12- Liquidated Damages Painting IDIQ.pdf

PDF 255 KB Posted

Attached to
Amendment 3 Multi Facility Schriever AFB Painting IDIQ Federal contract opportunity
Solicitation number
FA255021R0003
Issued by
Department of the Air Force Space Command

View the file

Other files for this federal contract opportunity

Other files attached to Amendment 3 Multi Facility Schriever AFB Painting IDIQ, newest first.
File Type Posted
Solicitation Amendment FA255021R00030003 SF 30.pdf PDF
RFIs_2_PAINTING IDIQ.pdf PDF
B30 Task Order_Revised_Amendment 0002.pdf PDF
Solicitation Amendment FA255021R00030002 SF 30.pdf PDF
B120 Task Order_Revised_Amendment 0002.pdf PDF
RFIs_PAINTING IDIQ.pdf PDF
Amendment 0001 FA255021R00030001.pdf PDF
14- Bldg 30 Task Order_Floor Plan_Sizing.pdf PDF
15- Bldg 120 Task Order_Floor Plan_Sizing.pdf PDF
16- Section L and M.pdf PDF
Solicitation - FA255021R0003.pdf PDF
9- Facility Excellence Plan.pdf PDF
6- Design Guide_Final.docx DOCX document
8- SAFB Overreaching Environmental.rtf RTF text file
10- Security Requirements.docx DOCX document
4- Safety Requirements.docx DOCX document
3- Environmental Requirements.docx DOCX document
5- Installation Facility Standards.pdf PDF
11- Wage Determination CO20200022_30 Oct20.pdf PDF
7- SAFB Environmental Supplement - 2020MAR_Final.docx DOCX document
1 -MFPR IDIQ SOW_14AUG20.docx DOCX document
17- Tables for RFP.xlsx XLSX spreadsheet
13- Submittal Register AF Form 66.xlsx XLSX spreadsheet
2- Schriever Paint Schemes.pptx PPTX presentation
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

UNITED STATES SPACE FORCE

50TH SPACE WING

12 November 2020

MEMORANDUM FOR RECORD

SUBJECT: Liquidated Damages for FA2550-21-R-0003 SAFB Painting IDIQ

1. The purpose of this memorandum is to document the need and the daily rate of liquidated damages incorporated on this contract.

2. In accordance with (IAW) FAR 11.501(a), the Contracting Officer has considered the potential impacts on this solicitation and contract, and the Government would likely suffer damage if the performance is delinquent.

3. Furthermore, DFARS 211.503 prescribes the use of FAR 52.211-12, Liquidated Damages –

Construction “in all construction contracts exceeding $700,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work.” This is not a cost-plus-fixed-fee contract and the contractor can control the pace of work. This contract is expected to exceed $700,000.

4. Therefore, liquidated damages are included and shall be assessed for delinquent performance on a case-by-case basis for each task order.

5. These liquidated damages were formulated IAW FAR 36.206 and FAR 11.502 Procedures, which FAR 36.206 refers to.

6. These will be assessed against the contractor for each day beyond the completion date set in the Period of Performance taken to complete the project, when such day/s are not excused under FAR 52.249-14 or 52.249-10.

7. These calculations were made using Air Force Instruction 65-503 and the associated table for

Civilian Base Pay, table A31-1, dated 16 October 2019 as accessed on 19 June 2020.

8. The calculations for the daily rate of damages for this contract, at a minimum, are:

a. Civil Engineering personnel:

Project Management Supervisor GS-13 1 hr/day at $82.90/hr = $82.90 Project Manager GS-12 1 hr/day at $68.10/hr = $68.10 Construction Inspector GS-11 2 hr/day at $56.95/hr = $113.90

b. Contracting personnel:

Construction Flight Chief GS-13 1 hr/day at $82.90/hr = $82.90 Contracting Officer GS-13 1 hr/day at $54.78/hr = $54.78 Contract Specialist GS-09 2 hr/day at $47.00/hr = $94.00 Policy Review Analyst GS-13 0.25 hr/day at $82.90/hr = $20.73

c. Legal personnel:

Attorney GS-13 0.25 hr/day at $82.90/hr = $20.73

d. Other expected expenses associated with delayed completion IAW FAR 11.502(b)

None identified at this time.

9. Therefore, the rate of liquidated damages assessed per day of delay is $538.04.

10. If there are any questions or concerns about this memorandum, please contact the undersigned at (719) 567-3456 or jan.mangubat@spaceforce.mil.

JAN A. MANGUBAT

Contracting Officer

2020-11-12T09:40:03-0700