12-25061 - Addendum 1.pdf

PDF 377 KB Posted

Attached to
Oakbrook Center for Early Education
Solicitation number
US.252787
Issued by
Berks County, Reese CDP, Pennsylvania

About this file

This is Addendum No. 1 to the contract documents for the Operations Facilities Expansion project of the City of Lancaster Department of Public Works, issued by Beers + Hoffman on October 6, 2026. The addendum modifies the original bid documents dated September 8, 2026, and addresses design clarifications and refinements for the construction of a warehouse facility with associated salt, covered, and material storage sheds. The addendum revises Section 133419 (Pre-Engineered Metal Building Systems) specifications and updates 20 architectural, structural, mechanical, fire protection, and electrical drawings. Key modifications include revised finish specifications for gray primer, added notes regarding roof loading for future solar panel installations on both the warehouse and covered shed, clarifications on metal liner panels at exterior walls, pallet racking group notes, floor slab and paving specifications across all three shed structures, bar joist details, sheathing locations, and alternate deduct options for floor slabs. The addendum also includes new HVAC detail drawings for concrete pads, electrical one-line diagrams, emergency generator pads, and circuit breaker configurations.

The document establishes that all revisions and attachments become integral to the contract documents upon issuance of this addendum and shall be binding on all bidders and contractors. No pricing information, set-asides, award dates, or contract term details are specified within the addendum itself, as it functions solely as a technical modification document to the original bid package.

View the file

Other files

File Type Posted
34-25061 - Addendum 3 Arch-struct-MEP summary.pdf PDF
3-C05 - Site Civil Specifications Combined.pdf PDF
15-2026-10-06 - ES Addendum 1.pdf PDF
35-25061 - Addendum 3 Arch-struct-MEP summary.pdf PDF
10-C08 - Construction Plan.pdf PDF
Demolition.dwg DWG drawing
17-323113 - CHAIN LINK FENCES AND GATES.pdf PDF
321723 - PAVEMENT MARKINGS.pdf PDF
6-C10 - Geotechnical Report.pdf PDF
42-312000 - EARTH MOVING.pdf PDF
PG.dwg DWG drawing
EG.dwg DWG drawing
49-B861-26-01 BidTabulationReport.xlsx XLSX spreadsheet
24-2026-10-14 - CD Addendum 2.pdf PDF
25-061_Pitney Rd Warehouse_Arch-Structural-MEP Drawings_Addendum 3.pdf PDF
28-312000 - EARTH MOVING.pdf PDF
48-CD-18 UTILITY PLAN.pdf PDF
9-C06 - Pitney Rd Warehouse Arch-Structural-MEP Bid Set.pdf PDF
32-25-061 Pitney Rd Warehouse Arch-Structural-MEP Drawings Addendum 3.pdf PDF
37-133418-USER-Post Frame Building Systems-10-23-2026.pdf PDF
22-B861-26-01 ADDENDUM 2 - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
25-2026-10-14 - ES Addendum 2.pdf PDF
18-329113 - SOIL PREPARATION.pdf PDF
41-2026-10-29 - ES Addendum 4.pdf PDF
ES.dwg DWG drawing
29-321723 - PAVEMENT MARKINGS.pdf PDF
25061 - Addendum 3_ Arch-struct-MEP summary.pdf PDF
44-B861-26-01 ADDENDUM 4 - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
30-2026-10-23 - ES Addendum 3.pdf PDF
Easements.dwg DWG drawing
Landscape.dwg DWG drawing
16-25-061 Pitney Rd Warehouse Arch-Structural-MEP Addendum 1.pdf PDF
20-City of Lancaster 150 Pitney Road Phase 1 ESA Sept2026.pdf PDF
33-Addendum 03 Arch Front End Specs.pdf PDF
13-133419-RIB- Pre-Engineered Metal Building Systems-09-17-2026.pdf PDF
11-B861-26-01 FINAL - MULTIPRIME Operations Facility Expansion Project.docx DOCX document
26-Pre-Bid Attendees Ops Center Expansion 10072026.pdf PDF
40-2026-10-29 - CD Addendum 4.pdf PDF
38-25061 - Addendum 4 Arch-struct-MEP summary.pdf PDF
2026-10-23 - ES Addendum 3.pdf PDF
Addendum 03_Arch & Front End Specs.pdf PDF
39-25-061 Pitney Rd Warehouse Arch-Structural-MEP Drawings Addendum 4.pdf PDF
45-FINAL QA Report.pdf PDF
2026-10-23 - CD Addendum 3.pdf PDF
47-CD-17 UTILITY PLAN.pdf PDF
7-C09 - Fill Assessment Summary.pdf PDF
31-2026-10-23 - CD Addendum 3.pdf PDF
5-C03 - Operations Facilities Expansion - Bid Specs - Vol I.pdf PDF
312000 - EARTH MOVING.pdf PDF
46-CD-16 UTILITY PLAN.pdf PDF
Show 40 more

Latest 50 of 63 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LITITZ LANCASTER LEBANON

www.BEERSHOFFMAN.com

Beers + Hoffman

Scott L. Shonk, AIA, LEED AP

Peter D. Kerekgyarto, AIA, LEED AP

Robert P. Hoffman, AIA

BH Project #: 25-061

Operations Facilities Expansion

City of Lancaster – Department of Public Works

Addendum No. 1

6 October 2026

Notice to all bidders

This Addendum forms a part of the Contract Documents and modifies the original Bid documents dated

September 8, 2026. The Contract Documents for the above-referenced Project are being modified as set forth in this

Addendum. This addendum is issued to clarify, amend, or supersede the drawings and specifications as applicable and shall become a part of the Contract Documents for the subject project as if fully incorporated and bound therein.

ATTACHMENTS:

• Revised Specifications:

o Section 133419 – PRE-ENGINEERED METAL BUILDING SYSTEMS

• Revised Drawings:

o A100 – OVERALL SITE LAYOUT & ROOF PLANS & SOUTH ELEVATION - PROPOSED o A101 – (W) WAREHOUSE PLAN – FIRST FLOOR - PROPOSED o A102 – (W) WAREHOUSE PLAN – MEZZANINE FLOOR - PROPOSED o A103 – (S) SALT SHED PLAN – PROPOSED, EXTERIOR ELEVATIONS, MISC. INFO.

o A104 – (C) COVERED SHED PLAN – PROPOSED & EXTERIOR ELEVATIONS o A105 – (M) MATERIAL SHED PLAN – PROPOSED & EXTERIOR ELEVATIONS o A111 – (W) WAREHOUSE PLAN – FIRST FLOOR – REFLECTED CEILING & DETAILS o A301 – (W) WAREHOUSE – BUILDING SECTIONS o A302 – (W) WAREHOUSE – BUILDING SECTIONS & WALL SECTIONS o A303 – (S) SALT, (C) COVERED & (M) MATERIAL SHEDS – BUILDING SECTIONS o A514 – (C) COVERED & (M) MATERIAL SHED – WALL SECTIONS & DETAILS o S103 – SALT SHED FOUNDATION AND ROOF FRAMING PLANS o S104 – COVERED SHED FOUNDATION PLAN o S105 – MATERIAL SHED FOUNDATION AND ROOF FRAMING PLAN o H001 – HVAC LEGENDS, SCHEDULES, NOTES & ABBREVIATIONS o FP100 – FIRST FLOOR PLAN – FIRE PROTECTION o E001 – ABBREVIATIONS, NOTES & SCHEDULES o E002 – SCHEDULES AND DETAILS

SPECIFICATION CHANGES:

• Section 133419 – PRE-ENGINEERED METAL BUILDING SYSTEMS: Delete Section in its entirety and replace with revised section.

a. 2.2_D_8. Revise finish to Gray Primer.

DRAWING CHANGES:

• Drawing A100 – OVERALL SITE LAYOUT & ROOF PLANS & SOUTH ELEVATION - PROPOSED

a. (W) Warehouse Roof Plan: added note regarding roof loading for future solar panels

b. (C) Covered Shed Roof Plan: added note regarding roof loading for future solar panels

• Drawing A101 – (W) WAREHOUSE PLAN – FIRST FLOOR - PROPOSED

a. Added notes regarding metal liner panels at exterior walls

b. Added columns and column notes at Archive Shelving Room (W104)

c. Added notes clarifying pallet racking groups for deduct alternate schedule

• Drawing A102 - (W) WAREHOUSE PLAN – MEZZANINE FLOOR - PROPOSED

a. Added notes regarding metal liner panels at exterior walls

• Drawing A103 - (S) SALT SHED PLAN – PROPOSED, EXTERIOR ELEVATIONS, MISC. INFO

a. 1/A103: Modified notes regarding salt shed floor slab/paving.

• Drawing A104 – (C) COVERED SHED PLAN – PROPOSED & EXTERIOR ELEVATIONS

a. 1/A104: Modified notes regarding floor paving

• Drawing A105 - (M) MATERIAL SHED PLAN – PROPOSED & EXTERIOR ELEVATIONS

a. 1/A105: Modified notes regarding floor slab/paving

• Drawing A111 - (W) WAREHOUSE PLAN – FIRST FLOOR – REFLECTED CEILING & DETAILS

a. 2/A111: Modified notes regarding bar joists

• Drawing A301 - (W) WAREHOUSE – BUILDING SECTIONS

a. 2/A301: Modified notes regarding bar joists

• Drawing A302 - (W) WAREHOUSE – BUILDING SECTIONS & WALL SECTIONS

a. 3/A302: Modified notes regarding bar joists

• Drawing A303 - (S) SALT, (C) COVERED & (M) MATERIAL SHEDS – BUILDING SECTIONS

a. 6/A303: Modified note regarding floor slab

• Drawing A514 - (C) COVERED & (M) MATERIAL SHED – WALL SECTIONS & DETAILS

a. 5/A514: Modified note regarding sheathing locations

b. 6/A514: Modified notes regarding floor slab, & stud framing size

• Drawing S103 - SALT SHED FOUNDATION AND ROOF FRAMING PLANS

a. Salt Shed Foundation Plan; Revised note clarifying details for alternate deduct of floor slab.

b. Salt Shed Roof Framing Plan and Plan Notes added to sheet.

• Drawing S104 - COVERED SHED FOUNDATION PLAN

a. Covered Shed Foundation Plan; Revised notes clarifying details for floor/slab material and associated alternate deduct.

• Drawing S105 - MATERIAL SHED FOUNDATION AND ROOF FRAMING PLAN

a. Material Shed Foundation Plan; Revised notes clarifying details for alternate deduct of floor slab.

b. Material Shed Roof Framing Plan; Revised plan note #3 regarding roof deck material

• Drawing H001 - HVAC LEGENDS, SCHEDULES, NOTES & ABBREVIATIONS

a. Concrete Pad-Typical detail added to sheet

• Drawing FP100 - FIRST FLOOR PLAN – FIRE PROTECTION

a. Plan 1/FP100; revised note regarding zone information

• Drawing E001 - ABBREVIATIONS, NOTES & SCHEDULES

a. One-Line Diagram detail added to sheet

• Drawing E002 - ABBREVIATIONS, NOTES & SCHEDULES

a. One-Line Diagram detail removed from sheet and placed on sheet E001

b. Generator - (with main circuit Breaker) Detail added to sheet

c. Emergency Generator Pad Detail added to sheet

End of Addendum No. 1