S06 - Pre-Proposal Conference slides NCOTA 3B.pdf

PDF 526 KB Posted

Attached to
Y1JZ--NCOTA 3B Completion Project
Solicitation number
36C10F25B0002
Issued by

About this file

These are pre-proposal conference slides for the National Cemetery of the Alleghanies Phase 3B Development (NCOTA 3B) project, solicitation number 36C10F25B0002. The Department of Veterans Affairs Office of Construction and Facilities Management is seeking proposals exclusively from Service-Disabled Veteran-Owned Small Businesses (SDVOSB) for a construction project with a project cost range between $2,000,000 and $5,000,000. The contract will be firm fixed price, with evaluation based on responsive bidder/lowest price, and is subject to the Davis-Bacon Act and Buy American Act.

Key solicitation details include a proposal due date of August 19, 2025 at 10:00 AM Eastern, with a tentative contract award date of September 16, 2025. Bidders must be registered in SAM and verified in SBA VetCert, provide a bid bond of 20% of the offer price (not exceeding $3,000,000), and submit performance and payment bonds for 100% of the award amount. The period of performance is 365 calendar days after the Notice to Proceed. Proposals must be submitted via mail or hand-carried to the National Cemetery of the Alleghanies in Bridgeville, Pennsylvania, with strict requirements for packaging and submission.

View the file

Other files

File Type Posted
36C10F25B0002 0008.docx DOCX document
Updated Wage Determination PA20250104.pdf PDF
BMP Chapter 6-7-3.pdf PDF
36C10F25B0002 0007.docx DOCX document
Store Front Shop Drawing.pdf PDF
Pages from 10 14 00.1.R2 Exterior Signage.pdf PDF
Joint Sealant- Product Data and Color Chart.pdf PDF
36C10F25B0002 0006.docx DOCX document
SI-009 R02 Directional Signage - 8.20.2020.pdf PDF
RFI SUBMISSION LOG 8 04 - FINAL.pdf PDF
36C10F25B0002 0005.docx DOCX document
04 40 10 01R1 Stone Caps AE rvw AN.pdf PDF
04 40 10 08 Revd Stone Caps at Ossuary AE rvw NET.pdf PDF
Submittal 05 52 00-1.1 Handrails.pdf PDF
05 52 00.4 New handrail sections with slip joints.pdf PDF
05 52 00-03 SS Handrail PD - AE rvw AN.pdf PDF
36C10F25B0002 0003.docx DOCX document
Appendix O - NCOTA PH3B Areas for Joint Sealant.pdf PDF
Appendix N1 - INFILTRATION BERM.pdf PDF
Appendix N - Section 14 Grid Markers.pdf PDF
Appendix L - Section 11 Grid Markers.pdf PDF
Appendix K - Section 9 Grid Markers.pdf PDF
Appendix D1 - Columbarium Niche Foundation Finish and Vertical Joints.pdf PDF
Appendix B6 - MC Cable.pdf PDF
Appendix B3 - Video Surveillance Cable.pdf PDF
Appendix A1 - TEMPORARY SHELTER RELOCATION.pdf PDF
Appendix M - Section 12 Grid Markers.pdf PDF
Appendix H - Cracked Mortar- Columbarium D.pdf PDF
Appendix D - Contract B- Caps to be Replaced Revised.pdf PDF
Appendix C - Sealant Replacement Locations.pdf PDF
Appendix B7 - Fire Detection and alarm Cable.pdf PDF
Appendix B5 - Pre-Product Data.pdf PDF
Appendix B1 - Video Surv. Product info.pdf PDF
Appendix A - FWS and Storm Structures.pdf PDF
Appendix T - NCOTA Phase 3B Development - Specifications Set 2.pdf PDF
Appendix Q - NCOTA Phase 3B Development - Package A Excerpts.pdf PDF
Appendix B - Existing columbarium concrete sidewalk replacement.pdf PDF
Appendix S - NCOTA Phase 3B Development - Specifications Set 1.pdf PDF
Appendix R - NCOTA Phase 3B Development - Package B Excerpts.pdf PDF
Appendix P - Sealant Technical Data Sheet.pdf PDF
Appendix J - Sect C8-C10 Grid Markers.pdf PDF
Appendix I - Niche Touch-up Locations.pdf PDF
Appendix G - Electrical MR ref dwg.pdf PDF
Appendix F - Cracked Mortar- Columbarium B.pdf PDF
Appendix E - Contract B- Sidewalk Sections to Be Replaced Revised.pdf PDF
Appendix B8 - Fire Detection and Alarm Submittal RE Response.pdf PDF
Appendix B4 - Pre-Product Data.pdf PDF
Appendix B2 - Video Surv. Product info.pdf PDF
36C10F25B0002_1.docx DOCX document
wage determination PA20250104.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IAS

National Cemetery of the Alleghanies Phase 3B Development (NCOTA 3B)

SOLICITATION 36C10F25B0002

PROJECT # 925-008B

PRE-PROPOSAL CONFERENCE

July 23, 2025

1 Office of Construction and Facilities Management

Agenda

Opening Remarks NCA Mission Solicitation Summary Milestones Project Scope and Overview Site walkthrough

2 Office of Construction and Facilities Management

Opening Remarks

Introductions VA Representatives

VA CFM: Victoria Wayne, Contracting Officer

VA CFM: Joyce Johnson, Senior Resident Engineer

VA CFM: Kim Giles, Resident Engineer

3 Office of Construction and Facilities Management

NCA Mission The National Cemetery Administration honors Veterans and their families with final resting places in national shrines and lasting tributes that commemorate their service and sacrifice to our Nation.

In 1865, during his second inaugural address, President Abraham

Lincoln pledged: “To care for him who shall have borne the battle and for his widow and his orphan.”

In 2023, the VA upholds this pledge through the mission:

“To fulfill President Lincoln’s promise to care for those who have served in our nation’s military and for their families, caregivers, and survivors.”

4 Office of Construction and Facilities Management

Solicitation Overview

Solicitation is set aside for Service Disabled Veteran Owned Small Business (SDVOSB) in accordance with 38 U.S.C. 8127(d).

SDVOSB Offerors must be registered in SAM and registered & verified in SBA VetCert prior to submission Annual Representation and Certification https://www.sam.gov/SAM/ Small Business Administration Veteran Certification

(VetCert) https://veterans.certify.sba.gov/ https://veterans.certify.sba.gov/

5 Office of Construction and Facilities Management

Service-Disabled

Veteran-Owned Small Business VA Office of Small and Disadvantaged

Business Utilization (OSDBU) Washington, D.C.

http://www4.va.gov/osdbu/

Contact OSDBU for information on Joint Ventures Teaming Agreement Mentor Protégée (See VAAR 819-71) SBA Veteran Certification (VetCert) http://www4.va.gov/osdbu/

6 Office of Construction and Facilities Management

Project Cost Range Between $2,000,000 and $5,000,000

Contract Type: Firm Fixed Price Evaluation Method: Responsive Bidder/Lowest Price

Federal , State, and Local Tax (FAR Clause 52.229-3) It’s the Responsibility of the Contractor, include it in your proposal price Construction Wage Rate Requirements (Davis

Bacon Act) Applies Buy American Act Applies

7 Office of Construction and Facilities Management

Contract Line Item Number (CLIN 001) CLIN 001: Base Bid – Lump sum for all work necessary to complete the 3B project in accordance with solicitation scope of wok and all attachments.

Period of Performance 365 calendar days after the Notice to

Proceed.

8 Office of Construction and Facilities Management

Bid Bond/Bid Guarantee (SF 24)

See Solicitation for more information.

Bond amount 20% of the offer price but shall not exceed $3,000,000 An original, hard copy, executed Bid Guarantee (on form SF-24) must be presented at the time of the proposal due date/time. Shall be within contractor’s proposal.

Ensure your bond is in compliance with Far Part 28.

Performance & Payment Bonds (SF 25) Required Penal sum = 100% of award amount Required of awardee within 10 calendar days of award.

9 Office of Construction and Facilities Management

Insurance See Solicitation Certificate of Insurance required prior to commencing work

Worker’s compensation and employers liability General Liability Automobile Liability

10 Office of Construction and Facilities Management

Pre-Proposal Inquiries (PPI)/Requests for Information (RFI’S) Must be in writing via email to Contracting Officer Questions Due:

July 30, 2025, at 12:00 PM Eastern Email to: Victoria.wayne@va.gov The subject line to read: “NCOTA – 3B Development- Technical Questions”

Answers posted on or about: August 5, 2025 mailto:Victoria.wayne@va.gov

11 Office of Construction and Facilities Management

Submission Instructions

BID PACKAGE CONTENTS (Pt. 1 of 2):

Standard Form (SF) 1442 Solicitation, Offer and Award: Bidders must complete & sign the “OFFER” section of the SF 1442. Please include your company’s Unique Entity Identifier number associate with SAM.gov in Block 14. Submissions may contain electronic signature or “wet signature” for the signatory of your firm.

Acknowledgement of All Amendments: Bidders must acknowledge all amendments by either 1.) Completing block 19 of the SF 1442, or 2.)

Returning the signed amendment form(s) with the submission.

Price Schedule: Bidders must include the total lump sum price (for all work) in Block 17 on the SF 1442.

Bid Guarantee: Bidders must furnish a bid guarantee (see FAR 52.228-1).

The bid guarantee must be provided on Standard Form 24.

Safety: See page 15 and 16 of the solicitation for submission requirements.

Representations & Certifications: The offeror must provide their Representations and Certifications or their response to FAR 52.204-8 (2)

(i) or (ii) Annual Representations and Certifications.

12 Office of Construction and Facilities Management

Submission Instructions

BID PACKAGE CONTENTS (Pt. 2 of 2):

Offeror must provide their responses to the following:

FAR 52.204-24 (d) Representation FAR 52.209-7 (b) Information Regarding Responsibility

Matters FAR 52.209-13 (b) (1) or (2) Violation of Arms Controls

Treaties or Agreements Tax on Certain Foreign Procurements: FAR 52.229-11 (d) Post Award Small Business Program Representations: FAR

52.219-28 (h)(If applicable) Limitations on Subcontracting Clause fill in Notice to SDVOSB Joint Venture/Mentor Protegee: You must provide a certification from each SDVOSB joint partner. See page 16 of solicitation for further details.

13 Office of Construction and Facilities Management

Submission Instructions

Proposal Submission Instructions Mail or Hand Carry ONLY by proposal due date and time.

Bidders may submit their bids by the deadline via mail or hand carry to:

National Cemetery of the Alleghenies Administration Building - Conference Room 318 1158 Morgan Road Bridgeville, PA 15017 ATTN: Victoria Wayne, Contracting Officer, CFM

Bids must be in sealed envelopes and labeled to read:

“CFM -FOUO-SEALED BID PACKAGE–36C10F25B0002

NCOTA 3B Development– SEALED BID DOCUMENTS –

COMPANY NAME”

Bids that are to be hand delivered will only be accepted starting one (1) hour prior to the bid opening time

Failure to provide a properly completed and signed original offer could result in the bid being determined non-responsive and rejected. EMAILED, FAXED, OR DELIVERY BY ANY OTHER

ELECTRONIC MEANS IS NOT AUTHORIZED AND WILL BE

REJECTED.

14 Office of Construction and Facilities Management

Milestones

• Solicitation Issued July 7, 2025

• RFI’s Due July 30, 2025, 12:00PM Eastern

• Proposal Due Date August 19,2025, 10:00AM Eastern

• Contract Award September 16, 2025 (Tentative)

• Notice To Proceed TBD (Tentative)

15 Office of Construction and Facilities Management

Project Scope/Overview

VA Office of Construction & Facilities Management

Joyce Johnson, SRE Kim Giles, RE

16 Office of Construction and Facilities Management

QUESTIONS???

No technical questions will be answered today or during the pre-proposal site visit.

Submit all technical Requests for Information in writing as per the solicitation.

Questions

Slide Number 1
Agenda
Opening Remarks
NCA Mission
Solicitation Overview
Solicitation Overview�Service-Disabled�Veteran-Owned Small Business
Solicitation Overview
Solicitation Overview
Solicitation Overview
Solicitation Overview
Solicitation Overview
Solicitation Overview�Submission Instructions
Solicitation Overview�Submission Instructions
Solicitation Overview�Submission Instructions
Milestones
Project Scope/Overview
Questions???��No technical questions will be answered today or during the pre-proposal site visit. ���Submit all technical Requests for Information in writing as per the solicitation.