26-8703_Bid_Schedule_(rev._1).xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Immokalee Sports Complex Phase 1A & 1B
Solicitation number
26-8703
Issued by
Collier County, Florida

About this file

This is a Bid Schedule for Construction Invitation for Bid (IFB) 26-8703 issued by Collier County, Florida for the Immokalee Sports Complex Phase 1A & 1B project. The project encompasses two phases of construction at a sports complex facility located at 505 Escambia Street, Immokalee, Florida. Phase 1A includes development of two artificial turf athletic fields (Fields 2 and 3), stormwater infrastructure improvements, perimeter fencing (2,200 linear feet of galvanized chain link fence with gates), soft net backstops (six units at 20 feet height), concrete sidewalks and pads (406 square yards), asphalt paving (507 square yards), landscaping and irrigation work covering approximately 182,000 square feet, utility connections, and site preparation and clearing. Phase 1B includes construction of a 1,190-square-foot restroom and storage building with mechanical, electrical, and plumbing systems, a 618-square-foot open-air pavilion with utility connections, concrete sidewalks (446 square yards), landscape and irrigation work covering approximately 93,000 square feet, and additional fencing (60 linear feet). The non-mandatory pre-bid meeting is scheduled for October 16 at 10:00 a.m. in Naples, Florida. Sealed bids are due November 2, 2026 (or November 12, 2026 per an alternate date listed) at 3:00 p.m. local time. The anticipated contract budget is $6.24 million, with substantial completion required within 180 calendar days from Notice to Proceed and final completion within 30 days thereafter. Liquidated damages are assessed at $5,549 per calendar day for failure to achieve substantial completion.

Contractors must demonstrate a minimum of ten years of experience as a business entity in construction and ten years providing services relevant to parks and recreation facilities, with a portfolio of at least five completed projects including a minimum of three qualifying projects with contract values of $1 million or greater. At least two qualifying projects must be completed within four years of the bid due date, and all three within ten years; at least one project must demonstrate experience performing work at an operating facility while maintaining operations. A $500,000 Owner's Allowance has been allocated for unforeseen conditions and work directed by the Owner, to be distributed through change orders. Bidders must submit a bid bond of 5 percent of the total bid amount and, upon award, provide Payment and Performance Bonds equal to 100 percent of the contract price. Required insurance includes workers' compensation at statutory limits, general liability of $1 million per occurrence and $2 million aggregate, employer's liability of $1 million, and automobile liability of $1 million. All work must comply with the 2023 Florida Building Code, 2020 National Electrical Code, 2023 Florida Fire Prevention Code, OSHA regulations, and Collier County Environmental, Health and Safety standards. Contractors must utilize Collier County's Procore project management platform for documentation and complete a county facilities background check. One contract will be awarded for all work.

View the file

Other files

File Type Posted
26-8703_Sheet_A-711.pdf PDF
26-8703_Sheet_A-700.2.pdf PDF
26-8703_Sheet_A-602.pdf PDF
26-8703_Sheet_A-101.2.pdf PDF
26-8703_Phase_1B_Sheet_C109.pdf PDF
26-8703_Phase_1B_Sheet_C106.pdf PDF
26-8703_Phase_1A_Sheet_C508.pdf PDF
26-8703_Phase_1A_Sheet_C500.pdf PDF
26-8703_Phase_1A_Sheet_C109.pdf PDF
26-8703_Phase_1A_Sheet_C106.pdf PDF
26-8703_Exhibit_K_SFWMD_ERP_Permit.pdf PDF
26-8703_Solicitation_(rev._1).pdf PDF
26-8703_Pre-Bid_Meeting_Audio.MP3 MP3 file
26-8703_Geotechnical_Report.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
Construction_Services_Agreement_2025_Template_ver_3_with_Exhibits.pdf PDF
26-8703_Supplemental_Qualifications.pdf PDF
26-8703_Scope_of_Work_Phase_1A_&_1B.pdf PDF
26-8703_Exhibit_M3_Phase_1A_Landscape_Architecture_Plans.pdf PDF
26-8703_Exhibit_M2_Phase_1A_Civil_Engineering_Plans.pdf PDF
26-8703_Exhibit_M1_Phase_1A_Keysheet.pdf PDF
26-8703_Exhibit_J3_Phase_1B_Technical_Specifcations_Part_2.pdf PDF
26-8703_Exhibit_J2_Phase_1B_Technical_Specifications_Part_1.pdf PDF
26-8703_Exhibit_J1_Phase_1A_Technical_Specifications.pdf PDF
26-8703_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
26-8703_Exhibit_M10_Phase_1B_Landscape_&_Irrigation_Plans.pdf PDF
26-8703_Exhibit_M9_Phase_1B_Structural_Plans.pdf PDF
26-8703_Exhibit_M8_Phase_1B_Electrical_Plans.pdf PDF
26-8703_Exhibit_M7_Phase_1B_Mechanical_&_Plumbing_Plans.pdf PDF
26-8703_Exhibit_M6_Phase_1B_Architecture_Plans.pdf PDF
26-8703_Exhibit_M5_Phase_1B_Civil_Engineering_Plans.pdf PDF
26-8703_Exhibit_M4_Phase_1B_Keysheet.pdf PDF
Construction_Bid_Instructions.pdf PDF
26-8703_Bid_Schedule.xlsx XLSX spreadsheet
26-8703_Solicitation.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Vendor Name:
BID SCHEDULE
CONSTRUCTION ITB: 26-8703
IMMOKALEE SPORTS COMPLEX PHASE 1A & 1B
PHASE 1A
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
1Survey - Layout and As-Built Survey1LS$ - 0$ - 0
2Mobilization/Demobilization1LS$ - 0$ - 0
3Payment and Performance Bond1LS$ - 0$ - 0
4Maintenance of Traffic1LS$ - 0$ - 0
5Record Drawings - Provide and Maintain record (as-built) drawings for Engineer's Certification1LS$ - 0$ - 0
SUBTOTAL DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS:$ - 0
DIVISION 01 -GENERAL REQUIREMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
6Temporary Tree and Plant Protection - Construction-phase tree and plant protection, trimming, protection - zone fencing, and pruning1ALLOW$ - 0$ - 0
7Construction Waste Management and Disposal - Salvaging, recycling, and disposing of non-hazardous demolition and construction waste1ALLOW$ - 0$ - 0
SUBTOTAL DIVISION 01 - GENERAL REQUIREMENTS:$ - 0
DIVISION 03 - CONCRETE
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
85" thick reinforced concrete sidewalk or slab w/ sub-base - Bleacher pads, sidewalks406SY$ - 0$ - 0
96" thick reinforced concrete pavement with sub-base - Drive apron77SY$ - 0$ - 0
10Detectable Warning Surface3EA$ - 0$ - 0
SUBTOTAL DIVISION 03 - CONCRETE:$ - 0
DIVISION 11 - EQUIPMENT
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
11Galvanized Chain Link Fence - 8.0' height 6-gauge galvanized chain link fence, posts, footings, fasteners, etc.2,200LF$ - 0$ - 0
12Single Swing Gate - 8.0' height x 4' wide 6-gauge galvanized chain link gate, latch hardware, posts, footings, fasteners, etc.2EA$ - 0$ - 0
13Double Swing Gate - 8.0' height x 8' wide (two 4' panels) 6-gauge galvanized chain link gates, latch hardware, posts, footings, fasteners, etc.1EA$ - 0$ - 0
14Manual Rolling Gate & Knox Box - 16' manual rolling gate atop v-track and concrete grade beam w/ Knox Box2EA$ - 0$ - 0
15Artificial Turf Field & Infrastructure - Includes Removal of Upper 6 Inches of Existing Field, Installation of Field/Underdrain system, Backfill, Turf Carpet, Field Striping, 8" Ribbon Curb Around Field & Furnishing, Zeofill Topping2EA$ - 0$ - 0
1620'H soft net backstops - 20'H soft net backstops, inline and freestanding poles, concrete ribbon curb/grade beam, net hoist system6EA$ - 0$ - 0
SUBTOTAL DIVISION 11 - EQUIPMENT:$ - 0
DIVISION 12 - FURNISHINGS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
17Trash Receptacle - Product selection by Collier County Parks and Recreation Department2EA$ - 0$ - 0
18Recycle Receptacle - Product selection by Collier County Parks and Recreation Department2EA$ - 0$ - 0
19Bleacher (Fixed) - Bleacher locations #3 and #4 between fields 2 and 32EA$ - 0$ - 0
SUBTOTAL DIVISION 12 - FURNISHINGS:$ - 0
DIVISION 13 - SPECIAL CONSTRUCTION
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
20Vehicular Rated Bollards - Vehicular rated guard bollard painted yellow with reflective markings3EA$ - 0$ - 0
21Sports Lighting Painting (does not include pool area)- Includes all materials, equipment, and labor to remove mold, algae, and staining buildup; prepare the pole for paint (1) coat primer per surface type (metal or concrete) and apply (2) coats high-quality Sherwin-Williams paint up to a height of 20'15EA$ - 0$ - 0
SUBTOTAL DIVISION 13 - SPECIAL CONSTRUCTION:$ - 0
DIVISION 31 - EARTHWORKS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
22Site Clearing - Clearing, grubbing, vegetation protection, stumping, stripping and stockpiling topsoil and rock, and disconnecting utilities. Includes removal of existing hardscape, irrigation and fencing1LS$ - 0$ - 0
23Erosion Control and NPDES - Includes silt fencing1LS$ - 0$ - 0
24Embankment - Includes miscellaneous fill as needed for construction and berm restoration - fields not included800CY$ - 0$ - 0
SUBTOTAL DIVISION 31 - EARTHWORKS:$ - 0
DIVISION 32 - EXTERIOR IMPROVEMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
251.5" thick asphaltic concrete type SP-12.5 - structural course507SY$ - 0$ - 0
261" thick asphaltic concrete type SP-9.5 - friction course507SY$ - 0$ - 0
2710" Limerock Base607SY$ - 0$ - 0
28Type F Curb62LF$ - 0$ - 0
29Painted pavement Markings STD1LS$ - 0$ - 0
306" PVC Conduits - Irrigation sleeves60LF$ - 0$ - 0
314" PVC Conduits - Irrigation sleeves60LF$ - 0$ - 0
32Planting Irrigation Retrofit - Includes Rerouting and Quick Connection Valves w/ Valve Box (includes repair and reactivation of Field #1 upon completion of construction)74,134SF$ - 0$ - 0
33Planting Irrigation New Installation - Includes irrigation control system, piping, valves, drip, bubbler, and sprinkler distribution (excludes field #1 irrigation intended to remain for re-use)107,927SF$ - 0$ - 0
34Soil Preparation (Performance Specification) - 6" depth in shrub beds for planting soils specified according to tesed performance requirements (particle size, organic matter percentage, pH, CEC, fertility, etc.), layered soil assemblies1,682CY$ - 0$ - 0
35Sod Areas - Seeded, sodded, plugged, and sprigged turf; pesticides, erosion-control materials, turf renovation, and grass paving. (excludes sod replacement of Field #1 upon completion of construction Phase 1B)109,685SF$ - 0$ - 0
36Plants - Canopy Tree - Nursery-grown trees and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates26EA$ - 0$ - 0
37Plants - Palm Tree - Nursery-grown trees and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates9EA$ - 0$ - 0
38Plants - Mulch Rings - 4' dia mulch ring x 3" depth typical6CY$ - 0$ - 0
39Plants - Root Barrier - Deeproot UB24-2: 24" deep rigid panel root barrier126LF$ - 0$ - 0
SUBTOTAL DIVISION 32 - EXTERIOR IMPROVEMENTS:$ - 0
DIVISION 33 - UTILITIES
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
40Proposed Fire Hydrant - Assumes up to 300 ft of fire main; fire hydrant installation; valves, fittings and isolation valve1LS$ - 0$ - 0
41Sanitary Sewer tie-in and clean-out - Assume 6" PVC pipe32LF$ - 0$ - 0
42Connect/modifications to existing drainage structures - 15-inch drainage pipe connection1EA$ - 0$ - 0
43Clean out existing Drainage Structures and flush pipe - 9 structures. Flush all pipes1LS$ - 0$ - 0
4415" RCP Stormwater Pipe13LF$ - 0$ - 0
4512" HPStorm PE Pipe374LF$ - 0$ - 0
4615" HPStorm PE Pipe390LF$ - 0$ - 0
4718" HPStorm PE Pipe506LF$ - 0$ - 0
4824" HPStorm PE Pipe415LF$ - 0$ - 0
496" PVC Drainage Pipe and Cap40LF$ - 0$ - 0
5010" PVC Drainage Pipe and Cap2LF$ - 0$ - 0
5112" PVC Drainage Pipe (C900 PVC, Class 305, DR 14) - Add 2 caps62LF$ - 0$ - 0
5215" PVC Drainage Pipe (C900 PVC, Class 305, DR 14)33LF$ - 0$ - 0
532" Potable water tie-in and stub out - Water line serving Restroom24LF$ - 0$ - 0
541" Potable water tie-in and stub out w/ Valve - Water line to service future 1" polytube to Phase 2 pool12LF$ - 0$ - 0
55Outlet Control Structure - Structure prior to Mitered End Sections (M.E.S.)2EA$ - 0$ - 0
56FDOT Mitered End Section2EA$ - 0$ - 0
57Proposed Catch Basin - Type C15EA$ - 0$ - 0
58Proposed Yard Drain - 18" ADS Basin9EA$ - 0$ - 0
SUBTOTAL DIVISION 33 - UTILITIES:$ - 0
BID ALTERNATES
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
ALT-1Electric Rolling Gate & Knox Box - 16' electric motor w/ emergency vehicle accessibility rolling gate atop v-track and concrete grade beam w/ Knox Box. Contractor to provide add alt pricing as part of bidding1EA$ - 0$ - 0
ALT-2Planting Irrigation Water Treatment System - Well-water treatment system to mitigate high levels of iron, sulfur, bacteria, and sediment. Contractor to provide add alt pricing as part of bidding1EA$ - 0$ - 0
SUBTOTAL BID ALTERNATES:$ - 0
PHASE 1A BASE BID TOTAL:$ - 0
PHASE 1A BASE BID + ALT-1:$ - 0
PHASE 1A BASE BID + ALT-2:$ - 0
PHASE 1A BASE BID + ALT-1 + ALT-2:$ - 0
PHASE 1B
DIVISION 00 - PROCUREMENT AND CONTRACT REQUIREMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
59Survey - Layout and As-Built Survey1LS$ - 0$ - 0
60Mobilization/Demobilization1LS$ - 0$ - 0
61Payment and Performance Bond1LS$ - 0$ - 0
62Maintenance of Traffic1LS$ - 0$ - 0
63Record Drawings - Provide and Maintain record (as-built) drawings for Engineer's Certification1LS$ - 0$ - 0
SUBTOTAL DIVISION 00 - PROCUREMENT AND CONTRACT REQUIREMENTS:$ - 0
DIVISION 01 - GENERAL REQUIREMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
64Temporary Tree and Plant Protection - Construction-phase tree and plant protection, trimming, protection - zone fencing, and pruning1ALLOW$ - 0$ - 0
65Construction Waste Management and Disposal - Salvaging, recycling, and disposing of non-hazardous demolition and construction waste1ALLOW$ - 0$ - 0
SUBTOTAL DIVISION 01 - GENERAL REQUIREMENTS:$ - 0
DIVISION 03 - CONCRETE
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
665" thick reinforced concrete sidewalk or slab w/ sub-base - Bleacher pads, sidewalks446SY$ - 0$ - 0
67Detectable Warning Surface1EA$ - 0$ - 0
SUBTOTAL DIVISION 03 - CONCRETE:$ - 0
DIVISION 11 - EQUIPMENT
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
68Galvanized Chain Link Fence - 8.0' height 6-gauge galvanized chain link fence, posts, footings, fasteners, etc.60LF$ - 0$ - 0
69Single Swing Gate - 8.0' height x 4' wide 6-gauge galvanized chain link gate, latch hardware, posts, footings, fasteners, etc.1EA$ - 0$ - 0
SUBTOTAL DIVISION 11 - EQUIPMENT:$ - 0
DIVISION 12 - FURNISHINGS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
70Trash Receptacle - Product selection by Collier County Parks and Recreation Department; Installed by Contractor3EA$ - 0$ - 0
71Recycle Receptacle - Product selection by Collier County Parks and Recreation Department; Installed by Contractor3EA$ - 0$ - 0
72Bleacher (Fixed) -Bleacher locations #1 and #2 between fields 1 and 22EA$ - 0$ - 0
SUBTOTAL DIVISION 12 - FURNISHINGS:$ - 0
DIVISION 13 - SPECIAL CONSTRUCTION
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
73Vehicular Rated Bollards - 1 Bollard (2 bollards installed with fire hydrant Ph 1A - NIC)1EA$ - 0$ - 0
Field Restroom / Storage / PavilionAssumes a 1,190 square foot CMU building on slab consisting of storage space, men’s and women’s restroom facilities, and a utility closet, along with a 618 square foot open-air pavilion structure. The building is assumed to include a standing seam metal roof, code-compliant LED lighting, mechanical ventilation, plumbing systems, and ADA-compliant restroom fixtures and accessories. The pavilion is assumed to include a standing seam metal roof supported by columns, lighting, ceiling fan, and a drinking fountain with bottle filler.
74Building Construction (1,190 SF) - CMU structure, slab, roof, interior buildout, plumbing, electrical, ventilation, drinking fountain1LS$ - 0$ - 0
75Pavilion Structure - Columns, standing seam metal roof, slab, lighting, fan, drinking fountain1LS$ - 0$ - 0
76Utility Tie-Ins - Water, sewer, electrical connections – assumed nearby1LS$ - 0$ - 0
77Site Preparation - Clearing, grading, building pad preparation1LS$ - 0$ - 0
78Signage - Wall mounted signage including ADA placards1LS$ - 0$ - 0
SUBTOTAL DIVISION 13 - SPECIAL CONSTRUCTION:$ - 0
DIVISION 31 - EARTHWORKS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
79Site Clearing - Clearing, grubbing, vegetation protection, stumping, stripping and stockpiling topsoil and rock, and disconnecting utilities. Includes removal of existing hardscape, irrigation and fencing1LS$ - 0$ - 0
80Erosion Control and NPDES - Includes silt fencing1LS$ - 0$ - 0
SUBTOTAL DIVISION 31 - EARTHWORKS:$ - 0
DIVISION 32 - EXTERIOR IMPROVEMENTS
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
816" PVC Conduits - Irrigation sleeves48LF$ - 0$ - 0
824" PVC Conduits- Irrigation sleeves48LF$ - 0$ - 0
83Planting Irrigation Retrofit - Includes Rerouting and Quick Connection Valves w/ Valve Box (includes repair and reactivation of Field #1 upon completion of construction)74,134SF$ - 0$ - 0
84Planting Irrigation New Installation - Includes irrigation control system, piping, valves, drip, bubbler, and sprinkler distribution (excludes field #1 irrigation intended to remain for re-use)18,976SF$ - 0$ - 0
85Soil Preparation (Performance Specification)- Avg. 6" depth in shrub beds for planting soils specified according to tesed performance requirements (particle size, organic matter percentage, pH, CEC, fertility, etc.), layered soil assemblies1,758CY$ - 0$ - 0
86Sod Areas - Seeded, sodded, plugged, and sprigged turf; pesticides, erosion-control materials, turf renovation, and grass paving. (Includes sod replacement of Field #1 upon completion of construction)93,109SF$ - 0$ - 0
87Plants - Canopy Tree - Nursery-grown trees and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates6EA$ - 0$ - 0
88Plants - Palm Tree - Nursery-grown trees and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates8EA$ - 0$ - 0
89Plants - Shrub / Groundcovers (Large) - Nursery-grown shrubs and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates36EA$ - 0$ - 0
90Plants - Shrub / Groundcovers (Small) - Nursery-grown shrubs and other plants, pesticides, tree stabilization, tree watering devices, landscape edgings, and tree grates180EA$ - 0$ - 0
91Plants - Mulch Rings - 4' dia mulch ring x 3" depth typical2CY$ - 0$ - 0
92Plants - Root Barrier - Deeproot UB24-2: 24" deep rigid panel root barrier157LF$ - 0$ - 0
93Mulch - 3" depth typical17CY$ - 0$ - 0
94#57 Stone - 4" depth washed #57 stone atop geotextile fabric - see landscape drawings377SF$ - 0$ - 0
SUBTOTAL DIVISION 32 - EXTERIOR IMPROVEMENTS:$ - 0
DIVISION 33 - UTILITIES
ITEM NO.DESCRIPTIONQTYUNITUNIT COSTTOTAL COST
95Connect/modifications to existing drainage structures - (1) 6-inch drainage pipe connection to serve bldg roof drain1EA$ - 0$ - 0
966" PVC Drainage Pipe and Fittings / Cleanout - Serving building roof drainage and sanitary sewer188LF$ - 0$ - 0
972" Potable water tie-in and stub out and valve - Serving restroom building50LF$ - 0$ - 0
SUBTOTAL DIVISION 33 - UTILITIES:$ - 0

PHASE 1B BASE BID TOTAL: $ - 0

PHASE 1A BASE BID + PHASE 1B BASE BID:$ - 0
PHASE 1A BASE BID + PHASE 1B BASE BID + ALT-1:$ - 0
PHASE 1A BASE BID + PHASE 1B BASE BID + ALT-2:$ - 0
PHASE 1A BASE BID + PHASE 1B BASE BID + ALT-1 + ALT-2:$ - 0

Staff has allocated $500,000.00 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.

File details come from the government source that posted it. Updated .