This document is a Summary of Work for the Big Creek Greenway Boardwalk Replacement Project, located in Forsyth County, Georgia. The project is divided into multiple phases and segments, focusing on replacing existing timber boardwalks with new timber-decked boardwalks supported by helical piles. The work spans several segments, including Fowler Park Connection, Mile Marker sections, and the Bethelview Trailhead area. Each segment involves reconstructing boardwalks using top-down construction methods to minimize ground disturbance, with total project lengths ranging from 0.140 to 1.401 miles. The project includes replacing approach slabs, reconstructing end bents, performing erosion repairs, and making various infrastructure improvements.
The Bethelview Trailhead component includes comprehensive site upgrades such as reconfiguring the parking lot with ADA-compliant spaces, installing new asphalt pavement, implementing drainage improvements with green infrastructure, and enhancing site accessibility. The project requires maintaining public access throughout construction and adhering to Georgia Environmental Protection Division, Georgia Soil and Water Conservation Commission standards, and Forsyth County construction guidelines. The contractor will be responsible for site restoration, utility coordination, and submitting as-built documentation. The scope of work emphasizes environmental protection, accessibility improvements, and infrastructure rehabilitation for the Big Creek Greenway trail system.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK
Phase 2&3, Segment 1 - Fowler Park Connection Length of Trail At Grade 0.010 Length of Boardwalk Replacement 0.130 Total Project Length 0.140
Summary of Work: This segment consists of the replacement of the existing timber boardwalk and timber support posts with a new timber-decked boardwalk supported by helical piles. Construction will be performed using top-down methods to minimize ground disturbance and protect the surrounding environment. The work includes the full reconstruction of the end bents to tie into the new boardwalk structure. Additionally, erosion repairs, as needed, will be completed along the shoulders adjacent to the boardwalk to restore stability and prevent future washouts.
Replace approximately 20’ approach slab into boardwalk to transition to wider boardwalk.
Phase 2&3, Segment 2 – Mile Marker 5.5 to 5.7 Length of Trail At Grade 0.081 Length of Boardwalk Replacement 0.134 Total Project Length 0.670
Summary of Work: This segment consists of the replacement of the existing timber boardwalk and timber support posts with a new timber-decked boardwalk supported by helical piles. Construction will be performed using top-down methods to minimize ground disturbance and protect the surrounding environment. The work includes the full reconstruction of the end bents to tie into the new boardwalk structure. Additionally, an existing boardwalk that was previously used for cattle crossing is to be removed and replaced with concrete trail on grade.
Phase 2&3, Segment 3 – Mile Marker 5.7 to 6.3 Length of Trail At Grade 0.015 Length of Boardwalk Replacement 0.257 Total Project Length 0.540
Summary of Work: This segment consists of the replacement of the existing timber boardwalk and timber support posts with a new timber-decked boardwalk supported by helical piles. Construction will be performed using top-down methods to minimize ground disturbance and protect the surrounding environment. The work includes the full reconstruction of the end bents to tie into the new boardwalk structure. Additionally, there is approximately 140’ of timber railing along the existing concrete trail that is to be replaced.
Replace approximately 20’ approach slab into boardwalk to transition to wider boardwalk.
Includes repair of settling bridge approach slabs (2 bridge locations).
Includes addition of drainage ditch at low point of field 100’ before mile marker 5.8.
Phase 2&3, Segment 4 – Miler Marker 6.3 to 6.8 Length of Trail At Grade 0.007 Length of Boardwalk Replacement 0.356 Total Project Length 0.553
Summary of Work: This segment consists of the replacement of the existing timber boardwalk and timber support posts with a new timber-decked boardwalk supported by helical piles. Construction will be performed using top-down methods to minimize ground disturbance and protect the surrounding environment. The work includes the full reconstruction of the end bents to tie into the new boardwalk structure. Additionally, erosion repairs, as needed, will be completed along the shoulders adjacent to the boardwalk to restore stability and prevent future washouts.
Phase 2&3, Segment 5 – Mile Marker 6.8 to Bethelview Trailhead Length of Trail At Grade 0.003 Length of Boardwalk Replacement 0.873 Total Project Length 1.401
Summary of Work: This project consists of the construction and improvement of the existing Bethelview Road Trailhead facility located at 5120 Bethelview Road in Forsyth County providing access to the Big Creek Greenway. The work will include grading, paving, drainage improvements, and associated site enhancements to upgrade the current trailhead infrastructure. A primary requirement of this project is that public access to the trailhead must remain open and operational throughout construction, requiring the contractor to phase work and coordinate access points to minimize disruption to trail users.
The scope of work includes the demolition and removal of existing asphalt within the designated parking area, followed by the installation of new asphalt pavement to accommodate a reconfigured and restriped parking layout. The improved parking lot will feature ADA-compliant parking spaces that connect to an ADA-accessible concrete ramp system, complete with metal railings and landing pads. Additional improvements include the installation of concrete wheel stops, new pavement striping, and updated regulatory signage, including the relocation of existing ADA signs and the addition of stop, turn, and wrong-way signs to improve traƯic circulation and overall safety. A new concrete slab with a thickened edge will be constructed adjacent to the existing maintenance building.
Comprehensive drainage upgrades will be implemented as part of the project. These include the construction of bioretention basins, enhanced dry swales, vegetated channels, trench drains, and a new network of PVC storm piping—both perforated and non-perforated. These green infrastructure components are designed to support stormwater infiltration, reduce surface runoƯ, and improve water quality. Engineered soil media, underdrain systems, riprap outlet protection, and other measures detailed in the construction documents will be used to ensure long-term drainage performance.
Additional work will include the relocation of existing fitness equipment to a newly designated fitness trail area, the installation of protective steel bollards, site landscaping, and implementation of erosion and sedimentation controls in accordance with the approved Stormwater Pollution Prevention Plan (SWPPP). All existing site features not designated for removal shall be preserved and protected. Construction must be performed in compliance with the Georgia Environmental Protection Division (EPD), Georgia Soil and Water Conservation Commission best management practices, and Forsyth County construction standards.
The contractor will be responsible for maintaining safe pedestrian and vehicular access throughout the life of the project. This includes managing traƯic flow, minimizing dust, securing the work zone, and coordinating utility protection and modifications as needed.
Upon completion, the contractor shall perform full site restoration, including the removal of debris, restoration of disturbed areas, and repair of any damaged infrastructure. As-built documentation for all completed work must be submitted as a condition of final acceptance.
Phase 4, Segment 1 – Bethelview Trailhead to Keithwood Drive Length of Trail At Grade 0.045 Length of Boardwalk Replacement 0.642 Total Project Length 1.283
Summary of Work: This segment consists of the replacement of the existing timber boardwalk and timber support posts with a new timber-decked boardwalk supported by helical piles. Construction will be performed using top-down methods to minimize ground disturbance and protect the surrounding environment. The work includes the full reconstruction of the end bents to tie into the new boardwalk structure.
Phase 4, Segment 2 – Keithwood Drive to Kelly Mill Road Length of Trail At Grade 0.046 Length of Boardwalk Replacement 0.231 Total Project Length 0.766
Summary of Work: Summary of Work: This segment consists of the replacement of the existing timber boardwalk and timber support posts with a new timber-decked boardwalk supported by helical piles. Construction will be performed using top-down methods to minimize ground disturbance and protect the surrounding environment. The work includes the full reconstruction of the end bents to tie into the new boardwalk structure.
Additionally, erosion repairs, as needed, will be completed along the shoulders adjacent to the boardwalk to restore stability and prevent future washouts. Work also includes replacement of a 36” cross pipe and raising the profile of a section of at-grade concrete trail to install a new cross pipe.
Bethelview Trailhead Summary of Work: This project consists of the construction and improvement of the existing Bethelview Road Trailhead facility located at 5120 Bethelview Road in Forsyth County providing access to the Big Creek Greenway. The work will include grading, paving, drainage improvements, and associated site enhancements to upgrade the current trailhead infrastructure. A primary requirement of this project is that public access to the trailhead must remain open and operational throughout construction, requiring the contractor to phase work and coordinate access points to minimize disruption to trail users.
The scope of work includes the demolition and removal of existing asphalt within the designated parking area, followed by the installation of new asphalt pavement to accommodate a reconfigured and restriped parking layout. The improved parking lot will feature ADA-compliant parking spaces that connect to an ADA-accessible concrete ramp system, complete with metal railings and landing pads. Additional improvements include the installation of concrete wheel stops, new pavement striping, and updated regulatory signage, including the relocation of existing ADA signs and the addition of stop, turn, and wrong-way signs to improve traƯic circulation and overall safety. A new concrete slab with a thickened edge will be constructed adjacent to the existing maintenance building.
Comprehensive drainage upgrades will be implemented as part of the project. These include the construction of bioretention basins, enhanced dry swales, vegetated channels, trench drains, and a new network of PVC storm piping—both perforated and non-perforated. These green infrastructure components are designed to support stormwater infiltration, reduce surface runoƯ, and improve water quality. Engineered soil media, underdrain systems, riprap outlet protection, and other measures detailed in the construction documents will be used to ensure long-term drainage performance.
Additional work will include the relocation of existing fitness equipment to a newly designated fitness trail area, the installation of protective steel bollards, site landscaping, and implementation of erosion and sedimentation controls in accordance with the approved Stormwater Pollution Prevention Plan (SWPPP). All existing site features not designated for removal shall be preserved and protected. Construction must be performed in compliance with the Georgia Environmental Protection Division (EPD), Georgia Soil and Water Conservation Commission best management practices, and Forsyth County construction standards.
The contractor will be responsible for maintaining safe pedestrian and vehicular access throughout the life of the project. This includes managing traƯic flow, minimizing dust, securing the work zone, and coordinating utility protection and modifications as needed.
Upon completion, the contractor shall perform full site restoration, including the removal of debris, restoration of disturbed areas, and repair of any damaged infrastructure. As-built documentation for all completed work must be submitted as a condition of final acceptance.