This is a Scope of Work specification document for the Earth Moving section (312000) of the Operations Center Expansion project for the City of Lancaster Department of Public Works, referenced as RGS 2025992-044. The specification outlines comprehensive earthwork requirements including excavation and filling for rough grading, subgrade preparation for slabs-on-grade, walks, pavements, turf, and plants, excavation and backfilling for buildings and structures, and installation of drainage courses, subbase courses, base courses for asphalt paving, and subsurface drainage backfill. The work incorporates requirements from a Geotechnical Engineering Study dated May 20, 2026, prepared by Hilles Carnes Engineering Associates (Project No. HAR260051A), which establishes subgrade preparation, earthwork, and compaction standards. Related work sections include Site Clearing (311000), Soil Preparation (329113), Turf and Grasses (329200), and Plants (329300). The specification prohibits blasting on the project and mandates notification of "One Call" before commencing earth-moving operations. A pre-installation conference must be conducted at minimum two weeks prior to work commencement with the Prime Excavation Contractor, sub-contractors, Owner, and Design Professional to review subgrade preparation, topsoil placement, coordination, and quality standards.
Soil materials must meet specific ASTM classifications, with satisfactory structural fill materials classified as ASTM D 2487 groups GC, GW, GP, GM, SP, SC, and SM, free of rock or gravel larger than 6 inches. Unsatisfactory materials identified in the Geotechnical Report—including uncontrolled fill, soft or loose soils, expansive soils, and soils with high organic content—must be remediated or replaced. Classified excavation is compensated through unit prices for Bulk Rock, Trench Rock, and Unsuitable/Unsatisfactory Soils, with Earth excavation included in the lump-sum contract price. Backfill and fill materials must be placed in layers with compaction requirements ranging from 85 to 95 percent of maximum dry unit weight per ASTM D 698, depending on application. The Owner will employ and pay for a qualified independent geotechnical testing and inspection laboratory to perform soil testing and inspection during earthwork operations. Subgrade tolerances are Plus or minus 1 inch for turf, unpaved areas, and walks, and Plus or minus 1/2 inch for pavements and inside building lines. Surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, must be removed and legally disposed of off-site at the contractor's expense.
View the file
Other files
Show 40 more
Latest 50 of 63 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Operations Center Expansion RGS 2025992-044
City of Lancaster - Department of Public Works
EARTH MOVING 312000
SECTION 312000 - EARTH MOVING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. Geotechnical Report: A geotechnical report titled: “Geotechnical Engineering Study - Operations
Center Expansion”, dated May 20, 2026, prepared by Hilles Carnes Engineering Associates, Project No. HAR260051A.
1. The report is incorporated into the Contract Documents for the purpose of establishing subgrade preparation, earthwork, and compaction requirements, including recommendations for removal and replacement of unsuitable soils. Subsurface descriptions, boring logs, and groundwater observations are provided for information only and are not a warranty of conditions between boring locations.
2. In the event of a conflict between the Geotechnical Report and the Drawings or this Section, the more stringent requirement governs.
1.2 SUMMARY
A. Section Includes:
1. Excavating and filling for rough grading the Site.
2. Preparing subgrades for slabs-on-grade, walks, pavements, turf and grasses, and plants.
3. Excavating and backfilling for buildings and structures.
4. Drainage course for concrete slabs-on-grade.
5. Subbase course for concrete walks, and pavements.
6. Subbase course and base course for asphalt paving.
7. Subsurface drainage backfill for walls and trenches.
8. Excavating and backfilling trenches for utilities and pits for buried utility structures.
B. Related Requirements:
1. Section 311000 "Site Clearing" for site stripping, grubbing, stripping and stockpiling topsoil, and removal of above- and below-grade improvements and utilities.
2. Section 329113 “Soil Preparation” for mixing and placement of topsoil.
3. Section 329200 "Turf and Grasses" for finish grading in turf and grass areas, including preparing and placing planting soil for turf areas.
4. Section 329300 "Plants" for finish grading in planting areas and tree and shrub pit excavation and planting.
1.3 DEFINITIONS
A. Excavation consists of removal of material to reach plan subgrade elevations and the subsequent relocation of materials removed.
B. Backfill: Soil material or controlled low-strength material used to fill an excavation.
1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.
2. Final Backfill: Backfill placed over initial backfill to fill a trench.
C. Fill: Satisfactory soil materials used to raise existing grades.
D. Structural Fill: Fill placed within the footprints of structures or pavement and extending six feet beyond said footprint to replace unsuitable soils and/or to raise existing grades to the plan subgrade elevation.
E. Subgrade: The undisturbed earth or the compacted soil layer immediately below the boundaries of pavement sections, floor slab sections, foundations, drainage fill, or topsoil materials.
F. Off-Site Borrow: Soil material obtained off-site when sufficient suitable soil material is not available from excavations.
G. Subbase Course: The aggregate layer placed between the subgrade and base course of a paving system or the layer placed between the subgrade and surface course of a bituminous or concrete pavement, walk or slab.
H. Base Course: The layer placed between the subbase and surface pavement course in a paving system.
I. Bedding Course: Aggregate course placed between the subgrade in a trench and pipe or other utility.
J. Drainage Fill: Aggregate course of washed granular material (AASHTO No. 57) supporting concrete slabs-on-grade placed to cut off upward capillary flow of pore water.
K. Structures: Buildings, footings, retaining walls, slabs, bridges, curbs, pavements, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below ground surface.
L. Utilities include on-site underground pipes, conduits, ducts, and cables, as well as underground services within building lines.
M. Pavements: Man-made or natural surfacing materials, including but not limited to, bituminous roadways, driveway, access drive or paths or concrete paving, slabs, or sidewalks.
N. Bulk Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders that exceed 3/4 cu. yd. for footing, pit and bulk excavation that cannot be removed by excavating equipment equivalent to the following in size and performance ratings, without systematic drilling, ram hammering, or ripping,:
O. Trench Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders that exceed 3/4 cu. yd. for trench excavation that cannot be removed by excavating equipment equivalent to the following in size and performance ratings, without systematic drilling, ram hammering, or ripping,:
P. Equipment for Footing, Trench, Pit and Bulk Excavation: Late-model, track- mounted hydraulic excavator (trackhoe); equipped with a 42-inch-maximum- width, short-tip-radius rock bucket;
rated at not less than 138-hp flywheel power with bucket-curling force of not less than 28,700 lbf and stick-crowd force of not less than 18,400 lbf with extra-long reach boom.
Q. Geotechnical Engineer: Licensed professional engineer retained by Owner to provide geotechnical engineering services, including observation of subgrade conditions and approval of earthwork operations. Geotechnical Engineer is Hilles Carnes Engineering Associates.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of the following manufactured products required:
1. Geotextiles.
2. Controlled low-strength material, including design mixture.
3. Warning tapes.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For qualified testing agency.
B. Material Test Reports: For each on-site and borrow soil material proposed for fill and backfill as follows:
1. Classification according to ASTM D 2487.
2. Laboratory compaction curve according to ASTM D 698
C. Geotechnical Testing Agency Qualifications: Qualified according to ASTM E 329 and
ASTM D 3740 for testing indicated.
1.6 QUALITY ASSURANCE
A. Codes and Standards: Perform excavation work in compliance with applicable requirements of authorities having jurisdiction.
B. Testing and Inspection Service: Owner will employ and pay for a qualified independent geotechnical testing and inspection laboratory to perform soil testing and inspection service during earthwork operations.
C. Pre-Installation Conference: Conduct conference at Project site to comply with requirements of
Division 1 Section "Project Meetings."
1. Before commencing earthwork, meet with representatives of the governing authorities, Conservation District, Owner, Design Consultants, independent testing agency, utilities and other concerned entities. Review earthwork procedures and responsibilities including testing and inspection procedures and requirements. Notify participants at least 3 working days prior to convening conference. Record discussions and agreements and furnish a copy to each participant.
D. Subgrade Preparation and Topsoil Placement Pre-Installation Conference: Conduct a meeting between the Prime Excavation Contractor, Sub-Contractors, the Owner and the Design
Professional to review the subgrade preparation and topsoil placement, coordination with other work, special project conditions and quality standards. Notify all parties and schedule the meeting a minimum of two (2) weeks prior to the anticipated start of this work.
1.7 FIELD CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities having jurisdiction.
B. Utility Locator Service: Notify “One Call" for area where Project is located before beginning earth moving operations.
C. Blasting: Blasting will not be permitted on this project.
D. Do not commence earth moving operations until temporary erosion- and sedimentation-control measures, depicted on plans, are in place.
E. Do not commence earth-moving operations until plant-protection measures, depicted on plans, are in place.
F. The following practices are prohibited within protection zones:
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Foot traffic.
4. Erection of sheds or structures.
5. Impoundment of water.
6. Excavation or other digging unless otherwise indicated.
7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.
G. Do not direct vehicle or equipment exhaust towards protection zones.
H. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones.
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.
B. Satisfactory Structural Fill Materials: On-site overburden and borrow materials meeting the requirements of ASTM D 2487 soil classification groups GC, GW, GP, GM, SP, SC and SM;
free of rock or gravel larger than 6 inches in any dimension, debris, waste, frozen materials, vegetation and other deleterious matter. ASTM D 2487 soil classification group ML, and CL are satisfactory if properly moisture conditioned in the presence of the on-site geotechnical engineer.
C. Unsatisfactory Soil Materials: All materials not meeting the requirements outlined above and those identified as unsuitable in the Geotechnical Report including uncontrolled fill, soft or loose soils, expansive soils and soils with high organic content.
D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; with at least 90 percent passing a
1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
E. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 294/D 2940M 0; with at least 95 percent passing a 1-1/2-inch sieve and not more than 8 percent passing a No. 200 sieve.
F. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; with at least 90 percent passing a
1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
G. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; except with 100 percent passing a
1-inch sieve and not more than 8 percent passing a No. 200 sieve.
H. Drainage Course: Narrowly graded mixture of washed crushed stone, or crushed or uncrushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and zero to 5 percent passing a No. 8 sieve.
I. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand; ASTM D 448; coarse-aggregate grading Size 67; with 100 percent passing a 1-inch sieve and zero to 5 percent passing a No. 4 sieve.
J. Sand: ASTM C 33/C 33M; fine aggregate.
K. Impervious Fill: Clayey gravel and sand mixture capable of compacting to a dense state.
2.2 GEOTEXTILES
A. Subsurface Drainage Geotextile: As indicated on plans.
B. Separation Geotextile: As indicated on plans.
2.3 ACCESSORIES
A. Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility; colored as follows:
1. Red: Electric.
2. Yellow: Gas, oil, steam, and dangerous materials.
3. Orange: Telephone and other communications.
4. Blue: Water systems.
5. Green: Sewer systems.
B. Detectable Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, a minimum of 6 inches wide and
4 mils thick, continuously inscribed with a description of the utility, with metallic core encased in a protective jacket for corrosion protection, detectable by metal detector when tape is buried up to 30 inches deep; colored as follows:
1. Red: Electric.
2. Yellow: Gas, oil, steam, and dangerous materials.
3. Orange: Telephone and other communications.
4. Blue: Water systems.
5. Green: Sewer systems.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations.
B. Protect and maintain erosion and sedimentation controls during earth-moving operations.
C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.
3.2 DEWATERING
A. Provide dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades.
B. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.
C. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.
1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.
D. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water and sediment in a manner that avoids inconvenience to others.
3.3 EXCAVATION, GENERAL
A. Classified Excavation: Excavate to subgrade elevations. Material to be excavated will be classified as earth, bulk rock, trench rock, and Unsuitable / Unsatisfactory Soils. Do not excavate
Bulk Rock, Trench Rock or Unsuitable / Unsatisfactory Soils until it has been classified by
Geotechnical Engineer and cross sectioned by Surveyor. Material removed before classification and cross-sectioning is pad as Earth. The Contract Sum will be adjusted for Bulk Rock, Trench
Rock, and Unsatisfactory / Unsuitable Soils excavation according to unit prices included by the
Contractor on the Bid Form. Changes in the Contract Time may be authorized for rock excavation.
1. Earth excavation includes excavating pavements and obstructions visible on surface;
underground structures, utilities, and other items indicated to be removed; and soil, boulders, and other materials not classified as Bulk Rock, Trench Rock, Unsatisfactory /
Unsuitable Soils or unauthorized excavation.
a. Intermittent drilling; ram hammering; or ripping of material not classified as rock excavation is earth excavation.
b. Remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at depths up to 4 feet below existing grade at the Storage
Building and Salt Storage Shed structures and depths up to 2 feet below finished subgrade at pavements.
c. Earth excavation is included in the lump-sum contract price.
2. Bulk Rock excavation includes removal and disposal of rock. Pay by in-place volume measured by pre- and post-excavation by contractor’s surveyor subject to owner verification. Remove rock to lines and subgrade elevations indicated to permit installation of permanent construction without exceeding the following dimensions:
a. 24 inches outside of concrete forms other than at footings.
b. 12 inches outside of concrete forms at footings.
c. 6 inches outside of minimum required dimensions of concrete cast against grade.
d. Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments.
e. 6 inches beneath bottom of concrete slabs-on-grade.
3. Trench Rock excavation includes removal and disposal of rock. Pay by maximum trench width and depth of rock to 6” below pipe. Remove rock to lines and subgrade elevations indicated to permit installation of permanent construction without exceeding the following dimensions:
a. 6 inches beneath pipe in trenches and the greater of 24 inches wider than pipe or 42 inches wide.
4. Unsatisfactory / Unsuitable Soils: includes:
a. remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at depths beyond 4 feet below existing grade at the Storage Building and Salt Storage Shed.
b. remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at depths beyond 2 feet below finished subgrade at pavements.
c. any remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at the Material Storage Bay and/or Covered Storage
Structure
3.4 EXCAVATION FOR STRUCTURES
A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections.
1. Excavations for Footings and Foundations: Do not disturb bottom of excavation. Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.
2. Pile Foundations: Stop excavations 6 to 12 inches above bottom of pile cap before piles are placed. After piles have been driven, remove loose and displaced material. Excavate to final grade, leaving solid base to receive concrete pile caps.
3. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Utility
Structures: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 1 inch. Do not disturb bottom of excavations intended as bearing surfaces.
B. Excavations at Edges of Tree- and Plant-Protection Zones:
1. Excavate by hand or with an air spade to indicated lines, cross sections, elevations, and subgrades. If excavating by hand, use narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots. Do not use mechanical equipment that rips, tears, or pulls roots.
2. Cut and protect roots according to requirements in Section 015639 "Temporary Tree and
Plant Protection."
3.5 EXCAVATION FOR WALKS AND PAVEMENTS
A. Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades.
3.6 EXCAVATION FOR UTILITY TRENCHES
A. Excavate trenches to indicated gradients, lines, depths, and elevations.
1. Beyond building perimeter, excavate trenches to allow installation of top of pipe below frost line.
B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches higher than top of pipe or conduit unless otherwise indicated.
1. Clearance: As indicated on plans.
C. Trench Bottoms: Excavate trenches 6 inches deeper than bottom of pipe and conduit elevations to allow for bedding course. Hand-excavate deeper for bells of pipe.
1. Excavate trenches 6 inches deeper than elevation required in rock or other unyielding bearing material to allow for bedding course.
D. Trenches in Tree- and Plant-Protection Zones:
1. Hand-excavate to indicated lines, cross sections, elevations, and subgrades. Use narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots.
Do not use mechanical equipment that rips, tears, or pulls roots.
2. Do not cut main lateral roots or taproots; cut only smaller roots that interfere with installation of utilities.
3. Cut and protect roots according to requirements in Section 015639 "Temporary Tree and
Plant Protection."
3.7 SUBGRADE INSPECTION
A. Notify Geotechnical Engineer when excavations have reached required subgrade.
B. If Geotechnical Engineer determines that unsatisfactory soil is present, remediate and/or remove and replace such soils as indicated on the Drawings and as directed by the Geotechnical Engineer.
1. Removal and replacement of unsatisfactory soil directed by the Geotechnical Engineer beyond the depths included in Earth Excavation, at any location, will be measured and paid as Unsuitable Soils under the unit price provided by the Contractor on the Bid Form
Unsatisfactory soil within the depths included in Earth Excavation is included in the lump sum.
C. Proof-roll subgrade in accordance with the direction of the project Geotechnical Engineer.
Contractor is responsible for understanding compaction technique limitations prior to initiating compaction or excavation efforts.
D. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Architect, without additional compensation.
3.8 UNAUTHORIZED EXCAVATION
A. Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without direction by the Architect or Geotechnical Engineer. Unauthorized excavation, as well as remedial work directed by the Architect, shall be at the Contractor’s expense.
B. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean concrete fill, with 28-day compressive strength of 2500 psi, may be used when approved by
Geotechnical Engineer.
1. Fill unauthorized excavations under other construction, pipe, or conduit as directed by
Geotechnical Engineer
3.9 STORAGE OF SOIL MATERIALS
A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.
3.10 BACKFILL
A. Place and compact backfill in excavations promptly, but not before completing the following:
1. Construction below finish grade including, where applicable, subdrainage, dampproofing, waterproofing, and perimeter insulation.
2. Surveying locations of underground utilities for Record Documents.
3. Testing and inspecting underground utilities.
4. Removing concrete formwork.
5. Removing trash and debris.
6. Removing temporary shoring, bracing, and sheeting.
7. Installing permanent or temporary horizontal bracing on horizontally supported walls.
B. Place backfill on subgrades free of mud, frost, snow, or ice.
3.11 UTILITY TRENCH BACKFILL
A. Place backfill on subgrades free of mud, frost, snow, or ice.
B. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits.
C. Trenches under Roadways: Provide 4-inch thick, concrete-base slab support for piping or conduit less than 30 inches below surface of roadways. After installing and testing, completely encase piping or conduit in a minimum of 4 inches of concrete before backfilling or placing roadway subbase course. Concrete is specified in Section 033010 "Cast-in-Place Concrete."
D. Backfill voids with satisfactory soil while removing shoring and bracing.
E. Initial Backfill:
1. Soil Backfill: Place and compact initial backfill of subbase material, free of particles larger than 1 inch in any dimension, to a height of 12 inches over the pipe or conduit.
a. Carefully compact initial backfill under pipe haunches and compact evenly up on both sides and along the full length of piping or conduit to avoid damage or displacement of piping or conduit. Coordinate backfilling with utilities testing.
2. Controlled Low-Strength Material: Place initial backfill of controlled low-strength material to a height of 12 inches over the pipe or conduit. Coordinate backfilling with utilities testing.
F. Final Backfill:
1. Soil Backfill: Place and compact final backfill of satisfactory soil to final subgrade elevation.
2. Controlled Low-Strength Material: Place final backfill of controlled low-strength material to final subgrade elevation.
G. Warning Tape: Install warning tape directly above utilities, 12 inches below finished grade, except 6 inches below subgrade under pavements and slabs.
3.12 SOIL FILL
A. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material.
B. Place and compact fill material in layers to required elevations as follows:
1. Under grass and planted areas, use satisfactory soil material.
2. Under walks and pavements, use satisfactory soil material.
3. Under steps and ramps, use engineered fill.
4. Under building slabs, use engineered fill.
5. Under footings and foundations, use engineered fill.
C. Place soil fill on subgrades free of mud, frost, snow, or ice.
3.13 SOIL MOISTURE CONTROL
A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 2 percent of optimum moisture content.
1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain frost or ice.
2. Remove and replace, or scarify and air dry, otherwise satisfactory soil material that exceeds optimum moisture content by 2 percent and is too wet to compact to specified dry unit weight.
3.14 COMPACTION OF SOIL BACKFILLS AND FILLS
A. Place backfill and fill soil materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment and not more than 4 inches in loose depth for material compacted by hand-operated tampers. Compaction to be in accordance with the recommendations of the Project Geotechnical Engineer.
B. Place backfill and fill soil materials evenly on all sides of structures to required elevations and uniformly along the full length of each structure.
C. Compact soil materials to not less than those noted in the Geotechnical Report or per Project
Geotechnical Engineer.
3.15 GRADING
A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.
1. Provide a smooth transition between adjacent existing grades and new grades.
2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances.
B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent ponding.
Finish subgrades to elevations required to achieve indicated finish elevations, within the following subgrade tolerances:
1. Turf or Unpaved Areas: Plus or minus 1 inch.
2. Walks: Plus or minus 1 inch.
3. Pavements: Plus or minus 1/2 inch.
C. Grading inside Building Lines: Finish subgrade to a tolerance of 1/2 inch when tested with a 10-foot straightedge.
3.16 SUBSURFACE DRAINAGE
A. Subsurface Drain: Place subsurface drainage geotextile around perimeter of subdrainage trench.
Place a 6-inch course of filter material on subsurface drainage geotextile to support subdrainage pipe. Encase subdrainage pipe in a minimum of 12 inches of filter material, placed in compacted layers 6 inches thick, and wrap in subsurface drainage geotextile, overlapping sides and ends at least 6 inches.
1. Compact each filter material layer to 85 percent of maximum dry unit weight according to
ASTM D 698 with a minimum of two passes of a plate-type vibratory compactor.
B. Drainage Backfill: Place and compact filter material over subsurface drain, in width indicated, to within 12 inches of final subgrade, in compacted layers 6 inches thick. Overlay drainage backfill with one layer of subsurface drainage geotextile, overlapping sides and ends at least 6 inches.
1. Compact each filter material layer to 95 percent of maximum dry unit weight according to
ASTM D 698 with a minimum of two passes of a plate-type vibratory compactor.
2. Place and compact impervious fill over drainage backfill in 6-inch-thick compacted layers to final subgrade.
3.17 SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS
A. Place subbase course and base course or structural soil, as indicated on plans, on subgrades free of mud, frost, snow, or ice.
B. On prepared subgrade, place subbase course and base course under pavements and walks as follows:
1. Place base course material over subbase course under hot-mix asphalt pavement.
2. Shape subbase course and base course to required crown elevations and cross-slope grades.
3. Place subbase course and base course 6 inches or less in compacted thickness in a single layer.
4. Place subbase course and base course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick.
5. Compact subbase course and base course at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 95 percent of maximum dry unit weight according to ASTM D 698.
3.18 FIELD QUALITY CONTROL
A. Special Inspections: Owner will engage a qualified special inspector to perform the following special inspections:
1. Determine prior to placement of fill that site has been prepared in compliance with requirements.
2. Determine that fill material classification and maximum lift thickness comply with requirements.
3. Determine, during placement and compaction that in-place density of compacted fill complies with requirements.
B. Testing Agency: Owner will engage a qualified geotechnical engineering testing agency to perform tests and inspections.
C. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earth moving only after test results for previously completed work comply with requirements.
D. Footing Subgrade: At footing subgrades, at least one test of each soil stratum will be performed to verify design bearing capacities. Subsequent verification and approval of other footing subgrades may be based on a visual comparison of subgrade with tested subgrade when approved by Architect.
E. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2937, and ASTM D 6938, as applicable. Tests will be performed at the following locations and frequencies:
1. Trench Backfill: At each compacted initial and final backfill layer, at least one test for every 150 feet or less of trench length but no fewer than two tests.
F. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required; recompact and retest until specified compaction is obtained.
3.19 PROTECTION
A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.
B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.
1. Scarify or remove and replace soil material to depth as directed by Landscape Architect;
reshape and recompact.
C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.
1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.
3.20 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Owner's property.
END OF SECTION - 312000
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| B. Geotechnical Report: A geotechnical report titled: “Geotechnical Engineering Study - Operations Center Expansion”, dated May 20, 2026, prepared by Hilles Carnes Engineering Associates, Project No. HAR260051A. |
| 1. The report is incorporated into the Contract Documents for the purpose of establishing subgrade preparation, earthwork, and compaction requirements, including recommendations for removal and replacement of unsuitable soils. Subsurface descriptions,... |
| 2. In the event of a conflict between the Geotechnical Report and the Drawings or this Section, the more stringent requirement governs. |
| 1.2 SUMMARY |
| A. Section Includes: |
| 1. Excavating and filling for rough grading the Site. |
| 2. Preparing subgrades for slabs-on-grade, walks, pavements, turf and grasses, and plants. |
| 3. Excavating and backfilling for buildings and structures. |
| 4. Drainage course for concrete slabs-on-grade. |
| 5. Subbase course for concrete walks, and pavements. |
| 6. Subbase course and base course for asphalt paving. |
| 7. Subsurface drainage backfill for walls and trenches. |
| 8. Excavating and backfilling trenches for utilities and pits for buried utility structures. |
| B. Related Requirements: |
| 1. Section 311000 "Site Clearing" for site stripping, grubbing, stripping and stockpiling topsoil, and removal of above- and below-grade improvements and utilities. |
| 2. Section 329113 “Soil Preparation” for mixing and placement of topsoil. |
| 3. Section 329200 "Turf and Grasses" for finish grading in turf and grass areas, including preparing and placing planting soil for turf areas. |
| 4. Section 329300 "Plants" for finish grading in planting areas and tree and shrub pit excavation and planting. |
| 1.3 DEFINITIONS |
| A. Excavation consists of removal of material to reach plan subgrade elevations and the subsequent relocation of materials removed. |
| B. Backfill: Soil material or controlled low-strength material used to fill an excavation. |
| 1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe. |
| 2. Final Backfill: Backfill placed over initial backfill to fill a trench. |
| C. Fill: Satisfactory soil materials used to raise existing grades. |
| D. Structural Fill: Fill placed within the footprints of structures or pavement and extending six feet beyond said footprint to replace unsuitable soils and/or to raise existing grades to the plan subgrade elevation. |
| E. Subgrade: The undisturbed earth or the compacted soil layer immediately below the boundaries of pavement sections, floor slab sections, foundations, drainage fill, or topsoil materials. |
| F. Off-Site Borrow: Soil material obtained off-site when sufficient suitable soil material is not available from excavations. |
| G. Subbase Course: The aggregate layer placed between the subgrade and base course of a paving system or the layer placed between the subgrade and surface course of a bituminous or concrete pavement, walk or slab. |
| H. Base Course: The layer placed between the subbase and surface pavement course in a paving system. |
| I. Bedding Course: Aggregate course placed between the subgrade in a trench and pipe or other utility. |
| J. Drainage Fill: Aggregate course of washed granular material (AASHTO No. 57) supporting concrete slabs-on-grade placed to cut off upward capillary flow of pore water. |
| K. Structures: Buildings, footings, retaining walls, slabs, bridges, curbs, pavements, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below ground surface. |
| L. Utilities include on-site underground pipes, conduits, ducts, and cables, as well as underground services within building lines. |
| M. Pavements: Man-made or natural surfacing materials, including but not limited to, bituminous roadways, driveway, access drive or paths or concrete paving, slabs, or sidewalks. |
| N. Bulk Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders that exceed 3/4 cu. yd. for footing, pit and bulk excavation that cannot be removed by excavating equipment equivalent to the following in size and p... |
| O. Trench Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders that exceed 3/4 cu. yd. for trench excavation that cannot be removed by excavating equipment equivalent to the following in size and performance ra... |
| P. Equipment for Footing, Trench, Pit and Bulk Excavation: Late-model, track- mounted hydraulic excavator (trackhoe); equipped with a 42-inch-maximum- width, short-tip-radius rock bucket; rated at not less than 138-hp flywheel power with bucket-curlin... |
| Q. Geotechnical Engineer: Licensed professional engineer retained by Owner to provide geotechnical engineering services, including observation of subgrade conditions and approval of earthwork operations. Geotechnical Engineer is Hilles Carnes Engineer... |
| 1.4 ACTION SUBMITTALS |
| A. Product Data: For each type of the following manufactured products required: |
| 1. Geotextiles. |
| 2. Controlled low-strength material, including design mixture. |
| 3. Warning tapes. |
| 1.5 INFORMATIONAL SUBMITTALS |
| A. Qualification Data: For qualified testing agency. |
| B. Material Test Reports: For each on-site and borrow soil material proposed for fill and backfill as follows: |
| 1. Classification according to ASTM D 2487. |
| 2. Laboratory compaction curve according to ASTM D 698 |
C. Geotechnical Testing Agency Qualifications: Qualified according to ASTM E 329 and ASTM D 3740 for testing indicated.
| 1.6 QUALITY ASSURANCE |
| A. Codes and Standards: Perform excavation work in compliance with applicable requirements of authorities having jurisdiction. |
| B. Testing and Inspection Service: Owner will employ and pay for a qualified independent geotechnical testing and inspection laboratory to perform soil testing and inspection service during earthwork operations. |
| C. Pre-Installation Conference: Conduct conference at Project site to comply with requirements of Division 1 Section "Project Meetings." |
| 1. Before commencing earthwork, meet with representatives of the governing authorities, Conservation District, Owner, Design Consultants, independent testing agency, utilities and other concerned entities. Review earthwork procedures and responsibilit... |
D. Subgrade Preparation and Topsoil Placement Pre-Installation Conference: Conduct a meeting between the Prime Excavation Contractor, Sub-Contractors, the Owner and the Design Professional to review the subgrade preparation and topsoil placement, coor...
| 1.7 FIELD CONDITIONS |
| A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations. |
| 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. |
| 2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities having jurisdiction. |
| B. Utility Locator Service: Notify “One Call" for area where Project is located before beginning earth moving operations. |
| C. Blasting: Blasting will not be permitted on this project. |
| D. Do not commence earth moving operations until temporary erosion- and sedimentation-control measures, depicted on plans, are in place. |
| E. Do not commence earth-moving operations until plant-protection measures, depicted on plans, are in place. |
| F. The following practices are prohibited within protection zones: |
| 1. Storage of construction materials, debris, or excavated material. |
| 2. Parking vehicles or equipment. |
| 3. Foot traffic. |
| 4. Erection of sheds or structures. |
| 5. Impoundment of water. |
| 6. Excavation or other digging unless otherwise indicated. |
| 7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated. |
| G. Do not direct vehicle or equipment exhaust towards protection zones. |
| H. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones. |
| PART 2 - PRODUCTS |
| 2.1 SOIL MATERIALS |
| A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations. |
| B. Satisfactory Structural Fill Materials: On-site overburden and borrow materials meeting the requirements of ASTM D 2487 soil classification groups GC, GW, GP, GM, SP, SC and SM; free of rock or gravel larger than 6 inches in any dimension, debris, ... |
| C. Unsatisfactory Soil Materials: All materials not meeting the requirements outlined above and those identified as unsuitable in the Geotechnical Report including uncontrolled fill, soft or loose soils, expansive soils and soils with high organic con... |
| D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No.... |
| E. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 294/D 2940M 0; with at least 95 percent passing a 1-1/2-inch sieve and not more than 8 percent passing a No. 200 ... |
| F. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. ... |
| G. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940/D 2940M; except with 100 percent passing a 1-inch sieve and not more than 8 percent passing a No. 200 sieve. |
| H. Drainage Course: Narrowly graded mixture of washed crushed stone, or crushed or uncrushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and zero to 5 percent passing a No. 8 sieve. |
| I. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand; ASTM D 448; coarse-aggregate grading Size 67; with 100 percent passing a 1-inch sieve and zero to 5 percent passing a No. 4 sieve. |
| J. Sand: ASTM C 33/C 33M; fine aggregate. |
| K. Impervious Fill: Clayey gravel and sand mixture capable of compacting to a dense state. |
| 2.2 GEOTEXTILES |
| A. Subsurface Drainage Geotextile: As indicated on plans. |
| B. Separation Geotextile: As indicated on plans. |
| 2.3 ACCESSORIES |
| A. Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility; colored as follows: |
| 1. Red: Electric. |
| 2. Yellow: Gas, oil, steam, and dangerous materials. |
| 3. Orange: Telephone and other communications. |
| 4. Blue: Water systems. |
| 5. Green: Sewer systems. |
| B. Detectable Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, a minimum of 6 inches wide and 4 mils thick, continuously inscribed with a description of the utilit... |
| 1. Red: Electric. |
| 2. Yellow: Gas, oil, steam, and dangerous materials. |
| 3. Orange: Telephone and other communications. |
| 4. Blue: Water systems. |
| 5. Green: Sewer systems. |
| PART 3 - EXECUTION |
| 3.1 PREPARATION |
| A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations. |
| B. Protect and maintain erosion and sedimentation controls during earth-moving operations. |
| C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials. |
| 3.2 DEWATERING |
| A. Provide dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades. |
| B. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area. |
| C. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation. |
| 1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches. |
D. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water and sediment in a manner that avoids inconvenience to others.
| 3.3 EXCAVATION, GENERAL |
| A. Classified Excavation: Excavate to subgrade elevations. Material to be excavated will be classified as earth, bulk rock, trench rock, and Unsuitable / Unsatisfactory Soils. Do not excavate Bulk Rock, Trench Rock or Unsuitable / Unsatisfactory Soils... |
| 1. Earth excavation includes excavating pavements and obstructions visible on surface; underground structures, utilities, and other items indicated to be removed; and soil, boulders, and other materials not classified as Bulk Rock, Trench Rock, Unsati... |
| a. Intermittent drilling; ram hammering; or ripping of material not classified as rock excavation is earth excavation. |
| b. Remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at depths up to 4 feet below existing grade at the Storage Building and Salt Storage Shed structures and depths up to 2 feet below finished subgrade ... |
| c. Earth excavation is included in the lump-sum contract price. |
| 2. Bulk Rock excavation includes removal and disposal of rock. Pay by in-place volume measured by pre- and post-excavation by contractor’s surveyor subject to owner verification. Remove rock to lines and subgrade elevations indicated to permit install... |
| a. 24 inches outside of concrete forms other than at footings. |
| b. 12 inches outside of concrete forms at footings. |
| c. 6 inches outside of minimum required dimensions of concrete cast against grade. |
| d. Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments. |
| e. 6 inches beneath bottom of concrete slabs-on-grade. |
| 3. Trench Rock excavation includes removal and disposal of rock. Pay by maximum trench width and depth of rock to 6” below pipe. Remove rock to lines and subgrade elevations indicated to permit installation of permanent construction without exceeding ... |
| a. 6 inches beneath pipe in trenches and the greater of 24 inches wider than pipe or 42 inches wide. |
| 4. Unsatisfactory / Unsuitable Soils: includes: |
| a. remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at depths beyond 4 feet below existing grade at the Storage Building and Salt Storage Shed. |
| b. remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at depths beyond 2 feet below finished subgrade at pavements. |
| c. any remediation by scarification, aeration, re-placement and compaction and/or removal and replacement at the Material Storage Bay and/or Covered Storage Structure |
| 3.4 EXCAVATION FOR STRUCTURES |
| A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other constr... |
| 1. Excavations for Footings and Foundations: Do not disturb bottom of excavation. Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work. |
| 2. Pile Foundations: Stop excavations 6 to 12 inches above bottom of pile cap before piles are placed. After piles have been driven, remove loose and displaced material. Excavate to final grade, leaving solid base to receive concrete pile caps. |
| 3. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Utility Structures: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 1 inch. Do not disturb bottom of excavations intended as bearing surfaces. |
| B. Excavations at Edges of Tree- and Plant-Protection Zones: |
| 1. Excavate by hand or with an air spade to indicated lines, cross sections, elevations, and subgrades. If excavating by hand, use narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots. Do not use mechanica... |
| 2. Cut and protect roots according to requirements in Section 015639 "Temporary Tree and Plant Protection." |
| 3.5 EXCAVATION FOR WALKS AND PAVEMENTS |
| A. Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades. |
| 3.6 EXCAVATION FOR UTILITY TRENCHES |
| A. Excavate trenches to indicated gradients, lines, depths, and elevations. |
| 1. Beyond building perimeter, excavate trenches to allow installation of top of pipe below frost line. |
| B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches higher than top of pipe or conduit unless otherwise indicated. |
| 1. Clearance: As indicated on plans. |
| C. Trench Bottoms: Excavate trenches 6 inches deeper than bottom of pipe and conduit elevations to allow for bedding course. Hand-excavate deeper for bells of pipe. |
| 1. Excavate trenches 6 inches deeper than elevation required in rock or other unyielding bearing material to allow for bedding course. |
| D. Trenches in Tree- and Plant-Protection Zones: |
| 1. Hand-excavate to indicated lines, cross sections, elevations, and subgrades. Use narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots. Do not use mechanical equipment that rips, tears, or pulls roots. |
| 2. Do not cut main lateral roots or taproots; cut only smaller roots that interfere with installation of utilities. |
| 3. Cut and protect roots according to requirements in Section 015639 "Temporary Tree and Plant Protection." |
| 3.7 SUBGRADE INSPECTION |