This document is the NAVFAC USACE Past Performance Questionnaire, which is Attachment B to the solicitation for the Chief Joseph Dam Units 1-16 Excitation System Replacement project (Solicitation Number W912DW24R0001).

The Past Performance Questionnaire is a form that will be used by offerors to collect past performance information from their customers for projects that are relevant to the requirements of the Chief Joseph Dam Excitation System Replacement solicitation. The questionnaire covers topics such as quality of product/service, schedule, management, business relations, and small business subcontracting. Offerors must submit completed questionnaires from their references as part of their proposal package.

View the file

Other files

File Type Posted
48 70 01.00 26 R0007.pdf PDF
Amendment 0007 Released (W912DW24R0001 (CJD Exciters)).pdf PDF
Amendment 0006_Released_W912DW24R0001 (CJD Exciters).pdf PDF
01 45 00.00 10 R0005.pdf PDF
Amendment 0005_Released_W912DW24R0001 (CJD Exciters).pdf PDF
01 35 26 R0005.pdf PDF
01 22 00 R0004.pdf PDF
48 19 26.00 26 R0004.pdf PDF
00 41 00 R0004.pdf PDF
W912DW24R0001 Amendment 0004.pdf PDF
01 33 00-A R0004.pdf PDF
Amendment 0003 (Released) W912DW24R0001 (CJD Exciters).pdf PDF
G-002 R0003.pdf PDF
E-801 R0003.pdf PDF
E-802 R0003.pdf PDF
26 05 00.00 26 R0003.pdf PDF
Chief Joseph Excitation System 100 pct Reference Drawings R0002.pdf PDF
26 05 13.00 26 R0002.pdf PDF
G-003 R0002.pdf PDF
00 72 00-A Drawing Index R0002.pdf PDF
26 05 19.00 26 R0002.pdf PDF
26 25 00.00 26 R0002.pdf PDF
Amendment 0002 W912DW24R0001 (CJD Exciters).pdf PDF
W912DW24R0001 Amendment 0001.pdf PDF
5_Attachment_D_Proposal_Data_Sheet.pdf PDF
8_Site_Visit_RSVP_Form_CJ_Exciters.pdf PDF
4_Attachment_C_Small_Business_Commitment_Document.pdf PDF
9_Chief_Joseph_Excitation_System_100Percent_Reference_Drawings.pdf PDF
2_Attachment_A_Past_Performance_Project_Relevancy_Form.pdf PDF
7_Statement_Of_Work_Chief_Joseph_Excitation_System_Units_1-16.pdf PDF
6_Attachment_E_Sample_Small_Business_Subcontracting_Plan.pdf PDF
10_W912DW24R0001_Project_Plan_CJD_Exciter__Units 1_16.pdf PDF
1_W912DW24R0001__RFP_Chief_Joseph_Dam_Exciters_1_16_Replacement.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT B – NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE

NAVFAC/USACE PAST PERFORMANCE QUESTIONNAIRE (Form PPQ-0)

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information

Firm Name: CAGE Code:

Address: Unique Entity ID:

Phone Number: Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: Prime Contractor Sub Contractor Joint Venture Other (Explain)

Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information

Contract Number:

Delivery/Task Order Number (if applicable):

Contract Type: Firm Fixed Price Cost Reimbursement Other (Please specify):

Contract Title:

Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable): Explain Differences:

d. Project Description:

Complexity of Work High Med Routine

How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information

Name: Title:

Phone Number: Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

NOTE: NAVFAC/USACE REQUESTS THAT THE CLIENT COMPLETES THIS

QUESTIONNAIRE AND SUBMITS DIRECTLY BACK TO THE OFFEROR. THE OFFEROR

WILL SUBMIT THE COMPLETED QUESTIONNAIRE TO USACE WITH THEIR PROPOSAL,

AND MAY DUPLICATE THIS QUESTIONNAIRE FOR FUTURE SUBMISSION ON USACE

SOLICITATIONS. CLIENTS ARE HIGHLY ENCOURAGED TO SUBMIT QUESTIONNAIRES

DIRECTLY TO THE OFFEROR. HOWEVER, QUESTIONNAIRES MAY BE SUBMITTED

DIRECTLY TO USACE. PLEASE CONTACT THE OFFEROR FOR USACE POC

INFORMATION. THE GOVERNMENT RESERVES THE RIGHT TO VERIFY ANY AND ALL

INFORMATION ON THIS FORM.

RATING DEFINITION NOTE

(E) Exceptional Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective.

An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.

(VG) Very Good Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified.

ADJECTIVAL RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE

Satisfactory Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified. Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.

(M) Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.

(U) Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.

(N) Not Applicable

No information or did not apply to your contract

Rating will be neither positive nor negative.

PLEASE CIRCLE THE ADJECTIVAL RATING WHICH BEST REFLECTS

YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE.

TO BE COMPLETED BY CLIENT

1. QUALITY:

a) Quality of technical data/report preparation efforts E VG S M U N

b) Ability to meet quality standards specified for technical performance

E VG S M U N

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance

E VG S M U N

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)

E VG S M U N

2. SCHEDULE/TIMELINESS OF PERFORMANCE:

a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract

E VG S M U N

3. CUSTOMER SATISFACTION:

a) To what extent were the end users satisfied with the project? E VG S M U N

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes;

responsiveness to administrative reports, businesslike and communication)

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?

E VG S M U N

d) Overall customer satisfaction E VG S M U N

4. MANAGEMENT/ PERSONNEL/LABOR

a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?

b) Ability to hire, apply, and retain a qualified workforce to this effort E VG S M U N

c) Government Property Control E VG S M U N

d) Knowledge/expertise demonstrated by contractor personnel E VG S M U N

e) Utilization of Small Business concerns E VG S M U N

f) Ability to simultaneously manage multiple projects with multiple disciplines

E VG S M U N

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution, and response to Government changes

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)

E VG S M U N

5. COST/FINANCIAL MANAGEMENT

a) Ability to meet the terms and conditions within the contractually agreed price(s)?

E VG S M U N

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.

Yes No

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.

Yes No

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.

Yes No

6. SAFETY/SECURITY

a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues?

(Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)

b) Contractor complied with all security requirements for the project and personnel security requirements. E VG S M U N

7. GENERAL

a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).

b) Compliance with contractual terms/provisions (explain if specific issues)

c) Would you hire or work with this firm again? (If no, please explain below)

Yes No

d) In summary, provide an overall rating for the work performed by this contractor.

Please provide responses to the questions above (if applicable) and/or additional remarks.

Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):