36C10F19R0003-022.pdf

PDF 856 KB Posted

Attached to
Research Office Building (ROB) Connecting Bridge VAPHS, Pittsburgh, PA
Solicitation number
36C10F19R0003
Issued by

About this file

36C10F19R0003 COMBINED PLUMBING.pdf

View the file

Other files

File Type Posted
36C10F19C0016-000.docx DOCX document
36C10F19R0003-0007000.docx DOCX document
36C10F19R0003-0007002.pdf PDF
36C10F19R0003-0007003.pdf PDF
36C10F19R0003-0007004.pdf PDF
36C10F19R0003-0007005.pdf PDF
36C10F19R0003-0007001.pdf PDF
36C10F19R0003-0006003.pdf PDF
36C10F19R0003-0006001.pdf PDF
36C10F19R0003-0006002.pdf PDF
36C10F19R0003-0006000.docx DOCX document
36C10F19R0003-0005000.docx DOCX document
36C10F19R0003-0005001.pdf PDF
36C10F19R0003-0005003.pdf PDF
36C10F19R0003-0005004.pdf PDF
36C10F19R0003-0005002.pdf PDF
36C10F19R0003-0004000.docx DOCX document
36C10F19R0003-0003000.docx DOCX document
36C10F19R0003-0002002.pdf PDF
36C10F19R0003-0002001.pdf PDF
36C10F19R0003-0002000.docx DOCX document
36C10F19R0003-0001001.pdf PDF
36C10F19R0003-0001000.docx DOCX document
36C10F19R0003-014.pdf PDF
36C10F19R0003-019.pdf PDF
36C10F19R0003-016.pdf PDF
36C10F19R0003-020.pdf PDF
36C10F19R0003-024.pdf PDF
36C10F19R0003-023.pdf PDF
36C10F19R0003-018.pdf PDF
36C10F19R0003-013.docx DOCX document
36C10F19R0003-017.pdf PDF
36C10F19R0003-021.pdf PDF
36C10F19R0003-015.pdf PDF
36C10F19R0003-000.docx DOCX document
36C10F19R0003.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DN

ICEU

P

D N

U P

D N

EXISTING BUILDING 1

2ND FLOOR

AREA W

LV

LA

G

LV

LA

G

LV

LA

G

G LA

LV

G

LA

LV

G

LA

LV

G

LA

LV

S T

12.8 x.7x.6x.5x.4 x.17x.16x.14 x.2 x.C

EA

6.5

FE E.7

S T

ST

S T

O

F D

E.6 x.J x.L x.N x.12 x.13

12.8 x.6x.5x.4 x.16x.14 x.2 x.1 x.C

EA

FULLY SPRINKLERED

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT/ENGINEERS:

Office of

Facilities

Management o n e e ig h th i n c h o n e f o o t

B

A

C

D

E

F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Department of Veterans Affairs

BIDDING DOCUMENTS - JANUARY 30, 2019

VA CARES CONSOLIDATION

VAMC, PITTSBURGH, PA

CONNECTING BRIDGE

PLD-101

646CA2500.23

MPBER

PLUMBING DEMOLITION

FLOOR PLANS

VAPHS UNIVERSITY DRIVE

1 & 30

1/8" = 1'-0"1

BUILDING 1 - 2ND FLOOR PLUMBING DEMOLTION PLAN

1 DISCONNECT, REMOVE AND RELOCATE EX. 3" V. PIPING

LOCATED BELOW EXISTING WALKWAY. REFER TO NEW WORK

PLAN FOR NEW LOCATION.

DISCONNECT AND REMOVE EX. 4" ST. & 4" ST. (OFD) PIPING

LOCATED BELOW EXISTING WALKWAY.

DISCONNECT AND REMOVE EX. 4" VRC (OFD).

DISCONNECT AND REMOVE EX. 4" VRC.

PLUMBING KEYED NOTES

1/8" = 1'-0"3

BUILDING 30 - 2ND FLOOR PLUMBING DEMOLITION PLAN

1/8" = 1'-0"2

BUILDING 1 - 1ST FLOOR PLUMBING DEMOLITION PLAN

EX. 3" V. UP

FROM FL. BLW.

EX. 3" V. UP

TO 3" VTR.

EX. 6" VRC.

DN.

DISCONNECT AND REMOVE EX. 4" VRC (OFD) TO POINT OF

DISCONNECT TO EX. 6" ST. (OFD) LOCATED AT THE GROUND FL.

CEILING.

DISCONNECT AND REMOVE EX. 4" ST. PIPING (LOCATED AT 1ST.

FL. CEILING) TO POINT OF DISCONNECT FROM TO EX. 6" VRC.

DISCONNECT AND REMOVE EX. 4" S. PIPING ABOVE CEILING

SERVING DEMOLISHED WATER CLOSET ON FL. ABOVE. CAP PIPING

GAS-TIGHT AT POINT OF DISCONNECTION FROM EX. 4" SS.

DISCONNECT AND REMOVE EX. CW. PIPING ABOVE CEILING SERVING

DEMOLISHED FIXTURES ON FL. ABOVE. CAP PIPING GAS-TIGHT AT

POINT OF DISCONNECTION AT EX. SHUT-OFF VALVE.

9 DISCONNECT AND REMOVE EX. W. PIPING ABOVE CEILING SERVING

DEMOLISHED LAVATORY ON FL. ABOVE. CAP PIPING GAS-TIGHT AT

POINT OF DISCONNECTION.

10 DISCONNECT, REMOVE AND RELOCATE EX. 4" V AND VTR -

REFER TO NEW WORK PLAN FOR NEW LOCATION.

10 11 DISCONNECT, REMOVE AND RELOCATE EX. CW. RISER. REFER

TO NEW WORK PLAN FOR NEW LOCATION.

12 DISCONNECT AND REMOVE EX. CW., HW. & W. PIPING ABOVE

CEILING SERVING DEMOLISHED SINK ON FL. ABOVE. CAP PIPING

GAS-TIGHT AT POINT OF DISCONNECTION.12

13 DISCONNECT AND REMOVE EX. LV, LA & G. RISERS AND

ASSOCIATED PIPING ABOVE CEILING. CAP PIPING GAS-TIGHT AT

POINT OF DISCONNECTION AT EX. SHUT-OFF VALVES.

14 DISCONNECT AND REMOVE EX. W. PIPING ABOVE CEILING SERVING

DEMOLISHED SINK ON FL. ABOVE. CAP PIPING GAS-TIGHT AT POINT

OF DISCONNECTION.

15 DISCONNECT AND REMOVE EX. LV., LA., & G. ZONE VALVE BOXES

AND ALL ASSOCIATE PIPING.

15 15

16 DISCONNECT AND REMOVE EX. LV., LA., & G. RISERS AND ALL

ASSOCIATE PIPING.

17 DISCONNECT AND REMOVE ALL EX. LV., LA., & G. PIPING ABOVE

CEILING.

18 DISCONNECT AND REMOVE EX. WATER CLOSET AND ALL

ASSOCIATED PIPING NO LONGER REQUIRED TO REMAIN AS PART

OF AN ACTIVE SYSTEM. CAP PIPING GAS TIGHT AT POINT OF

DISCONNECTIONS.

19 DISCONNECT AND REMOVE EX. LAVATORY AND ALL ASSOCIATED

PIPING NO LONGER REQUIRED TO REMAIN AS PART OF AN ACTIVE

SYSTEM. CAP PIPING GAS TIGHT AT POINT OF DISCONNECTIONS.

20 DISCONNECT AND REMOVE EX. SINK, EYE WASH AND ALL

ASSOCIATED PIPING NO LONGER REQUIRED TO REMAIN AS PART

OF AN ACTIVE SYSTEM. CAP PIPING GAS TIGHT AT POINT OF

DISCONNECTIONS.

21 DISCONNECT AND REMOVE EX. SINK AND ALL ASSOCIATED PIPING

NO LONGER REQUIRED TO REMAIN AS PART OF AN ACTIVE

SYSTEM. CAP PIPING GAS TIGHT AT POINT OF DISCONNECTIONS.

22 DISCONNECT, REMOVE & RELOCATED EX. CW. & HW. RISERS.

REFER TO NEW WORK PLAN FOR NEW LOCATION.

EX. 4" VRC.

EX. 4" ST. DN. FROM

EX. 4" RD. ABV.

CUT AND CAP ALL PLUMBING PIPING BACK TO THE MAIN LATERAL

TO ENSURE NO DEAD LEGS OR ENDS ARE CREATED.

GENERAL PLUMBING DEMOLITION NOTES:

1.

23 REMOVE EXISTING FLOOR DRAIN AND RELATED PIPING. CAP AT

MAIN AS REQUIRED.

24 DISSCONNECT AND REMOVE EXISTING 3" S. PIPING ABOVE

CEILING SERVING DEMOLISHED FLOOR DRAIN ON FLOOR ABOVE.

REMOVE PIPING BACK TO THE MAIN.

COORDINATE ALL NEW AND DEMOLITION WORK REQUIRED WITH

EXISTNG USERS TO KEEP AREAS OF WORK UP AND RUNNING IN

CASE OF POSSIBLE SHUTDOWNS AND OR DISRUPTIONS.

2.

25 REMOVE AND RE-ROUTE EXISTING 3/4" CW. PIPING SERVING THE

HOSE BIBB AS REQUIRED.

1 AMENDMENT 3 01-31-17

ABBREVIATIONS

P101

WR

SECTION INDICATOR

TOP INDICATES SECTION NUMBER

BOTTOM INDICATES DRAWING NUMBER

STORM

STORM - EXISTING

STORM - DEMO

WASTE

WASTE - EXISTING

WASTE - DEMO

VENT - DEMO

VENT - EXISTING

VENT

HOT WATER RETURN - DEMO

HOT WATER RETURN

HOT WATER RETURN - EXISTING

HOT WATER - EXISTING

HOT WATER

HOT WATER - DEMO

COLD WATER - DEMO

COLD WATER

COLD WATER - EXISTING

BACKFLOW PREVENTER (BFP)

SLEEVE

WATER HAMMER ARRESTER (LETTER

INDICATES SIZE)

WR

ELBOW DOWN

ELBOW UP

DROP OR RISE

VALVE - PRESSURE-TEMPERATURE RELIEF (PRV)

PLUG END OF PIPE

AQUASTAT

"A"

A

PRESSURE GAUGE WITH GAUGE COCK (PG)

THERMOMETER

STRAINER

CLEANOUT - WALL

CO CLEANOUT

DRAIN - FLOOR

DRAIN - ROOF

WH

HB

WALL HYDRANT - NON-FREEZE

HOSE BIB

VALVE - PRESSURE REDUCING (PRV)

VALVE - ANGLE

PLUG VALVE

UNION

PIPE ANCHOR

DIRECTION OF FLOW

PIPE GUIDE

CAPPED PIPING

VALVE - CHECK (SHOWN W/FLOW)

VALVE - BALANCING

VALVE - OS&Y

VALVE - SAFETY/RELIEF

VALVE - SOLENOID

VALVE - GAS PRESSURE REGULATOR

UNDERGROUND SANITARY OR STORM

UNDERGROUND SANITARY OR STORM EXISTING

UNDERGROUND SANITARY OR STORM DEMO

UNDERGROUND VENT DEMO

UNDERGROUND VENT EXISTING

UNDERGROUND VENT

CLEANOUT - FLOORFCO

DRAIN - FLOOR

DRAIN - TRENCH

SYMBOLS

GENERAL NOTES

INDIRECT WASTE

INDIRECT WASTE - EXISTING

INDIRECT WASTE - DEMO

ABV ABOVE

AC AIR COMPRESSOR

AD AREA DRAIN

AFF ABOVE FINISHED FLOOR

AFG ABOVE FINISHED GRADE

AHJ AUTHORITY HAVING JURISDICTION

AHU AIR HANDLING UNIT

AP ACCESS PANEL

ATM ATMOSPHERE

AUTO AUTOMATIC

B/S BELOW SLAB

BFP BACKFLOW PREVENTER

BFV BUTTERFLY VALVE

BOB BOTTOM OF BEAM

BOP BOTTOM OF PIPE

BTU BRITISH THERMAL UNIT

BV BALL VALVE

CA COMPRESSED AIR

CALC CALCULATE

CAP CAPACITY

CLG CEILING

CM CENTIMETER

CO CLEANOUT

COL COLUMN

COMPR COMPRESSOR

CONC CONCRETE

CV CHECK VALVE

CW COLD WATER

DCV DOUBLE CHECK VALVE

DIA DIAMETER

DIM DIMENSION

DN DOWN

DR DRAIN

DS DOWNSPOUT OR RAIN LEADER

DW DISHWASHER

DWG DRAWING

DHW DOMESTIC HOT WATER

EA EACH

EF EXISTING FIXTURE TO REMAIN

EFF EFFICIENCY

EJ EXPANSION JOINT

ELEC ELECTRICAL

ELEV. ELEVATION

EQUIP EQUIPMENT

ES EMERGENCY SHOWER

ET EXPANSION TANK

EWC ELECTRIC WATER COOLER

EWH ELECTRIC WATER HEATER

EXIST EXISTING

EXP EXPANSION

F FAHRENHEIT

FA FIRE ALARM

FCO FLOOR CLEANOUT

FD1,2,3...FLOOR DRAIN

FF FINISHED FLOOR

FH FUME HOOD

FIN FINISH

FIXT FIXTURE

FLR FLOOR

FPM FEET PER MINUTE

FPS FEET PER SECOND

FS FLOW SWITCH OR FLOOR SINK

FT FOOT/FEET

FV FLUSH VALVE

G NATURAL GAS

GC GENERAL CONTRACTOR

GCO GRADE OR GROUND CLEANOUT

GI GREASE INTERCEPTOR

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GTV GATE VALVE

GW GARAGE WASTE

H HYDROGEN PIPING

HB HOSE BIBB

HD HEAD OR HUB DRAIN

HE HELIUM PIPING

HP HORSEPOWER OR HIGH POINT

HR HOUR

HS HOSE STATION

HVAC HEATING-VENTILATION-AIR CONDITIONING

HW HOT WATER

HWR HOT WATER RETURN

HYD HYDRAULIC

HZ HERTZ

IC INSULATING COUPLING

ID INDIRECT DRAIN

IM ICE MACHINE

IN INCHES

INSUL INSULATION

INV. ELEV. INVERT ELEVATION

IW INDIRECT WASTE

IWH INTERIOR WALL HYDRANT

KEC KITCHEN EQUIPMENT CONTRACTOR

KW KITCHEN WASTE

L LAVATORY

LA LABORATORY AIR

LBS POUNDS

LP LIQUID PROPANE

LPA LINE PRESSURE ALARM

LPG LIQUID PROPANE GAS

LPM LITERS PER MINUTE

LPT LOW POINT

LSK LAB SINK

LT LAUNDRY TUB

LV LABORATORY VACUUM

LW LAUNDRY WASTE OR LAB WASTE

LWH LAB WATER HEATER

MAX MAXIMUM

MD MAIN DRAIN

MECH MECHANICAL

MEZZ MEZZANINE

MFR MANUFACTURER

MH MANHOLE

MIN MINIMUM OR MINUTES

MM MILLIMETER

MS MOP SINK

MTD MOUNTED

MV MEDICAL VACUUM

N.C. NORMALLY CLOSED

NIC NOT IN CONTRACT

NO. NUMBER

N.O. NORMALLY OPEN

NTS NOT TO SCALE

OBY OIL BASIN VENT

OD OUTSIDE DIAMETER

OFD OVERFLOW DRAIN

OM OXYGEN MANIFOLD

OS&Y OUTSIDE SCREW AND YOKE

PBV PRESSURE BALANCING VALVE

PC PLUMBING CONTRACTOR

PG PRESSURE GAUGE

PH PENTHOUSE OR PHASE

PITCH PITCHES UP OR DOWN

PIV POST INDICATOR VALVE

PKG PACKAGE

POCPOINT OF CONNECTION

PRV PRESSURE REDUCING VALVE

PSI POUNDS PER SQUARE INCH

QTY QUANTITY

RD ROOF DRAIN

ROBROD OUT BASIN

RP RECIRCULATING PUMP

RPM REVOLUTIONS PER MINUTE

RPZ REDUCED PRESSURE ZONE

RTU ROOF TOP UNIT

SAN SANITARY SEWER (EXTERIOR)

SB SETTLING BASIN

S.F. SQUARE FOOT

SH SHOWER

SK SINK

SL SLOPE

SMP SUMP PUMP

SP STANDPIPE

SQ SQUARE

SS SERVICE SINK

SSS SURGEONS SCRUB SINK

ST STORM SEWER

STK STACK

SYS SYSTEM

T&P TEMPERATURE AND PRESSURE

TB THRUST BLOCK

TD TRENCH DRAIN

TEMP TEMPERATURE

TH THERMOMETER

TMV THERMOSTATIC MIXING VALVE

TOB TRIPLE OIL BASIN

TW TEMPERED WATER

TYP TYPICAL

UG UNDERGROUND

UNO UNLESS NOTED OTHERWISE

UR URINAL

V VENT

VB VACUUM BREAKER

VEL VELOCITY

VERT VERTICAL

VIF VERIFY IN FIELD

VTR VENT THRU ROOF

W WASTE (INTERIOR)

W/ WITH

W/O WITHOUT

WC WATER CLOSET

WCO WALL CLEANOUT

WF WASH FOUNTAIN OR WATER FILTER

WH WALL HYDRANT

WM WATER METER

WR WATER RISER

YH YARD HYDRANT

YCO YARD CLEANOUT

ZVB ZONE VALVE BOX

DEMOLITION NOTES

VALVE - BALL

VALVE - CONTROL

CLEANOUT - GROUNDGCO

P-TRAP

DROP OFF BOTTOM

EXPANSION JOINT

FLEXIBLE CONNECTION

WATER METER

EXPANSION LOOP

VENT THRU ROOF

ZONE VALVE BOX

WASHING MACHINE SUPPLY AND DRAIN BOX

KEYED NOTE TAG - DEMOLITION

M

X

(E)XXX

EXISTING EQUIPMENT TAG

EXISTING

AREA MATCHLINE1. DEMOLITION INFORMATION SHOWN ON THE DRAWINGS IS BASED

ON EXISTING DRAWINGS AND A REVIEW OF THE EXISTING CONDITIONS.

2. PERFORM ALL WORK OF A DEMOLITION NATURE THAT MAY BE

REQUIRED OR NECESSARY FOR A FULL AND COMPLETE EXECUTION

OF THE WORK, WHETHER OR NOT SHOWN OR SPECIFIED. THE

EXACT EXTENT OF DEMOLITION MAY NOT BE FULLY INDICATED BY

THE DRAWINGS. DETERMINE THE NATURE AND EXTENT OF

DEMOLITION THAT WILL BE NECESSARY BY COMPARING THE

CONTRACT DOCUMENTS WITH THE EXISTING FIELD CONDITIONS

PRIOR TO BIDS.

3. MATERIALS AND EQUIPMENT TO BE SALVAGED OR REUSED SHALL

BE IDENTIFIED BY THE OWNER. THESE ITEMS ARE THE PROPERTY

OF THE OWNER AND SHALL BE RETURNED TO THE OWNERS

DESIGNATED STORAGE AREA. WHERE REMOVAL IS REQUIRED THE

CONTRACTOR SHALL BE RESPONSIBLE FOR CARE TAKEN DURING

THE HANDLING OF THESE ITEMS.

4. DEMOLISHED MATERIALS AND EQUIPMENT NOT BEING SALVAGED

OR REUSED, SHALL BECOME THE PROPERTY OF THE CONTRACTOR

AND REMOVED FROM THE SITE AND LEGALLY DISPOSED OF.

5. WHERE EXISTING FIXTURES ARE INDICATED TO BE DEMOLISHED.

THIS SHALL INCLUDE ALL ASSOCIATED PIPING, CARRIERS, SUPPORTS,

SLEEVES, HANGERS, FITTINGS, AND OTHER ACCESSORIES. PIPING

SHALL BE REMOVED TO A LOCATION ABOVE CEILING OR BEHIND

WALLS AND CAPPED. HOWEVER NO INACTIVE BRANCH OF MORE

THAN 2 FEET IN LENGTH CAN REMAIN ON ANY PIPE. CONTRACTOR

SHALL REMOVE AS REQUIRED.

6. WHERE DEMOLITION OF FIXTURE AND REMOVAL OF PIPING OR

OTHER ACCESSORY LEAVES AN OPENING IN THE FLOOR, WALL, OR

CEILING, SAME SHALL BE PATCHED TO MATCH EXISTING ADJACENT

FINISH.

POINT OF CONNECTION (NEW TO EXISTING)

POINT OF DISCONNECT (REMOVE PIPING IN IT'S

ENTIRETY BACK TO MAIN)

9.

NO PIPING SHALL BE INSTALLED ABOVE ELECTRICAL PANELS OR

SWITCHGEAR IN ACCORDANCE WITH THE NATIONAL ELECTRIC CODE.

7.

FURNISH AND INSTALL ACCESS PANELS IN CEILINGS (EXCEPT LAY-IN

TILE CEILING) AND WALLS FOR ACCESS TO VALVES, CLEANOUTS AND

SIMILAR EQUIPMENT FOR THE OPERATION OF THE PLUMBING SYSTEM.

3.

COORDINATE LOCATIONS OF FLOOR DRAINS IN MECHANICAL ROOMS

WITH ACTUAL EQUIPMENT BEING INSTALLED.

11.

COORDINATE ALL PLUMBING WORK WITH ALL OTHER TRADES TO

ASSURE PROPER INSTALLATION AND AVOID INTERFERENCES. ANY

ADDITIONAL PIPING, OFFSETS, ETC. REQUIRED SHALL BE PROVIDED AT

NO ADDITIONAL COST OVER THE CONTRACT AMOUNT.

2.

THE PLUMBING DRAWINGS ARE DIAGRAMMATIC AND INTENDED TO

CONVEY SLOPE AND GENERAL ARRANGEMENT ONLY. REFER TO

ARCHITECTURAL DRAWINGS FOR DIMENSIONS AND DETAILS OF

CONSTRUCTION.

THE PLUMBING CONTRACTOR SHALL LOCATE UNDERGROUND PIPING

WITHIN LIMITS OF THE STRUCTURE IN COORDINATION WITH THE OTHER

CONTRACTORS TO ASSURE NO FOOTING WILL BE UNDERMINED BY

TRENCHING. ALL PIPING BELOW GRADE SHALL BE INSTALLED TO CLEAR

FOOTINGS AND SHALL NOT BE BELOW THE 45° BEARING PLANE OF THE

FOOTING. WHEN THE BOTTOM OF THE PIPING TRENCH MUST BE LOWER

THAN THE BOTTOM OF THE FOOTING, TO ENSURE THAT THE TRENCH

DOES NOT ENCROACH ON THE BEARING PLANE OF THE FOOTING, THE

TRENCH SHALL BE INSTALLED ONE AND ONE HALF (1-1/2) UNITS

HORIZONTALLY FOR EACH UNIT VERTICALLY THAT THE BOTTOM OF THE

TRENCH IS BELOW THE BOTTOM OF THE FOOTING (I.E. FOR A TRENCH 1

FOOT BELOW THE BOTTOM OF THE FOOTING THE TRENCH SHALL BE 1-

1/2 FEET AWAY FROM THE FOOTING). IF THIS CRITERIA CANNOT BE MET,

CONSULT THE DESIGN PROFESSIONAL FOR DIRECTION.

12.

13.

14.

ALL VENT TERMINALS SHALL BE A MINIMUM OF 3" IN DIAMETER AND

SHALL TERMINATE A MINIMUM OF 2'-0" ABOVE THE ROOF MAINTAINING A

DISTANCE OF 10'-0" FROM ANY AIR INTAKE. IF THE 10'-0" DISTANCE

CANNOT BE MAINTAINED THE VENT TERMINAL SHALL EXTEND A MINIMUM

OF 3'-0" ABOVE THE AIR INTAKE.

16.

ALL PIPE PENETRATIONS OF SMOKE-STOP PARTITIONS, FIRE WALLS

AND/OR FLOOR SLABS SHALL BE PROVIDED WITH SLEEVES AND SEALED

AIRTIGHT WITH FIRE RESISTANT MATERIALS PER MANUFACTURERS

RECOMMENDATIONS.

15.

REFER TO ARCHITECTURAL DRAWINGS FOR ADDITIONAL ROOF PENETRATION DETAILS.

17.

REFER TO THE ARCHITECTURAL LIFE SAFETY PLANS FOR LOCATIONS OF

SMOKE PARTITIONS AND FIRE RATED WALLS.

5.

ALL HORIZONTAL SANITARY DRAINAGE PIPING 3" AND SMALLER SHALL

BE SLOPED NO LESS THAN 1/4" PER FOOT AND NO LESS THAN 1/8" PER

FOOT FOR PIPING 4" AND LARGER. HORIZONTAL VENT PIPING SHALL BE

SLOPED BACK TO THE SOIL OR WASTE PIPE IT SERVES.

8.

ALL PIPING IN FINISHED AREAS SHALL BE INSTALLED ABOVE THE CEILING

AND/OR WITHIN WALLS. IN AREAS WITHOUT FINISHED CEILINGS PIPING

SHALL BE INSTALLED AS CLOSE TO THE STRUCTURE ABOVE AS

POSSIBLE.

18. THE PLUMBING CONTRACTOR SHALL BE RESPONSIBLE FOR CUTTING

AND/OR PATCHING OF WALLS, FLOORS AND ROOF OPENINGS AS

REQUIRED BY THE INSTALLATION OF THE PLUMBING WORK.

THE PLUMBING CONTRACTOR SHALL BE RESPONSIBLE FOR ALL

PLUMBING SYSTEMS WITHIN THE BUILDING TO APPROXIMATELY 5'-0"

FROM THE EXTERIOR OF THE BUILDING.

1.

THE MATERIALS AND INSTALLATION OF THE PLUMBING SYSTEM

SHALL CONFORM TO THE REQUIREMENTS OF THE APPLICABLE

EDITION OF THE INTERNATIONAL PLUMBING CODE AND THE

CONTRACT SPECIFICATIONS.

10.

ALL PIPING SHALL BE INSTALLED IN SUCH A WAY THAT DOES NOT

HAMPER ACCESS TO VALVES, ACCESS DOORS OR EQUIPMENT.

4.

PROVIDE CLEANOUTS IN SANITARY AND STORM PIPING AT ENDS OF

RUNS, AT CHANGES IN DIRECTION GREATER THAN 45°, AT THE BASE

OF STACKS, EVERY 50'-0" FOR HORIZONTAL RUNS 4" AND SMALLER,

EVERY 100'-0" FOR HORIZONTAL RUNS 6" AND LARGER AND

ELSEWHERE AS INDICATED. ALL CLEANOUTS SHALL BE THE FULL

SIZE OF THE PIPE FOR SIZES 4" AND SMALLER AND SHALL BE 4" FOR

PIPE SIZES LARGER THAN 4".

INSTALL TRAP PRIMER VALVE ASSEMBLIES AT ALL FLOOR DRAIN

TRAPS TO PROTECT AGAINST EVAPORATION UNLESS THE FLOOR

DRAIN TRAP RECEIVES A REGULAR WASTE DISCHARGE.

6.

RISER INDICATOR - TOP INDICATES TYPE

OF RISER, BOTTOM INDICATES RISER

NUMBER (ARROW INDICATES DIRECTIONAL

VIEW OF ISOMETRIC RISERS)

RISER INDICATOR / DETAIL NO.

TOP INDICATES TYPE OF RISER / DETAIL NO.

BOTTOM INDICATES RISER NUMBER / DWG NO

RD

FD

FD

TD

WCO

GPR

TH

V

V

V

W

W

W

ST

ST

ST

IW

IW

IW

VALVE

X KEYED NOTE TAG - NEW

VALVE - GAS COCK

FULLY SPRINKLERED

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT/ENGINEERS:

Office of

Facilities

Management o n e e ig h th i n c h o n e f o o t

B

A

C

D

E

F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Department of Veterans Affairs

BIDDING DOCUMENTS - JANUARY 30, 2019

VA CARES CONSOLIDATION

VAMC, PITTSBURGH, PA

CONNECTING BRIDGE

PL1-001

646CA2500.23

MPBER

SYMBOLS, ABBREVIATIONS

AND GENERAL NOTES

VAPHS UNIVERSITY DRIVE

1 & 30

DNUP

DN

ICEU

P

D N

U P

D N

EXISTING BUILDING 30

2ND FLOOR

3"

3"

3"

3"

3"

3"

4"

2"

3/4"3/4"

S T

ST

S T

S T

EXISTING BUILDING 1

2ND FLOOR

D

E

E.6

E.7

F

6.5

6.1 x.19x.18x.17 x.16x.14 x.1 x.C

EA

4"

3/4" x.12 x.13

4"

3/4"

3/4"3/4" x.16x.14 x.2 x.1 x.C

EA

FULLY SPRINKLERED

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT/ENGINEERS:

Office of

Facilities

Management o n e e ig h th i n c h o n e f o o t

B

A

C

D

E

F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Department of Veterans Affairs

BIDDING DOCUMENTS - JANUARY 30, 2019

VA CARES CONSOLIDATION

VAMC, PITTSBURGH, PA

CONNECTING BRIDGE

PL1-101

646CA2500.23

MPBER

PLUMBING NEW WORK

PLANS

VAPHS UNIVERSITY DRIVE

1 & 30

1/8" = 1'-0"

BUILDINGS 1 & 30 - 2ND FLOOR PLUMBING NEW WORK PLAN

CONNECT NEW 3" V. TO EX. 3" V., RISE UP & OFFSET ABOVE

CEILING.

PLUMBING KEYED NOTES

1/8" = 1'-0"

BUILDING 1 - 1ST FLOOR PLUMBING NEW WORK PLAN

CONNECT NEW 3" V. TO EX. 3" V. RISE AT CEILING.2

CONNECT NEW 4" V. TO EX. 4" SV. & OFFSET ABOVE CEILING.3

CONNECT NEW 3/4" CW. TO EX. CW. ABOVE CEILING (FIELD

VERIFY EXACT SIZE & LOCATION).

NEW 3/4" CW. & 4" V. ABOVE CEILING: RISE UP TO FLOOR

ABOVE.

CONNECT NEW 3/4" CW. & 3/4" HW. TO EX. CW. & HW. ABOVE

CEILING (FIELD VERIFY EXACT SIZE & LOCATION).

NEW 3/4" CW. & 3/4" HW. ABOVE CEILING: RISE UP TO FLOOR

ABOVE.

CO

NEW 3" ST. DN. FROM ROOF DRAIN (RD-1) ON ROOF ABOVE:

OFFSET ABOVE CEILING.

CO

EX. 4" VRC.

EX. 4" ST. DN. FROM

EX. 4" RD. ABV.

CONNECT NEW 3" ST. TO EX. 4" VRC.9

EX. 3/4" CW. UP TO

ROOF ABV.

NEW 3/4" CW. & 4" V. UP FROM FLOOR BELOW: RISE ABOVE

CEILING & OFFSET.

PROVIDE NEW 4" VENT THRU ROOF - MAINTAIN 25'-0" FROM ANY

O.A. INTAKES

CONNECT NEW 3/4" CW. TO EX. 3/4" CW. ABOVE CEILING (FIELD

VERIFY EXACT SIZE & LOCATION).

CONNECT NEW 2" V. TO EX. 2" V. ABOVE CEILING, EXTEND AND

CONNECT TO 4" VENT ABOVE CEILING. (FIELD VERIFY EXACT

SIZE & LOCATION).

NEW 3/4" CW. & 3/4" HW. UP FROM FLOOR BELOW: RISE ABOVE

CEILING & OFFSET.

NEW 3/4" CW. & 3/4" HW. ABOVE CEILING: DROP DN. IN CHASE

& CONNECT TO EX. CW. & HW. (FIELD VERIFY EXACT SIZE &

LOCATION).

GENERAL PLUMBING NOTES:

COORDINATE ALL NEW AND DEMOLITION WORK REQUIRED WITH

EXISTNG USERS TO KEEP AREAS OF WORK UP AND RUNNING IN

CASE OF POSSIBLE SHUTDOWNS AND OR DISRUPTIONS.

1.

3" ST PIPING LOCATED IN

BULKHEAD PROVIDED BY G.C.

NOTES

1.

2.

ATTACH SUPPORTS FOR ALL PIPING SUSPENDED FROM THE STEEL

STRUCTURE TO THE TOP CORD OF JOISTS OR BEAMS WHERE

POSSIBLE.

PROVIDE COPPER OR PLASTIC COATED HANGERS FOR

NON-INSULATED COPPER PIPE.

CONTINUOUS HANGER ROD TO BEAM

OR FRAMING CHANNEL

ADJUSTABLE CLEVIS

PIPE INSULATION SHIELD REQUIRED FOR

INSULATED PIPE

WHERE REQUIRED BY CODE. HANGER ROD

SIZE FOR LOAD AND SPACING TO MEET

REQUIREMENTS FOR SEISMIC RESTRAINT

8" THROUGH 12" PIPE

ADJUSTIBLE STEEL YOKE PIPE ROLL

FOR PIPING WITH HIGH EXPANSION AND

CONTRACTION FORCES

2 1/2" THROUGH 6" PIPE

INSULATION PROTECTION. PIPE SADDLE

SIZE TO FIT INSULATION AND PIPE SIZE

WHERE REQUIRED BY CODE. HANGER ROD

SIZE FOR LOAD AND SPACING TO MEET

REQUIREMENTS FOR SEISMIC RESTRAINT

PIPE HANGER FOR LIGHT WEIGHT PIPE

PIPE INSULATION SHIELD REQUIRED FOR

INSULATED PIPE

CONTINUOUS HANGER ROD TO BEAM

OR FRAMING CHANNEL

CONTINUOUS HANGER ROD TO BEAM

OR FRAMING CHANNEL

HANGER ROD

HEAVY DUTY CLEVIS

HANGER

LOCKING NUT

EYE SOCKET

STEEL BEAM

WELDED BEAM

ATTACHMENT

HANGER ROD

LOCKING NUT

STEEL BEAM

INSULATION WHERE SPECIFIED

SHALL COVER PIPE HANGER

STURCTURAL STEEL BEAM.

SEE PROJECT PLANS FOR

SIZES.

ADJUSTABLE BEAM

CLAMP

ADJUSTABLE BAND

HANGER

INSULATION WHERE SPECIFIED

SHALL COVER PIPE HANGER

STURCTURAL STEEL BEAM.

SEE PROJECT PLANS FOR

SIZES.

LENGTH VARIES

"C" TYPE BEAM CLAMP (2"

PIPE AND SMALLER)

ALL THREAD ROD(TYP)

BAR JOIST

FENDER WASHER

DOUBLE NUT

STEEL STRUCTURE

BAR JOIST

NOTES:

1. FOR HANGER PLACMENT REQUIREMENTS, AND HANGER ROD SPACING,

REFER TO THE SPECIFICATIONS

2. HANGER LOAD SHALL BE LIMITED PER MANUFACTURES RECOMMENDATIONS

LENGTH VARIES

3M FS-195 WRAP/STRIP

AND CP 25 CAULK TO

MAINTAIN FIRE RATING

PIPE & INSULATION

(WHERE APPLICABLE)

INTERIOR WALL

WALL CONSTRUCTION

(SEE ARCH. DWGS.)SHEET METAL SLEEVE

STAINLESS STEEL

ESCHUTCHION

PLATE IN FINISHED

AREAS ONLY

1"1"

1.

2.

NOTES:

INSTALL ALL MATERIALS IN ACCORDANCE WITH MANUFACTURER'S PRINTED INSTALLATION INSTRUCTIONS.

SEE ARCHITECTURAL AND STRUCTURAL DRAWINGS FOR FLOOR CONSTRUCTION MATERIALS AND OTHER PERTINENT INFORMATION.

STANDARD WEIGHT STEEL PIPE

FLOOR SLEEVE. TERMINATE 1"

ABOVE FINISHED FLOOR SURFACE

FLOOR

PIPE

CENTER PIPE IN SLEEVE

PIPE

INSULATION

SEAL OR CAULK SLEEVE WITH

FIRE STOPPING MATERIAL TO

MEET WALL FIRE, SMOKE, OR

COMBINATINO RATING

INSULATED UNINSULATED

BALLAST SEE

ARCH DWGS

SUMP RECEIVER

ROOF DRAIN, SEE SPECS

FOR REQUIREMENTS

ROOFING MATERIAL,

SEE ARCH DWGS

INSULATION

METAL DECK

16 GA SHEET

METAL WELDED TO

BOTTOM OF DECK

UNDER DECK CLAMPDEFLECTION

CONNECTION

INSULATE DRAIN BODY AND

HORIZONTAL STORM WATER

PIPING TO THE VERTICAL

PVC PIPING

3/4" DCW

3/4" DCW

4" V

4" V

3" ST

3" ST

3" ST

4" ST

4" ST

EXISTING

EXISTING

3/4" DCW

EXISTING

4" SAN

3" SAN

3/4" DCW

1/2" DCW

EXISTING

EXISTING

EXISTING

RELOCATED

4" V

ABV. CLG.

ABV. CLG.

ETR

ETR

1" DHW

EXISTING

3/4" DHW

1/2" DHW

3/4" DCW

3/4" DHW

EXISTING

EXISTING

EXISTING

EXISTING

3/4" DHW 3/4" DCW

EXISTING EXISTING

1 1/2" DCW

EXISTING

FULLY SPRINKLERED

Drawing Title

Approved: Project Director

Project Title

Date

Location

Checked

Building Number

Project Number

Drawing Number

Drawn

Dwg. ofRevisions: Date

CONSULTANTS: ARCHITECT/ENGINEERS:

Office of

Facilities

Management o n e e ig h th i n c h o n e f o o t

B

A

C

D

E

F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t

VA FORM 08-6231, OCT 1978

1 2 3 4 5 6 87 9

F

E

D

C

B

A

97 8654321

Department of Veterans Affairs

BIDDING DOCUMENTS - JANUARY 30, 2019

VA CARES CONSOLIDATION

VAMC, PITTSBURGH, PA

CONNECTING BRIDGE

PL1-401

646CA2500.23

MPBER

PLUMBING DETAILS

VAPHS UNIVERSITY DRIVE

1 & 30

NTS

PL1-401_1_

NTS

PL1-401_2_

NTS3

PL1-401_3_

NTS4

Plumbing

NTS7

PL1-401_7_

NTS6

ROOF DRAIN

PLUMING RISER DIAGRAM

4" VTR

RD-1

RD-1

CO

CO

PLD-101 - PLUMBING DEMOLITION FLOOR PLANS
Sheets
PL-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
PL-101 - PLUMBING NEW WORK PLANS
PL-401 - PLUMBING DETAILS
PLD-101 - PLUMBING DEMOLITION FLOOR PLANS
PL1-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
Sheets
FA1-001 - FIRE PROT. SYMBOLS & ABBREVIATIONS
FA1-101 - FIRE PROTECTION FLOOR PLAN
PL1-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
PL1-101 - PLUMBING NEW WORK PLANS
PL1-401 - PLUMBING DETAILS
PL1-101 - PLUMBING NEW WORK PLANS
Sheets
FA1-001 - FIRE PROT. SYMBOLS & ABBREVIATIONS
FA1-101 - FIRE PROTECTION FLOOR PLAN
PL1-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
PL1-101 - PLUMBING NEW WORK PLANS
PL1-401 - PLUMBING DETAILS
PL1-401 - PLUMBING DETAILS
Sheets
FA1-001 - FIRE PROT. SYMBOLS & ABBREVIATIONS
FA1-101 - FIRE PROTECTION FLOOR PLAN
PL1-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES
PL1-101 - PLUMBING NEW WORK PLANS
PL1-401 - PLUMBING DETAILS

File details come from the government source that posted it.