Bldg 74 ACM Survey Report.pdf
PDF 5 MB Posted
- Solicitation number
- 36C10F22R0045
About this file
This is a solicitation for a long term spinal cord injury project at the VA Medical Center in Dallas, Texas. The solicitation is for project 549-820B and involves renovations and upgrades to Building 74 which serves as the Spinal Cord Injury building. The work includes upgrades to mechanical, electrical, and plumbing systems as well as installation of new finishes, fixtures, and casework. Bids are due by February 22, 2022 and the contract is expected to be awarded by April 2022. The estimated value of the contract is between $5-10 million. The solicitation is being conducted by the Department of Veterans Affairs Office of Construction and Facilities Management.
View the file
Other files
Show 40 more
Latest 50 of 117 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL ASBESTOS
SURVEY REPORT
FOR
ASBESTOS-CONTAINING MATERIALS
Prepared for:
Page Southerland Page, LLP 3500 Maple Avenue, Suite 600
Dallas, Texas 75219
Attn:
Mr. Dee Maxey
Senior Vice President
Project Name:
LT-SCI (VA Project #549-820 / PSP Project #309070)
Project Building:
Building 74
Spinal Cord Injury Building VA Medical Center - Dallas, Texas
CONXSIS Project No. 10-002-1
Date: December 27, 2010
Prepared by:
POB 120725
Arlington, Texas 76012-0725
(817) 348-0060 (Phone)
(817) 469-8311 (Fax) www.CONXSIS.com
ASBESTOS SURVEY REPORT
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas
TABLE OF CONTENTS
1. Introduction
2. Summary 2.1.Asbestos-Containing Material Listing 2.2.Recommendations
3. Survey Scope of Work
4. Assumptions
5. Limitations
6. Applicable Regulatory Standards
7. Survey and Sample Collection Procedure
8. Previous Survey / Plans Review
9. Suspect ACM Materials Not Sampled
10. Survey Sampling Results
11. Appendices
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 1 OF 22
1. Introduction
In accordance with our proposal dated September 21, 2010, the CONXSIS Group, Inc. (CONXSIS) performed an asbestos visual assessment at selected locations of Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas. The assessment occurred on October 14, 2010. No representatives of the client were present during the assessment on October 14, 2010.
The 76,561 square feet building was identified to have been constructed in 1996. A total of 87 samples were collected from the building during this assessment on October 14, 2010.
The objective of the Asbestos Survey is to determine the location and quantity of asbestos-containing materials (ACM) at the Project building and to provide budget estimates for asbestos abatement activities to address the ACM at the below mention building:
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas
CONXSIS’ Scope of Work included:
Reviewed existing asbestos survey conducted by Micro Air of Texas, Inc., dated June 14, 2010.
Field verified the location of ACMs identified in Micro Air of Texas, Inc. survey.
Collected additional samples as necessary for demolition-specific survey data and specifications.
Estimated approximate quantities and general locations of ACM.
Assessed the condition of the ACM identified.
Assigned a hazard rating to each type of ACM.
This report has been prepared for the use of Page Southerland Page, LLP. Our investigation was performed using the degree of care and skill ordinarily exercised under similar circumstances by professional consultants practicing in this or similar localities. No other warranty or guarantee, expressed or implied, is made as to the conclusions included in this report.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 2 OF 22
CONXSIS did not perform destructive sampling procedures at the site; therefore, regardless of the thoroughness of this survey, it is possible that suspected asbestos-containing materials (ACMs) might exist in the building beneath the floors, behind walls, within pipe chases, or in other inaccessible locations. If, during renovation or demolition activities, materials not addressed in this survey are discovered, these materials should be sampled and analyzed for asbestos content prior to disturbance.
Surveyed by:
Jeffrey R. Smith
Department of State Health Services Individual Asbestos Consultant
License #105079
Report Written by:
Manju Ramasamudra
Department of State Health Services (DSHS) Individual Asbestos Consultant
License #105455
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 3 OF 22
2. Summary
CONXSIS performed an Asbestos Survey and Hazard Assessment at Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas on October 14, 2010. The following report summarizes the independent conclusions representing CONXSIS’ best professional judgment based on information and data available to us during the course of this survey. Factual information regarding operations, conditions, and tests data provided by the Client, Owner or their representative has been assumed to be correct and complete. Additionally, the conclusions presented are based on the conditions that existed on the date (October 14, 2010) of the assessment.
The 76,561 square feet building was identified to have been constructed in 1996. A total of 87 samples were collected from the building during this assessment on October 14, 2010.
2.1. Asbestos-Containing Material Listing
No homogeneous materials were identified as asbestos-containing material during the CONXSIS Asbestos Survey on October 14, 2010. In addition, review of the existing asbestos survey conducted by Micro Air of Texas, Inc. dated June 14, 2010 identified no homogeneous material of asbestos-containing materials.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 4 OF 22
2.2. Suspect ACMs
Although not included in CONXSIS’ scope of work, the following is included for informational purposes:
A. The following suspect asbestos-containing materials were not sampled as part of this scope of work:
Suspect fibrous electrical cable covering was not sampled due to the danger of possible electrocution.
Since ordinary demolition activities do not include sanding, grinding, cutting, and abrading, these materials may remain in place during building demolition as long as they remain in good condition and are not friable.
If the material is in poor condition and is friable at the time of demolition or renovation, or if it will be subjected to sanding, grinding, cutting, or abrading, it should first be removed by a licensed asbestos removal contractor and disposed of as asbestos-containing waste.
When removing asphalt-roofing products, the material should be removed using a method that does not subject the material to sanding, cutting, grinding, or abrading (hand tools). Asbestos-containing roofing may be disposed of as construction debris.
2.3. Recommendations
No further action is needed at this time.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 5 OF 22
3. Survey Scope of Work
This survey was conducted for the purpose of identifying asbestos-containing materials (ACM) throughout the building and to conduct a hazard assessment on existing ACM. The survey was non-destructive in nature and limited only to those areas that were readily accessible.
Specific areas to which access was limited by tenant request, unavailability of keys, or by site conditions included the following:
Behind the walls
Beneath the floors
Any suspect ACM not sampled as part of the assessment and any additional suspect materials identified behind walls and beneath the floors should be sampled prior to repair, renovation, or demolition activities.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 6 OF 22
4. Assumptions
The report was prepared based on the following assumptions:
Our on-site inspection only included areas readily accessible and viewable and did not include any destructive inspection actions such as demolition of walls and floors.
Our ACM quantification process was based on the assumptions identified above.
Our asbestos abatement budget estimate of probable costs is based on standard industry rates for work of a similar nature. Actual asbestos abatement costs can only be determined by a bid or negotiation process with duly licensed asbestos abatement contractor(s) which includes project-specific specifications and a definitive scope of work prepared by a duly licensed asbestos professional.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 7 OF 22
5. Limitations
CONXSIS did not attempt to disassemble mechanical equipment, open pipe chases, or access materials within wall voids. Regardless of the thoroughness of a survey, the possibility exists that some areas containing asbestos were not identified, were inaccessible, or were different from those at the specific locations surveyed. The findings and opinions presented are relative to the dates of our site work and should not be relied upon to represent conditions at substantially later dates. Changes in the condition of ACM may change over time due to renovations and/or repairs.
This report is for the exclusive use of the Client and its agents and use by any unauthorized parties in whole or in part, except as directed by legal jurisdiction, is at the sole risk of the user. If this assessment includes reliance on work products and/or documents prepared by others, CONXSIS has no responsibility for the accuracy of information contained therein.
Although this assessment has attempted to identify the presence or absence of ACM, potential sources of ACM may have escaped detection due to: (1) the scope of this assessment, (2) the inaccuracy of records, interviews, work products or documents made available to CONXSIS for this report, (3) the presence of undetected or unreported renovations and repairs, (4) inaccessible areas, and/or (5) deliberate concealment of detrimental information.
Estimates presented in this report are based upon observations during the survey and owner-provided information. These reasonable estimates may be affected by unanticipated conditions potentially present in inaccessible or un-surveyed areas. CONXSIS does not warrant or guarantee the quantity estimates. The use of such estimates shall be at the user's own risk and shall constitute a release and agreement to defend and indemnify CONXSIS from and against any liability. If questions arise during the planning for renovation, demolition, or other construction activities, CONXSIS should be notified to permit review of the data and present recommendations.
Interior of the following rooms were inaccessible during our Asbestos Survey on October 14, 2010: None.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 8 OF 22
6. Applicable Regulatory Standards
The following regulatory standards and specific asbestos-related statutes/protocols were applied by CONXSIS and its contract laboratory during the performance of field efforts related to this study, analytical review of resulting bulk samples, and reduction of observations and data into this report.
29 CFR 1910.1101 (formerly 1926.58) - Construction Industry
This regulation addresses asbestos exposure during construction and renovation activity and sets forth standards which employers must follow in protecting and documenting the protection of workers. The current survey was based on the Final Rules for Asbestos Exposure in General Industry and Construction, issued August 10, 1996, and effective October 1, 1995.
An employer or owner may demonstrate that PACM (includes thermal system insulation, sprayed-on or troweled-on surfacing material, and debris in work areas where such material is present) does or does not contain asbestos by having conducted an inspection pursuant to requirements of the Asbestos Hazard Emergency Response Act (AHERA), 40 CFR 763, Subpart E, to be discussed below. Material testing is to include analysis of a minimum of at least three bulk samples of each homogeneous area of PACM collected in a randomly distributed manner. The tests, evaluation and sample collection are to be performed by an accredited/licensed inspector or by a CIH. The employer/building owner may demonstrate that a non-PACM material such as flooring material, including associated mastic and backing, does not contain asbestos based upon recognized analytical techniques. The material sampled may be designated as "asbestos free" if such material does not contain greater than 1% asbestos.
29 CFR 1910.134 - Respirator Program
This regulation outlines rules for respiratory protection in a specific work environment. A respirator program must be put into place when asbestos is disturbed (i.e. during the performance of response actions), and as necessitated by OSHA in the designation of a “regulated area" during the performance of Class I, II, or III work. A respirator program must be put into place with the implementation of an Operations and Maintenance (O&M) Program for the safe management of asbestos-containing material (ACM) in place.
29 CFR 1910.1001 - General Industry
This regulation addresses potential asbestos exposure involving general industry applications other than construction and renovation workers. This standard establishes minimum standards for the protection of workers involved in asbestos-related work or employees exposed to asbestos-contaminated places.
These standards include required work practices, engineering controls, permissible exposure limits, written programs for respiratory protection and medical surveillance, methods for compliance, hazard communication, housekeeping, competent person training and responsibilities, and required record keeping.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 9 OF 22
40 CFR 763, Subpart E - Asbestos in Schools / Commercial Buildings
In October, 1986, AHERA was signed into law. Included in this law were specific provisions directing the USEPA to establish regulations and address standards for identifying, evaluating and controlling asbestos materials in schools (40 CFR, Part 763 Subpart E). This rule requires that all nonprofit elementary and secondary schools, both public and private, inspect their school buildings for asbestos-containing building materials (ACBM), develop a plan to manage the asbestos for each school building, notify parents and staff regarding management plan availability, provide asbestos awareness training to school maintenance and custodial workers among other requirements of the law. AHERA required schools to perform building inspections and prepare management plans for asbestos-containing building materials (ACBM). Later, in 1995, OSHA adopted AHERA inspection protocols and procedures for use in public buildings (per 29 CFR 1910.1101). These protocols are used as the framework for OSHA inspections and inspection procedures utilized for this assessment.
40 CFR 61, Subpart M National Emissions Standards for Hazardous Air Pollutants (NESHAP)
This regulation provides for the control of environmental releases of asbestos caused by renovation and/or renovation activities. These regulations specify control requirements for most asbestos emissions and include work practices being followed to minimize the release of asbestos fibers during handling, removal and disposal of asbestos waste materials. NESHAP regulations are frequently enforced by a State or local agency. The NESHAP Standard requires:
No discharge of visible emissions to the outside air during the collection processing, packaging, or transporting of any asbestos-containing waste material;
Adequate wetting of asbestos-containing material; and
Processing of asbestos-containing waste material into non-friable forms.
25 TAC §295, Texas Asbestos Health Protection Rules
The State of Texas adopted rules (statutes) governing asbestos maintenance, removal and/or any related asbestos response action involving PACM or ACM. These rules, the Texas Asbestos Health Protection Rules (TAHPR), also include licensing requirements for individuals, consultants, abatement firms and building owners when asbestos is present, and/or when testing is performed to locate such material.
Rules were issued under 25 TAC 295.71. Every aspect of asbestos management from inspection to removal, and maintenance in place, is to be performed by a licensed individual trained in accordance with TAHPR requirements.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 10 OF 22
Beginning January 1, 2002, Texas Senate Bill 509, formally codified under 25 TAC 295.34 (l), required municipalities to verify that an asbestos survey has been conducted prior to issuing renovation/demolition permits for the interiors of public or commercial buildings. Such surveys must comply with state and federal laws governing asbestos surveys, must incorporate the areas of the building where renovation or demolition will occur, and must accurately describe the building materials where the renovation/demolition will take place.
In accordance with 25 TAC 295.34 (i), contractor installation of asbestos-containing products (unless there is no alternative building material) was prohibited. Additionally, contractors are required to have material safety data sheets (MSDS’s) for all newly installed building materials (25 TAC 295.34 (j)).
Maintaining and archiving the MSDS’s along with an architect or engineer signed statement stating the absence of ACM in new construction products will serve the purpose of a survey. This effort is intended to alleviate the need for an asbestos survey for the same areas, if they are to be renovated in the future.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 11 OF 22
7. Survey and Sample Collection Procedure
Based on United States Environmental Protection Agency (USEPA) guidance documents, CONXSIS considered that all material applications identified during the visual assessment were suspect ACM and sampled as described below.
Bulk samples were collected of any materials which were suspected of containing asbestos with the exception of fire doors. Fire doors were not sampled because the damage caused by sampling would render these materials friable and may also void the fire rating. Since these materials were not sampled, they should be assumed to be asbestos containing unless sampled and proven otherwise. Sampling of these assumed ACMs should be performed prior to any renovation or other activity that may cause a material disturbance.
Samples of the remaining suspect ACM were taken in accordance with USEPA recommendations.
The number and location of samples collected were based on the type of material, the manner of application, and the homogeneity of the ACM (similarity of color, texture, and type). Each sample was collected and placed into an individual sample container. The sample location was noted on the field survey form and assigned an individual identification number. This number was affixed to the sample container as the sample was collected. The survey form was also used to note the material type and general condition of the material. During the inspection, each suspect material's accessibility, location, and friability were recorded. This information was used to assess the potential hazard of the ACM and to prioritize response action recommendations.
The USEPA defines asbestos-containing materials (ACM) as those that contain greater than one percent asbestos. Friable materials are defined as those that can be crumbled or reduced to powder by hand pressure.
CONXSIS utilized the “positive-stop” method of sample analysis. In this method, analysis is stopped on a group of samples once the first positive (e.g., greater than 1% asbestos) sample is analyzed.
According to the USEPA, if one sample of a homogenous material is identified to be asbestos containing, the entire material must be considered asbestos containing. By using the positive-stop method, CONXSIS reduces the Client’s laboratory analysis cost by not analyzing the additional samples.
Samples collected were carried and submitted under Chain-of-Custody to Steve Moody Micro Services, Inc., Farmers Branch, Texas for analysis of asbestos using USEPA Method 40 CFR, Chapter 1, Part 763, Subpart F, Appendix A, also known as Polarized Light Microscopy (PLM). Steve Moody Micro Services, Inc. is certified by the National Voluntary Laboratory Accreditation Program (NVLAP) and licensed by the Texas Department of State Health Services.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 12 OF 22
8. Previous Survey / Plans Review
CONXSIS was provided with an existing asbestos survey conducted by Micro Air of Texas, Inc. dated June 14, 2010. Review of the Micro Air of Texas, Inc. asbestos survey identified the following information:
Micro Air performed a comprehensive asbestos survey of Building 74 on June 14, 2010.
Building 74 has a basement level with a swimming pool base, mechanical rooms, a pipe chase with a gravel floor, and a connecting corridor leading to Building 2. The first floor of the building is characterized by four wings (A-Wing, B-Wing, C-Wing and D-Wing). Improvements on the first floor include offices, a pharmacy, swimming pool, recreation center, physical therapy rooms, exam rooms and patient rooms. Building 74 does not have an attic. Finish materials inside Building 74 consist of concrete floors with vinyl floor tile, rubber flooring, sheet vinyl flooring, ceramic tile and carpeting. Walls are sheetrock with cove base; ceilings consist of several different types of lay-in tile. The exterior of the building is brick with a flat roof.
Fiberglass pipe insulation with white mastic wrap was observed throughout the building. Gray mastic is present on some of the metal HVAC ducts. Vibration dampeners were rubber.
A total of 125 bulk material samples were collected during this comprehensive survey, and all of the collected samples were analyzed by PLM.
No asbestos-containing material was identified.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 13 OF 22
9. Suspect ACM Materials Not Sampled
During the course of the property visit, CONXSIS performed a preliminary review of interior, accessible areas of the subject building for the presence of suspect asbestos-containing materials (ACMs). This limited asbestos survey was conducted for overview purposes only. Additional suspect materials may exist in concealed locations (behind walls and above ceilings, beneath the floors, within machinery, etc.). Also, not all suspect materials may have been sampled due to the condition or the location of the suspect materials. Destructive sampling of suspect ACMs was not performed. Suspect ACMs in an overall undamaged condition were not sampled, as that will damage the materials. CONXSIS will not be responsible for damaging materials or causing the materials to become friable. The USEPA defines asbestos-containing material as material containing greater than one percent asbestos. This review was not a pre-demolition/renovation survey or for regulatory submittal purposes.
No other suspect and/or presumed ACMs were observed within the subject building during the property visit.
Building 74, Spinal Cord Injury Building, VA Medical Center, Dallas, Texas PAGE 14 OF 22
10. Survey Sampling Results
The results of the Survey are presented in the tables on the following pages. The tables describe the entire suspect Asbestos-Containing Materials (ACMs) identified in the building and list respective sample numbers and laboratory results. Sample numbers presented in the tables correspond to the sample numbers on attached Laboratory Analysis Forms. Also presented in the tables is the estimated quantity and assessed friability for each suspect ACM. For each suspect material identified as ACM, the assessed hazard potential is presented along with CONXSIS’ recommended response action. Hazard potential for each material application is based on the material condition and accessibility to the public and maintenance personnel.
Glossary of Items for the following Table
Type of Asbestos (1) CH = Chrysotile AM = Amosite CR = Crocidolite AN = Anthophyllite TR = Tremolite AC = Actinolite ND = No Asbestos Detected PC = Point Count Method
Type of ACM (2) M = Miscellaneous S = Surfacing TSI = Thermal Systems Insulation
Friability (3) F = Friable NF = Non Friable
Physical Condition (4) G = Good D = Damaged SD = Significantly Damaged
Potential for Disturbance (5) NPD = No Potential for Disturbance PD = Potential for Disturbance PSD = Potential for Significant Disturbance
Assessment Category (6) 1 = Damaged or significantly damaged TSI ACBM, 2 = Damaged friable surfacing ACBM 3 = Significantly damaged friable surfacing ACBM 4 = Damaged or significantly damaged friable miscellaneous ACBM 5 = ACBM with potential for damaged 6 = ACBM potential for significant damage 7 = Any remaining friable ACBM or friable suspected
ACBM
X = not applicable
Unit of Measurement SF = Square Feet
LF = Linear Feet
Sample Description
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 1
Wall Covering, Light Purple
Yes M No G XND - Wall Covering74-201 PDMain Entrance along East Side
Yes M No G XND - Wall Covering74-202 PDOut Side Room 1A-101
Yes M No G XND - Wall Covering74-203 PDOut Side Room 1B-208
Homogeneous Area 2
Wall Covering, Dark Purple
Yes M No G XND - Wall Covering74-204 PDMain Lobby at Pharmacy
Yes M No G XND - Wall Covering74-205 PDOut Side Room 1D-119
Yes M No G XND - Wall Covering74-206 PDOut Side Room 1C-162
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 3
Wall Covering, White with Pink and Green Spotches
Yes M No G XND - Wall Covering74-207 PDMain Lobby at Pharmacy
Yes M No G XND - Wall Covering74-208 PDOut Side Room 1C-122
Yes M No G XND - Wall Covering74-209 PDOut Side Room 1C-162
Homogeneous Area 4
Wall Covering, Peach with Black Spotches
Yes M No G XND - Wall Covering74-210 PDOut side Room 1D-106B
Yes M No G XND - Wall Covering74-211 PDOut Side Room 1C-171
Yes M No G XND - Wall Covering74-212 PDOut Side Room 1C-151
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 5
Wall Covering, Tan and Brown Speckled
Yes M No G XND - Wall Covering74-213 PDRoom 1B-220 by Water Fountain
Yes M No G XND - Wall Covering74-214 PDOut Side Room 1C-154C
Yes M No G XND - Wall Covering74-215 PDRoom 1C-154 @ Room 1C-154A
Homogeneous Area 6
Wall Covering, Beige with Green Spotches
Yes M No G XND - Wall Covering74-216 PDRoom 1C-154E
Yes M No G XND - Wall Covering74-217 PDRoom 1C-154 West Wing
Yes M No G XND - Wall Covering74-218 PDRoom 1C-154
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 7
Covebase and Associated Mastic, Peach Cove Base
Yes M No G XND - Cove Base ND - Yellow Mastic
74-219 PDRoom 1C-154 West Wing
Yes M No G XND - Cove Base ND - Yellow Mastic
74-220 PDRoom 1C-127
Yes M No G XND - Cove Base ND - Yellow Mastic
74-221 PDOut Side Room 1D-119
Homogeneous Area 8
Covebase and Associated Mastic, Purple Cove Base
Yes M No G XND - Cove Base ND - Yellow Mastic
74-222 PDOut Side Room 220 by Water Fountain
Yes M No G XND - Cove Base ND - Yellow Mastic
74-223 PDOut Side Room 1C-171
Yes M No G XND - Cove Base ND - Yellow Mastic
74-224 PDOut Side Room 1B-224
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 9
Wall Covering, Green with Horizontal Pattern
Yes M No G XND - Wall Covering74-225 PDRoom 1C-154, Large MTS Room Behind Door
Yes M No G XND - Wall Covering74-226 PDRoom 1C-154, Large MTS Room Behind Suite Door
Yes M No G XND - Wall Covering74-227 PDRoom 1C-154, East Wall Small MTS Room Across from Large MTS Room
Homogeneous Area 10
Carpet and Associated Mastic, 2' X 2' Squares, Green
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-228 PDRoom 1C-154, Large MTS room North
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-229 PDRoom 1C-154, Large MTS room South
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-230 PDRoom 1C-154, Small MTS Room Across from Large MTS Room
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 11
Carpet and Associated Mastic, 2' X 2' Squares, Blue Green with Circle Pattern
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-231 PDRoom 1c-154, Corridor North
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-232 PDRoom 1c-154, Corridor Middle
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-233 PDRoom 1c-154, Corridor South
Homogeneous Area 12
Non Skid Strip, Black Yes M No G XND - Non Skid Strip ND - Clear Mastic
74-234 PDRoom 1B-111AA
Yes M No G XND - Non Skid Strip ND - Clear Mastic
74-235 PDRoom 1B-111AB
Yes M No G XND - Non Skid Strip ND - Clear Mastic
74-236 PDRoom 1B-111AC
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 13
Ceramic Tile and Associated Grout, 12" X 12" Tile
Yes M No G XND - Ceramic Tile ND - Grout ND - Cream Mastic
74-237 PDRoom 1B-111AB
Yes M No G XND - Ceramic Tile ND - Grout
74-238 PDRoom 1C-154E
Yes M No G XND - Ceramic Tile ND - Grout
74-239 PDRoom 1C-154E
Homogeneous Area 14
Carpet and Associated Mastic, 2' X 2' Squares, Maroon with Stripe Pattern
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-240 PDRoom 1B-120A
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-241 PDRoom 1A-101
Yes M No G XND - Carpet ND - Carpet Pad
74-242 PDRoom 1A-142
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 15
Covebase and Associated Mastic, Maroon
Yes M No G XND - Cove Base ND - Yellow Mastic
74-243 PDRoom 1B-120A
Yes M No G XND - Cove Base ND - Yellow Mastic
74-244 PDRoom 1A-101
Yes M No G XND - Cove Base ND - Yellow Mastic
74-245 PDRoom 1A-142
Homogeneous Area 16
Carpet and Associated Mastic, 2' X 2' Squares, Purple
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-246 PDRoom 1B-220
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-247 PDSection C Nurse's Station
Yes M No G XND - Carpet ND - Carpet Pad
74-248 PDRoom 1D-100
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 17
Wall Covering, Maroon Speckled
Yes M No G XND - Wall Covering74-249 PDRoom 1A-142, Behind Entrance
Yes M No G XND - Wall Covering74-250 PDRoom 1A-142A, Door Way
Yes M No G XND - Wall Covering74-251 PDRoom 1A-142, SE Corner
Homogeneous Area 18
Wall Covering, Beige with Maroon Swirls
Yes M No G XND - Wall Covering74-252 PDRoom 1A-142, Behind Entrance
Yes M No G XND - Wall Covering74-253 PDRoom 1A-142 @ Room 1A-142B
Yes M No G XND - Wall Covering ND - Joint Compound
74-254 PDRoom 1A-142 @ Room 1A-142D
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 19
Carpet and Associated Mastic, 2' X 2' Squares, Maroon Multi Color
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-255 PDRoom 1A-142, Behind Entrance
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-256 PDRoom 1A-142, SE Corner
Yes M No G XND - Carpet ND - Carpet Pad ND - Yellow Mastic
74-257 PDRoom 1C-143
Homogeneous Area 20
Caulking, Gray, Wall Filler
Yes M No G XND - Caulking74-258 PDRoom BA-112
Homogeneous Area 21
Sink Undercoating, Black
Yes S No G XND - Sink Undercoating
74-259 PDRoom 1D-120
Yes S No G XND - Sink Undercoating
74-260 PDRoom 1D-120
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 22
Wall Covering, Blue Orange and Green (Blue)
Yes M No G XND - Wall Covering74-261 PDRoom BA-130
Wall Covering, Blue Orange and Green (Orange)
Yes M No G XND - Wall Covering74-262 PDRoom BA-130
Wall Covering, Blue Orange and Green (Green)
Yes M No G XND - Wall Covering74-263 PDRoom BA-130
Homogeneous Area 23
Covebase and Associated Mastic, Blue Green Cove Base
Yes M No G XND - Cove Base ND - Yellow Mastic
74-264 PDRoom BA-132
Yes M No G XND - Cove Base ND - Yellow Mastic
74-265 PDRoom BA-132
Yes M No G XND - Cove Base
74-266 PDRoom BA-132
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 24
Caulking, White, Around Restroom Fixtures (Sink)
Yes M No G XND - Caulking74-267 PDRoom 1A-115
Caulking, White, Around Restroom Fixtures (Urinal)
Yes M No G XND - Caulking74-268 PDRoom 1A-113
Caulking, White, Around Restroom Fixtures (Toilet)
Yes M No G XND - Caulking74-269 PDRoom 1C-154E
Homogeneous Area 25
Brick and Associated Mortar, Red Brick
Yes M No G XND - Brick ND - Mortar
74-270 PDNW Corner
Yes M No G XND - Brick ND - Mortar
74-271 PDNE Corner
Yes M No G XND - Brick ND - Mortar
74-272 PDSE Corner
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 26
Caulking, Around Door and Window Frames
Yes M No G XND - Caulking74-273 PDWest Entry
Yes M No G XND - Caulking74-274 PDNorth Central Window
Yes M No G XND - Caulking74-275 PDEast Entry
Homogeneous Area 27
Expansion Joint, Red Yes M No G XND - Expansion Material
74-276 PDEast Side
Yes M No G XND - Expansion Material
74-277 PDNorth Side West End
Yes M No G XND - Expansion Material
74-278 PDNorth Side East End
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 28
Roof, Membrane Roof, Flat Roof
Yes M No G XND - Foam ND - Rubber Membrane
74-279 PDOver Pool
Yes M No G XND - Foam ND - Rubber Membrane
74-280 PDEast Side South End
Yes M No G XND - Foam ND - Rubber Membrane
74-281 PDEast Side North End
Homogeneous Area 29
Roof, Sealer, at Penetrations and Seams
Yes M No G XND - Roof Sealant74-282 PDSE Corner
Yes M No G XND - Roof Sealant74-283 PDNE Corner
Yes M No G XND - Roof Sealant74-284 PDNW Corner
Sample Location
Sample Analyzed
Yes/No
Approximate
ACM
Quantity
Assessment Category
Physical Condition
Friable Yes/No
Type of
ACM
% and Type of Asbestos Detected
Sample ID Potential For
Distrubance
Building 74, VA Medical Center
Homogeneous Area 30
Wall Covering, Gray with Gray Spots
Yes M No G XND - Wall Covering74-285 PDRoom 1B-120A
Yes M No G XND - Wall Covering74-286 PDRoom 1B-120A
Yes M No G XND - Wall Covering74-287 PDRoom 120A
1. CH = Chrysotile; AM = Amosite; CR = Crocidolite; AN = Anthophyllite; TR = Tremolite; AC = Actinolite; ND = No Asbestos Detected; or PC = Point Count Method
2. M = Miscellaneous; S = Surfacing; or TSI = Thermal Systems Insulation
3. F = Friable or NF = Non Friable
4. G = Good; D = Damaged; or SD = Significantly Damaged
5. NPD = No Potential for Disturbance; PD = Potential for Disturbance; or PSD = Potential for Significant Disturbance
6. 1 = Damaged or significantly damaged TSI ACBM, 2 = Damaged friable surfacing ACBM, 3 = Significantly damaged friable surfacing ACBM, 4 = Damaged or significantly damaged friable miscellaneous ACBM, 5 = ACBM with potential for damage, 6 = ACBM potential for significant damage, 7 = Any remaining friable ACBM or friable suspected ACBM, or X = not applicable
SF = Square Feet LF = Linear Feet
11. Appendices
Appendix A— Laboratory Results and Chain of Custody Appendix B— ACM Sample Location Drawings Appendix C— Prior ACM Survey Reports Appendix D— ACM Location Drawings Appendix E— Certificates and Licenses
Appendix A
Laboratory Results and Chain of Custody
PLM Summary Report
Client :
Project :
Project # :
Identification :
Test Method :
ConXsis
VA Medical Center Dallas, Building #74
10-002-01
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 10/15/2010, eighty seven (87) bulk material samples were submitted by a representative of ConXsis for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Lab Job No. :
Report Date :
10B-10553
10/14/2010
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
74-201 Wall Covering (Light Purple) None Detected - Wall Covering
74-202 Wall Covering (Light Purple) None Detected - Wall Covering
74-203 Wall Covering (Light Purple) None Detected - Wall Covering
74-204 Wall Covering (Dark Purple) None Detected - Wall Covering
74-205 Wall Covering (Dark Purple) None Detected - Wall Covering
74-206 Wall Covering (Dark Purple) None Detected - Wall Covering
74-207 Wall Covering (White with Pink and Green Splotches) None Detected - Wall Covering
74-208 Wall Covering (White with Pink and Green Splotches) None Detected - Wall Covering
74-209 Wall Covering (White with Pink and Green Splotches) None Detected - Wall Covering
74-210 Wall Covering (Peach with Black Specks) None Detected - Wall Covering
74-211 Wall Covering (Peach with Black Specks) None Detected - Wall Covering
74-212 Wall Covering (Peach with Black Specks) None Detected - Wall Covering
74-213 Wall Covering (Tan and Brown Speckled) None Detected - Wall Covering
74-214 Wall Covering (Tan and Brown Speckled) None Detected - Wall Covering
74-215 Wall Covering (Tan and Brown Speckled) None Detected - Wall Covering
74-216 Wall Covering (Beige with Green Splotches) None Detected - Wall Covering
74-217 Wall Covering (Beige with Green Splotches) None Detected - Wall Covering
74-218 Wall Covering (Beige with Green Splotches) None Detected - Wall Covering
74-219 Cove Base (Peach) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-220 Cove Base (Peach) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
Project :
Project # :
Identification :
Test Method :
ConXsis
VA Medical Center Dallas, Building #74
10-002-01
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 10/15/2010, eighty seven (87) bulk material samples were submitted by a representative of ConXsis for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Lab Job No. :
Report Date :
10B-10553
10/14/2010
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
74-221 Cove Base (Peach) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-222 Cove Base (Purple) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-223 Cove Base (Purple) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-224 Cove Base (Purple) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-225 Wall Covering (Green with Horizontal Pattern) None Detected - Wall Covering
74-226 Wall Covering (Green with Horizontal Pattern) None Detected - Wall Covering
74-227 Wall Covering (Green with Horizontal Pattern) None Detected - Wall Covering
74-228 2' x 2' Carpet Squares (Green) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-229 2' x 2' Carpet Squares (Green) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-230 2' x 2' Carpet Squares (Green) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-231 2' x 2' Carpet Squares (Blue Green with Circle Pattern) and
Mastic
None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-232 2' x 2' Carpet Squares (Blue Green with Circle Pattern) and
Mastic
None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-233 2' x 2' Carpet Squares (Blue Green with Circle Pattern) and
Mastic
None Detected - Carpet
None Detected - Carpet Pad
Project :
Project # :
Identification :
Test Method :
ConXsis
VA Medical Center Dallas, Building #74
10-002-01
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 10/15/2010, eighty seven (87) bulk material samples were submitted by a representative of ConXsis for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Lab Job No. :
Report Date :
10B-10553
10/14/2010
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
74-234 Non Skid Strips None Detected - Non-skid Strip
None Detected - Clear Mastic
74-235 Non Skid Strips None Detected - Non-skid Strip
None Detected - Clear Mastic
74-236 Non Skid Strips None Detected - Non-skid Strip
None Detected - Clear Mastic
74-237 Ceramic Tile and Grout None Detected - Ceramic Tile
None Detected - Grout
None Detected - Cream Mastic
74-238 Ceramic Tile and Grout None Detected - Ceramic Tile
None Detected - Grout
74-239 Ceramic Tile and Grout None Detected - Ceramic Tile
None Detected - Grout
74-240 2' x 2' Carpet Squares (Maroon with Stripe Pattern) and
Mastic
None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-241 2' x 2' Carpet Squares (Maroon with Stripe Pattern) and
Mastic
None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-242 2' x 2' Carpet Squares (Maroon with Stripe Pattern) and
Mastic
None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-243 Cove Base (Maroon) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-244 Cove Base (Maroon) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-245 Cove Base (Maroon) and Mastic None Detected - Cove Base
Project :
Project # :
Identification :
Test Method :
ConXsis
VA Medical Center Dallas, Building #74
10-002-01
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 10/15/2010, eighty seven (87) bulk material samples were submitted by a representative of ConXsis for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Lab Job No. :
Report Date :
10B-10553
10/14/2010
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
74-246 2' x 2' Carpet Squares (Purple) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-247 2' x 2' Carpet Squares (Purple) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-248 2' x 2' Carpet Squares (Purple) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-249 Wall Covering (Maroon Speckled) None Detected - Wall Covering
74-250 Wall Covering (Maroon Speckled) None Detected - Wall Covering
74-251 Wall Covering (Maroon Speckled) None Detected - Wall Covering
74-252 Wall Covering (Beige with Maroon Swirls) None Detected - Wall Covering
74-253 Wall Covering (Beige with Maroon Swirls) None Detected - Wall Covering
74-254 Wall Covering (Beige with Maroon Swirls) None Detected - Joint Compound
None Detected - Wall Covering
74-255 2' x 2' Carpet Squares (Maroon Multicolored) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-256 2' x 2' Carpet Squares (Maroon Multicolored) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-257 2' x 2' Carpet Squares (Maroon Multicolored) and Mastic None Detected - Carpet
None Detected - Carpet Pad
None Detected - Yellow Mastic
74-258 Caulk (Gray), Wall Filler None Detected - Caulking
74-259 Sink Undercoating (Black) None Detected - Sink Undercoating
74-260 Sink Undercoating (Black) None Detected - Sink Undercoating
Project :
Project # :
Identification :
Test Method :
ConXsis
VA Medical Center Dallas, Building #74
10-002-01
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 10/15/2010, eighty seven (87) bulk material samples were submitted by a representative of ConXsis for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Lab Job No. :
Report Date :
10B-10553
10/14/2010
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
74-261 Wall Covering (Blue, Orange, and Green) None Detected - Wall Covering
74-262 Wall Covering (Blue, Orange, and Green) None Detected - Wall Covering
74-263 Wall Covering (Blue, Orange, and Green) None Detected - Wall Covering
74-264 Cove Base (Blue Green) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-265 Cove Base (Blue Green) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-266 Cove Base (Blue Green) and Mastic None Detected - Cove Base
None Detected - Yellow Mastic
74-267 Caulk, Restroom Fixtures None Detected - Caulking
74-268 Caulk, Restroom Fixtures None Detected - Caulking
74-269 Caulk, Restroom Fixtures None Detected - Caulking
74-270 Brick (Red) and Mortar None Detected - Brick
None Detected - Mortar
74-271 Brick (Red) and Mortar None Detected - Brick
None Detected - Mortar
74-272 Brick (Red) and Mortar None Detected - Brick
None Detected - Mortar
74-273 Caulk, Door and Window Frames None Detected - Caulking
74-274 Caulk, Door and Window Frames None Detected - Caulking
74-275 Caulk, Door and Window Frames None Detected - Caulking
74-276 Expansion Joint Material None Detected - Expansion Material
74-277 Expansion Joint Material None Detected - Expansion Material
74-278 Expansion Joint Material None Detected - Expansion Material
Project :
Project # :
Identification :
Test Method :
ConXsis
VA Medical Center Dallas, Building #74
10-002-01
Asbestos, Bulk Sample Analysis
Polarized Light Microscopy / Dispersion Staining (PLM/DS)
EPA Method 600 / R-93 / 116
Sample Number Client Sample Description / Location Asbestos Content
Sample Date :
On 10/15/2010, eighty seven (87) bulk material samples were submitted by a representative of ConXsis for asbestos analysis by PLM/DS. The PLM
Detail Report is attached; additional information may be found therein. The results are summarized below:
Lab Job No. :
Report Date :
10B-10553
10/14/2010
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
74-279 Roof Membrane with Insulation None Detected - Foam
None Detected - Rubber Membrane
74-280 Roof Membrane with Insulation None Detected - Foam
None Detected - Rubber Membrane
74-281 Roof Membrane with Insulation None Detected - Foam
None Detected - Rubber Membrane
74-282 Roof Sealer, on Seams and Penetrations None Detected - Roof Sealant
74-283 Roof Sealer, on Seams and Penetrations None Detected - Roof Sealant
74-284 Roof Sealer, on Seams and Penetrations None Detected - Roof Sealant
74-285 Wall Covering (Gray Cloth) None Detected - Wall Covering
74-286 Wall Covering (Gray Cloth) None Detected - Wall Covering
74-287 Wall Covering (Gray Cloth) None Detected - Wall Covering
Brian R. SchmidtAnalyst(s):
Lab Director : Steve Moody Approved Signatory :
Thank you for choosing Steve Moody Micro Services
These samples were analyzed by layers. Quantification, unless otherwise noted, is performed by calibrated visual estimate. Results may not be reproduced except in full. This test report relates only to the samples tested. These test results do not imply endorsement by NVLAP or any agency of the U.S. Government. Accredited by the
National Voluntary Laboratory Accreditation Program for Bulk Asbestos Fiber Analysis under Lab Code 102056.
Lab Manager : Bruce Crabb Approved Signatory :
PLM Detail Report
Project # : 10-002-01
Sample Number Layer Components % Of
Sample
Analysis
Date
% of
Layer Analyst
Supplement to PLM Summary Report
Client :
Project :
ConXsis
VA Medical Center Dallas, Building #74
Lab Job No. :
Report Date :
10B-10553
10/19/2010
2051 Valley View Lane
Farmers Branch, TX 75234 Phone: (972) 241-8460
Steve Moody Micro Services, LLC NVLAP Lab No. 102056
TDSHS License No. 30-0084
Synthetic Fibers74-201 Wall Covering (Light Purple) 100% 10/1815% BS
Cotton Fibers74-201 Wall Covering (Light Purple) 100% 10/1815% BS
Vinyl Binders74-201 Wall Covering (Light Purple) 100% 10/1870% BS
Synthetic Fibers74-202 Wall Covering (Light Purple) 100% 10/1815% BS
Cotton Fibers74-202 Wall Covering (Light Purple) 100% 10/1815% BS
Vinyl Binders74-202 Wall Covering (Light Purple) 100% 10/1870% BS
Synthetic Fibers74-203 Wall Covering (Light Purple) 100% 10/1815% BS
Cotton Fibers74-203 Wall Covering (Light Purple) 100% 10/1815% BS
Vinyl Binders74-203 Wall Covering (Light Purple) 100% 10/1870% BS
Synthetic Fiber Mesh74-204 Wall Covering (Dark Purple) 100% 10/18100% BS
Synthetic Fiber Mesh74-205 Wall Covering (Dark Purple) 100% 10/18100% BS
Synthetic Fiber…
This is the start of the file's text. The full file is on GovTribe.