26-8703_Sheet_A-101.2.pdf

PDF 778 KB Posted

Attached to
Immokalee Sports Complex Phase 1A & 1B
Solicitation number
26-8703
Issued by
Collier County, Florida

About this file

This file is an architectural drawing (Sheet A-101.2) for the Field Restroom and Pavilion Plan associated with Collier County's Immokalee Sports Complex Phase 1A & 1B construction project (IFB 26-8703). The drawing depicts the floor plan layout of a 1,184-square-foot sports field restroom facility and a 618-square-foot open-air pavilion structure, with detailed annotations showing room designations including men's and women's restrooms, storage areas, and equipment yards. The plan includes specifications for concrete slabs at elevation 0'-0", CMU wall construction with various finishes (stucco and tile), metal stud framing details, roof overhangs, and utility provisions such as electrical panels, hose bibs, wall sconces, and a manual roll-up door. General notes require the contractor to field verify the locations of existing sports lighting poles and foundations to ensure they do not conflict with the proposed building, with all existing poles to be braced and supported during construction. The drawing references coordination with structural, civil, electrical, and plumbing drawings, as well as a finish schedule on Sheet A-711. The site is located at 505 Escambia Street, Immokalee, Florida, with sealed bids due November 2 or November 12, 2026 (per conflicting notices) at 3:00 p.m. local time, and a non-mandatory pre-bid meeting scheduled for October 16, 2026 at 10:00 a.m. in Naples, Florida.

The anticipated contract budget for the entire Immokalee Sports Complex Phase 1A & 1B project is $6.24 million, with a $500,000 Owner's Allowance for unforeseen conditions. Substantial completion must be achieved within 180 calendar days from Notice to Proceed, with final completion within 30 days after punch list delivery; liquidated damages are assessed at $5,549 per calendar day for failure to meet the substantial completion deadline. The contractor must provide a bid bond of 5 percent of the total bid amount, Payment and Performance Bonds equal to 100 percent of the contract award, and comprehensive insurance including workers' compensation at statutory limits, general liability of $1 million per occurrence/$2 million aggregate, employer's liability of $1 million, and automobile liability of $1 million. Bidders must demonstrate a minimum of 10 years of experience as a business entity and 10 years providing construction services relevant to parks and recreation facilities, with submission of at least five completed projects, including three qualifying projects with minimum contract values of $1 million each, at least two completed within four years of the bid due date and all three within ten years, and at least one demonstrating experience at an operating facility while maintaining operations.

View the file

Other files

File Type Posted
26-8703_Sheet_A-711.pdf PDF
26-8703_Sheet_A-700.2.pdf PDF
26-8703_Sheet_A-602.pdf PDF
26-8703_Phase_1B_Sheet_C109.pdf PDF
26-8703_Phase_1B_Sheet_C106.pdf PDF
26-8703_Phase_1A_Sheet_C508.pdf PDF
26-8703_Phase_1A_Sheet_C500.pdf PDF
26-8703_Phase_1A_Sheet_C109.pdf PDF
26-8703_Phase_1A_Sheet_C106.pdf PDF
26-8703_Exhibit_K_SFWMD_ERP_Permit.pdf PDF
26-8703_Bid_Schedule_(rev._1).xlsx XLSX spreadsheet
26-8703_Solicitation_(rev._1).pdf PDF
26-8703_Pre-Bid_Meeting_Audio.MP3 MP3 file
26-8703_Geotechnical_Report.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
Construction_Services_Agreement_2025_Template_ver_3_with_Exhibits.pdf PDF
26-8703_Supplemental_Qualifications.pdf PDF
26-8703_Scope_of_Work_Phase_1A_&_1B.pdf PDF
26-8703_Exhibit_M3_Phase_1A_Landscape_Architecture_Plans.pdf PDF
26-8703_Exhibit_M2_Phase_1A_Civil_Engineering_Plans.pdf PDF
26-8703_Exhibit_M1_Phase_1A_Keysheet.pdf PDF
26-8703_Exhibit_J3_Phase_1B_Technical_Specifcations_Part_2.pdf PDF
26-8703_Exhibit_J2_Phase_1B_Technical_Specifications_Part_1.pdf PDF
26-8703_Exhibit_J1_Phase_1A_Technical_Specifications.pdf PDF
26-8703_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
26-8703_Exhibit_M10_Phase_1B_Landscape_&_Irrigation_Plans.pdf PDF
26-8703_Exhibit_M9_Phase_1B_Structural_Plans.pdf PDF
26-8703_Exhibit_M8_Phase_1B_Electrical_Plans.pdf PDF
26-8703_Exhibit_M7_Phase_1B_Mechanical_&_Plumbing_Plans.pdf PDF
26-8703_Exhibit_M6_Phase_1B_Architecture_Plans.pdf PDF
26-8703_Exhibit_M5_Phase_1B_Civil_Engineering_Plans.pdf PDF
26-8703_Exhibit_M4_Phase_1B_Keysheet.pdf PDF
Construction_Bid_Instructions.pdf PDF
26-8703_Bid_Schedule.xlsx XLSX spreadsheet
26-8703_Solicitation.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEN'S

WOMEN'S

J.C.

1 2

A

B

4 A-602

8 A-602

STORAGE

104A

104B

L2 L1 L1

L1 L1

12 A-602

A-200.2

R.O.

R.O.

SLOPE

D.F.

D.F.

R .O

R

.O

R .O

A-200.2

A-200.2

A-200.2

A-500.2

A-500.2

A-500.2

A-500.2

A-500.2

A-500.2

A-500.2

A-500.2

L1

L1

L1

L1

P

W

W

W

W

P

EDGE OF ROOF

OVERHANG ABOVE

T.O. SLAB

EL. 0'-0"

T.O. SLAB

EL. 0'-0"

H.C.

H.C. H.C.

H.C. H.C. H.C.

CONCRETE COLUMNS, SEE

STRUCTURAL DRAWINGS

GENERAL NOTES:

1. Contractor shall field verify the location of all existing sports lighting poles, foundations, and associated clearances relative to the proposed field restroom building.

Verify that all existing utilities, slabs, walls, footings, and roof lines of the proposed building clear the existing lighting poles and pole foundations. All existing lighting poles shall be braced and adequately supported during all phases of building construction activities. Contractor shall field stake all proposed building corners prior to construction and notify the Architect and Civil Engineer of any discrepancies, conflicts, or issues identified during field verification for review and resolution prior to proceeding with construction. Coordinate as required to avoid delays or impacts to existing facilities.

2. REFER TO SHEET A-711 FOR FINISH SCHEDULE, RESTROOM TABULATIONS, PLUMBING FIXTURE AND RESTROOM ACCESSORIES SCHEDULE.

WALL SCONCE

WALL SCONCE

7' X 12' MANUAL

ROLL-UP DOOR

CMU WALL, EXPOSED

HOSE BIB

ELECTRICAL

PANEL

4" CONCRETE

PAD FOR

TRANSFORMER

T.O. SLAB

EL. 0'-0"

CMU WALL

WALL SCONCE

HOSE BIB

TYPICAL

CONTROL

JOINTS

SLAB ON GRADE PATIO.

SEE STRUCTURAL

DRAWINGS

4"X6" ALUMINUM BOX

GUTTER WITH 4"X4"

ALUMINUM DOWNSPOUT

CONNECTED TO STORM

LINE, SEE CIVIL DRAWINGS.

CONCRETE WALKWAY

REFER TO CIVIL DRAWINGS

FLUSH

CONCRETE WALKWAY

REFER TO CIVIL DRAWINGS

FLUSH

CONCRETE WALKWAY

REFER TO CIVIL DRAWINGS

1/2" MAX

FE

FIRE EXTINGUISHER

CHAINLINK FENCE

AND GATE

EQUIPMENT YARD

CHAINLINK FENCE

4"X4" DOWNSPOUT

CONCRETE SPLASH PAD

4"X4" DOWNSPOUT

CONCRETE SPLASH PAD

W

W

P

2"

2"

2"

EXISTING

LIGHT POLE

(V.I.F.)

(V .I

.F

EWH

FLOOR AREA TABLE

FLOOR AREA AND BUILDING HEIGHT

FLOOR AREA, LDC SEC1.08.02. DEFINITIONS: MEASURED FROM THE OUTSIDE OF EXTERIOR WALL:

INCLUDES HABITABLE SPACE: EXCLUDES ACCESSORY SPACE (COURTS & VENT SHAFTS)

FLOOR AREA, LDC PARKING ONLY (SEC4.05.04.B.1 PARKING SPACE REQUIREMENT):

MEASURED FROM INSIDE OF EXTERIOR WALLS, INCLUDES HABITABLE AND ACCESSORY SPACE

(COURTS & VENT SHAFTS)

(FLOOR AREA GROSS) BUILDING FBC (DEFINITIONS, SEC.202): THE AREA INCLUDED WITHIN

SURROUNDING EXTERIOR WALLS (OR EXTERIOR WALLS AND FIRE WALLS) EXCLUSIVE OF

VENT SHAFTS AND COURTS. AREAS OF THE BUILDING NOT PROVIDED WITH THE

SURROUNDING WALLS SHALL BE INCLUDED IN THE BUILDING AREA IF SUCH AREAS ARE

INCLUDED WITHIN THE HORIZONTAL PROJECTION OF THE ROOF OR FLOOR BELOW

BUILDING TYPE AND SQUARE FOOTAGE (SF)

SPORTS FIELD AND STORAGE FACILITY/ PAVILION

1,184.16 SF

N/A

1,792.44 SF

DBL. ROW OF 3-5/8" 25GA. METAL

STUD FRAMING @ 24" O.C.

5/8"

REFER

TO

FLOOR

PLAN 3 5/8"

5/8"

3-1/2" FIBER GLASS SOUND BATT

INSUL.

THINSET MORTAR

WALL TILE

3 5/8"

STL. RUNNER BRACING, SCREW TO STUDS

(1) LAYER 5/8" GWB MOISTURE RESISTANT TYPE, FULL-HT.

P

3 5/8" MTL. STUD CHASE WALL TILED

PLAN VIEW

3 5/8" (6") 5/8"5/8"

(1) LAYER MOISTURE RESISTANT 5/8" GWB, FULL-HT.

3-5/8" MTL. STUD PARTITION NON-RATED

METAL STUDS @ 24" O.C., FULL-HT.

4 7/8" (7 1/4")

EXTERIOR VIEW5/8" 7 5/8"1 1/2"

W

CMU - 1 1/2" MTL FURRING

9 3/4"

SEE FINISH SCHEDULEVERIFY RESTROOM WALL FINISH

5/8" GWB

1 1/2" STEEL HAT CHANNEL

FI-FOIL MULTI LAYER REFLECTIVE

INSULATION. R-VALUE TO MEET ENERGY

CALCULATIONS

8" NOM. CMU WALL

INTERIOR VIEW

SHIM AS NEEDED

EXTERIOR VIEW5/8" 7 5/8"1 1/2"

W

CMU - 1 1/2" MTL FURRING - STUCCO FIN.

10 3/8"

5/8" THICK STUCCO

5/8" GWB

1 1/2" STEEL HAT CHANNEL

FI-FOIL MULTI LAYER REFLECTIVE

INSULATION. R-VALUE TO MEET ENERGY

CALCULATIONS

8" NOM. CMU WALL

INTERIOR VIEW

SHIM AS NEEDED

5/8"

EXTERIOR VIEW7 5/8"

W

CMU - STUCCO FIN.

8 1/4"

5/8" THICK STUCCO

8" NOM. CMU WALL

INTERIOR VIEW 5/8"

SEE FINISH SCHEDULE

8" X 5" CONCRETE CURB

TILE COVE BASE

DBL. ROW OF 3-5/8" 25GA. METAL

STUD FRAMING @ 24" O.C.

5/8"

3 5/8"

5/8"

3-1/2" FIBER GLASS SOUND BATT

INSUL.

THINSET MORTAR

WALL TILE

STL. RUNNER BRACING, SCREW TO STUDS

(1) LAYER 5/8" GWB MOISTURE RESISTANT TYPE, FULL-HT.

P

3 5/8" MTL. STUD CHASE WALL TILED

8" X 5" CONCRETE CURB

TILE COVE BASE

EXTERIOR VIEW5/8" 7 5/8"1 1/2"

W

TILE ON CMU- 1 12" MTL. FURRING

W-STUCCO FINISH

9 3/4"

8" STUCCO (OMIT STUCCO ON INTERIOR)

5/8" MR GWB ON 1 12" MTL. FRAMING

THINSET MORTAR

WALL TILE

8" NOM. CMU WALL

INTERIOR VIEW

CONC. SLAB

5/8"

SHLUTER TILE EDGING TRIM

PLASTER

FIELD RESTROOM AND PAVILION PLAN

Scale: 1/4" = 1'-0"

A-101.2

P10

P6

P10

P6

P10

P6

P10

P6

P10

P6

A8

A8

A9

P7

P11 P11

A5 A5 A5A6

A6

A14

A14

A14

P8

A10

A10

A10

A10

A1 A2

A1 A2

A2

A2

A12

A12

A4

A3

A4

A4

A3

A4

A3

A4

A3

A14 A14

P9

A11 A11

A13

A13

A13

A3

A3

P4

P4

P2

P2

A3

P2

A13

P2

P4

P4

P7

P4

A9

FIELD RESTROOM

AND PAVILION PLAN

A

T T

E N

T

IO

N

T h e s e d ra w in g s m a y i n c lu d e i n fo rm a ti o n p ro v id e d b y o th e rs

S ta n te c h a s n o t v e ri fi e d th e a c c u ra c y a n d /o r c o m p le te n e s s o f th is in fo rm a ti o n a n d s h a ll n o t b e r e s p o n s ib le f o r a n y e rr o rs o r o m is s io n s w h ic h m a y b e in c o rp o ra te d h e re in a s a r e s u lt

A-101.2

A13

A3 P4

A13

2026-11-10T13:40:30-0500
Elvira C Freire Santamaria
I have reviewed this document

File details come from the government source that posted it. Updated .