36C10F19R0003-019.pdf
PDF 569 KB Posted
- Solicitation number
- 36C10F19R0003
About this file
36C10F19R0003 COMBINED FIRE PROTECTION.pdf
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DNUP
DN
6.5
FE
D x.G x.J x.L x.5 x.6
E.7
EA
x.12 x.13
EXISTING BUILDING 1
2ND FLOOR
AREA W
EXISTING BUILDING 30
2ND FLOOR
~ FP
F P
F P
F P
FP
D
E
E.6
E.7 F
3.4
6.5
6.1
12.8 x.8x.7x.6x.5x.4 x.19x.18x.17x.16x.14 x.2 x.1 x.C
EA
x.J x.L x.N x.P x.3
FP
FP
FP
2" ETR
2"
ETR
2"
ETR
FULLY SPRINKLERED
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
Office of
Facilities
Management o n e e ig h th i n c h o n e f o o t
B
A
C
D
E
F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Department of Veterans Affairs
BIDDING DOCUMENTS - JANUARY 30, 2019
VA CARES CONSOLIDATION
VAMC, PITTSBURGH, PA
CONNECTING BRIDGE
FAD-101
646CA2500.23
MPBER
FIRE PROTECTION
DEMOLITION FLOOR PLAN
VAPHS UNIVERSITY DRIVE
1 & 30
1/8" = 1'-0"
PLUMBING / FIRE PROTECTION DEMOLITION FLOOR PLAN
1 DISCONNECT AND REMOVE EXISTING SPRINKLERS AND
ASSOCIATED BRANCH PIPING ABOVE AND BELOW DEMOLISHED
RAISED WALKWAY IN THIS AREA.
DISCONNECT AND REMOVE EXISTING SPRINKLERS AND
ASSOCIATED BRANCH PIPING THIS AREA.
FIRE PROTECTION KEYED NOTES
EXISTING SPRINKLER RISER3
EXISTING BUILDING #30 - 2ND FLOOR ZONE CONTROL VALVE
ASSEMBLY.
EXISTING BRIDGE ZONE CONTROL VALVE ASSEMBLY.5
EXISTING SPRINKLER FEED MAIN.6
EXISTING SPRINKLER FEED MAIN TO 2ND FLOOR SPRINKLER
SYSTEM.
EXISTING STANDPIPE WITH 2-1/2" FIRE HOSE VALVE. RAISE
EXISTING 2-1/2" FIRE HOSE VALVE AS REQUIRED.
EXISTING BUILDING #1 - 2ND FLOOR ZONE CONTROL VALVE
ASSEMBLY: DISCONNECT, RELOCATE & RECONNECT AS
REQUIRED TO ACCOMMODATE NEW CORRIDOR WALL.
EXISTING SPRINKLER SYSTEM TO REMAIN THIS AREA.10
1 AMENDMENT 3 01-31-17
ABBREVIATIONS
PRESSURE SWITCH
VALVE - CHECK (SHOWN W/FLOW)
VALVE - OS&Y
DIRECTION OF FLOW
PIPE ANCHOR
UNION
VALVE
BACKFLOW PREVENTER (BFP)
SPRINKLER HEAD - CONCEALED
FIRE PROTECTION PIPING - EXISTING
FIRE PROTECTION PIPING
FIRE PROTECTION PIPING - DEMO
EX. FP
FP
SPRINKLER HEAD - UPRIGHT
SYMBOLS
GC GENERAL CONTRACTOR
GPM GALLONS PER MINUTE
IN INCHES
ITC INSPECTORS TEST CONNECTION
MD MAIN DRAIN
NA NOT APPLICABLE
N.C. NORMALLY CLOSED
NIC NOT IN CONTRACT
NO. NUMBER
N.O. NORMALLY OPEN
NS NOT SPRINKLERED
NTS NOT TO SCALE
N&C NIPPLE AND CAP
OSW OPEN SITE WASTE
OS&Y OUTSIDE SCREW AND YOKE
P PUMP
PG PRESSURE GAUGE
PIV POST INDICATOR VALVE
PKG PACKAGE
POC POINT OF CONNECTION
PRESS PRESSURE
PRV PRESSURE REDUCING VALVE
PSI POUNDS PER SQUARE INCH
PSIG POUNDS PER SQUARE INCH GAUGE
QTY QUANTITY
RN RISER NIPPLE
RPM REVOLUTIONS PER MINUTE
SCV SECTIONAL CONTROL VALVE W/ TAMPER SWITCH
SP STANDPIPE
SPKR SPRINKLER
SUB-CTR. SUB CONTRACTOR
SYS SYSTEM
TB THRUST BLOCK
TEMP TEMPERATURE
TH THERMOMETER
TS TAMPER SWITCH
TYP TYPICAL
UG UNDERGROUND
UNO UNLESS OTHERWISE NOTED
VEL VELOCITY
VERT VERTICAL
VIF VERIFY IN FIELD
W/ WITH
W/O WITHOUT
WIP WALL INDICATOR POST
DEMOLITION NOTES
DESIGN CRITERIA
VALVE - POST INDICATOR
VALVE - DRY PIPE
DPV
PIV
VALVE - SOLENOID
VALVE - CONTROL
ELBOW DOWN
ELBOW UP
PUMP (SCHEMATIC)
BOTTOM DROP
FLOW SWITCH
FIRE DEPARTMENT VALVE
FIRE HOSE CABINET
FIRE DEPARTMENT HOSE VALVE
FIRE DEPARTMENT CONNECTION
FIRE DEPARTMENT CONNECTION - FREE-STANDING
FIRE PUMP TEST HEADER - FLUSH
FIRE PUMP TEST HEADER - FREE-STANDING
POINT OF CONNECTION (NEW TO EXISTING)
POINT OF CONNECTION (NEW TO EXISTING)
AREA MATCHLINE
FDV
FHC
FDC
CAPPED PIPING
FPT
1. DEMOLITION INFORMATION SHOWN ON THE DRAWINGS IS BASED ON EXISTING
DRAWINGS AND A PRELIMINARY REVIEW OF THE EXISTING CONDITIONS.
PERFORM ALL WORK OF A DEMOLITION NATURE THAT MAY BE REQUIRED
OR NECESSARY FOR A FULL AND COMPLETE EXECUTION OF THE WORK,
WHETHER OR NOT SHOWN OR SPECIFIED. THE EXACT EXTENT OF
DEMOLITION MAY NOT BE FULLY INDICATED ON THE DRAWINGS.
CONTRACTOR TO FIELD VERIFY EXISTING CONDITIONS PRIOR TO BIDS
AND CONFIRM COMPLETE EXTENT OF DEMOLITION REQUIRED.
2. MATERIALS AND EQUIPMENT TO BE SALVAGED SHALL BE
IDENTIFIED BY THE OWNER. THESE ITEMS ARE THE PROPERTY OF THE
OWNER AND SHALL BE RETURNED TO THE OWNERS DESIGNATED
STORAGE AREA. WHERE REMOVAL IS REQUIRED THE CONTRACTOR
SHALL BE RESPONSIBLE FOR CARE TAKEN DURING THE HANDLING OF
THESE ITEMS.
3. DEMOLISHED MATERIALS AND EQUIPMENT NOT BEING SALVAGED OR
REUSED, SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND
REMOVED FROM THE SITE AND LEGALLY DISPOSED OF.
4. COORDINATE ALL DEMOLITION WORK REQUIRED INCLUDING DRAINING OF SYSTEMS,
PHASING, SHUTDOWNS AND/OR DISRUPTIONS AS REQUIRED.
1. SPRINKLER SYSTEM SHALL BE DESIGNED IN ACCORDANCE WITH THE
V.A. FIRE PROTECTION DESIGN MANUAL SEVENTH EDITION 2015,
NFPA 13 AND FM STANDARDS. NEW SPRINKLER PIPING
SHALL BE HYDRAULICALLY SIZED TO MEET THE FOLLOWING CRITERIA:
A. OCCUPANCY CLASSIFICATION LIGHT HAZARD, AREA OF
APPLICATION LARGEST ROOM, DESIGN DENSITY .10 GPM/SQ. FT.
SPRINKLER K FACTOR 5.6, CLASSIFICATION 135 DEGREE F.
B. LIGHT HAZARD OCCUPANCY - DENSITY .10 GPM PER SQ. FT.
OVER MOST HYDRAULICALLY REMOTE 1500 SQ. FT. MAXIMUM
COVERAGE PER HEAD 225 SQ. FT.
C. ORDINARY HAZARD - DENSITY .15 GPM PER SQ. FT. OVER MOST
HYDRAULICALLY REMOTE 1500 SQ. FT. MAXIMUM COVERAGE
PER HEAD 130 DQ. FT.
D. EXACT LOCATION OF SPRINKLER HEADS IN FINISHED AREAS WITH
SUSPENDED CEILINGS SHALL BE ON CENTER OF TILE AND AS
INDICATED ON SPRINKLER CEILING PLANS. PIPING TO BE
COORDINATED WITH OTHER TRADES.
E. DISCHARGE FROM EACH SPRINKLER HEAD SHALL NOT BE LESS
THAN REQUIRED FOR AREA COVERED BY THIS HEAD. AREA
COVERAGE PER HEAD SHALL BE DETERMINED IN ACCORDANCE
WITH NFPA STANDARD NO. 13, PARAGRAPH 7-4.3.1.2.
F. MINIMUM PRESSURE AT SPRINKLER HEAD 7 PSI.
G. HYDRAULIC CALCULATIONS SHALL BE BROUGHT BACK TO
CONNECTION TO WATER SUPPLY.
H. CONTRACTOR SHALL ORDER HYDRANT FLOW TEST AND BASE
ALL HYDRAULIC CALCULATIONS ON RESULTS OF TEST.
1. HYDRANTS TESTED SHALL BE LOCATED AS CLOSE AS
POSSIBLE TO POINT OF FIRE SERVICE CONNECTION TO
CITY MAIN.
2. TEST DATA SHALL INDICATE STATIC PRESSURE, RESIDUAL
PRESSURE AT TEST FLOW AND GRADE ELEVATION AT
HYDRANT TESTED.
3. HYDRANT TEST DATA SHALL BE SUBMITTED FOR REVIEW
ALONG WITH SHOP DRAWINGS AND HYDRAULIC
CALCULATIONS.
I. RESULT OF HYDRAULIC CALCULATIONS SHALL INDICATE MINIMUM
10 PSI PRESSURE SAFETY MARGIN, I.E. EXCESS OF PRESSURE
AVAILABLE OVER PRESSURE REQUIRED.
2. FIRE PUMP INFORMATION:
A. FIRE PUMP PATTERSON PUMP MODEL 5x4x12 SSC HORIZONTAL SPLIT CASE
FIRE PUMP. RATED AT 750 GPM AT 140 PSI 323' TDH, DRIVEN BY 100 HP,
3550 RPM, 460 VOLT, 3 PHASE 60 CYCLE. (COUNTER CLOCKWISE ROTATION).
B. JOCKEY PUMP - PATTERSON PUMP MODEL PM3-17 VERTICAL MULTI-STAGE
CENTRIFUGAL JOCKEY PUMP. RATED AT 15 GPM AT 164 PSI 379' TDH, 3 HP,
460 VOLT, 3 PHASE, 60 CYCLE, 3450 RPM.
POINT OF DISCONNECT (DEMO TO EXISTING)
VALVE - BALL
GENERAL NOTES
1. THE FIRE PROTECTION CONTRACTOR SHALL PROVIDE AN AUTOMATIC SPRINKLER
SYSTEM TO PROTECT ALL AREAS OF THE FACILITY.
2.
THE COMPLETE INSTALLATION AND TESTING OF THE AUTOMATIC SPRINKLER SYSTEM
SHALL CONFORM TO THE REQUIREMENTS OF THE APPLICABLE EDITION OF NFPA 13,
AND THE AUTHORITY HAVING JURISDICTION AND THE CONTRACT SPECIFICATIONS.
3.
THE FIRE PROTECTION DRAWINGS ARE INTENDED FOR BIDDING PURPOSE ONLY
AND ARE NOT INTENDED TO COVER EACH AND EVERY ITEM REQUIRED FOR AN
APPROVED SYSTEM. SHOULD ADDITIONAL SPRINKLER HEADS OR EQUIPMENT
NEED TO BE INSTALLED TO MEET THE REQUIREMENTS SET FORTH BY NFPA, THE
FIRE PROTECTION CONTRACTOR SHALL DO SO AT HIS EXPENSE.
4.
THE FIRE PROTECTION CONTRACTOR SHALL VERIFY ALL CEILING TYPES, CEILING
HEIGHTS, ROOM DIMENSIONS, AND SPRINKLER HEAD LOCATIONS BEFORE
PERFORMING ANY WORK. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS
AND ROOM FINISH SCHEDULES.
6.
THE FIRE PROTECTION CONTRACTOR SHALL SHOW ALL LIGHT FIXTURES, HVAC
GRILLES, EXPOSED DUCTWORK, AND BULKHEADS ON THE SPRINKLER SHOP
DRAWINGS.
SPRINKLER HEADS NEAR HEATERS AND LOCATED WITHIN HEATER ZONES AS
DEFINED BY NFPA 13 SHALL BE HIGH TEMPERATURE RATED.
8.
9.
SPRINKLER PIPING SHALL NOT BE INSTALLED ABOVE ELECTRICAL PANELS OR
SWITCHGEAR IN ACCORDANCE WITH THE NATIONAL ELECTRIC CODE.
ALL VALVE SUPERVISORY SWITCHES AND WATER FLOW SWITCHES SHALL BE
FURNISHED AND INSTALLED BY THE FIRE PROTECTION CONTRACTOR AND WIRED
BY THE ELECTRICAL CONTRACTOR. (EXISTING TO REMAIN).
11.
ALL DRAIN LINES INCLUDING THE DRAIN FOR THE AUTOMATIC SPRINKLER SYSTEM
INSPECTOR'S TEST CONNECTION AND THE AUTOMATIC SPRINKLER SYSTEM MAIN DRAIN
SHALL BE GALVANIZED STEEL. THE INSPECTORS TEST CONNECTION SHALL TERMINATE
WITH A FULL PORT BALL VALVE AND A SMOOTH BORE CORROSION RESISTANT OUTLET
GIVING FLOW EQUIVALENT TO ONE SPRINKLER HEAD.
14.
A PRESSURE TEST OF THE AUTOMATIC SPRINKLER SYSTEM SHALL BE WITNESSED BY
THE FIRE DEPARTMENT. TWO WEEKS ADVANCED WRITTEN NOTICE OF TEST SHALL BE
GIVEN. ALL LEAKAGE EVIDENCED BY THE TESTING SHALL BE REPAIRED AT THE
CONTRACTOR'S EXPENSE BY TIGHTENING OR REPLACING FITTINGS OR EQUIPMENT.
15.
16.
MAXIMUM SPRINKLER SPACING FOR LIGHT HAZARD AREAS SHALL NOT EXCEED 225
SQUARE FEET PER SPRINKLER. MAXIMUM SPACING FOR ALL ORDINARY HAZARD AREAS
SHALL NOT EXCEED 130 SQUARE FEET PER SPRINKLER.
17.
THE SPRINKLER HEAD TEMPERATURE RATING (EXCEPT WHERE HIGHER
TEMPERATURE REQUIRED BY NFPA 13) SHALL BE 165 DEGREES F.
13.
ALL SPRINKLER SYSTEMS SHALL BE HYDRAULICALLY DESIGNED TO PROVIDE THE
MINIMUM DENSITIES AS INDICATED OR SPECIFIED. THE FIRE PROTECTION HYDRAULIC
CALCULATIONS FOR THE AUTOMATIC SPRINKLER SYSTEMS SHALL INCORPORATE A
MINIMUM 10 PSI SAFETY FACTOR.
12.
ALL PIPE PENETRATIONS OF SMOKE PARTITIONS AND BARRIERS, FIRE WALLS AND
BARRIERS, AND FLOORS SHALL BE PROVIDED WITH SLEEVES AND SEALED WITH FIRE
RESISTANT MATERIALS PER MANUFACTURERS RECOMMENDATIONS IN ACCORDANCE
WITH DIVISION 7. REFER TO THE ARCHITECTURAL LIFE SAFETY PLANS FOR
LOCATIONS OF SMOKE PARTITIONS AND FIRE RATED CONSTRUCTION.
5.
COORDINATE ALL FIRE PROTECTION WORK WITH ALL OTHER TRADES TO
ASSURE PROPER INSTALLATION AND AVOID INTERFERENCES. ANY ADDITIONAL
PIPING, OFFSETS, ETC.. REQUIRED SHALL BE PROVIDED AT NO ADDITIONAL
COST OVER THE CONTRACT AMOUNT.
10.
ALL WATERFLOW SWITCHES MUST BE ISOLATED BY MEANS OF A FITTING OR UNION ON
BOTH SIDES TO FACILITATE REMOVAL AND SERVICE OF THE FLOW SWITCH. (EXISTING
ASSEMBLY TO BE RELOCATED AS REQUIRED)
7.
ALL SPRINKLER HEADS LOCATED IN LAY-IN CEILING TILES SHALL BE LOCATED IN THE
CENTER OF THE 2x2 PORTION OF THE 2x4 CEILING TILES. REFER TO THE ARCHITECTS
REFLECTED CEILING PLANS. IF FOR ANY REASON SPRINKLERS CANNOT BE LOCATED IN
THE CENTER OF 2x2 PORTION OF THE 2x4 CEILING TILES OR WHERE SHOWN IN OTHER
TYPES OF CEILINGS, THE ARCHITECT SHALL BE CONTACTED FOR NEW LOCATIONS
BEFORE INSTALLING ANY SPRINKLER HEADS OR PIPING.
AC AIR COMPRESSOR
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AHJ AUTHORITY HAVING JURISDICTION
AP ACCESS PANEL
ARCH ARCHITECTURE
ASSY ASSEMBLY
ATM ATMOSPHERE
AUTO AUTOMATIC
AUX AUXILIARY
BOB BOTTOM OF BEAM
BOP BOTTOM OF PIPE
CA COMPRESSED AIR OR CLEAN AGENT
CALCS CALCULATIONS
CAP CAPACITY
CC CEILING COLUMN
CCD CHICAGO CITY DATUM
CLG CEILING
CM CENTIMETER
CO2 CARBON DIOXIDE
COL COLUMN
CONC CONCRETE
CONN. CONNECTION
CONT. CONTINUED
CSP COMBINED STANDPIPE/SPRINKLER SYSTEM
CV CHECK VALVE
DCV DOUBLE CHECK VALVE
DDCV DOUBLE DETECTOR CHECK VALVE
DIA DIAMETER
DIM DIMENSION
DN DOWN
DPV DRY PIPE VALVE
DR DRAIN
DV DRAIN VALVE
DWG DRAWING
EA EACH
ELEV. ELEVATION
ELEC ELECTRICAL
EQUIP EQUIPMENT
EX EXISTING
EXIST EXISTING
EXP EXPANSION
F FAHRENHEIT
FA FIRE ALARM
FACP FIRE ALARM CONTROL PANEL
FBO FURNISHED BY OTHERS
FDC FIRE DEPARTMENT CONNECTION
FDV FIRE DEPARTMENT VALVE
FEC FIRE EXTINGUISHER CABINET
FH FIRE HOSE
FHC FIRE HOSE CABINET
FHR FIRE HOSE RACK
FIN FINISHED
FLR FLOOR
FP FIRE PROTECTION
FPC FIRE PUMP CONTROLLER
FPM FEET PER MINUTE
FPS FEET PER SECOND
FPTC FIRE PUMP TEST CONNECTION
FS FLOW SWITCH
FT FEET
FIRE SPRINKLER WATER DEMAND
CORRIDOR GA153.
LANDING 1,2, & 3.
STAIR #5
OCCUPANCY CLASSIFICATION:
TYPE OF SPRINKLER SYSTEM:
DESIGN OF WATER APPLICATION:
MINIMUM DENSITY
SPRINKLER TEMERATURE RATING
SPRINKLER 'K' FACTOR:
SPRINKLER HEAD TYPE:
HOSE STREAM ALLOWANCE:
LIGHT HAZARD
WET
1500 SQ. FT.
.10 GPM/SQ. FT.
135°
K = 5.6
QUICK RESPONSE CONCEALED PENDENT
100 GPM
FULLY SPRINKLERED
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
Office of
Facilities
Management o n e e ig h th i n c h o n e f o o t
B
A
C
D
E
F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Department of Veterans Affairs
BIDDING DOCUMENTS - JANUARY 30, 2019
VA CARES CONSOLIDATION
VAMC, PITTSBURGH, PA
CONNECTING BRIDGE
FA1-001
646CA2500.23
AuthorChecker
FIRE PROT. SYMBOLS &
ABBREVIATIONS
VAPHS UNIVERSITY DRIVE
1 & 30
1 AMENDMENT 3 01-31-17
6.5
FE
D x.G x.J x.L x.5 x.6
E.7
EA
x.12
F P
F P
FP
FP
F P
F P
FPFP
F P
D
E
E.6
E.7 F
6.5
6.1
12.8 x.11x.10x.8x.7x.6x.5x.4 x.19x.18x.17x.16x.14 x.2 x.1 x.C
EA
x.D x.E x.F x.G
FP
FP
FP ~
ETR
ETR
(TYP.)
ETR
ETR
(TYP.)
ETR
(TYP.)
2"ETR
2"
ETR
2"
2"
FULLY SPRINKLERED
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
CONSULTANTS: ARCHITECT/ENGINEERS:
Office of
Facilities
Management o n e e ig h th i n c h o n e f o o t
B
A
C
D
E
F th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t 4 o n e q u a rt e r in c h o n e f o o t
VA FORM 08-6231, OCT 1978
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Department of Veterans Affairs
BIDDING DOCUMENTS - JANUARY 30, 2019
VA CARES CONSOLIDATION
VAMC, PITTSBURGH, PA
CONNECTING BRIDGE
FA1-101
646CA2500.23
MPBER
FIRE PROTECTION FLOOR
PLAN
VAPHS UNIVERSITY DRIVE
1 & 30
1/8" = 1'-0"1
FA1-101_1_
1 EXTENT OF NEW SPRINKLER WORK CONNECTING TO EXISTING
BRIDGE ZONE CONTROL VALVE ASSEMBLY.
EXTENT OF NEW SPRINKLER WORK CONNECTING TO EXISTING
BULIDING 1 - 2ND FLOOR ZONE CONTROL VALVE ASSEMBLY.
FIRE PROTECTION KEYED NOTES
CONNECT NEW SPRINKLER FEED MAIN TO EXISTING
SPRINKLER FEED MAIN CAPPED CONNECTION (FIELD VERIFY
EXACT SIZE, LOCATION & ELEVATION).
NEW SPRINKLER: PROVIDE NEW BRANCH PIPE AND CONNECT
TO EXISTING SPRINKLER FEED MAIN PIPING.
4 4 4
4 4 4 4 44
NEW SPRINKLER: CONNECT TO NEW SPRINKLER FEED MAIN
PIPING.
EXISTING SPRINKLER (TYP.)6
EXISTING SPRINKLER RISER7
EXISTING BUILDING #30 - 2ND FLOOR ZONE CONTROL VALVE
ASSEMBLY.
EXISTING BRIDGE ZONE CONTROL VALVE ASSEMBLY.9
EXISTING SPRINKLER FEED MAIN TO 2ND FLOOR SPRINKLER
SYSTEM.
EXISTING STANDPIPE, RAISE WITH 2-1/2" FIRE HOSE VALVE
TO NOT LESS THAN 3'-0" OR MORE THAN 5'-0" ABOVE NEW
FLOOR LINE.
RELOCATED BUILDING #1 - 2ND FLOOR ZONE CONTROL
VALVE ASSEMBLY.
6 6
PROVIDE AUXILLIARY
DRAIN AS REQUIRED
1 AMENDMENT 3 01-31-17
| FAD-101 - FIRE PROTECTION DEMOLITION FLOOR PLAN |
| Sheets |
| FA-001 - FIRE PROT. SYMBOLS & ABBREVIATIONS |
| FA-101 - FIRE PROTECTION FLOOR PLAN |
| FAD-101 - FIRE PROTECTION DEMOLITION FLOOR PLAN |
| FA1-001 - FIRE PROT- SYMBOLS & ABBREVIATIONS |
| Sheets |
| FA1-001 - FIRE PROT. SYMBOLS & ABBREVIATIONS |
| FA1-101 - FIRE PROTECTION FLOOR PLAN |
| PL1-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES |
| PL1-101 - PLUMBING NEW WORK PLANS |
| PL1-401 - PLUMBING DETAILS |
| FA1-101 - FIRE PROTECTION FLOOR PLAN |
| Sheets |
| FA1-001 - FIRE PROT. SYMBOLS & ABBREVIATIONS |
| FA1-101 - FIRE PROTECTION FLOOR PLAN |
| PL1-001 - SYMBOLS, ABBREVIATIONS AND GENERAL NOTES |
| PL1-101 - PLUMBING NEW WORK PLANS |
| PL1-401 - PLUMBING DETAILS |
File details come from the government source that posted it.