19-H. AGREEMENT.pdf

PDF 208 KB Posted

Attached to
FORT KING ROAD FROM HESTER ROAD TO NORTH OF COLEMAN AVENUE SIDEWALK
Solicitation number
IFB-KM-26-002
Issued by
Pasco County, Florida

About this file

This is a construction services agreement executed between Pasco County, Florida Board of County Commissioners and a contractor for the Fort King Road sidewalk project (Bid No. IFB-KM-26-002). The project encompasses construction of a six-foot sidewalk on the east side of Fort King Road from Hester Road to north of Coleman Avenue and a sidewalk on the west side from Morningside Drive to the south side of Pasco High School property. The work includes enhanced pedestrian crosswalks with pushbutton-activated rapid rectangular flashing beacons at the south side of Pasco High School and at the Coleman Avenue intersection, modifications to an existing culvert and headwall on the east side of Fort King Road between Dixie Avenue and Poinsettia Avenue, and construction of new guardrail with reduced post spacing. The initial contract time for completion is 240 calendar days from the Notice to Proceed, with an additional 90 calendar days allocated for allowance work performance.

The total contract price shall not exceed $95,000.00, which includes $100.00 for indemnification and $100.00 for termination for convenience provisions. Liquidated damages are set at $1,685.00 per diem for delays in meeting milestone dates or final completion. The contractor must furnish certificates of insurance and performance and payment bonds within ten days of award notification. Funding for the project is contingent upon the availability and appropriation of Pasco County funds by the Board of County Commissioners. The agreement incorporates all contract documents by reference, including general conditions, project-specific conditions, and all issued addendums. The contractor must comply with Title VII of the Civil Rights Act of 1964 and the Florida Civil Rights Act of 1992, and Title VI when federal grants are involved.

View the file

Other files

File Type Posted
13-F. BID PROPOSAL-OFFEROR FORM - EDITABLE 8-28-25.pdf PDF
23-C. GENERAL CONDITIONS.pdf PDF
8-E7. Appendix 4.pdf PDF
18-G5. REQUIRED DOCUMENTS FOR LAP PROJECTS - ONLY IF APPLICABLE.pdf PDF
4-E9. Appendix 7 cover.pdf PDF
1-A. ADVERTISEMENT PAGE.pdf PDF
29-E1. ROADWAY PLANS.pdf PDF
26-G1. REQUIRED BID BOND.pdf PDF
5-E5. Appendix 2 cover.pdf PDF
7-E4. Appendices Coversheet.pdf PDF
31-E3. Utility Coordination.pdf PDF
30-E4.2 Appendix 1 LAP agreement.pdf PDF
14-G3. REQUIRED CONFLICT OF INTEREST DISCLOSURE.pdf PDF
32-E8. Appendix 5 Cover.pdf PDF
22-E3.2 Geotechnical Report.pdf PDF
17-G2. REQUIRED FLORIDA TRENCH SAFETY ACT CERTIFICATION AND DISCLOSURE STATEMENT.pdf PDF
11-E6. Appendix 3.pdf PDF
3-E. PROJECT-SPECIFIC CONDITIONS Mar 2026-WK.pdf PDF
10-E4.1 Appendix 1 cover.pdf PDF
21-I. POST AWARD DOCUMENTS - LAP CONSTRUCTION.pdf PDF
9-E5.1 Appendix 2.pdf PDF
12-F1. FEDERAL PROVISIONS - CONSTRUCTION - IF NEEDED.pdf PDF
28-E8.2 Appendix 6.pdf PDF
24-E9.1 Appendix 7.pdf PDF
27-B. INSTRUCTIONS TO BIDDERS.pdf PDF
16-G4. REQUIRED CERTIFICATION OF UNDERSTANDING.pdf PDF
20-E3.3 Culvert Design Calculations.pdf PDF
6-D. SPECIAL CONDITIONS.pdf PDF
25-E3.1 Drainage Design Memorandum.pdf PDF
2-E2. ERP Approve 05.08.2025.pdf PDF
15-E8.1 Appendix 5.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AGREEMENT

THIS AGREEMENT is made and entered into by and between PASCO COUNTY, FLORIDA, by and through its Board of County Commissioners, hereinafter called COUNTY, and , hereinafter called the CONTRACTOR, whose business address is .

WITNESSETH THAT:

In consideration of the mutual covenants and provisions contained herein, the parties hereto agree as follows:

1. The CONTRACTOR shall provide to the COUNTY, within the Contract Time, all labor, materials, and appurtenances thereto per the requirements set forth in the Contract Documents for:

Solicitation Title:

Bid No.:

2. The CONTRACTOR shall complete the Work to be performed under this Agreement within calendar days (the initial Contract Time) from the date of the Notice to Proceed issued by the COUNTY.

3. In addition to the number of calendar days specified for the initial Contract Time in the preceding paragraph, calendar days have been included in the overall Contract Time for allocation to the CONTRACTOR for performance of Allowance Work in accordance with the Allowances provision of the Contract Documents.

4. Time is of the essence for this Agreement. Timely completion of the Work after the issuance of the aforesaid Notice to Proceed is of central importance to the COUNTY. This Project has certain various critical milestones to be met.

5. Liquidated damages shall apply to compensate for delays. The parties acknowledge and agree that the damages to the COUNTY associated with any delay in completion of the Project are not readily ascertainable as of the time of execution of this Agreement, and concur that the sum of $ ___ per diem, bears a reasonable relationship to the actual damages which the COUNTY would suffer as a consequence of any such delay in completion of the Work. The parties agree that such sums are reasonable and would not constitute a penalty against the CONTRACTOR. In arriving at these sums, consideration has been given to the loss to the public of the use of the Project due to delay, the additional administrative costs caused by any delay, higher labor and material costs associated with delay, risks associated with litigation from delay, and other factors. Failure to complete the Work by any Milestone Date(s) set forth in the agreed upon Work Schedule or in this Agreement, up to and including that for Final Completion, therefore, shall entitle the COUNTY to deduct these sums from the Contract Price for each day of delay in meeting each such Milestone Date. The amounts of Liquidated Damages for individual Milestone Dates are additive for each day of delay they are concurrently in effect.

6. This Agreement includes and incorporates by reference all Contract Documents, as the term

Contract Documents is defined within Article 1 of the General Conditions.

7. The total Contract Price for the full and complete performance by Contractor of all Work required by the Contract Documents shall not exceed $ , unless otherwise modified as provided herein. The total Contract Price includes $100.00 for Indemnification, $100.00 for termination for convenience, $ ___ for Allowance Work, and $___________ for Alternate No. _. Payment shall be made not more often than once per month and in accordance with the Contract Documents.

8. During the performance of this Agreement, the CONTRACTOR herein assures the COUNTY that said CONTRACTOR is in compliance with Title VII of the 1964 Civil Rights Act, as amended, and The Florida Civil Rights Act of 1992 in that the CONTRACTOR does not on the grounds of race, color, national origin, religion, sex, age, handicap or marital status, discriminate in any form or manner against the employees of the CONTRACTOR or its applicants for employment. The CONTRACTOR understands and agrees that this Agreement is conditioned upon the veracity of this Statement of Assurance. Furthermore, the CONTRACTOR herein assures the COUNTY that said CONTRACTOR shall comply with Title VI of the Civil Rights Act of 1964 when any Federal grant is involved. Other applicable Federal and State laws, executive orders and regulations prohibiting the type of discrimination as hereinabove delineated are included by this reference thereto. This Statement of Assurance shall be interpreted to include Vietnam Era Veterans and Disabled Veterans within its protective range of applicability.

9. The CONTRACTOR shall furnish to the COUNTY (when and in the manner required by the

Contract Documents) all appropriate Certificates of Insurance, and a Performance Bond and/or Payment Bond for the Contract Price within ten (10) days following Notification of Award.

10. The COUNTY and the CONTRACTOR acknowledge the acceptance from the Bid Proposal of the following Alternate(s).

No. No. No. No.

No. No. No. No.

The COUNTY and the CONTRACTOR acknowledge that the corresponding price as shown in the

Bid Proposal for each accepted Alternate is incorporated in the amount of compensation specified in paragraph 7 above.

11. The COUNTY and the CONTRACTOR acknowledge that all addendums issued with respect to this

Project are herein incorporated into the list of Contract Documents listed in Article 1 of the General Conditions.

12. The funding required for this Project is contingent upon the availability of County funds and the appropriation of such funds by the Board of County Commissioners.

13. This Agreement and any changes hereto shall constitute the entire agreement between

CONTRACTOR and COUNTY relating to Work. This Agreement supersedes all previous or contemporary representations or warranties of COUNTY or CONTRACTOR not set forth or referenced in the Contract Documents.

14. Except as specifically provided herein, no modification, waiver, termination, rescission, discharge, or cancellation of this Agreement, or of any term thereof, shall be binding on the COUNTY unless in writing and executed by the Board of County Commissioners.

15. Waiver by the COUNTY of a breach of any provision of this Agreement by the CONTRACTOR shall not be deemed to be a waiver or any other breach and shall not be construed to be a modification of the terms of this Agreement.

16. No modification, waiver, termination, discharge, or cancellation of the Agreement or of any terms thereof shall impair the rights of the COUNTY with respect to any liabilities, whether or not liquidated, of the CONTRACTOR to the COUNTY theretofore accrued.

17. The duties and obligations imposed upon the CONTRACTOR by this Agreement and the rights and remedies available hereunder, shall be in addition, and not limited, to any otherwise imposed or available in law or in equity, whether by statute, special guarantee, or otherwise.

18. The CONTRACTOR shall at all times remain an independent contractor and shall have no power, nor shall the CONTRACTOR represent that the CONTRACTOR has any power, to bind COUNTY or to assume or to create any obligation expressed or implied on behalf of the COUNTY.

19. This Agreement shall be binding upon, and its benefits and advantages shall inure to the heirs, personal representatives, successors and assigns of the parties hereto.

20. The parties agree that if any part, term, or provision of this Agreement is held to be illegal, unenforceable or in conflict with any applicable federal, state or local law or regulation, such part, term or provision shall be severable with the remainder of the Agreement remaining valid and enforceable.

IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the last day written below (bid award date for the Project subject thereto).

ATTEST BOARD OF COUNTY COMMISSIONERS OF

PASCO COUNTY, FLORIDA

By:_________________________ By:

Nikki Alvarez-Sowles, Esq. Chairman Clerk & Comptroller

Date: , 20

CONTRACTOR:

(NAME OF COMPANY)

BY:

(SIGNATURE)

(PRINTED NAME)

(TITLE OF SIGNER)

NOTARY ACKNOWLEDGMENT

STATE OF }

} ss

COUNTY OF }

The foregoing instrument was acknowledged before me on ________________, 20_____, by means of:

[___] physical presence, or [___] online notarization by:

[as applicable, complete one (1) of the four (4) choices below]:

(1) FOR A CORPORATION OR LIMITED LIABILITY COMPANY:

[Name] , who executed the foregoing instrument as [Title] ____ of [Corporation or Company Name] , a:

[___] corporation, or [___] limited liability company organized under the laws of [State] __ ,

(2) FOR AN INDIVIDUAL ACTING IN HIS OR HER OWN RIGHT:

[Name] _____________________________________________________________.

(3) FOR A PARTNERSHIP:

[Name] ________________Partner (or Agent), on behalf of [Name of Partnership] , a [State] partnership.

(4) FOR AN INDIVIDUAL ACTING AS PRINCIPAL BY AN ATTORNEY IN FACT:

[Name] , as attorney in fact.

Said person is (check one below):

[___] Personally known to me, or [___] Has produced as identification.

Signature of person taking acknowledgment

[Notary Stamp or Seal] Print Notary’s Name (This line is required to be completed by §117.05, F.S.)

hereinafter called the CONTRACTOR:
whose business address is:
Solicitation Title: FORT KING ROAD FROM HESTER TO NORTH OF COLEMAN AVENUE SIDEWALK
Bid No: IFB-KM-26-002
calendar days the initial Contract Time from the date of the Notice to Proceed: 240
paragraph: 90
required by the Contract Documents shall not exceed:
No: N/A
No_2:
No_3:
No_4:
No_5:
No_6:
No_7:
No_8:
NAME OF COMPANY:
PRINTED NAME:
The foregoing instrument was acknowledged before me on:
20_2:
Name:
of Corporation or Company Name:
Name_2:
Partner or Agent on behalf of Name of Partnership:
Name_3:
a State:
Name_4:
Has produced:
Print Notarys Name:
Text1: 1685.00
Text2: 95,000.00
Text3: N/A
Text4: N/A
Text5:
Text6:
Check Box7: Off
Check Box8: Off
Text9:
Text10:
Check Box11: Off
Check Box12: Off
Text13:
Check Box14: Off
Check Box15: Off

File details come from the government source that posted it. Updated .