About this file

This solicitation is for the construction of a new parking garage at the Wilkes-Barre VA Medical Center campus. The project scope includes providing all labor, materials, tools, equipment, permits, testing and reports required to construct a new 435-space parking structure according to the drawings and specifications. The magnitude of the project is estimated between $10-20 million. The NAICS code is 236220 for commercial and institutional building construction. This procurement is set aside for verified service-disabled veteran-owned small businesses and uses a tiered evaluation process including large businesses. Pricing must be in whole US dollars. The contractor will be responsible for correct worker classification and wage compliance. The solicitation may be canceled before award if in the government's best interest.

View the file

Other files for this federal contract opportunity

Other files attached to Y1LZ--693-222 | Parking Structure Solicitation Amendment 2, newest first.
File Type Posted
014219 Reference Standards.docx DOCX document
014500 Quality Control.docx DOCX document
Parking Garage Arch Dwgs Add 1.pdf PDF
A6.2 Signage.pdf PDF
329000 Planting.pdf PDF
283100.pdf PDF
280528-33.pdf PDF
262416.pdf PDF
262200.pdf PDF
260573.pdf PDF
238216.pdf PDF
230593.pdf PDF
230541.pdf PDF
230510.pdf PDF
211200.pdf PDF
088000 General Glazing.pdf PDF
081100 Steel Doors and Frames.pdf PDF
079200 Joint Sealants Spec.pdf PDF
076200 Sheet Metal Flashing _ Trim.pdf PDF
072100 Building Insulation.pdf PDF
019100.docx DOCX document
017800 Final Cleaning_Single Prime.pdf PDF
015816.docx DOCX document
015719.doc DOC document
014219.docx DOCX document
014500.docx DOCX document
013323.docx DOCX document
013200 Construction Progress Documentation_Single Prime.pdf PDF
013150 Project Meetings_Single Prime.pdf PDF
S02 ParkStruct FP Dwg.pdf PDF
Pstruct Dwg 16-20.pdf PDF
Pstruct Dwg 11-15.pdf PDF
Pstruct Dwg 4.pdf PDF
S02 Dwg P1-P2.pdf PDF
S02 Dwg E3-E4.pdf PDF
S02 Geotechnical Report 11-30-15.pdf PDF
EXHIBIT C - Calculation of Self-Performed Work.docx DOCX document
36C24420R0075.docx DOCX document
012700 Cutting and Patching_Single Prime.pdf PDF
334000 Storm Sewer Utilities.pdf PDF
316326 Drilled Caissons.pdf PDF
312319 Dewatering.pdf PDF
280526.pdf PDF
264313.pdf PDF
280500.pdf PDF
260533.pdf PDF
260519.pdf PDF
260511.pdf PDF
230711.pdf PDF
220800.pdf PDF
Show all 50

Y1LZ--693-222 | Parking Structure Solicitation Amendment 2 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Parking Garage Project Number 693-222 Department of Veterans Affairs Wilkes-Barre, Pennsylvania

280800 - 1

SECTION 28 08 00 - COMMISSIONING OF ELECTRONIC SAFETY AND SECURITY

SYSTEMS

PART 1 - GENERAL

1.1 DESCRIPTION

A. The requirements of this Section apply to all sections of Division 28.

B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned are specified in Section 01 91 00

GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL

COMMISSIONING REQUIREMENTS. A Commissioning Agent (CxA) appointed by the

VA will manage the commissioning process.

1.2 RELATED WORK

A. Section 01 00 00 GENERAL REQUIREMENTS.

B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY

A. This Section includes requirements for commissioning the electronic safety and security systems, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS.

B. The commissioning activities have been developed to support the VA requirements to meet guidelines for Federal Leadership in Environmental, Energy, and Economic

Performance.

Wilkes-Barre, Pennsylvania

280800 - 2

D. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more specifics regarding processes and procedures as well as roles and responsibilities for all

Commissioning Team members.

1.4 DEFINITIONS

A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.

1.5 COMMISSIONED SYSTEMS

A. Commissioning of a system or systems specified in this Division is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel, is required in cooperation with the VA and the Commissioning Agent.

B. The following Electronic Safety and Security systems will be commissioned:

1. Fire Detection and Alarm (Master panel and software, addressable units – i.e. pull stations, flow detectors, hear detectors, etc., controls and alarm functions, horns/bells/door releases and other output devices, and fire command center functions – stairwell communications, stairwell pressurization fan start, mechanical systems shutdowns).

1.6 SUBMITTALS

A. The commissioning process requires review of selected Submittals. The

Commissioning Agent will provide a list of submittals that will be reviewed by the

Commissioning Agent. This list will be reviewed and approved by the Resident Engineer prior to forwarding to the Contractor. Refer to Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.

B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.

Wilkes-Barre, Pennsylvania

280800 - 3

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 PRE-FUNCTIONAL CHECKLISTS

A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional

Performance Testing. The Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the

Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the

Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING

REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment

Startup Reports, and other commissioning documents.

3.2 CONTRACTORS TESTS

A. Contractor tests as required by other sections of Division 28 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL REQUIREMENTS. The

Commissioning Agent will witness selected Contractor tests. Contractor tests shall be completed prior to scheduling Systems Functional Performance Testing.

3.3 SYSTEMS FUNCTIONAL PERFORMANCE TESTING:

A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test

Wilkes-Barre, Pennsylvania

280800 - 4 system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems

Functional Performance Test procedures for review and approval by the Resident

Engineer. The Contractor shall review and comment on the tests prior to approval. The

Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional details.

- - - END OF SECTION - - -