36C10F19R0003-0002001.pdf

PDF 41 KB Posted

Attached to
Research Office Building (ROB) Connecting Bridge VAPHS, Pittsburgh, PA
Solicitation number
36C10F19R0003
Issued by

About this file

36C10F19R0003 0002 2019 04 25 PreBid RFIs CFM.pdf

View the file

Other files

File Type Posted
36C10F19C0016-000.docx DOCX document
36C10F19R0003-0007000.docx DOCX document
36C10F19R0003-0007002.pdf PDF
36C10F19R0003-0007003.pdf PDF
36C10F19R0003-0007004.pdf PDF
36C10F19R0003-0007005.pdf PDF
36C10F19R0003-0007001.pdf PDF
36C10F19R0003-0006003.pdf PDF
36C10F19R0003-0006001.pdf PDF
36C10F19R0003-0006002.pdf PDF
36C10F19R0003-0006000.docx DOCX document
36C10F19R0003-0005000.docx DOCX document
36C10F19R0003-0005001.pdf PDF
36C10F19R0003-0005003.pdf PDF
36C10F19R0003-0005004.pdf PDF
36C10F19R0003-0005002.pdf PDF
36C10F19R0003-0004000.docx DOCX document
36C10F19R0003-0003000.docx DOCX document
36C10F19R0003-0002002.pdf PDF
36C10F19R0003-0002000.docx DOCX document
36C10F19R0003-0001001.pdf PDF
36C10F19R0003-0001000.docx DOCX document
36C10F19R0003-014.pdf PDF
36C10F19R0003-019.pdf PDF
36C10F19R0003-016.pdf PDF
36C10F19R0003-020.pdf PDF
36C10F19R0003-022.pdf PDF
36C10F19R0003-024.pdf PDF
36C10F19R0003-023.pdf PDF
36C10F19R0003-018.pdf PDF
36C10F19R0003-013.docx DOCX document
36C10F19R0003-017.pdf PDF
36C10F19R0003-021.pdf PDF
36C10F19R0003-015.pdf PDF
36C10F19R0003-000.docx DOCX document
36C10F19R0003.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA - Pittsburgh ROB Connecting Bridge

RFI # RFI Comment Date

Received

Response Date

Returned

Responder

1 There is (1) existing steam line and (2) existing vent lines that run under the existing elevated walk way in B30 - they are not shown to be relocated on the drawings. Please confirm what is to be done with existing lines.

4/8/2019 A field survey will be completed to fully understand location and routing of existing steam and vent lines. Demo and new construction drawings will be modified as necessary.

4/19/2019 Berteotti

On MDO-100, we are to demo chilled water, steam and condensate down through the floor. On MHO-100, we are rerouting those same lines down through the floor in a different location. It is unclear if we are core drilling 4 new holes, and what is exactly underneath, as it will be pretty messy, and work will need to be performed below to reconnect the lines from the demo point. The demo drawing only shows one demo point, when actually it should have another demo/tie in point on the floor beneath. Also, please advise if this portion of the work has to take place after hours, what exactly do these lines serve and how long can they be shut down?

4/8/2019 Disconnect pipes at penetration to roof and on floor below. Field verify/coordinate new penetration location in floor slab and pipe routing in ceiling space below. Core drill new penetrations after coordinating with existing structure and objects below. Disconnect piping on floor below, install new piping and reconnect to existing piping penetrating through roof. Coordinate work hours and equipment disruption with VA.

4/19/2019 Berteotti

On the door schedule, doors A-01, A-02, A-09 are all to receive operators. However, doors A-02 and A-09 have door types that are not listed on the door schedule. Also, with the hardware schedule, doors A-02 and A-09 are listed to have one operator.

Is that a single operator on a double door? Or a dual operator on a double door? The size of these doors on the door schedule tell us they are double doors, but we are not sure which type of operator you would like. With Door A-01, the door schedule shows a single door panel, but the hardware schedule is calling for 2 operators.

4/8/2019 Door A-02 is door type A. Door A-09 is door type A. Provide one operator that works both doors (Doors A-02 and A-09).

Door A-01 is a single leaf and only 1 operator is required.

4/25/2019 Beswick

4 Specs are calling for the coping to be .0125 Aluminum, which is

1/8". Please verify what thickness and finish for all roofing related metal flashing. (coping, scupper, expansion joint cover, etc.).

4/8/2019 See specifications 07 71 00 Roof Specialties and 07 60 00 Flashing and Sheet Metal for thicknesses and finishes.

4/25/2019 Beswick

5 Will the existing equipment, and case work in the lad area be removed from second floor of building one buy VA or will be the responsibly of the contractor.

4/8/2019 Dwg AD1-101 – the demolition key notes identify the specific demo requirements.

4/25/2019 Beswick

6 Any lighting protection need for the new bridge. 4/8/2019 Lightning Protection is not required for this project. 4/25/2019 Beswick

7 Will dumpster be remove from alley before work starts. 4/8/2019 See attached sketch for VAMC limit of work drawing for location of dumpsters. Locations to be coordinated with VAMC.

4/25/2019 Beswick

8 Will the VA give us a Dumpster location and lay down area. 4/8/2019 See attached sketch for VAMC limit of work drawing for location of dumpsters. Locations to be coordinated with VAMC.

4/25/2019 Beswick

9 What is below the lab area in building one and how do we get access to this area and what kind of ceiling is in this area.

4/8/2019 Laboratories and offices are on the floor below; VAMC will provide access to these areas.

4/25/2019 Beswick vacoezellj Text Box 36C10F19R0003 0002, Response to RFIs posted 4-26-2019