RFIs and Govt responses.pdf

PDF 244 KB Posted

Attached to
Y1JZ--NCOTA 3B Completion Project
Solicitation number
36C10F25B0002
Issued by

About this file

This document is a Request for Information (RFI) Submission Log for the NCOTA - 3B Development project (Solicitation #36C10F25B0002) for the CFM National Region, dated 7/29/2025 through 8/05/2025. The RFI covers multiple technical and administrative aspects of the project, including site logistics, environmental controls, building systems, and contractor requirements. Key details include temporary laydown areas along Morgan Road, delivery protocols, erosion control measures, security system integration with VAMC network, emergency lighting upgrades, fire alarm installations, and specific requirements for limestone cap repairs and wall coating systems.

The log addresses numerous technical questions from potential contractors, with responses from the VA providing clarification on project specifications. Notable requirements include securing work areas, coordinating deliveries during general contractor work hours, installing Edwards Rate Compensation Heat Detectors, ensuring security systems tie back to the local VAMC network, and maintaining specific warranty conditions for wall coatings. The document also clarifies administrative requirements such as tax inclusion, wage determinations (PA20250104 dated 03/28/2025), and strict guidelines for project personnel roles, stipulating that superintendent, SSHO, and QA/QC positions cannot be "triple hatted" and must be full-time, qualified individuals.

View the file

Other files

File Type Posted
36C10F25B0002 0008.docx DOCX document
Updated Wage Determination PA20250104.pdf PDF
BMP Chapter 6-7-3.pdf PDF
36C10F25B0002 0007.docx DOCX document
SI-009 R02 Directional Signage - 8.20.2020.pdf PDF
RFI SUBMISSION LOG 8 04 - FINAL.pdf PDF
Store Front Shop Drawing.pdf PDF
Pages from 10 14 00.1.R2 Exterior Signage.pdf PDF
Joint Sealant- Product Data and Color Chart.pdf PDF
36C10F25B0002 0006.docx DOCX document
36C10F25B0002 0005.docx DOCX document
04 40 10 01R1 Stone Caps AE rvw AN.pdf PDF
04 40 10 08 Revd Stone Caps at Ossuary AE rvw NET.pdf PDF
05 52 00-03 SS Handrail PD - AE rvw AN.pdf PDF
36C10F25B0002 0003.docx DOCX document
Submittal 05 52 00-1.1 Handrails.pdf PDF
05 52 00.4 New handrail sections with slip joints.pdf PDF
S06 - Pre-Proposal Conference slides NCOTA 3B.pdf PDF
Appendix M - Section 12 Grid Markers.pdf PDF
Appendix H - Cracked Mortar- Columbarium D.pdf PDF
Appendix D - Contract B- Caps to be Replaced Revised.pdf PDF
Appendix C - Sealant Replacement Locations.pdf PDF
Appendix B7 - Fire Detection and alarm Cable.pdf PDF
Appendix B5 - Pre-Product Data.pdf PDF
Appendix B1 - Video Surv. Product info.pdf PDF
Appendix A - FWS and Storm Structures.pdf PDF
Appendix T - NCOTA Phase 3B Development - Specifications Set 2.pdf PDF
Appendix Q - NCOTA Phase 3B Development - Package A Excerpts.pdf PDF
Appendix B - Existing columbarium concrete sidewalk replacement.pdf PDF
Appendix O - NCOTA PH3B Areas for Joint Sealant.pdf PDF
Appendix N1 - INFILTRATION BERM.pdf PDF
Appendix N - Section 14 Grid Markers.pdf PDF
Appendix L - Section 11 Grid Markers.pdf PDF
Appendix K - Section 9 Grid Markers.pdf PDF
Appendix D1 - Columbarium Niche Foundation Finish and Vertical Joints.pdf PDF
Appendix B6 - MC Cable.pdf PDF
Appendix B3 - Video Surveillance Cable.pdf PDF
Appendix A1 - TEMPORARY SHELTER RELOCATION.pdf PDF
Appendix S - NCOTA Phase 3B Development - Specifications Set 1.pdf PDF
Appendix R - NCOTA Phase 3B Development - Package B Excerpts.pdf PDF
Appendix P - Sealant Technical Data Sheet.pdf PDF
Appendix J - Sect C8-C10 Grid Markers.pdf PDF
Appendix I - Niche Touch-up Locations.pdf PDF
Appendix G - Electrical MR ref dwg.pdf PDF
Appendix F - Cracked Mortar- Columbarium B.pdf PDF
Appendix E - Contract B- Sidewalk Sections to Be Replaced Revised.pdf PDF
Appendix B8 - Fire Detection and Alarm Submittal RE Response.pdf PDF
Appendix B4 - Pre-Product Data.pdf PDF
36C10F25B0002_1.docx DOCX document
wage determination PA20250104.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI SUBMISSION LOG 7/29/2025

Solicitation# 36C10F25B0002

NCOTA - 3B DEVELOPMENT

CFM NATIONAL REGION

1. Can you please provide locations and acreage available to the Contractor for temporary laydown of equipment, materials, trailers, etc.?

Reference Drawing CS100 in Appendix Q of RFP. The contractor’s temporary laydown area will be along Morgan Rd behind the engraver’s yard.

2. Will we be permitted to keep equipment within the work areas during off hours?

Yes, it must be secured. The location must be coordinated with the RE.

3. Is there a delivery schedule protocol for the site? Are we required to have escorts with all trucks or deliveries to the job?

Deliveries must be made during GC work hours; large deliveries like concrete trucks should be escorted by the GC.

4. What will be the requirements for Temporary Fence? Will certain areas require a “Privacy” type Fence?

Privacy fencing will not be required, however the Contractor will still be required to secure any work areas from public access

5. Can you please release as-built drawings for the entire project? Specifically looking for as-built information regarding the storm sewer, grading plan, and irrigation or other utilities that may be within the work limits.

As-built drawings are not available. Please reference Appendix Q and Appendix R of the RFP.

6. Can you please provide a marked up drawing with the limits of erosion control removal? Being a firm price, this item is very difficult to quantify without more information. Alternatively for bidding purposes, would the Owner consider Erosion Control paid on a time and material basis against an allowance? The site is overgrown in several areas and is difficult to quantify from the site walk or from the drawings provided.

Please reference attachment file “NCOTA 3B – Temporary E&S measures left in place”.

A time and material compensation structure is not allowed.

7. Is the Contractor and/or earthwork subcontractor required to become a Co-Permittee of the existing NPDES Permit?

No

8. Who is the authority over the NPDES permit for the project? Are there any inspection reports from the authority or other that can be shared at bid time?

RFI SUBMISSION LOG 7.29.2025

NCOTA - 3B DEVELOPMENT

The PA DEP is the agency with authority over the project NPDES permit. No prior inspection reports are available. The contractor shall follow the DEP requirements for conducting weekly inspections/inspections after precipitation events utilizing the DEP form.

9. Installation of new erosion control devices was mentioned on the site walk. Are we to assume all perimeter controls are still in place and functional? This reinforces the importance to understand what is currently installed for the removal, and if the Contractor must install new BMP in an area where it is already called for an current BMP to be removed.

The Contractor to assume all E&S needs to be installed.

10. Items 1.12.1 through 1.12.3 for the slope repair, plunge pool and infiltration berm will require a large amount of waste and borrow to satisfy the grading plan. Is there a designated waste or borrow site within the property limits for the Contractor's use?

There are no designated waste or borrow sites within the property limits.

11. Is there a drawdown sequence or other details provided for the work associated with Item

1.12.3 for the Infiltration Berm? There is a significant amount of water and/or wildlife within the wetland area that will need drained in order to complete the work.

The infiltration berms are provided with a valved underdrain for dewatering. The area can also be dewatered with a small pump.

12. Can you please confirm the difference between the red and black contours shown on SI- 006 in the Infiltration Berm exhibit? The contours and layout on SI-006 do not match CG102. It would appear from the site visit the area is graded to match CG102.

SI-006 was issued during construction to modify the infiltration berm grades shown on sheet CG102. The red contours indicate the modified grading.

13. There is a temporary channel DD shown on SI-006 in the Infiltration Berm area. Is this channel still installed? Will it be utilized to bypass water around the work area while we perform work associated with Item 1.12.3?

The channel was not installed.

14. Is there a temporary riser, skimmer or other BMP to serve as temporary outlet device in the infiltration berm that needs installed to prevent future sediment build up in the 4" underdrain? To act as a temporary control device while the new vegetation is established?

Per detail 3/CG502 the underdrain is installed in a 36” deep by 12” wide stone envelope wrapped in geotextile fabric. The geotextile wrap should prevent sediment

RFI SUBMISSION LOG 7.29.2025

entering the underdrain. The Contractor shall remove and replace the stone/geotextile wrap after all the other grading work is completed in the basins.

15. For Item 1.12.2 there is currently no work specified for the southern plunge pool. Based on the site visit there does not appear to be any stone per Detail 2/CG-501 at the southern plunge pool. Can you please confirm the only scope to be performed for this item is in the northern plunge pool?

The contractor shall remove the sediment and/or restore the rock surfacing in both the northern and southern plunge pools.

16. For Item 1.12.1 major slope repair, what additional erosion control measures are required to be installed at the toe of slope above the plunge pools? These plunge pool areas will be difficult to protect from rolling debris on the hillside during regrading operations.

The contractor shall restore adjacent areas affected by work to their original condition prior to project completion. Measures to protect adjacent areas from damage are the contractor’s responsibility and means/method.

17. If plunge pools need to be reworked, is there a sequence of construction or other erosion control devices that will need to be installed to complete the work?

The Contractor shall establish E&S measures to prevent sedimentation from leaving the site.

18. Concrete pads will need removed for the underdrain installation for Item 1.8 Flower

Watering Stations. Will the concrete pad need replaced entirely? Or will patching be sufficient?

The drain is outside of the flower watering station pad. The concrete does not need to be cut/removed.

19. In general there are several irrigation lines within various work areas. Will the VA be responsible for repair or patching of any irrigation lines that may be disturbed in order to safely install the proposed work?

The VA will not be responsible for the repair and/or patching of irrigation lines. The GC will be responsible for repairing/replacing anything that is damaged due to their work.

The contractor shall conduct a joint walk through of each area with the SRE/RE prior to beginning work to note the existing conditions of any adjacent irrigation.

RFI SUBMISSION LOG 7/30/2025

CFM NATIONAL REGION

P a g e 1 / 3

1. 1.2 PIC Building

1.2.1 & 1.2.2 – There are already emergency battery back Exit lights in the main area and the office has remote heads, wouldn’t these be acceptable for emergency egress lighting? During the walk through it was mentioned the office didn’t need the overhead fixtures to work on emergency because of the battery pack remote heads.

The same could apply to the entrance area. Image attached (Emergency Lighting)

The Contractor shall replace two existing emergency battery packs in the lobby with larger battery packs and larger light fixtures that is sufficient to provide illumination throughout the entire lobby

2. 1.3 Security

1.3.3 – We are told, due to security implemented over the network, OI&T doesn’t allow for the VA Pittsburgh to give access to the Cemetery, Please advise? Threre may be a Cloud Solution that would work if the NCOTA and VA accept that type of option

This is inaccurate. The security systems cannot be stand alone, they must tie back to the local VAMC network. A Cloud Solution is not acceptable.

1.3.4 – can a product detail/submittal be provide for these devices?

Please refer to Appendix B1-B8 in RFP.

1.3.4 – Can you provide the Access Control Software for the required programming to be added?

“RS Access-IT Universal” is what the VAPHS uses for access control system

3. 1.4 Maintenance Building

1.4.1 – Can you provide the product detail/submittal for the existing hangers used in the photo so we can verify their use for this application? Image attached (Light Hangers)

No submittal was made, the Contractor will need to confirm in the field after award.

4. 1.6 Fire Alarm

1.6.1 – Can the Fire Alarm programming be provided for testing and commissioning?

If not can the original Vendor be provided?

The vendor is IES

1.6.3 – Fire Smoke Detectors do not come in “Low Temp” this installation may require engineering to be installed in a cross Beam Smoke Detection or Hea Detectors, please advise?

P a g e 2 / 3

The Contractor shall furnish and install Edwards Rate Compensation Heat Detectors (or equal) with cable run back to the administration building where Edwards Monitoring Module shall be installed.

5. Additional - There was an existing panel in the Maint Building without fireboard installed behind it, please advise if this needs addressed . Image attached (Panel)

This item is outside the scope of the Phase 3B project.

6. Will the sign-in sheet from site visit be available in addendum?

Yes, this has already been posted in an amendment to the solicitation at sam.gov.

Amm#0001

7. Please clarify if a superintendent can be a dual hat to cover the requirements of

SSHO?

No, the superintendent must be one, qualified individual wearing one hat working full time on the project.

8. If no to the question above, will the SSHO need to be full-time for this project?

Yes, SSHO/QCM may be dual hatted and must be one, qualified individual wearing only these two hats working full time on the project.

9. Please clarify if a superintendent can be a dual hat to cover the requirements of

QA/QC?

10. If no to the question above, will the QA/QC need to be full time for this project?

Yes, QCM/SSHO may be dual hatted and must be one, qualified individual wearing only these two hats working full time on the project.

11. Can a superintendent be a triple hat to cover the requirements of SSHO and

QA/QC?

P a g e 3 / 3

12. Please confirm if tax should be included in our proposal?

Yes, tax shall be included

13. Please provide the latest wage determination for this project’s county.

The latest wage determination for this project’s county was included in the solicitation. It is Wage determination number PA20250104 dated 03/28/2025.

14. Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

Yes

RFI SUBMISSION LOG 8/05/2025

1. Please provide shop drawings from Limestone Cap Installation.

Please reference attached drawings:

- “04 40 10-01R1 Stone Caps ~ AE rvw (AN)”

- “04 40 10-01R1 Stone Caps Submittal Revised (RE Response 20200531)”

- “04 40 10-08 Revd Stone Caps at Ossuary - AE rvw (NET)”

2. Please confirm that a Representative for the Manufacturer of the Memorial Wall coating system must be present to approve of application in order to maintain warranty. Please provide contact information for representative.

The VA did not specify a manufacturer/representative for the wall coating product.

Contractor shall submit Memorial Wall coating system product data complying with Contract Documents for review and approval by VA. Contractor will be responsible for satisfying conditions provided by coating system manufacturer to maintain required warranty.

3. During the site walk, it was observed that several caulking joints between the limestone caps have failed, dropping 2 to 4 inches. Upon further investigation, it appears there is no mortar in these joints, which seems to be the cause of the failure. Please advise on the required repair procedure for these areas and confirm if the scope includes the installation of new mortar prior to recaulking.

Treatment for joints between limestone caps is backer rod and sealant. See details 5 & 6 on sheet CI709 and details 1 & 2 on sheet CI713.

4. Was there a Joint Sealant Pull Test conducted as part of the QA/QC? If so, please provide.

The Contractor shall provide a sealant pull test for new sealant install.

RFI Submission Log 7 29 - final