDOWN
OTHER
SHUTDOWN
NOTES
TEMPORARY POWER
SETUP TEMPORARY POWER NO YES
"SEE
NOTES"
SETUP TEMPORARY POWER
1. INSTALL NEW DISTRIBUTION BOARD DP-14A-HCC'.
2. REMOVE EXISTING 200A BREAKER 52D19 IN GENERATOR PARALLELING SWITCHGEAR AND RELATED FEEDER
POWERING PANEL '14-L-LS'.
3. INSTALL NEW 1000A BREAKER 52D19 IN GENERATOR PARALLELING SWITCHGEAR.
4. INSTALL NEW FEEDER FROM BREAKER 52D19 TO NEW DISTRIBUTION BOARD 'DP-14A-HCC'.
5. RE-FEED EXISTING PANEL '14A-L-LS' FROM NEW DISTRIBUTION BOARD 'DP-14A-HCC'.
6. INSTALL NEW ATS-CP-EDP2 AND DISTRIBUTION BOARD 'CP-EDP2'.
7. INSTALL FEEDERS TO TEMPORARY BOILERS #1 AND #2.
8. INSTALL TRANSFORMER AND PANEL AT TEMPORARY BOILER CONTROL ROOM.
9. INSTALL NEW PANEL CP-ELP1 AND RELATED TRANSFORMER.
10. SETUP TEMPORARY FEEDER TO MAKEUP AIR UNIT
11. SETUP TEMPORARY FEEDERS TO DOMESTIC HOT WATER HEATERS
12. SETUP TEMPORARY FEEDERS TO SUMMER BOILER AND WINTER BOILER FUEL OIL PUMPS
13. SETUP TEMPORARY FEEDERS TO NEW CONDENSATE STORAGE TANK AND PUMPS
14. SETUP TEMPORARY FEEDERS TO NEW DOMESTIC HOT WATER HEATERS AND STEAM CONDENSATE PUMPS
15. SETUP 120V FEED TO EXISTING CONTROL ROOM
16. SETUP TEMPORARY FEEDS TO EXISTING COMPRESSORS
TEMPORARY PROTECTION FOR AIR COMPRESSORS
PROVIDE TEMPORARY PROTECTION FOR
AIR COMPRESSORS
NO NO NO PROVIDE TEMPORARY PARTITIONS. USE EXISTING FAN FOR EXHAUST
PROVIDE LEAD/LAG CONTROLS FOR
EXISTING COMPRESSORS
NO NO
REMOVAL OF EXISTING #6 DIESEL PUMPS
REMOVE # 6 FUEL OIL PUMPS/HEATERS NO NO NO CURRENTLY ABANDONED AND NOT IN USE
REMOVAL OF GAS CONNECTION TO #1 BOILER
DECOMMISSIONING BOILER B-1 AND
REMOVE NATURAL GAS BRANCH PIPING TO
BOILER B-11
NO NO YES
SHUTDOWN DOWN OF BOILER B-1
FOR FUTURE CONNECTION TO TEMPORARY BOILER. UTILIZE EXISTING ISOLATION VALVE TO BOILER #1 TO
ISOLATE NATURAL GAS
TEMPORARY BOILER HOOKUP
FUEL OIL NO NO NO
CROSS CONNECT SUMMER AND WINTER FUEL OIL PIPING TO ALLOW SUMMER BOILER FUEL OIL PUMPS TO
SERVE EXISTING BOILERS WHEN REPLACING WINTER BOILER FUEL OIL PUMPS.
INSTALL NEW WINTER FUEL OIL PUMPS AND EXTEND PIPING TO TEMPORARY BOILERS. PROVIDE TAPS AND
VALVE CONNECTIONS FOR NEW BOILERS INSTALLED AS PART OF PHASE 3.
NATURAL GAS NO NO NO EXTEND NATURAL GAS FROM BOILER #1 CONNECTION TO TEMPORARY BOILERS
COLD WATER NO NO YES
TAP INTO EXISTING COLD WATER SUPPLY IN CHILLER ROOM. EXTEND COLD WATER SUPPLY FROM EXISTING BACKFLOW PREVENTER IN CHILLER ROOM TO TEMPORARY BOILERS. THE CW SYSTEM SHUTDOWN WILL NEED TO BE TIMED WITH THE MAINTENANCE/TESTING OF EXISTING BACKFLOW PREVENTER. EXPECTED DURATION- 4
HOURS
EXTEND POWER TO TEMPORARY BOILERS NO NO NO NO MCC SHUTDOWN REQUIRED (ONLY INDIVIDUAL BREAKERS FEEDING EQUIPMENT AFFECTED)
STEAM YES NO NO
1. TAP 8"Ø PIPING FROM TEMPORARY BOILERS INTO EXISTING 8"Ø STEAM LINE LOCATED IN CHILLER PLANT.
2. PROVIDE 8"Ø HPS PIPING TO CROSS CONNECT EXISTING 8"Ø HPS LINE FROM CHILLER PLANT TO EXISTING
10"Ø HPS SERVING HOSPITAL.
3. CROSS CONNECT 6"Ø PIPING SERVING LAUNDRY TO EXISTING 6"Ø HPS SECONDARY HEADER.
4. CROSS CONNECT 4"Ø PIPING SERVING DA TANK PRV, MUA-1 PRV AND HPR HEATERS IN EXISTING 6"Ø
SECONDARY HEADER.
5. PROVIDE NEW DRIP TRAPS TO SECONDARY HEADER AND RUN TO EXISTING HPR LINE.
BOILER FEED (INSTALL NEW CONDENSATE
TANK)
YES NO NO
1. INSTALL NEW CONDENSATE RETURN TANK AND PUMPS IN PLACE OF OLD #6 DIESEL PUMPS.
2. TEMPORARILY RUN EXISTING BOILERS ON 100% MAKEUP. TEMPORARY MANAGEMENT OF CONDENSATE RETURN FROM HOSPITAL, BOILER PLANT, CHILLER PLANT SHALL BE PROVIDED BY THE CONTRACTOR IN COORDINATION WITH THE VA, INCLUDING BUT NOT LIMIT TO TEMPORARY DRAINAGE OF CONDENSATE AT ALL
SOURCES, AND EQUIPMENT LOCK OUT.
3. PROVIDE NEW CONDENSATE TANK HEADERS, LOW PRESSURE AND MEDIUM PRESSURE. CONNECT EXISTING
CONDENSATE RETURN LINES TO THE HEADERS RESPECTIVELY.
4. INSTALL NEW CONDENSATE PIPING SERVING TEMPORARY BOILERS, PROVIDE TAPS FOR FUTURE
CONNECTIONS TO NEW BOILERS AND FEED WATER PUMPS.
5. PROVIDE NEW MAKE-UP WATER FROM EXISTING WATER SOFTENER TO THE NEW TANK. PROVIDE A TEEs AND
VALVES FOR FUTURE CONNECTION TO NEW BLOWDOWN HEAT RECOVERY UNIT.
6. TEST NEW TANK AND PUMPS BY TEMPORARILY BYPASSING CONDENSATE PUMP DISCHARGE TO FLOOR DRAIN.
TEST AND OPERATE TEMPORARY BOILERS NO NO NO
1. TEST AND RUN ON 100% MAKEUP INITIALLY. BYPASS STEAM TO EXTERIOR DURING TESTING.
2. OPEN STEAM SUPPLY TO SYSTEM AND SLOWLY RETURN THE BOILER FEED BACK TO THE TEMPORAY BOILERS.
HOOK UP CONTROL ROOM
CW NO NO NO UTILIZE CW CONNECTION FOR TEMPORARY BOILERS
SEWER NO NO NA SEWER WILL BE PUMPED OUT ON A WEEKLY BASIS
ELECTRIC NO NO NO SEE TEMPORARY POWER SECTION. TEMPORARY POWER PROVIDED SO NO ASSOCIATED SHUTDOWN.
CENTRAL MONITORING (MED GAS, TANK
LEVELS, EMERGENCY GENERATOR, AIR
COMPRESSOR, GAS VALVES, DRYER,
FIRE/SECURITY MONITORING ....)
NO NO YES
ALL EQUIPMENT AND ALARMS IN BOILER PLAN TO BE MONITORED WILL BE MIRRORED TO THE CONTROLLERS IN THE TEMPORARY CONTROL ROOM . EXPECTED UNAVAILABILITY OF POINTS AT BMS- 4 HOURS. PROVIDE A NEW CONTROLLER INI CONTROL ROOM AND TIE TO ALC SYSTEM NETWORK FOR MONITORING AND ALARM
VA IT NO NO MINOR EXTENT ETHERNET CONNECTION FROM NETWORK SWITCH TO TEMPORARY CONTROL ROOM.
BMS NO NO MINOR
EXTEND DDC MONITORING FOR EXISTING AIR COMPRESSORS, GAS VALVE, DRYERS, FIRE/SECURITY
MONITORING. EXPECTED UNAVAILABILITY OF POINTS AT BMS- 4 HOURS
REMOVAL OF EXISTING CONDENSATE TANK AND PUMPS
REMOVE EXISTING CONDENSATE TANKS
AND PUMPS
NO NO NO REMOVAL TO ALLOW INSTALLATION OF NEW DHW HEATERS
REMOVAL OF EXISTING MUA-1 PRV AND REPLACEMENT OF HPS UNIT HEATERS
REPLACE EXISTING PRV SERVING MUA-1
AND REPLACE EXISTING HPS UNIT
HEATERS WITH LPS ONES
NO NO
YES,
SHUTDOWN
OF MUA-1
AND UNIT
HEATERS
OPEN WINDOWS FOR COMBUSTION AIR AND PROVIDE TEMPORARY HEAT IN EMERGENCY GENERATOR ROOM
AND SUMMER BOILER ROOM AS NEEDED
REMOVAL AND REPLACEMENT OF EXISTING FLASH TANK AND PIPING
REMOVE EXISTING FLASH TANK AND PIPING NO NO NO NEW FLASH TANK WILL BE INSTALLED.
INSTALL NEW DHW HEATERS
INSTALL NEW PRV AND HPS PIPING NO NO NO
CONNECT 6" HPS SERVING NEW PRV INTO EXISTING 6"HPS SECONDARY HEADER. PROVIDE TEE AND VALVE FOR FUTURE CONNECTION BACK TO PRIMARY HEADER. INSTALL NEW PRV NEAR THE DWHs
INSTALL NEW DHW HEATERS AND
CONDENSATE PUMPS
NO NO MINOR
CONNECT INTO EXISTING CW/HW PIPING. INSTALL NEW STEAM CONDENSATE PUMPS AND TIE CONNECTIONS TO NEW CONDENSATE TANK HEADER. MINOR SHUTDOWN OF EXISTING DHW SYSTEM- 2 -4 HOURS. COMMISSIONING
BY VA.
REMOVE EXISTING DHW HEATERS
REMOVE EXISTING DHW HEATERS NO NO NO
PROVIDE FREEZE PROTECTION IN BOILER ROOM AND BATHROOM
PROVIDE FREEZE PROTECTION IN BOILER
ROOM AND BATHROOM
NO NO NO PROVIDE STEAM HEATERS AS REQUIRED FOR TEMPORARY HEAT
PHASE 3
TASK
STEAM
SHUTDOWN
ELECTRIC
SHUTDOWN
OTHER
SHUTDOWN
NOTES
REMOVE EXISTING DA TANKS AND PUMPS
REMOVE EXISTING DA TANKS NO NO NO OPERATE EXISTING BOILERS AND TEMPORARY ON CONDENSATE STORAGE BYPASSING DA TANK CONNECTION
INSTALL NEW DA TANKS AND PUMPS
INSTALL NEW DA TANK AND PUMPS NO NO NO INSTALL IN PLACE OF EXISTING TANK
UPGRADE VENTILATION AND EXHAUST SYSTEM
REPLACE VFD OF EXISTING MUA-1.
EXISTING EXHAUST FANS AND INSTALL
NEW EXHAUST FANS ON ROOF
NO NO NO PROVIDE BMS HARDWIRED CONNECTIONS FOR CONENCTION TO NEW BOILERS
REMOVE SUMMER BOILER FUEL OIL PUMPS
REMOVE SUMMER BOILER PUMP NO NO NO REMOVE SUMMER BOILER FUEL OIL PUMPS AFTER THE DEMOLITION OF ALL EXISTING BOILERS.
REPLACE EXISTING DIESEL OIL PUMP MOTORS AND PROVIDE PIPING FOR STANDBY GENERATOR
REPLACE PUMP MOTORS IN THE DIESEL
PUMP IN TANK VAULT. UPGRADE DIESEL
CONTROL PANEL AS REQUIRED.
NO NO YES
DIESEL SYSTEM WILL BE SHUTDOWN FOR APPROXIMATELY 16 HOURS. EMERGENCY GENERATOR BELLY TANKS
WILL FILLED BY DIESEL TRUCK WHICH WILL BE MADE AVAILABLE WITHIN 30 MILES.
INSTALL NEW STANDBY GENERATOR AND APPURTENANCES
INSTALL NEW STANDBY GENERATOR,
LOUVERS, DAY TANK, DAMPERS, DIESEL
EXHAUST ETC
NO NO NO
CROSS CONNECT NEW GENERATOR TO
THE EXISTIING ELECTRICAL SYSTEM
NO YES NO
INTERCEPT EXISTING EMERGENCY FEED FROM THE EMRGENCY PARALLEL SWITCHBOARD. INTERCEPT NORMAL FEED FROM ATS-BREQ. PROVIDE NEW AUTOMATED TRANSFER SWITCH. EXPECTED SHUTDOWN 4-8 HOURS.
DEMOLISH EXISTING BOILER AND ANCILLARY EQUIPMENT
DEMOLISH EXISTING BOILERS, BLOWDOWN
TANK, PIPING, CONTROL SYSTEMS AS
CALLED ON DRAWINGS
NO NO NO
REMOVE EMERGENCY GAS SHUTOFF VALVE AND RELOCATE IT INSIDE THE PLANT
REMOVE EMERGENCY GAS SHUTOFF
VALVE AND RELOCATE IT INSIDE THE PLANT
NO NO
NATURAL
GAS
SHUTDOWN
EXPECTED SHUTDOWN- 8 HOURS. OPERATE TEMPORARY BOILERS ON FUEL OIL FROM PLANT DURING
RELOCATION
PAINT ALL SPECIFIED AREAS BEFORE NEW WORK BEGINS
PAINT ALL SPECIFIED AREAS BEFORE NEW
WORK BEGINS
NO NO NO
INSTALL NEW BOILERS AND EQUIPMENT
INSTALL NEW BOILERS AND EQUIPMENT AS
SHOWN ON PLANS
NO NO NO
INCLUDE ALL EQUIPMENT, PIPING, TIE-INS SHOWN ON PLANS. INTENT IS TO UPGRADE ELECTRIUCAL FEEDERS TO THE EXISTING MOTOR CONTROL CENTERS AS REQUIRED DURING DEMOLITION/CONSTRUCTION TO AVOID AN
ELECTRICAL SHUTDOWN WHEN THE TIME COMES TO HOOKUP NEW EQUIPMENT.
COMMISSION NEW BOILER PLANT
COMMISSION NEW BOILER PLANT NO NO NO
REMOVE TEMPORARY BOILERS
REMOVE TEMPORARY BOILERS AND
RESTORE SITE
NO NO NO
REMOVE EXISTING BOILER PLANT MCC
DEMOLISH EXISTING BOILER PLANT MCC.
REFEED BOILER PLANT PANELS 'BP--H4A', 'BP-H4B', BP-P2A', 'BP-P2B' AND RELATED TRANSFORMERS FROM NEW
BOILER PLANT SWITCHGEAR.
INSTALL CHILLER PLANT PERMANENT STANDBY POWER
INSTALL CHILLER PLANT PERMANENT
AUTOMATIC TRANSFER SWITCH.
YES
DISCONNECT TEMPORARY AUTOMATIC TRANSFER SWITCH 'U2-ATS-CP'.
INSTALL CHILLER PLANT PERMANENT AUTOMATIC TRANSFER SWITCH 'CP-ATS-EDP2'.
PROJECT CLOSEOUT
CLOSE OUT PROJECT PER VA
REQUIREMENTS
NO NO NO
GENERAL NOTES:
1. CONTRACTOR TO COORDINATE ALL SHUTDOWNS REQUIREMENT IN WRITING WITH THE VA COR AT LEAST FOUR WEEKS IN ADVANCE.
2. THE CONSTRUCTION PHASING SEQUENCE IS MEANT AS A DESIGN INTENT. CONTRACTOR IS RESPONSIBLE FOR PROVIDING A DETAILED STEP BY STEP CONSTRUCTION PHASING SEQUENCE AND SUBMIT
TO THE VA COR AND A&E FOR APPROVAL.
3. IN CASE OF ANY DISCREPANCIES BETWEEN THE NARRATIVE BELOW, DRAWINGS OR SPECS, A RFI SHALL BE GENERATED BY THE CONTRACTOR TO THE DESIGN TEAM. THE NARRATIVE BELOW MAY OR
MAY NOT CONTAIN ALL THE DETAILS LISTED ELSEWHERE ON THE DRAWINGS/SPECS, REFER TO DRAWINGS/SPECS FOR MORE INFORMATION.
4. CONTRACTOR TO COORDINATE WITH LOCAL DIESEL DELIVERY COMPANIES TO ENSURE THAT FUEL DELIVERY TRACKS AREA AVAILABLE ON STANDBY TO ENSURE THAT FUEL OIL IS AVAILABLE AT ALL
TIMES TO FILL THE EXISTING GENERATOR BELLY TANKS DURING SHUTDOWNS.
PHASE 2 - INSTALL TEMPORARY BOILERS
THE INTENT OF PHASE 2 IS TO INSTALL TEMPORARY BOILERS PRIOR TO DEMOLITION OF THE EXISTING BOILERS OR ANY PHASE 32 WORK SO THERE IS NO DISRUPTION TO FACILITY OPERATIONS.
THE BASIS OF DESIGN FOR THE TEMPORARY BOILERS IS POWERHOUSE. THE TEMPORARY BOILERS HAVE THE CAPACITY TO HANDLE THE FACILITY STEAM LOADS FOR BOTH WINTER AND SUMMER AS INDICATED ON THE DRAWINGS. EACH BOILER WILL HAVE THE CAPABILITY TO HAVE DUEL FUELS (NATURAL GAS AND #2 FUEL OIL) AND WILL HAVE A DA TANK, CHEMICAL SYSTEM AND OTHER ANCILLARY EQUIPMENT. PRESSURE RELIEF VALVE WILL BE INSTALLED ON 8” HPS IN CHILLER PLANT AND TIED INTO EXISTING 10” MAIN VENT STACK. PRESSURE RELIEF VALVE WILL BLOW OFF STEAM TO MAIN VENT
STACK DURING LOW SUMMER LOAD.
A CONTROL TRAILER WILL BE INSTALLED ADJACENT TO THE TEMPORARY BOILER TRAILERS. THE CONTROL TRAILER WILL CONTAIN SINK, CONTROLLERS, SCREENS AND A REST ROOM. THE REST ROOM AND
SINK WILL BE PUMPED OUT ON A WEEKLY BASIS.
PREPARATION WORK MUST BE CONDUCTED IN ORDER TO OPERATE THE TEMPORARY BOILERS. THE PREPARATION WORK INCLUDES:
1. UTILITY TIE-INS TO EXISTING FACILITY UTILITIES
2. MODIFICATION OF THE NATURAL GAS AUTOMATIC SHUT-OFF VALVE
3. REMOVE NATURAL GAS LINE TO BOILER #1.
4. INSTALL TEMPORARY NATURAL GAS SERVICE FOR TEMPORARY BOILERS.
5. INSTALL TEMPORARY WATER SERVICE FOR TEMPORARY BOILERS.
6. INSTALL NEW TEMPORARY MEDICAL GAS CABINETS AND ALARMS IN TEMPORARY CONTROL ROOM.
7. MODIFICATION OF THE STEAM HEADER PIPING IN THE BOILER PLANT.
8. MODIFICATION OF THE EXISTING CONDENSATE SYSTEM.
9. EXISTING DOMESTIC WATER HEATERS WILL BE REPLACED.
10. EXISTING AHU VFD WILL BE RELOCATED.
11. EXISTING COMPRESSORS WILL BE RETROFITTED WITH A LEAD/LAG CONTROLS. PRESSURE ALARM WILL BE EXTENDED TO THE TEMPORARY CONTROL ROOM.
12. EXISTING MAIN GAS VALVE ALARM WILL BE EXTENDED TO THE TEMPORARY CONTROL ROOM
13. EXISTING HIGH PRESSURE STEAM UNIT HEATERS WILL BE REPLACED.
14. EXISTING WINTER BOILER FUEL OIL PUMPS WILL BE REPLACED.
15. INSTALLATION OF PROTECTIVE PARTITIONS, A DUST BARRIER ENCLOSURE TO PROTECT EXISTING EQUIPMENT IN THE BOILER PLANT
THE UTILITIES INCLUDING NATURAL GAS, DIESEL FUEL OIL, CONDENSATE PIPING, ELECTRIC, DDC CONTROLS, AND WATER MUST BE CONNECTED TO THE TEMPORARY BOILERS. SHUTDOWNS WILL BE REQUIRED. IN ADDITION, THE STEAM PIPING FROM THE TEMPORARY BOILERS SHALL BE CONNECTED TO THE EXISTING STEAM HEADER VIA A CONNECTION POINT IN THE EXISTING CHILLER PLANT. THIS
CONNECTION POINT WILL PROVIDE STEAM TO THE FACILITY.
THE ELECTRIC FEEDS WILL BE FROM THE EXISTING PANELS AND SWITCHGEAR IN THE EXISTING BOILER PLANT. THE BUILDING AUTOMATION SYSTEM (BAS) AND OTHER COMMUNICATIONS WILL BE EXTENDED FROM THE EXISTING BOILER PLANT TO THE TEMPORARY BOILER CONTROL ROOM. ALL FUNCTIONS OF THE CURRENT CONTROL ROOM AND HOSPITAL CRITICAL MONITORING SYSTEMS (MEDICAL GASES, EMERGENCY GENERATOR STATUS, TANKS.) NEED TO BE REPLICATED TO THE TEMPORARY CONTROL ROOM.
THE NATURAL GAS MAIN LINE WILL REQUIRE MODIFICATION PRIOR TO PHASE 2 WORK. A TEE WILL HAVE TO BE INSTALLED IN THE MAIN LINE AND THE EXISTING MANUAL SHUT OFF VALVE WILL REQUIRE RELOCATION TO INSIDE THE BOILER PLANT. THE EXISTING PLANT WILL REQUIRE A SWITCH OVER TO DIESEL FUEL OIL WHILE THE NATURAL GAS LINE IS MODIFIED.
THE CONDENSATE SYSTEM WILL BE MODIFIED SO THE FACILITY CONDENSATE CAN BE TRANSFERRED TO THE TEMPORARY BOILERS. THE NEW CONDENSATE TANK WILL BE LOCATED AT THE EXISTING FUEL OIL #6 PUMPING AREA WITHIN THE BOILER PLANT. THE PIPING FROM THE NEW CONDENSATE TANK WILL BE PIPED TO THE TEMPORARY BOILERS WITH SEVERAL BRANCHES (VALVED AND CAPPED) FOR FUTURE CONNECTIONS TO BOILER FEED SYSTEM IN PHASE 2. EXISTING CONDENSATE TANK AND PUMPS WILL BE DEMOLISHED AFTER NEW CONDENSATE TANK, PUMPS AND PIPING ARE INSTALLED AND
COMMISSIONED.
THE FOLLOWING PIPE MODIFICATIONS WILL NEED TO BE MADE PRIOR TO PHASE 2 INCLUDING STEAM CONNECTION IN THE CHILLER ROOM TO TEMPORARY BOILER, MODIFYING THE CONNECTION TO HOSPITAL STEAM BRANCH, MODIFYING THE CONNECTION TO LAUNDRY STEAM BRANCH, AND MODIFYING THE 4” CONNECTION TO DA TANK PRV. SIMILARLY, CONNECTIONS TO CONDENSATE RETURN LINES FROM HOSPITAL, MEDIUM PRESSURE DRIPS WILL REQUIRE MODIFICATION. THE STEAM PIPING CONNECTIONS FROM THE TEMPORARY BOILERS TO THE HOSPITAL AND LAUNDRY BRANCHES WILL HAVE A TEE WITH SHUTOFF VALVES SO ONCE THE TEMPORARY BOILERS ARE OPERATING, THE EXISTING BOILERS CAN BE ISOLATED.
ONCE ALL THE UTILITIES HAVE BEEN TIED IN, THE TEMPORARY BOILERS WILL BE COMMISSIONED. THE TEMPORARY BOILERS MUST OPERATE FOR TWO WEEKS AFTER COMMISSIONING TO ENSURE THE
BOILERS ARE OPERATING WITHOUT ISSUES BEFORE THE EXISTING BOILERS ARE DEMOLISHED.
EXISTING DOMESTIC WATER HEATERS WILL BE REPLACED WITH NEW IN THIS PHASE. PROVIDE NEW PRV AND CONNECT TO 6” HPS SECONDARY HEADER TO PROVIDE LOW PRESSURE STEAM FOR NEW
DWHS.
EXISTING AHU VFD WILL BE RELOCATED. ALSO EXISTING AIR COMPRESSORS WILL BE PROVIDED WITH THE DDC MONITORING AT THE TEMPORARY CONTROL ROOM.
REPLACE EXISTING HIGH PRESSURE STEAM UNIT HEATER WITH LOW PRESSURE. REPLACE PRV SERVING MUA-1 WITH HIGHER CAPACITY TO PROVIDE LOW PRESSURE STEAM FOR EXISTING MUA-1 AND NEW
UNIT HEATERS.
CROSS-CONNECT EXISTING SUMMER BOILER FUEL PIPING AND WINTER BOILER FUEL PIPING TO ALLOW SUMMER BOILER PUMP TO SERVE EXISTING AND TEMPORARY BOILERS DURING REPLACEMENT OF
WINTER BOILER PUMPS.
LASTLY, PROTECTIVE PARTITIONS, A DUST BARRIER ENCLOSURE WILL BE INSTALLED TO PROTECT EXISTING EQUIPMENT IN THE PLANT THAT ARE NOT SLATED FOR DEMOLITION SO THAT BOILER PLANT
PERSONNEL CAN SERVICE THIS EQUIPMENT DURING CONSTRUCTION.
PHASE 3: (NEW WORK)
PHASE 3 CANNOT COMMENCE UNTIL PHASE 2 WORK HAS BEEN COMPLETED AND ACCEPTED BY THE VA. THE GC WILL RECEIVE A NOTICE TO PROCEED TO PHASE 3 ONCE PHASE 2 WORK IS ACCEPTED BY
THE VA.
THIS PHASE INCLUDES THE DEMOLITION OF EXISTING EQUIPMENT NOT DEMOLISHED DURING PHASE 2 AND INCLUDES THE INSTALLATION OF NEW BOILERS, WATER HEATERS, AND RELATED EQUIPMENT. A NEW STANDBY GENERATOR WILL ALSO BE INSTALLED DURING PHASE 3. THE EXISTING CHIMNEY WILL BE REUSED.
THE FOLLOWING EXISTING EQUIPMENT IS TO BE REMOVED FROM THE BOILER PLANT DURING PHASE 3:
1. (3) EXITING 1000 HP WATER TUBE BOILERS WITH ECONOMIZERS
2. (1) 400 HP SUMMER FIRETUBE BOILER
3. DEAERATOR TANK AND PUMPS
4. BLOWDOWN TANK
5. DIESEL FUEL OIL PUMPS (SERVING 400 HP SUMMER BOILER)
6. DIESEL FUEL OIL PUMPS (SERVING EMERGENCY GENERATORS)
7. CHEMICAL FEED SYSTEM
8. STEAM HEADER PIPING
9. NATURAL GAS METER
10. ADVANCED STEAM METERS
11. CIRCULAR CHART RECORDERS, CONTROLLERS LOCATED IN THE CONTROL ROOM
12. EXISTING WATER HEATERS (AFTER INSTALLATION OF NEW WATER HEATERS)
THE FOLLOWING DEMOLITION WORK IN THE EXISTING INTERIOR SPACE WILL ALSO TAKE PLACE DURING PHASE 3:
1. GENERATOR ROOM: DEMOLISH PORTIONS OF EAST AND WEST WALLS FOR RIGGING AND NEW AIR INTAKE LOUVERS
2. BOILER ROOM: DEMOLISH THE EXISTING WINDOW AND PORTION OF WEST WALL AND SOME RAILING AT THE CATWALK BELOW THE EXISTING WINDOW FOR NEW BOILER RIGGING WORK.
3. CONTROL ROOM: DEMOLISH THE EXISTING CEILING AND LIGHTING
4. ROOF: COORDINATE WITH MEP FOR REMOVING THE FANS, VENT PIPING, DOMESTIC WATER HEATERS AND STACKS, AND ROOF PENETRATION WORK
ONCE THE EQUIPMENT IS DEMOLISHED AND PRIOR TO RIGGING IN THE NEW BOILERS AND RELATED EQUIPMENT, THE PLANT INSIDE WALLS SHALL BE PAINTED AND SECTIONS OF MASONRY REPOINTED.
AFTER PAINTING AND REPOINTING, THE BOILERS AND RELATED EQUIPMENT CAN BE INSTALLED. IN ORDER TO RIG IN THE NEW EQUIPMENT, CERTAIN SECTIONS OF THE EXISTING MASONRY WALLS AND WINDOWS IN THE BOILER PLANT WILL REQUIRE MODIFICATION SO THE NEW BOILERS CAN BE RIGGED INTO THE BUILDING. EXISTING UTILITIES ON THE WALL WILL HAVE TO BE RELOCATED. ONCE THE NEW BOILERS HAVE BEEN RIGGED INTO THE BOILER PLANT, THE WALL OPENING SHALL BE CLOSED WITH NEW AIR INTAKE LOUVER.
PATCHING THE ROOF OF THE ROOM OPENING FROM DEMOLITION WORK WHERE IS NOT USED FOR INSTALLATION OF NEW PIPING AND NEW STACKS. TEHER ARE SOME NEW ARCHITECTURAL WORK IN THE UPGRADE CONTROL ROOM INCLUDING THE NEW CEILING OF A SUSPENDED TILE SYSTEM, NEW ROOF DECKING AS WELL AS MEP WORK. ANOTHER NEW WORK WILL BE REQUIRED AT THE EXISTING OPENING BETWEEN MECHANIAL ROOM AND CHIMNEY. A NEW BREECHING OF 3-DUCT SYSTEM WILL REPLACE THE EXISTING SINGLE DUCT. SOME OF NEW WORK WILL BE SCHEDULED IN THIS AREA INCLUDING, NEW
STRUCTURAL FRAMING OPENING TO PROTECT THE NEW DUCTS, A NEW ACCESS PANEL AND WALL INFILL.
THE CATWALKS WILL BE INSTALLED AFTER THE BOILERS ARE IN PLACE.
IT SHOULD BE NOTED WHILE THE DIESEL FUEL OIL PUMPS SERVING EMERGENCY GENERATOR ARE BEING REMOVED, PROVISIONS MUST BE MADE TO PROVIDE FUEL OIL TO THE EXISTING EMERGENCY GENERATOR FUEL OIL USING BELLY TANKS. THE CONTRACTOR WILL CONTRACT WITH A FUEL OIL PUMPING COMPANY LOCATED WITHIN A 30 MILE RADIUS TO ENSURE FUEL OIL IS READILY AVAILABLE.
ONCE THE NEW BOILER PLANT AND RELATED SYSTEM ARE OPERATING, THE SYSTEMS SHALL BE COMMISSIONED.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .