Attachment J-2

View the file

Other files for this federal contract opportunity

Other files attached to Building 14 and Building 53A Renovation, newest first.
File Type Posted
amendment_7.pdf PDF
Attachment_2_23_08_00_-_Commissioning_Of_HVAC_Systems_53A.pdf PDF
Amendment_6.pdf PDF
Attachment_1_23_08_00_-_Commissioning_Of_HVAC_Systems_bldg_14.pdf PDF
Attachment_2-_Revised_drawing_MH101_in_attachment_J-3_of_solicitation.pdf PDF
Attachment_3-_architectural_revisions.pdf PDF
amendment_5.pdf PDF
Attachment_1_site_visit_list.pdf PDF
amendment_4.pdf PDF
Attachment_J-10.pdf PDF
Amendment_3.pdf PDF
Amendment_2.pdf PDF
Attachment_1.pdf PDF
Amendment_1.pdf PDF
15-223-SOL-00107.pdf PDF
Attachment_J-6_Bldg_53A__Air_Handlers_ _2nd_Floor_Offices__TME_Specs.pdf PDF
Attachment_J-6_Bldg_53A__Air_Handlers_ _2nd_Floor_Offices__Stuck_Specs.pdf PDF
Attachment_J-9_Wage_Decision.pdf PDF
Attachment_J-8_bldg_53A_chiller_2_replacement.pdf PDF
Attachment_J-3_(1_of_3).pdf PDF
Attachment_J-3_(2_of_3).pdf PDF
Attachment_J-1_(3_of_4).pdf PDF
Attachment_J-1_(4_of_4).pdf PDF
Attachment_J-3_(3_of_3).pdf PDF
Attachment_J-1_(2_of_4).pdf PDF
Attachment_J-10_FDA_Form_3391.pdf PDF
Attachment_J-5_(_2_of_3)_Building_53A_Replace_Air_Handlers_ _2nd_Floor_Offices.pdf PDF
Attachment_J-5_(_3_of_3)_Building_53A_Replace_Air_Handlers_ _2nd_Floor_Offices.pdf PDF
Attachment_J-7_Building_53_Chiller_Replacement.pdf PDF
Attachment_J-1_(1_of_4).pdf PDF
Attachment_J-12_SAMPLE_CLIENT__LETTER.doc DOC document
Attachment_J-5_(_1_of_3)_Building_53A_Replace_Air_Handlers_ _2nd_Floor_Offices.pdf PDF
Attachment_J-11_FDA_Form_3398.pdf PDF
Attachment_J-4_Bldg_53A__Renovate_Animal_Rms__Labs__Specs.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

cromwell architects engineers, inc.

101 s. spring street, little rock, arkansas 72201-2490 t: 501-372-2900 f: 501-372-0482 www.cromwell.com cromwell@cromwell.com

PROJECT MANUAL

for

NCTR-BUILDING 14

RENOVATION

Jefferson, Arkansas

Architect Engineer Project No. 2015-056

July 15, 2015

This page was intentionally left blank for duplex printing.

NCTR-Building 14 Renovation 2015-056 Jefferson, Arkansas July 2015

CERTIFICATIONS

00 01 05 - 1

SECTION 00 01 05

CERTIFICATIONS

I hereby certify that the architectural portions of work included in these plans and specifications, except as otherwise indicated by other registered professionals, have been prepared by me or under my direct supervision, and that I have coordinated the architectural portions with those portions sealed by other registered professionals. I further certify that to the best of my knowledge this portion of the plans and specifications are as required by law and in compliance with the International Building Code 2012.

Greg B. Cockmon, AIA, Architect Principal

CROMWELL ARCHITECTS

ENGINEERS, INC.

Architects Engineers 101 S. Spring Street Little Rock, Arkansas

Date

I hereby certify that the civil portions of work included in these plans and specifications, except as otherwise indicated, have been prepared by me, or under my direct supervision.

Scott Martin, PE Civil Engineer

CROMWELL ARCHITECTS

ENGINEERS, INC.

Architects Engineers 101 S. Spring Street Little Rock, Arkansas

I hereby certify that the structural portions of work included in these plans and specifications, except as otherwise indicated, have been prepared by me, or under my direct supervision. I further certify that to the best of my knowledge this portion of the plans and specifications are as required by law and in compliance with the the International Building Code 2012. I further certify that to the best of my knowledge the structural elements are designed as required by law and in compliance with the requirements of Arkansas Earthquake Resistant Design for Public Structures (ASA 12-80-101 et seq.) for and the latest edition of the International Building Code with revisions.

Anthony G Jacuzzi, PE Structural Engineer

CROMWELL ARCHITECTS

ENGINEERS, INC.

Architects Engineers

CERTIFICATIONS

00 01 05 - 2

I hereby certify that the mechanical portions of work included in these plans and specifications, except as otherwise indicated, have been prepared by me, or under my direct supervision. I further certify that to the best of my knowledge this portion of the plans and specifications are as required by law and in compliance with the International Building Code 2012.

Maxwell A Good, PE Mechanical Engineer

CROMWELL ARCHITECTS

ENGINEERS, INC.

Architects Engineers

I hereby certify that the electrical portions of work included in these plans and specifications, except as otherwise indicated, have been prepared by me, or under my direct supervision. I further certify that to the best of my knowledge this portion of the plans and specifications are as required by law and in compliance with the International Building Code 2012.

Allan Fuller, PE Electrical Engineer

CROMWELL ARCHITECTS

ENGINEERS, INC.

Architects Engineers

TABLE OF CONTENTS

00 01 10 - 1

SECTION 00 01 10

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 05 - Certifications 00 01 10 - Table of Contents

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01 10 00 - Summary 01 20 00 - Price and Payment Procedures 01 30 00 - Administrative Requirements 01 32 16 - Construction Progress Schedule 01 33 00 - Submittal Procedures 01 35 14.01 - LEED-NC 2009 Credit Summary

LEED Project Checklist 01 35 15 - LEED Certification Procedures 01 35 16 - LEED Submittal Forms

01 35 16.01 - LEED Material Cost Summary Form 01 35 16.02 - LEED Wood-Containing Product List 01 35 16.03 - LEED Metal-Containing Product List 01 35 16.04 - LEED New Product Content Form 01 35 16.05 - LEED New Product Source Form 01 35 16.06 - LEED Reused Product Form 01 35 16.07 - LEED Prohibited Content Installer Certification

01 40 00 - Quality Requirements 01 42 16 - Definitions 01 45 33 - Special Inspections

Statement of Special Inspections Statement of SI Requirements for Seismic Resistance Schedule of Special Inspections Final Report of Special Inspections Contractor Statement of Responsibility Fabricator Certificate of Compliance Minimum Qualifications Table Special Inspection Daily Report Special Inspection Discrepancy Notice

01 50 00 - Temporary Facilities and Controls 01 51 00 - Temporary Utilities 01 57 13 - Temporary Erosion and Sediment Control 01 57 21 - Indoor Air Quality Controls 01 60 00 - Product Requirements 01 60 01 - Substitution Request Form 01 61 16 - Volatile Organic Compound (VOC) Content Restrictions

01 61 16.01 - Accessory Material VOC Content Certification Form

00 01 10 - 2

01 70 00 - Execution and Closeout Requirements 01 74 19 - Construction Waste Management and Disposal 01 78 00 - Closeout Submittals 01 79 00 - Demonstration and Training 01 91 13 - General Commissioning Requirements

DIVISION 02 -- EXISTING CONDITIONS

02 41 00 - Demolition

DIVISION 03 -- CONCRETE

03 20 00 - Concrete Reinforcing 03 30 00 - Cast-in-Place Concrete 03 35 43 - Polished Concrete Finishing

DIVISION 04 -- MASONRY

04 20 00 - Unit Masonry

DIVISION 05 -- METALS

05 12 00 - Structural Steel Framing 05 31 00 - Steel Decking 05 40 00 - Cold-Formed Metal Framing 05 44 00 - Cold-Formed Metal Trusses 05 50 00 - Metal Fabrications 05 51 00 - Metal Stairs 05 52 13 - Pipe and Tube Railings

DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

06 10 00 - Rough Carpentry 06 11 40 - Wood Blocking and Curbing 06 20 00 - Finish Carpentry

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07 01 50.19 - Preparation for Re-Roofing 07 19 00 - Water Repellents 07 21 00 - Thermal Insulation 07 25 00 - Weather Barriers 07 25 20 - Air Barrier Window And Door Perimeter Sealing 07 41 13 - Preformed Metal Roof Panels 07 42 64 - Metal Composite Material Wall Panels 07 56 01 - Acrylic Liquid Applied Wall System 07 56 02 - Modified Silane Liquid Applied Roof Membrane System 07 56 03 - Acrylic Liquid Applied Roof Membrane System 07 62 00 - Sheet Metal Flashing and Trim 07 84 00 - Firestopping 07 90 05 - Joint Sealers 07 95 13 - Expansion Joint Cover Assemblies

00 01 10 - 3

DIVISION 08 -- OPENINGS

08 11 13 - Hollow Metal Doors and Frames 08 14 16 - Flush Wood Doors 08 31 00 - Access Doors and Panels 08 43 13 - Aluminum-Framed Storefronts 08 44 13 - Glazed Aluminum Curtain Walls 08 71 00 - Door Hardware 08 80 00 - Glazing 08 83 00 - Mirrors

DIVISION 09 -- FINISHES

09 05 61 - Common Work Results for Flooring Preparation 09 21 16 - Gypsum Board Assemblies 09 30 00 - Tiling 09 51 00 - Acoustical Ceilings 09 65 00 - Resilient Flooring 09 67 00 - Fluid-Applied Walls and Flooring 09 68 13 - Tile Carpeting 09 84 53 - Sound Barrier Mullion Trim Cap 09 90 00 - Painting and Coating 09 98 50 - Sprayed Encapsulant Coating

DIVISION 10 -- SPECIALTIES

10 11 01 - Visual Display Boards 10 14 00 - Interior Signage 10 21 13.19 - Plastic Toilet Compartments 10 26 01 - Wall and Corner Guards 10 44 00 - Fire Extinguishers, Cabinets and Accessories 10 73 00 - Protective Covers

DIVISION 11 -- EQUIPMENT

11 53 00 - Laboratory Service Fittings, Fixtures and Accessories 11 70 50 - Miscellaneous Laboratory Equipment General Purpose Fume Hoods and Accessories

DIVISION 12 -- FURNISHINGS

12 24 13 - Roller Window Shades 12 31 10 - Manufactured Casework

Casewook Cutsheets 12 35 53.19 - Wood Laboratory Casework 12 36 00 - Countertops 12 48 13 - Entrance Floor Mats and Frames 12 51 00 - Furniture Components

Furniture Cutsheets 12 56 50 - Laboratory Furniture System 12 93 13 - Bicycle Racks

00 01 10 - 4

DIVISIONS 13 - 20 -- (NOT USED)

DIVISION 21 -- FIRE SUPPRESSION

21 05 00 - Common Work Results for Fire Suppression 21 05 23 - General-Duty Valves for Water-Based Fire-Suppression Piping 21 05 48 - Fire Suppression Vibration Isolation And Seismic Restraint 21 05 53 - Identification for Fire Suppression Piping and Equipment 21 13 00 - Fire-Suppression Sprinkler Systems

DIVISION 22 -- PLUMBING

22 05 16 - Expansion Fittings and Loops for Plumbing Piping 22 05 19 - Meters and Gages for Plumbing Piping 22 05 48 - Plumbing Vibrations Isolation And Seismic Restraint 22 05 53 - Identification for Plumbing Piping and Equipment 22 07 19 - Plumbing Piping Insulation 22 10 05 - Plumbing Piping 22 10 06 - Plumbing Piping Specialties 22 15 00 - General-Service Compressed-Air Systems 22 30 00 - Plumbing Equipment 22 40 00 - Plumbing Fixtures 22 60 05 - High Purity Dionized Water Piping 22 60 06 - Process Laboratory Piping Systems

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 00 10 - Basic Mechanical Requirements 23 05 11 - Equipment, Motor Equipment And Filter Information 23 05 16 - Expansion Fittings and Loops for HVAC Piping 23 05 48 - Vibration and Seismic Controls for HVAC Piping and Equipment 23 05 53 - Mechanical Identification 23 05 93 - Testing, Adjusting, and Balancing for HVAC 23 07 13 - Duct Insulation 23 07 19 - HVAC Piping Insulation 23 08 00 - Commissioning of HVAC 23 08 60 - Heat Recovery Air Handling System 23 08 62 - AHU UV Lights 23 09 23 - BACnet Direct-Digital Control System for HVAC 23 21 13 - Hydronic Piping 23 21 14 - Hydronic Specialties 23 21 23 - Hydronic Pumps 23 22 13 - Steam and Condensate Heating Piping 23 23 00 - Refrigerant Piping 23 31 00 - HVAC Ducts and Casings 23 33 00 - Air Duct Accessories 23 36 00 - Air Terminal Units 23 37 00 - Air Outlets and Inlets

00 01 10 - 5

23 81 29 - Variable Refrigerant Volume (VRV) HVAC System

DIVISIONS 24 - 25 -- (NOT USED)

DIVISION 26 -- ELECTRICAL

26 05 01 - Minor Electrical Demolition 26 05 13 - Medium-Voltage Cables 26 05 19 - Low-Voltage Electrical Power Conductors and Cables 26 05 26 - Grounding and Bonding for Electrical Systems 26 05 29 - Hangers and Supports for Electrical Systems 26 05 34 - Conduit 26 05 35 - Surface Raceways 26 05 36 - Cable Trays for Electrical Systems 26 05 37 - Boxes 26 05 53 - Identification for Electrical Systems 26 05 73 - Overcurrent Protective Device Coordination Study 26 08 00 - Commissioning Of Electrical Systems 26 09 23 - Lighting Control Devices 26 12 00 - Medium-Voltage Transformers 26 22 00 - Low-Voltage Transformers 26 24 13 - Switchboards 26 24 16 - Panelboards 26 27 16 - Cabinets and Enclosures 26 27 26 - Wiring Devices 26 28 13 - Fuses 26 28 17 - Enclosed Circuit Breakers 26 28 18 - Enclosed Switches 26 32 13 - Engine Generators 26 36 00 - Transfer Switches 26 43 00 - Surge Protective Devices 26 51 00 - Interior Lighting 26 56 00 - Exterior Lighting

DIVISION 27 -- COMMUNICATIONS

27 10 05 - Structured Cabling for Voice and Data - Inside-Plant

Special Requirements for NCTR Campus Cabling

DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

28 31 00 - Fire Detection and Alarm

DIVISIONS 29 - 30 -- (NOT USED)

DIVISION 31 -- EARTHWORK

Soil and Foundation Investigation 31 10 00 - Site Clearing 31 22 00 - Grading 31 23 16 - Excavation 31 23 16.13 - Trenching

00 01 10 - 6

31 23 23 - Fill 31 31 16 - Termite Control

DIVISION 32 -- EXTERIOR IMPROVEMENTS

32 12 16 - Asphalt Paving 32 13 13 - Concrete Paving 32 92 23 - Sodding

DIVISION 33 -- UTILITIES

33 05 13 - Manholes and Structures 33 11 16 - Site Water Utility Distribution Piping 33 13 00 - Disinfecting of Water Utility Distribution 33 31 11 - Site Sanitary Utility Sewerage Piping 33 41 11 - Site Storm Utility Drainage Piping

DIVISIONS 34 - 49 -- (NOT USED)

END OF SECTION

SUMMARY

01 10 00 - 1

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: Building 14 Renovation.

B. Government's Name: National Center for Toxilogical Research.

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price.

1.03 OWNER OCCUPANCY

A. Government intends to continue to occupy adjacent portions of the existing building during the entire construction period.

B. Government intends to occupy the Project upon Substantial Completion.

C. Cooperate with Government to minimize conflict and to facilitate Government's operations.

D. Schedule the Work to accommodate Government occupancy.

1.04 CONTRACTOR USE OF SITE AND PREMISES

A. Conform to the following "Procedure for Attaining Clearance to the Nonhuman Primate Facility."

B. Construction Operations: Limited to areas noted on Drawings.

C. Arrange use of site and premises to allow:

1. Government occupancy.

2. Work by Others.

3. Work by Government.

D. Provide access to and from site as required by law and by Government:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

E. Utility Outages and Shutdown:

1. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire alarm system, without 7 days notice to Government and authorities having jurisdiction.

2. Limit shutdown of utility services to two hours at a time, arranged at least 24 hours in advance with Government.

3. Prevent accidental disruption of utility services to other facilities.

1.05 WORK SEQUENCE

A. Contractor to provide a detailed schedule showing starting and completion date of all phases and the major item of work in each phase. Comply with requirements of Sections 01 32 16 - Construction Progress Schedule.

B. Coordinate construction schedule and operations with Government's Representative.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

PRICE AND PAYMENT PROCEDURES

01 20 00 - 1

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

D. Correlation of Contractor submittals based on changes.

E. Procedures for preparation and submittal of application for final payment.

1.02 SCHEDULE OF VALUES

A. Form to be used: AIA G703, or approved equivalent.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Government's Representative for approval.

C. Forms filled out by hand will not be accepted.

D. Submit Schedule of Values in duplicate within 20 days after date of Owner-Contractor

Agreement.

E. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification Section. Identify site mobilization and bonds and insurance.

F. Include in each line item, the amount of Allowances specified in this section. For unit cost

Allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

G. Include separately from each line item, a direct proportional amount of Contractor's overhead and profit.

H. Revise schedule to list approved Change Orders, with each Application For Payment.

1.03 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Form to be used: Use forms provided by Contracting Officer.

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Government's Representative for approval.

D. Forms filled out by hand will not be accepted.

E. For each item, provide a column for listing each of the following:

1. Item Number.

2. Description of work.

3. Scheduled Values.

4. Previous Applications.

5. Work in Place and Stored Materials under this Application.

6. Authorized Change Orders.

7. Total Completed and Stored to Date of Application.

8. Percentage of Completion.

9. Balance to Finish.

10. Retainage, if any.

F. Execute certification by signature of authorized officer.

G. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored Products.

H. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of Work.

PRICE AND PAYMENT PROCEDURES

01 20 00 - 2

I. Submit three copies of each Application for Payment.

J. Include the following with the application:

1. Transmittal letter as specified for Submittals in Section 01 30 00 - Administrative Requirements.

2. Construction progress schedule, revised and current as specified in Section 01 30 00.

3. Current construction photographs specified in Section 01 30 00.

4. Partial release of liens from major Subcontractors and vendors.

5. Sustainable design documentation applicable to work for which application is being made;

see Section 01 33 29.

6. LEED submittals applicable to work for which application is being made; see Section 01 35

16.

7. Project record documents as specified in Section 01 78 00, for review by Government which will be returned to the Contractor.

K. When Government's Representative requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal. Show application number and date, and line item by number and description.

1.04 MODIFICATION PROCEDURES

A. Submit name of the individual authorized to receive change documents and who will be responsible for informing others in Contractor's employ or subcontractors of changes to the Contract Documents.

B. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Government's Representative will issue instructions directly to Contractor.

C. For other required changes, Government's Representative will issue a document signed by Government instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

D. For changes for which advance pricing is desired, Government's Representative will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 7 days.

E. Contractor may propose a change by submitting a request for change to Government's Representative, describing the proposed change and its full effect on the Work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation and a statement describing the effect on Work by separate or other contractors. Document any requested substitutions in accordance with Section 01 60 00.

F. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

1. For change requested by Government's Representative for work falling under a fixed price contract, the amount will be based on Contractor's price quotation.

2. For change requested by Contractor, the amount will be based on the Contractor's request for a Change Order as approved by Government's Representative.

3. For pre-determined unit prices and quantities, the amount will based on the fixed unit prices.

4. For change ordered by Government's Representative without a quotation from Contractor, the amount will be determined by Government's Representative based on the Contractor's substantiation of costs as specified for Time and Material work.

G. Substantiation of Costs: Provide full information required for evaluation.

PRICE AND PAYMENT PROCEDURES

01 20 00 - 3

1. Provide following data:

a. Quantities of products, labor, and equipment.

b. Taxes, insurance, and bonds.

c. Overhead and profit.

d. Justification for any change in Contract Time.

e. Credit for deletions from Contract, similarly documented.

2. Support each claim for additional costs with additional information:

a. Origin and date of claim.

b. Dates and times work was performed, and by whom.

c. Time records and wage rates paid.

d. Invoices and receipts for products, equipment, and subcontracts, similarly documented.

3. For Time and Material work, submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

H. Execution of Change Orders: Government's Representative will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

I. After execution of Change Order, promptly revise Schedule of Values and Application for

Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum.

J. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit.

K. Promptly enter changes in Project Record Documents.

1.05 APPLICATION FOR FINAL PAYMENT

A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due.

B. Application for Final Payment will not be considered until the following have been accomplished:

1. All closeout procedures specified in Section 01 70 00 - Execution and Closeout

Requirements.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

ADMINISTRATIVE REQUIREMENTS

01 30 00 - 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Electronic document submittal service.

B. Preconstruction meeting.

C. Site mobilization meeting.

D. Progress meetings.

1.02 RELATED REQUIREMENTS

A. Section 01 32 16 - Construction Progress Schedule: Form, content, and administration of schedules.

B. Section 01 33 00 - Submittal Procedures : Submittal procedures.

C. Section 01 60 00 - Product Requirements: Product Options and Substitution Requirements.

D. Section 01 70 00 - Execution and Closeout Requirements: Additional coordination requirements.

E. Section 01 78 00 - Closeout Submittals: Project record documents.

F. Section 01 91 13 - General Commissioning Requirements: Additional procedures for submittals relating to commissioning.

1. Where submittals are indicated for review by both Government's Representative and the

Commissioning Authority, submit one extra and route to Government's Representative first, for forwarding to the Commissioning Authority.

2. Where submittals are not indicated to be reviewed by Government's Representative, submit directly to the Commissioning Authority; otherwise, the procedures specified in this section apply to commissioning submittals.

1.03 REFERENCE STANDARDS

A. AIA G810 - Transmittal Letter; 2001, or approved equivalent.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Government's Representative will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Contracting Officer.

2. Government's Representative.

3. Contractor.

C. Agenda: Including, but not necessarily limited to following.

1. Execution of Government-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract and Government's

Representative.

6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Scheduling.

8. Scheduling activities of a Geotechnical Engineer.

ADMINISTRATIVE REQUIREMENTS

01 30 00 - 2

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Government's Representative, Government, participants, and those affected by decisions made.

3.02 SITE MOBILIZATION MEETING

A. Government's Representative will schedule a meeting at the Project site prior to Contractor occupancy.

B. Attendance Required:

1. Contractor.

2. Contracting Officer.

3. Government's Representative.

4. Special Consultants.

5. Contractor's Superintendent.

6. Major Subcontractors.

C. Agenda: Including, but not necessarily limited to following.

1. Use of premises by Government and Contractor.

2. Government's requirements and occupancy prior to completion.

3. Temporary utilities provided by Government.

4. Survey and building layout.

5. Security and housekeeping procedures.

6. Schedules.

7. Application for payment procedures.

8. Procedures for testing.

9. Procedures for maintaining record documents.

10. Requirements for start-up of equipment.

11. Inspection and acceptance of equipment put into service during construction period.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Government's Representative, Government, participants, and those affected by decisions made.

3.03 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job superintendent, major Subcontractors and suppliers, Contracting

Officer, Government's Representative, as appropriate to agenda topics for each meeting.

D. Agenda: Including, but not necessarily limited to following.

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

ADMINISTRATIVE REQUIREMENTS

01 30 00 - 3

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Government's Representative, Government, participants, and those affected by decisions made.

3.04 SUBMITTAL PROCEDURES

A. Comply with requirements of Section 01 33 00 - Submittal Procedures

CONSTRUCTION PROGRESS SCHEDULE

01 32 16 - 1

SECTION 01 32 16

CONSTRUCTION PROGRESS SCHEDULE

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preliminary schedule.

B. Construction progress schedule, bar chart type.

1.02 RELATED SECTIONS

A. Section 01 10 00 - Summary: Coordination and Work sequence.

1.03 REFERENCES

A. AGC (CPSM) - Construction Planning and Scheduling Manual; Associated General Contractors of America; 2004.

1.04 SUBMITTALS

A. Within 10 days after date established in Notice to Proceed, submit preliminary schedule defining planned operations for the first 60 days of Work, with a general outline for remainder of Work.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

F. Submit under transmittal letter form specified in Section 01 30 00 - Administrative

Requirements.

1.05 SCHEDULE FORMAT

A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.

B. Diagram Sheet Size: Maximum 22 x 17 inches or width required.

C. Scale and Spacing: To allow for notations and revisions.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRELIMINARY SCHEDULE

A. Prepare preliminary schedule in the form of a horizontal bar chart.

3.02 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Identify work of separate stages and other logically grouped activities.

D. Provide sub-schedules to define critical portions of the entire schedule.

E. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

F. Provide separate schedule of submittal dates for shop drawings, product data, and samples, and dates reviewed submittals will be required from Government's Representative. Indicate decision dates for selection of finishes.

G. Coordinate content with schedule of values specified in Section 01 20 00 - Price and Payment Procedures.

CONSTRUCTION PROGRESS SCHEDULE

01 32 16 - 2

H. Provide legend for symbols and abbreviations used.

3.03 BAR CHARTS

A. Include a separate bar for each major portion of Work or operation.

B. Identify the first work day of each week.

3.04 REVIEW AND EVALUATION OF SCHEDULE

A. Participate in joint review and evaluation of schedule with Government's Representative at each submittal.

B. Evaluate project status to determine work behind schedule and work ahead of schedule.

C. After review, revise as necessary as result of review, and resubmit within 10 days.

3.05 UPDATING SCHEDULE

A. Maintain schedules to record actual start and finish dates of completed activities.

B. Indicate progress of each activity to date of revision, with projected completion date of each activity.

C. Update diagrams to graphically depict current status of Work.

D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.

E. Indicate changes required to maintain Date of Substantial Completion.

F. Submit reports required to support recommended changes.

G. Provide narrative report to define problem areas, anticipated delays, and impact on the schedule. Report corrective action taken or proposed and its effect including the effects of changes on schedules of separate contractors.

3.06 DISTRIBUTION OF SCHEDULE

A. Distribute copies of updated schedules to Contractor's project site file, to Subcontractors, suppliers, Government's Representative, Government, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections shown in schedules.

SUBMITTAL PROCEDURES

01 33 00 - 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

1.02 RELATED SECTIONS INCLUDE

A. Section 01 30 00 - Administrative Requirements.

B. Section 01 60 00 - Product Requirements: Submitting substitution requests.

C. Section 01 78 00 - Closeout Submittals: Project record documents, operation and maintenance data, warranties and bonds.

D. Other Sections for specific requirements for submittals in those Sections.

1.03 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Government's

Representative's responsive action.

B. Informational Submittals: Written information that does not require Government's

Representative's responsive action. Submittals may be rejected for not complying with requirements.

1.04 ELECTRONIC DOCUMENT SUBMITTAL

A. All documents transmitted for purposes of administration of the contract are to be in electronic

(PDF) format.

1. Besides submittals for review, information, and closeout, this procedure applies to requests for information (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project record.

1.05 SUBMITTAL PROCEDURES

A. Review submittals prior to submission to Government's Representative.

B. Transmit submittals to Government's Representative for delivery to Government.

C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Government's Representative reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

3. Submittals for finishes and colors shall be coordinated and submitted at the same time.

D. Basis Of Design:

1. Products indicated in the color and finish schedules or drawing notes; including color, shade, hue, translucence, opacity, pattern, or texture; establish the Basis of Design. Use the Basis of Design. Submit a request for substitution for any product not indicated.

2. Substitutions will not be considered for finishes and colors unless all finishes and colors are coordinated and submitted together.

E. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Schedule" for list of submittals and time requirements for scheduled performance of related construction activities.

SUBMITTAL PROCEDURES

01 33 00 - 2

F. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Government's Representative's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with other Contractors and/or subsequent submittals is required.

Government's Representative will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 15 days for review of each resubmittal.

4. Sequential Review: Where sequential review of submittals by Government's

Representative's consultants, Government, or other parties is indicated, allow 21 days for initial review of each submittal.

G. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space approximately 6 by 8 inches on label or beside title block to record

Contractor's review and approval markings and action taken by Government's Representative.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Government's Representative's project number.

c. Government's project number.

d. Date.

e. Name and address of architect.

f. Name and address of contractor.

g. Name and address of subcontractor.

h. Name and address of supplier.

i. Name of manufacturer.

j. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).

k. Number and title of appropriate Specification Section.

l. Drawing number and detail references, as appropriate.

m. Location(s) where product is to be installed, as appropriate.

n. Other necessary identification.

H. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.

I. Copies: Minimum 5 hard copies and electronic file. Hard copy and electronic file shall be identical. In addition, provide number of hard copies indicated in individual technical sections.

J. Additional Copies: Unless additional copies are required for final submittal, and unless Government's Representative observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

1. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Government's Representative.

2. Additional copies submitted for maintenance manuals will be marked with action taken and will be returned.

K. Transmittal: Package each submittal individually and appropriately for transmittal and handling.

Transmit each submittal using a transmittal form. Government's Representative will return submittals, without review, received from sources other than Contractor.

1. Transmittal Form: Use form acceptable to Government's Representative.

SUBMITTAL PROCEDURES

01 33 00 - 3

2. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Government's Representative on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same label information as related submittal.

L. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in label or title block and clearly indicate extent of revision.

3. Resubmit submittals until they are approved.

M. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

N. Use for Construction: Use only final submittals with mark indicating "No Exceptions Taken" or "Approved as Noted" by Government's Representative.

PART 2 PRODUCTS

2.01 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections or subsequently requested by Contracting Officer or Government's Representative.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Standard color charts.

e. Manufacturer's catalog cuts.

f. Wiring diagrams showing factory-installed wiring.

g. Printed performance curves.

h. Operational range diagrams.

i. Mill reports.

j. Standard product operation and maintenance manuals.

k. Compliance with specified referenced standards.

l. Testing by recognized testing agency.

m. Application of testing agency labels and seals.

n. Notation of coordination requirements.

4. Submit Product Data before or concurrent with Samples.

5. Number of Copies: Submit four hard copies and electronic file of Product Data, unless otherwise indicated. No copies will be returned. Mark up and retain one copy as a Project Record Document.

C. Shop Drawings: Prepare Project specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

SUBMITTAL PROCEDURES

01 33 00 - 4

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Shopwork manufacturing instructions.

g. Templates and patterns.

h. Schedules.

i. Design calculations.

j. Compliance with specified standards.

k. Notation of coordination requirements.

l. Notation of dimensions established by field measurement.

m. Relationship to adjoining construction clearly indicated.

n. Seal and signature of professional engineer if specified.

o. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

2. Sheet Size: Same size as contract drawings, 30 inch x 42 inch maximum.

3. Number of Copies: Submit 2 blue or black line prints. One copy will returned. In addition, provide number of hard copies indicated in individual technical sections.

D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Number and title of appropriate Specification Section.

3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual

Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Government's property, are the property of Contractor.

4. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit three sets of Samples. Government's Representative will retain one Sample set; remainder will be returned. Mark up and retain one returned Sample set as a Project Record Sample.

1) Submit a single Sample where assembly details, workmanship, fabrication techniques, connections, operation, and other similar characteristics are to be demonstrated.

2) If variation in color, pattern, texture, or other characteristic is inherent in material or product represented by a Sample, submit at least three sets of paired units that show approximate limits of variations.

E. Product Schedule or List: As required in individual Specification Sections, prepare and maintain a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form:

SUBMITTAL PROCEDURES

01 33 00 - 5

1. Type of product. Include unique identifier for each product.

2. Number and name of room or space.

3. Location within room or space.

4. Number of Copies: Submit three copies of product schedule or list, unless otherwise indicated. Government's Representative will return two copies.

a. Mark up and retain one returned copy as a Project Record Document.

F. Submittals Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Schedule."

G. Application for Payment: Comply with requirements specified in Division 01 Section "Payment Procedures."

H. Schedule of Values: Comply with requirements specified in Division 01 Section "Payment Procedures."

I. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Use form acceptable to Government's Representative. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

4. Number of Copies: Submit three copies of subcontractor list, unless otherwise indicated.

Two copies will be returned.

a. Mark up and retain one returned copy as a Project Record Document.

2.02 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated in the individual specification section. Copies will not be returned.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements specified in Division 1 Section "Quality Requirements."

B. Coordination Drawings: Comply with requirements specified in Division 01 Section "Project Management and Coordination."

C. Construction Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Documentation."

D. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.

F. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

G. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

H. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

SUBMITTAL PROCEDURES

01 33 00 - 6

I. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

J. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

K. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

L. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

1. Name of evaluation organization.

2. Date of evaluation.

3. Time period when report is in effect.

4. Product and manufacturers' names.

5. Description of product.

6. Test procedures and results.

7. Limitations of use.

M. Schedule of Tests and Inspections: Comply with requirements specified in Division 1 Section "Quality Requirements."

N. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

O. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

P. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

Q. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in Division 01 Section "Operation and Maintenance Data."

R. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations.

Include page numbers.

S. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer. Include the following, as applicable:

1. Preparation of substrates.

2. Required substrate tolerances.

3. Sequence of installation or erection.

4. Required installation tolerances.

5. Required adjustments.

6. Recommendations for cleaning and protection.

T. Manufacturer's…