This Scope of Work document outlines the construction requirements for Collier County's Immokalee Sports Complex Phase 1A & 1B project. Phase 1A encompasses construction of two artificial turf fields (Fields 2 and 3), stormwater improvements, fencing, and landscaping and hardscaping work. The aquatic center and parking area will remain open to the public during Phase 1A construction, requiring continuous coordination with Parks and Recreation. Field 1 is designated as the construction staging area and must be restored to the satisfaction of Collier County Parks & Recreation Department upon completion in accordance with Sports Field Management Association Standards. Phase 1B includes construction of a new 1,190 square foot restroom facility with mechanical, electrical, and plumbing systems plus a drinking fountain, a pavilion structure with utility tie-ins for drainage and water lines, landscaping and irrigation, fencing, and concrete sidewalks. Sealed bids are due no later than November 2 at 3:00 p.m. local time. A non-mandatory pre-bid meeting is scheduled for October 16 at 10:00 a.m. at 3295 Tamiami Trail East Building C-2, Conference Room A, Naples, Florida. Complete bid documents are available through Collier County's procurement portal at https://procurement.opengov.com/portal/collier-county-fl.
Contractors must have a minimum of 10 years of experience with sports field construction and provide at least five references for similar work completed within the past four years. All project workers, from the superintendent to entry-level staff, must clear a Collier County Facilities background check. The contractor will utilize Collier County's Procore project management platform for all documentation, communications, submittals, and coordination, with full access and responsibility for managing the RFI and submittal workflows. A 4-by-8-foot construction sign displaying the project name and stakeholder logos must be installed on-site along with a permit box containing all required permits. The contractor is responsible for all permitting except the updated Site Development Plan, which has been applied for by Stantec, the design services provider. The east side of the parking lot is reserved exclusively for construction vehicle access.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work - Immokalee Sports Complex Phase 1 (1A & 1B)
The Immokalee Sports Complex shown above has three sport fields and an aquatic center.
The County has engaged Stantec for the design services of a 2-phased renovation (Phase
1- 1A & 1B and Phase 2). Updated SDP has been applied for by Stantec. The contractor will be responsible for all other permitting.
Phase 1 - 1A construction scope of work will include - but is not limited to – the following:
A. Construction of two artificial turf fields (Fields 2 and 3) B. Stormwater improvements C. Fencing D. Landscaping and hardscaping
The aquatic center and parking area will remain open to the public during phase 1A construction. Therefore, the contractor will be required to continuously coordinate with Parks and Recreation to ensure their needs are continuously met. The east side of the parking lot is to be used for construction vehicle access only. Field 1 is designated as the construction staging area. Field 1 is to be restored at construction completion to the satisfaction of the Collier County Parks & Recreation Department and in accordance with the Sports Field Management Association Standards.
Phase 1-1B construction scope of work includes the following:
A. Construction of new 1,190 S.F. restroom complete with MEP/Drinking Fountain.
B. Pavilion structure, utility tie-ins (Drainage, water lines, C. Landscaping & Irrigation, Fencing D. Concrete sidewalks
The contractor will install a 4’x8’ construction sign displaying the project name, the stakeholders’ names and the stakeholder’s logos will need to be installed at the site along with a permit box containing all copies of all required permits.
The Contractor shall use Collier County’s project management platform (Procore) and utilize all tools including Requests for Information (RFIs), Submittals, Daily Log, Photos, Drawings, Specification, Meetings, Schedule, Transmittals, Inspections, Incidents, Budget, Documents, and Directory. The Contractor will be given full access to Procore and will be empowered to manage the RFI and Submittal workflows, document management, meeting management, and all other project management tools to ensure an efficient project. The Contractor will have the ability to invite subcontractors to the project to ensure full participation, access to the latest drawings, and efficient handling of RFIs and submittals.
All workers involved with this project – from the superintendent to the least skilled workman must clear the Collier County Facilities background check. The contractor must have a minimum of 10 years of experience with sport fields construction and provide a minimum of 5 references not older than 4 years for work of similar magnitude.