File Type Posted
Solicitation Amendment FA255021R00030003 SF 30.pdf PDF
RFIs_2_PAINTING IDIQ.pdf PDF
B30 Task Order_Revised_Amendment 0002.pdf PDF
Solicitation Amendment FA255021R00030002 SF 30.pdf PDF
B120 Task Order_Revised_Amendment 0002.pdf PDF
RFIs_PAINTING IDIQ.pdf PDF
Amendment 0001 FA255021R00030001.pdf PDF
14- Bldg 30 Task Order_Floor Plan_Sizing.pdf PDF
15- Bldg 120 Task Order_Floor Plan_Sizing.pdf PDF
16- Section L and M.pdf PDF
Solicitation - FA255021R0003.pdf PDF
9- Facility Excellence Plan.pdf PDF
6- Design Guide_Final.docx DOCX document
8- SAFB Overreaching Environmental.rtf RTF text file
12- Liquidated Damages Painting IDIQ.pdf PDF
10- Security Requirements.docx DOCX document
4- Safety Requirements.docx DOCX document
3- Environmental Requirements.docx DOCX document
2- Schriever Paint Schemes.pptx PPTX presentation
5- Installation Facility Standards.pdf PDF
11- Wage Determination CO20200022_30 Oct20.pdf PDF
7- SAFB Environmental Supplement - 2020MAR_Final.docx DOCX document
1 -MFPR IDIQ SOW_14AUG20.docx DOCX document
13- Submittal Register AF Form 66.xlsx XLSX spreadsheet
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submission Req for Proposal

TITLEHARD COPIESPAGE MAXIMUMDVDs
Volume I - Executed Contract Documentation and Price ProposalOriginal and

one (1) copy

No page limitation1
Volume II - Technical ProposalOriginal and

one (1) copy 10 pages 1

Factor 1- Technical

Table 1. Technical Acceptable/Unacceptable Rating Method
Adjectival RatingDescription
AcceptableThe proposal acceptably meets specified requirements of the solicitation.
UnacceptableThe proposal does not meet specified requirements of the solicitation

Base Coefficient Worksheet

Insert the proposed coefficient in Section B for each coefficient including the option periods. Limit coefficient to four (4) decimal places. The offeror’s price proposal shall contain downward-sloping pricing for the total weighted average coefficient for each option period. Downward-sloping pricing must be reflected by the fourth decimal place (see example below). Offers which do not comply with this requirement shall be considered non-responsive and not eligible for award. Include the coefficient worksheet.
Standard Hours-Secured Area (Order $750,000 and Below)43%
Standard Hours-Secured Area (Order Above $750,000)1%
Standard Hours-Non-Secured Area (Order $750,000 and Below)49%
Standard Hours-Non-Secured Area (Order Above $750,000)1%
Non-Standard Hours-Secured Area (Order $750,000 and Below)3%
Non-Standard Hours-Secured Area (Order Above $750,000)1%
Non-Standard Hours-Non-Secured Area (Order $750,000 and Below)1%
Non-Standard Hours-Non-Secured Area (Order Above $750,000)1%
Total:100%
COEFFICIENT SCHEDULE B
Base Period: DATE OF AWARD, THROUGH 28 FEBRUARY 2024
B0001 Standard Hours-Secured Area (Order $750,000 and Below)______________
B0002 Standard Hours-Secured Area (Order Above $750,000)______________
B0003 Standard Hours-Non-Secured Area (Order $750,000 and Below)______________
B0004 Standard Hours-Non-Secured Area (Order Above $750,000)______________
B0005 Non-Standard Hours-Secured Area (Order $750,000 and Below)______________
B0006 Non-Standard Hours-Secured Area (Order Above $750,000)______________
B0007 Non-Standard Hours-Non-Secured Area (Order $750,000 and Below)______________
B0008 Non-Standard Hours-Non-Secured Area (Order Above $750,000)______________

Option Pd 1 Worksheet Option Period One:

B0009 Standard Hours-Secured Area (Order $750,000 and Below)______________
B0010 Standard Hours-Secured Area (Order Above $750,000)______________
B0011 Standard Hours-Non-Secured Area (Order $750,000 and Below)______________
B0012 Standard Hours-Non-Secured Area (Order Above $750,000)______________
B0013 Non-Standard Hours-Secured Area (Order $750,000 and Below)______________
B0014 Non-Standard Hours-Secured Area (Order Above $750,000)______________
B0015 Non-Standard Hours-Non-Secured Area (Order $750,000 and Below)______________
B0016 Non-Standard Hours-Non-Secured Area (Order Above $750,000)______________

Option Pd 2 Worksheet Option Period Two:

B0017 Standard Hours-Secured Area (Order $750,000 and Below)______________
B0018 Standard Hours-Secured Area (Order Above $750,000)______________
B0019 Standard Hours-Non-Secured Area (Order $750,000 and Below)______________
B0020 Standard Hours-Non-Secured Area (Order Above $750,000)______________
B0021 Non-Standard Hours-Secured Area (Order $750,000 and Below)______________
B0022 Non-Standard Hours-Secured Area (Order Above $750,000)______________
B0023 Non-Standard Hours-Non-Secured Area (Order $750,000 and Below)______________
B0024 Non-Standard Hours-Non-Secured Area (Order Above $750,000)______________

EXAMPLE- Coefficient Worksheet

The following is an EXMAPLE of the evaluation for the base period:
Schriever AFB (Base Year)Anticipated Work %Proposed Coeff.Weighted Coeff.
Standard Hours-Secured Area (Order $750,000 and Below)43%1.270.5461
Standard Hours-Secured Area (Order Above $750,000)1%1.250.0125
Standard Hours-Non-Secured Area (Order $750,000 and Below)49%1.170.5733
Standard Hours-Non-Secured Area (Order Above $750,000)1%1.150.0115
Non-Standard Hours-Secured Area (Order $750,000 and Below)3%1.320.0396
Non-Standard Hours-Secured Area (Order Above $750,000)1%1.30.013
Non-Standard Hours-Non-Secured Area (Order $750,000 and Below)1%1.220.0122
Non-Standard Hours-Non-Secured Area (Order Above $750,000)1%1.20.012
SUBTOTAL100%1.2202
Below is an example of downward sloping coefficients based on the calculated coefficient.
Base Period1.2202
Option Period 11.2201
Option Period 21.22
TOTAL3.6603

Total (Base Year plus Option Period, used for proposal evaluation) 3.6603/3 Ordering Periods = 1.2201

1.2201 x $5,000,000.00 = $6,100,500.00 as the Total Evaluated Price (TEP)