260469_ICE.pdf
PDF 286 KB Posted
- Solicitation number
- 260469
- Issued by
- Orange County, California
About this file
This is an Independent Cost Estimate (ICE) document prepared by the Orange County Transportation Authority (OCTA) for a three-year towing and recovery services procurement. The ICE supports the related Request for Proposal (RFP) for qualified contractors to provide towing and recovery services to the Authority. The procurement is structured as a three-year contract with a term ending on December 8, 2025. The ICE was prepared by Christine Herrera, Contracts Analyst, on December 8, 2025, and includes projected annual usage based on historical data, expanded scope coverage, and current industry rate benchmarks.
The total estimated cost for the three-year procurement is $438,225.00, which exceeds the RFP budget of $435,000 by approximately $3,225. The estimate is composed of Revenue Services at 355 hours per year at $360.00 per hour, totaling $383,400 over three years, and Non-Revenue Services at 85 hours per year at $215.00 per hour, totaling $54,825 over three years. Storage services are anticipated to be incidental and included within the overall estimate. The ICE substantiates the cost estimate using historical usage data, industry rate benchmarks, and projected annual service requirements, with all three pages of the ICE document required to be submitted to Contracts Administration & Materials Management (CAMM) along with the requisition and scope of work before procurement can begin.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INDEPENDENT COST ESTIMATE (ICE)
FA-CAMM-006.docm (09/25/15) Page 1 of 3
INSTRUCTIONS
Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.
PART I – GENERAL INFORMATION
Project Description: Towing and Recovery Services SHADED AREA FOR PROCUREMENT USE ONLY
Assigned Buyer No.:
D/M/WBE%:
Purchase Requisition No.: R001064
New Contract / Procurement
Contract Amendment Current IFAS Printout Contract / PO No.:
(Required for Amendments)
Contract Task Order
Option Term
Date: 12/8/2025
Requestor: Christine Herrera Contracts Analyst Phone Ext.: 5485 Name Title
Signature:
Cost Estimate: $ 438,225.00 (include shipping, handling and taxes, if applicable)
PART II – ESTIMATE GUIDE
Please substantiate the estimate using the following information.
Estimate Type Items to Include Where to Find Supporting Information
Services (Other than A&E)
1. Tasks you want done
2. Types of people needed (i.e., supervisor, administrative assistant, other)
3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Prevailing wage rate category applied
7. Profit / applied fee
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Estimate Guide Continued
FA-CAMM-006.docm (09/25/15) Page 2 of 3
Estimate Type Items to Include Where to Find Supporting Information
Architects, Engineers, Designers
1. Tasks you want done
2. Types of people needed (i.e., engineers, administrative assistant, other)
3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)
4. Estimated hours by position
5. Salary / billing rates applied
6. Profit / applied fee
7. Overhead rate (%)
8. Direct expenses
9. Completion schedule
1. Current or past contracts for similar services
2. Other properties / departments doing similar work
3. Historical price and cost data
Goods/Equipment 1. Product needed
2. Quantity
3. Unit price
4. Markups, overhead, profit
5. Delivery schedule desired
6. Warranty
1. Vendor survey / market survey
2. Current or past contracts for the same or similar product
3. Historical price and cost data
4. Various published indices
Construction 1. Product needed
2. Labor (at a minimum use Davis Bacon)
3. Materials
4. Bonds
5. Insurance
6. Mobilization
7. Equipment
8. Markups, fringes, overheads, profit
9. Completion schedule
1. “Means Book”
2. “Blue Book”
3. Davis Bacon wage rates / prevailing wages
4. Current or past contracts for the same project
5. Historical price and cost data
Additional Information: The Independent Cost Estimate (ICE) for this three (3)-year procurement is based on projected annual usage, reflecting historical usage, expanded scope coverage, and current industry rate benchmarks.
Storage services are anticipated to be incidental and are included within the overall estimate.
Revenue Services: 355 Hours x $360.00/hr = $127,800 annually x 3 years = $383,400 Non-Revenue Services: 85 Hours x $215.00/hr = $18,275 annually x 3 years = $54,825 Total 3-Year Estimate for Towing and Recovery Services: $438,225
FA-CAMM-006.docm (09/25/15) Page 3 of 3
PART III – INDEPENDENT COST ESTIMATE
Using the information provided in Part II, prepare the ICE for your procurement.
Use any or all of the categories listed below.
Prepared By: Christine Herrera Date: 12/8/2025
Signature:
DESCRIPTION OF COST ELEMENTS
1. DIRECT LABOR
(List of Labor Categories)
Estimated Hours
Rate Per Hour ($)
Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00
Total Direct Labor: $ 0.00
2. OVERHEAD
Rate (%)
(use decimal input)
Total Labor ($)
Estimated Cost ($)
Total Est.
Cost ($)
% $ 0.00 $ 0.00 $ 0.00
3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)
Total Est.
Cost ($)
Towing and Recovery Services $ 438,225.00 $ 438,225.00
4. INFORMATION TECHNOLOGY SUPPORT Estimated Cost ($)
Total Est.
Cost ($)
Total IT Support: $ 0.00
5. TRAVEL Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
6. SUBCONTRACTOR(S) / CONSULTANT(S) Estimated Cost ($)
Total Est.
Cost ($)
Total Subcontractor(s) / Consultant(s): $ 0.00
7. OTHER DIRECT COSTS Estimated Cost ($)
Total Est.
Cost ($)
$ $ 0.00
8. TOTAL ESTIMATED COST: $ 438,225.00