04 40 10 01R1 Stone Caps Submittal Revised RE Response 20200531.pdf
PDF 96 KB Posted
- Attached to
- Y1JZ--NCOTA 3B Completion Project
- Solicitation number
- 36C10F25B0002
About this file
This is a Submittal document for Limestone Caps for the Department of Veterans Affairs' National Cemetery of the Alleghenies Phase 3 Development project, Contract No. 36C10F19C0002. C&C Contractors, LLC is the primary contractor, with 3D Stone as the manufacturer and Koppenberg as the installer. The submittal covers product data, samples, shop drawings, and verification materials for limestone caps, with a specific focus on meeting design requirements for color, testing, and installation. The document includes a detailed workflow showing review and approval by Joyce Johnson from the Department of Veterans Affairs, with the submittal being "Approved as Noted" on 5/31/2020, with a key remaining action to provide a plan view layout of the ossuary radial sill to show how three equal sill pieces will work along a curved wall.
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C&C Contractors 209 Lyons Street Notasulga, Alabama 36866 Phone: (334) 257-4307
Project: 1901 - 1901 Alleghenies Major 2018 1158 Morgan Rd
Bridgeville, Pennsylvania 15017
04 40 10-01R01 Limestone Cap Submittal Revised REVISION: 1 SUBMITTAL MANAGER: Brandon Johnson (C&C Contractors, LLC)
STATUS: Open DATE CREATED: 05/5/2020 ISSUE DATE: 05/5/2020 SPEC SECTION: 04 40 10 - Cut Stone Assemblies
RESPONSIBLE
CONTRACTOR:
3D Stone RECEIVED FROM: Logan Sylvester
RECEIVED DATE: 04/29/2020 SUBMIT BY: 03/5/2020
FINAL DUE DATE: 06/2/2020 LOCATION: NCOTA
COST CODE:
TYPE: Product Information
APPROVERS: Joyce Johnson (Department of Veteran Affairs), Brandon Johnson (C&C Contractors, LLC)
BALL IN COURT:
Brandon Johnson (C&C Contractors, LLC)
DISTRIBUTION:
Robert Meyer (C&C Contractors, LLC) , Jason Gerhart (Gordon) , John Keoshian (Department of Veteran Affairs) , Carlton Fuqua (C&C Contractors, LLC)
DESCRIPTION:
SUBMITTAL TRANSMITTAL
DEPARTMENT OF VETERANS AFFAIRS PROJECT: National Cemetery of the Alleghenies- Phase 3 Development
CONTRACT NO: 36C10F19C0002
Obligation No. 925CM20006
Contractor: C & C Contractors, LLC Supplier: 3D Stone- Manufacturer/ Koppenberg- Installer
Item No.
Specification Section No.:
04 40 10 Registered Submittal No.:
Paragraph No. Description of Item (Size, Type, Name, Manufacturer, Use, etc.)
No. of Copies Submitted
Submittals- Cut Stone Assemblies- Limestone Caps Submittal
1 1.3.B Product Data- See Attached for Limestone Caps ONLY 3
2 1.3C Samples for Initial Selection- No colored mortar for Limestone Caps 3
3 1.3D
Samples for Verification
1. Three samples- Limestone Cap sample to match existing to be sent to site
2. Shop Drawings- See attached Limestone Caps ONLY shop drawings (Revised to AE mark-ups attached)
3. Mortar Color Samples- No colored mortar for Limestone Caps
4 1.3E Engraving Samples- Mockup will be provided for Approval 3
5 1.3F List of Materials to be used in Construction Mockup- List to be submitted with stone veneer submittal NIC
C&C Contractors Page 1 of 3 Printed On: 06/01/2020 08 :55 AM
Submittal #04 40 10-1.1
04 40 10 - Cut Stone Assemblies
6 1.3G Qualification Data- Installer- Cap Installer Koppenberg 3
7 1.4A QA-Installer Qualification- See 1.3G- No Exceptions on 1st Submittal NIC
8 1.4B QA- Source Limitations for Stone- See 1.3B Product Data 3
9 1.4C QA- Source Limitations for Mortar- See 1.3B Product Data- Argos Materials 3
10 1.4D Mockup 3
11 1.4E Pre-installation Conference- To be set up by onsite QC 3
ATTACHMENTS:
04 40 10-01R1 Stone Caps Submittal Revised.pdf
SUBMITTAL WORKFLOW
NAME DUE DATE RETURNED
DATE RESPONSE ATTACHMENTS COMMENTS
Joyce Johnson 5/19/2020 5/31/2020 Approved As Noted
04 40 10-01R1 Stone Caps ~ AE rvw (AN).pdf
Approved as Noted
1. See the following page for submittal review comments from the L.A. Group.
2. As noted in previous review, Contractor to provide plan view details/layout of ossuary radial sill (Sheet H – Detail J/8) to show how these (3) equal sill pieces will work along the curved wall. Please provide in a separate submittal.
LA Group:
1.3B
1. ‘Gray’ color sample as reviewed/approved in the field by Jason Gerhart and John Keoshian is acceptable.
2. Revised Indiana Geological Survey testing results for ‘Gray’ stone noted.
3. Clarification of non-exposed mortar noted.
1.3D
1. In general, the revised shop drawings submitted appear to be in accordance with the design intent. Overall shop drawings do not require resubmission.
2. As noted in previous review, Contractor to provide plan view details/layout of ossuary radial sill (Sheet H – Detail J/8) to show how these (3) equal sill pieces will work along the curved wall.
Brandon Johnson 6/2/2020 Pending
C&C Contractors Page 2 of 3 Printed On: 06/01/2020 08 :55 AM https://app.procore.com/743331/project/submittal_logs/document_downloader?attachment_id=2338679594&item_id=22589087&item_type=SubmittalLog&project_id=743331 https://app.procore.com/743331/project/submittal_logs/22589087/submittal_log_approvers/document_downloader?attachment_id=2366993374&item_id=38110616&item_type=SubmittalLogApprover&project_id=743331 https://app.procore.com/743331/project/submittal_logs/22589087/submittal_log_approvers/document_downloader?attachment_id=2366993374&item_id=38110616&item_type=SubmittalLogApprover&project_id=743331
BY DATE COPIES TO
C&C Contractors Page 3 of 3 Printed On: 06/01/2020 08:55 AM