BF SISK SAFETY OF DAMS (SOD) MODIFICATIONS, PHASE I
Solicitation number
140R2021R0004
Issued by

About this file

This document provides details for a federal contract solicitation. The solicitation number is 140R2021R0004 and seeks proposals for Phase I of safety modifications to the BF Sisk Dam. The project scope includes construction of shear keys, stability berms, and spillway modification to address issues with the dam's select foundation materials and help prevent destabilization of the dam embankment. This will reduce safety concerns and help maintain water supply deliveries to downstream state and federal contractors in the event of seismic activity. The soliciting agency is the Department of the Interior Bureau of Reclamation.

View the file

Other files

File Type Posted
Sol_140R2021R0004_Amd_0011.pdf PDF
Amendment_No__0010_to_140R2021R0004_0010.pdf PDF
Sol_140R2021R0004_Amd_0010.pdf PDF
Amendment_No__0008_and_No__0009_to_140R2021R0004_0009.pdf PDF
Sol_140R2021R0004_Amd_0009.pdf PDF
Sol_140R2021R0004_Amd_0008.pdf PDF
047_508-D-60073_Amendment_0007_0007.pdf PDF
805-D-3221-RD-1_Amendment_0007_0007.PDF PDF
031_508-D-60044_Amendment_0007_0007.pdf PDF
Amendment_No__0007_to_140R2021R0004_0007.pdf PDF
Sol_140R2021R0004_Amd_0007.pdf PDF
059_508-D-60084_Amendment_0007_0007.pdf PDF
Attachment_J3_Past_Performance_Questionnaire_Amendment_0007_0007.pdf PDF
Attachment__J5_Key_Personnel_rev_1_Amendment_0007_0007.pdf PDF
048_508-D-60074_Amendment_0007_0007.pdf PDF
Attachment_B_1_Schedule_of_Prices_Amendment_0007_0007.xlsx XLSX spreadsheet
015_508-D-60025_Amendment_0007_0007.pdf PDF
068_508-D-60133_Amendment_0007_0007.pdf PDF
060_508-D-60085_Amendment_0007_0007.pdf PDF
061_508-D-60086_Amendment_0007_0007.pdf PDF
Sol_140R2021R0004_Amd_0006.pdf PDF
Amendment_No__0006_to_140R2021R0004_0006.pdf PDF
Sol_140R2021R0004_Amd_0005.pdf PDF
Amendment_No__0005_to_140R2021R0004_0005.pdf PDF
Sol_140R2021R0004_Amd_0004.pdf PDF
Amendment_No__0004_to_140R2021R0004_0004.pdf PDF
Sol_140R2021R0004_Amd_0003.pdf PDF
Amendment_No__0003_to_140R2021R0004_0003.pdf PDF
Amendment_No__0002_to_140R2021R0004_0002.pdf PDF
Sol_140R2021R0004_Amd_0002.pdf PDF
Sol_140R2021R0004_Amd_0001.pdf PDF
Amendment_No__0001_to_140R2021R0004_0001.pdf PDF
Attachment_J1_General_Decision_Number_CA20210018.pdf PDF
Attachment_J10_Electronic_Proposal_Submission.pdf PDF
Attachment_J4_-_Past_Performance_Data_Form.pdf PDF
Attachment__J2_Subcontracting_Plan.pdf PDF
Sol_140R2021R0004.pdf PDF
Attachment_J8_Invoicing_Documents.pdf PDF
Attachment_J3_Past_Performance_Questionnaire.pdf PDF
Attachment__J6_Corporate_Experience_and_Management.pdf PDF
Attachment_B_1_Schedule_of_Prices.xlsx XLSX spreadsheet
Attachment__J7_Offeror_Responsibility_Information.pdf PDF
Attachment__J9_Release_of_Claims.pdf PDF
Attachment__J5_Key_Personnel.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Department of the Interior September 2021

Solicitation No. 140R2021R0004

Specifications No. 20-C0909

B.F. Sisk Dam SOD Modifications, Phase I

San Luis Unit, West San Joaquin Division, Central Valley Project, California

California-Great Basin Region

This page intentionally left blank.

B. F. SISK DAM

SOD MODIFICATIONS, PHASE 1

SAN LUIS UNIT, WEST SAN JOAQUIN DIVISION, CENTRAL VALLEY PROJECT,

CALIFORNIA

FOREWORD

Work is located approximately 12 miles west of Los Banos, California in Merced County.

Principal features of work include excavating embankment; excavation from borrow; material processing and supply; furnishing and placing various earthfill materials; constructing access roadways; removal and control of water; earthwork for structures; constructing cast-in-place concrete outlet works tunnel extension and spillway chute modification; and removing existing and reinstalling new electrical raceway, conduit, and power and control cables.

PRE-BID SITE VISIT: A VIRTUAL PREBID MEETING WILL BE HELD ON

WEDNESDAY, SEPTEMBER 29, BEGINNING AT 1:00 PM FOLLOWED BY AN IN-

PERSON SITE VISIT ON THURSDAY, SEPTEMBER 30, BEGINNING AT 10:00 AM

AT THE PROJECT LOCATION. PROSPECTIVE BIDDERS SHOULD MAKE

ARRANGEMENTS BY CONTACTING REYNALDO “HENRY” GARCIA AT 530-308-

47940 OR RGARCIA@USBR.GOV AND ROXANA AHOLA AT 916-978-5549 OR

RAHOLA@USBR.GOV. ATTENDEES ARE TO PROVIDE AND WEAR STURDY

ATTIRE, SAFETY BOOTS, HARD HATS, AND SAFETY VESTS.

FOR DATE AND PLACE OF BID OPENING, SEE "SOLICITATION, OFFER, AND

AWARD," STANDARD FORM 1442.

FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION

"RECLAMATION SAFETY AND HEALTH STANDARDS" INCLUDING REVISIONS

AT https://www.usbr.gov/safety/rshs/index.html) WHICH IS APPLICABLE TO WORK

UNDER THIS CONTRACT, SEE CLAUSE AT "WBR 1452.223-81 SAFETY AND

HEALTH."

mailto:RGARCIA@USBR.GOV mailto:RAHOLA@USBR.GOV

Solicitation No. 140R2021R0004 – BF SISK Safety of Dams (SOD) Modifications

TABLE OF CONTENTS

SECTION A - Solicitation, Offer and Award Form (SF 1442)

SECTION B - Pricing Schedule

SECTION C - Specifications/Appendices

SECTION D - Packaging and Marking

SECTION E - Inspection and Acceptance

SECTION F - Deliveries or Performance

SECTION G - Contract Administration Data

SECTION H - Special Contract Requirements

SECTION I - Contract Clauses

SECTION J - List of Documents, Exhibits, and Other Attachments

SECTION K - Representations, Certifications and Other Statements of Offerors

SECTION L - Instructions, Conditions and Notices to Offerors

SECTION M - Evaluation Factors for Award

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

Bureau of Reclamation

Mid-Pacific Region

Regional Office Division of Acquisition Services

R20

2800 Cottage Way, Room E-1815

Sacramento CA 95825-1898

8. ADDRESS OFFER TO

Bureau of Reclamation CGB-Great Basin, Region 10 Division of Acquisition 2800 Cottage Way, Room e-1815 Sacramento

Roxana Ahola

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

916-978-5549

20-C0909 x 09/20/2021

140R2021R0004

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

calendar days and complete it within 7___ 1095 calendar days after receiving

a. Sealed offers in original and

11/04/2021

NSN 7540-01-155-3212

x copies to perform the work required are due at the place specified in Item 8 by _____________ 14:00 (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

A.Title: BF SISK Safety of Dams (SOD) Modifications, Phase I B.Work Site location:

C.Site Visit Information: See Section L, FAR 52.236-27 Site

Visit (Construction) - Alt. 1 D.Estimated Price Range: The estimated cost of this project is between $100,000,000.00 and $500,000,00.00.

E.Set Aside Information: This requirement is an unrestricted procurement using NAICS 237990 and applicable size standard of $39.5 million.

F.Refer to Section L (Instructions to Offerors) for additional proposal requirements.

G.All inquiries pertaining to this solicitation (except where noted for the site visit) shall be submitted in writing to both the Contract Specialist, Roxana Ahola at rahola@usbr.gov and Contracting Officer, Erik Danger at edanger@usbr.gov no later than 12:00 PM Pacific, October 12, 2021. Responses pertinent to all prospective offerors will be included in an amendment to the solicitation.

x Section F x

BF Sisk Dam, 12 miles west of Los Banos, CA

X

EDanger Cross-Out

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Mid-Pacific Region

Regional Office Division of Acquisition Services

R20

2800 Cottage Way, Room E-1815

Sacramento CA 95825-1898

31a. NAME OF CONTRACTING OFFICER (Type or print)

Erik Danger

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R2021R0004

Section B - Supplies and Services and Prices "AU" - Activity Unit is used solely for the purposes of allowing progress payments under the Department of Interior's Financial & Business Management System (FBMS).

BF SISK Safety of Dams (SOD) Modification Phase 1

Pricing Schedule:

CLIN 1-93

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

00010 1 AU

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

BF SISK Safety of Dams (SOD) Modifications, Phase I

B.1 GENERAL

The contractor shall, except as otherwise noted, provide all necessary labor, equipment, materials, supplies, transportation, travel, and per diem necessary to perform the work specified in the attached Specifications No. 20-C0909 entitled “BF SISK Safety of Dams (SOD) Modifications, Phase I.”

B.2 Schedule of Prices

(a) Offers will be considered for award on the Price Schedule at attachment B.1, but no offer will be considered for award on only a part of the Price Schedule.

(1) Offerors should complete Schedule of Prices excel attachment B.1.

(2) Pricing Schedule should be submitted as an unlocked excel spreadsheet without password protection or locked cells. Unit prices and totals should reflect actual prices within two decimals without the use of rounding or weighting in cell formulas.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) The quantities in the schedule are estimated quantities for comparison of offers only, and except as provided in the contract clause at 52.211-18 “Variation in Estimated Quantity,” no claim shall be made against the Government for overruns or underruns.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) CLIN – Contract Line Item Number.

B. F. Sisk Dam SOD Modifications, Phase 1 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Table of Contents

00 01 10 - 1

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 11 16 Work By Others 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 16 Permits 01 14 20 Reservoir Operations 01 14 30 Interruption of Service 01 31 22 Coordination Meetings 01 31 30 Contract Document Management System (CDMS) 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 35 50 Site Security 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 52 10 Government Field Office 01 52 14 Field Laboratory Facility 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 55 28 Temporary Traffic Signs 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 56 32 Temporary Safety Fence 01 56 34 Exclusion Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution and Erosion Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 57 70 Fire Protection and Prevention 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

00 01 10 - 2

01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents 01 83 13 Project Monitoring

DIVISION 02 - EXISTING CONDITIONS

02 01 60 Wildlife Spillway Crossing 02 01 80 Tule Elk Herd Management 02 21 13 Survey Monuments 02 21 34 Structure Measurement Points

DIVISION 03 - CONCRETE

03 05 00 Spillway Modification 03 11 10 Concrete Forming 03 15 12 PVC Waterstop 03 15 14 PVC Retro-Fit Waterstop 03 20 00 Concrete Reinforcing 03 20 30 Grouted Anchor Bars 03 30 00 Cast-In-Place Concrete 03 62 20 Nonshrink Grout for Equipment and Metalwork 03 81 10 Concrete Removal

DIVISION 05 - METALS

05 50 00 Metal Fabrications

DIVISION 08 - OPENINGS

08 31 20 Access Hatches

DIVISION 26 - ELECTRICAL

26 05 02 Basic Electrical Materials and Methods 26 05 04 Overview of Raceway Electrical Work 26 05 06 Removal and Disposal of Existing Electrical Equipment 26 05 10 Conductors and Cables 26 05 22 Medium-Voltage Power Cable 26 05 33 Raceways and Boxes

DIVISION 31 - EARTHWORK

31 02 10 Water for Dust Abatement

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

00 01 10 - 3

31 02 30 Dust Palliative 31 03 33 Removal and Control of Water 31 09 10 Abandoning and Removing Existing Instrumentation 31 09 12 Temporary Inclinometers 31 09 13 Slope Stability Monitoring 31 09 22 Protecting Existing Instrumentation 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 02 Compacting Earth Materials 31 23 05 Blasting 31 23 11 Earthwork for Structures 31 23 12 Earthwork for Electrical Trench 31 23 14 Excavation of Rock Blanket Material 31 23 17 Excavation of Shear Key 31 23 19 Excavation from Borrow 31 23 20 Excavation from Quarry 31 23 21 Stockpiling Riprap 31 23 22 Constructing Haul Roads 31 23 39 Disposal of Excavated Materials 31 23 50 Quarry Reclamation 31 23 70 Controlled Low Strength Material (CLSM) 31 24 12 General Earthfill Construction 31 24 13 Zone 1, Impervious Fill 31 24 14 Zone 9A, Sand Filter / Zone 9B, Crest Sand Filter 31 24 15 Zone 11, Gravel Drain 31 24 16 Zone 8, Miscellaneous Fill 31 24 17 Zone 10, Shear Key Rockfill 31 24 18 Downstream Rock Blanket Material 31 24 19 Zone 2A, Embankment Filter 31 24 20 Zone 4A, Embankment Drain 31 32 32 Geotextile

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 10 12 Roadwork, General 32 10 16 Removing Existing Asphalt Pavement and Base Course 32 11 23 Aggregate Base Course 32 12 22 Asphalt Concrete Pavement 32 12 26 Restoring Existing Roads 32 15 10 Gravel Surfacing 32 17 20 Painted Traffic Lines and Markers 32 31 01 Fence Grounding 32 31 10 Chain Link Fence 32 91 19 Topsoil

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

00 01 10 - 4

32 92 20 Restoration and Revegetation

DIVISION 33 - UTILITIES

33 05 31 Toe Drain Terminal Wells 33 29 04 Removing Existing Toe Drain Pipes 33 29 05 Abandoning Existing Toe Drains Using Grout 33 46 36 Toe Drains 33 46 42 Weir Boxes

DIVISION 34 – TRANSPORTATION

34 71 19 Roadway Markers

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 21 95 Spillway Vent Pipe Modifications

DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors 51 00 10 Climatic Conditions 51 00 40 Historical Reservoir Elevation Data 51 00 70 Example Drawings 51 00 80 Environmental Reports, Records, and Permits 51 00 90 Instrumentation Data

DIVISION 52 - DRAWINGS

52 00 00 Drawings

DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS

53 10 00 Geotechnical Baseline Conditions 53 20 00 Geologic Characterization 53 30 00 Records of Geologic and Subsurface Investigations

END OF CONTENTS

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Summary of Work

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located approximately 12 miles west of Los Banos, California in Merced County.

1.02 SUMMARY OF WORK

A. Construct shear keys and berms at each of three separate locations along the dam: SW36, SW145, and SW180. Refer to the drawings.

B. Remove a portion of the spillway chute and replace with conduit section. Cover with earthen materials to construct a berm.

C. Develop Basalt Hill Quarry and Borrow Area 14 to provide materials for use as part of this contract.

1.03 PRINCIPAL COMPONENTS OF WORK

A. General:

1. Developing, supplying, and furnishing Government Field Office and Government

Laboratory Facility, each complete with utilities.

2. Obtaining necessary permits.

3. Installation and monitoring of environmental mitigation measures and protection of species.

B. Material Processing and Supply:

1. Blasting.

2. Material processing and stockpiling.

3. Supplying and transporting materials.

4. Transporting materials from on-site borrow areas or commercial sources.

C. Earthwork:

1. Removal and control of water.

2. Installation and monitoring of instrumentation.

3. Earthwork for structures.

4. Excavation of existing rock blanket materials.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 11 00 - 2

5. Excavation of foundation materials for shear keys.

6. Excavation from borrow areas.

7. Excavation from quarry.

8. Furnishing and placing shear key earthfill materials.

9. Furnishing and placing berm earthfill materials.

10. Placing rock blanket material.

11. Furnishing and placing controlled low strength material (CLSM).

12. Constructing haul roads.

D. Instrumentation:

1. Abandoning and removing existing instrumentation.

2. Furnishing and installing temporary inclinometers.

3. Slope stability monitoring.

4. Groundwater instrumentation and monitoring.

5. Protecting existing instrumentation.

E. Structures:

1. Removal and disposal of existing concrete along portion of spillway chute.

2. Constructing cast-in-place concrete spillway conduit extension and transition.

F. Electrical:

1. Removal and replacement of electrical raceway, conduit, power and control cables.

G. Exterior Improvements:

1. Furnishing and placing gravel surfacing for new roads.

2. Paving for new roads.

3. Restoring existing roads damaged by haul activities.

4. Restoration and revegetation of borrow areas and use areas.

5. Work associated with meeting environmental permit requirements.

H. Utilities:

1. Abandoning existing toe drains using grout.

2. Constructing toe drains.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 11 00 - 3

1.04 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

D. Laboratory testing shall be performed in accordance with the current version of the applicable ASTM standards.

1.05 DEFINITIONS

A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.

1.06 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 53:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

3. OGR: Onsite Government Representative for the Contracting Officer’s

Representative.

4. SW: Slopewash.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 11 00 - 4

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Work by Others

01 11 16 - 1

SECTION 01 11 16

WORK BY OTHERS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include coordination in prices offered in the Price Schedule for other items of work.

1.02 WORK BY OTHERS

A. San Luis Transmission Project by Western Area Power Administration (WAPA):

1. Construction of multiple transmission lines through the site.

a. Two transmission lines extending from San Luis Substation (Gianelli Pump Generating Plant) to Los Banos Substation.

b. The transmission line will have a minimum 40-foot ground to line clearance along haul routes to minimize impact to construction traffic.

B. Gonzaga Wind Farm Transmission Lines by Scout Clean Energy:

1. Towers and circuits throughout construction area will be constructed by others prior to or during construction.

a. Includes transmission lines along the eastern side of Borrow Area 14 and transmission lines that cross miscellaneous access roads.

b. 40-Foot ground to line clearance to facilitate traffic beneath for construction.

c. Protect new towers after they are constructed. Maintain 50-foot horizontal clearance (i.e., a 50-foot radius setback). Beyond setback, slope at 1:1.

C. Verizon Cell Tower:

1. A new cell tower will be constructed by others prior to, or during, construction approximately 75 feet northeast of the State Parks office.

1.03 RESIDENT STATE OF CALIFORNIA DEPARTMENT OF WATER

RESOURCES (DWR) AND CALIFORNIA DEPARTMENT OF PARKS AND

RECREATION (STATE PARKS)

A. Resident DWR and State Parks maintains office and maintenance facilities and staff onsite.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Work by Others

01 11 16 - 2

B. Assure adequate access for DWR and State Parks staff to maintain and monitor equipment and facilities, including to DWR and State Park offices, Basalt Hill Campground, intake towers, monitoring points, onsite instrumentation, etc.

1. Includes daily access to residences located at the Basalt Hill Campground area to be maintained.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 COORDINATION

A. Prior to Contractor beginning onsite work, coordinate with COR to verify the items of work and timing of work performed by others.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. Cleaning Manual-2012 Inspection and Cleaning Manual for

Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land.

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences and permanent fences.

7) Access roads and gates.

8) Staging and stockpile areas.

http://www.usbr.gov/mussels/prevention

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 10 - 2

9) Borrow areas and processing sites.

10) Material conveyor routes.

11) Proposed extents of clearing, grubbing, and stripping.

12) Sanitary facilities.

13) Recreational area closures.

14) Existing roadway closures and detours.

15) Measures to secure work areas.

16) Reservoir access points for water for construction purposes.

17) Location of water storage.

b. Describe methods for removing temporary structures and facilities, cleanup, and restoration and revegetation of site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

1.04 PROJECT CONDITIONS

A. All construction activities shall be within the Contractor Use Area and project disturbance areas shown on Drawings.

B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

C. Location, construction, operation, maintenance, and removal of facilities in use on Government land will be subject to approval by COR.

D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

E. Housing for construction personnel will not be permitted on Government work site land.

1. Security personnel may stay on Government land, as approved by CO.

F. Always provide access for Government and DWR personnel to all areas within construction site.

PART 2 PRODUCTS

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 10 - 3

PART 3 EXECUTION

3.01 CLEANING

A. Construction equipment:

1. Before bringing on site, clean construction equipment and temporary facilities to remove all dirt, vegetation, and other organic material to prevent introduction of invasive plant and animal species and noxious weeds.

2. Government will inspect construction equipment and temporary facilities following procedures described in Reclamation Cleaning Manual before allowing the equipment and temporary facilities onsite.

3. Clean equipment and temporary facilities prior to removal from the site.

3.02 RESTORATION

A. Restore Contractor use areas to pre-construction condition and in accordance with Section 01 74 00 – Cleaning and Waste Management and Section 32 92 20 – Restoration and Revegetation.

B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion in accordance with Section 32 92 20 – Restoration and Revegetation.

C. Seed disturbed areas of Government land used for construction purposes and not required for completed installation in accordance with Section 32 92 20 – Restoration and Revegetation.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 10 - 4

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Work Restrictions

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 WORK RESTRICTIONS

A. Spillway

1. Spillway work shall be performed when reservoir levels are below elevation (El.)

510. Refer to Section 01 14 20 – Reservoir Operations and Section 51 00 40 – Historical Reservoir Elevation Data.

a. The COR will provide notification by May 15 if the reservoir operations will not allow spillway work to occur during a given year.

2. Spillway excavation shall be backfilled with zoned materials per drawings to El.

470 (NGVD29) while the reservoir is below El. 510 (NGVD29).

3. Backfilling shall be continuous to final grade by November 30, unless otherwise approved by COR.

4. Spillway work below El. 470 (NGVD29) shall not be concurrent with shear key excavation at SW145.

B. Shear Keys

1. Reservoir elevations:

a. Shear key construction at SW180 shall be performed when the reservoir level is below El. 500 (NGVD29 datum).

b. Shear key construction at SW36 and SW145 shall be performed when the reservoir level is below El. 480 (NGVD29 datum).

c. The COR will provide notification by May 15 if the reservoir operations will not allow shear key work to occur during a given year.

1) Excavation is not expected to begin until June 15 in accordance with Section 01 14 20 – Reservoir Operations.

a) The COR will provide notification if an earlier-than-normal start to excavation should be expected based on forecasted reservoir levels.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Work Restrictions

01 14 12 - 2

d. Excavation shall not begin after September 1 without approval from the

COR.

2. Shear key construction shall be completed by December 15, unless otherwise approved by the COR.

a. Includes placement of at least 3 feet of Zone 8 cover (vertically) over

Zone 2A separator blanket. Refer to drawings.

3. Shear key work is subject to the limitations described in Section 31 23 17 –

Excavation of Shear Key.

a. Excavations shall be performed using rolling excavation methods with a maximum open excavation length in the direction parallel to the dam axis.

Refer to Section 31 23 17 – Excavation of Shear Key.

b. Specified portions of the individual shear keys shall not be constructed simultaneously.

C. Allowable Work Hours

1. 24 hours per day, Monday through Sunday, with the following exception:

a. Blasting shall be scheduled in advance and only occur between the hours of 6:00 AM to 6:00 PM daily.

D. Comply with Sections 01 57 20 – Environmental Controls, 01 57 30 – Water Pollution and Erosion Control, and 01 57 60 – Protected Species regarding project environmental requirements and limitations.

E. Comply with requirements described in Section 31 23 19 – Excavation from Borrow/Quarry.

F. Maintain reliable power to the four outlet works intake towers throughout construction.

Refer to Section 01 14 30 – Interruption of Service and Drawings.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Permits

01 14 16 - 1

SECTION 01 14 16

PERMITS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. State of California, Department of Transportation (CALTRANS)

1. CALTRANS Application for Encroachment Permit:

a. Available online at: https://dot.ca.gov/programs/traffic-operations/ep

B. Merced County Department of Public Works

1. Merced County Department of Public Works Application for Encroachment

Permit:

a. Available online at:

https://www.co.merced.ca.us/DocumentCenter/View/1662/ Encroachment-Permit-Application-fillable?bidid=

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 – Submittals.

B. RSN 01 14 16-1, Encroachment Permits

1. State of California, Department of Transportation Encroachment Permits, if needed.

a. Provide copy of the Application for Encroachment including supporting forms, drawings, and documents.

b. Provide copy of permit once received.

2. Merced County Department of Public Works Encroachment Permit.

a. Provide copy of the Application for Encroachment including supporting forms, drawings, and documents.

b. Provide copy of permit once received.

https://dot.ca.gov/programs/traffic-operations/ep

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 16 - 2

1.04 REGULATORY REQUIREMENTS

A. Meet requirements established by jurisdictional authority for use of existing roadways and haul routes; including seasonal or other limitations or restrictions, payment of excess size and weight fees, and posting of bonds conditioned upon repair of damage.

B. Comply with applicable regulations for haul routes over public highways, roads, or bridges.

C. Acquire and comply with State of California, Department of Transportation encroachment permit requirements including additional requirements specific to the project, as applicable.

1. The Contractor shall be responsible for any fees associated with the Contractor’s permit.

2. The Contractor shall be responsible for any fees or renewal requirements for annual renewal of the permit.

3. A complete permit package submittal is required by the permit applicant consisting of but not limited to 100 percent engineered and stamped plans by a California State licensed Civil Engineer, location map, letter of authorization from the government, environmental documentation, stormwater permit(s), certification of compliance with the Americans with Disabilities Act, fees, surety bonds, liability insurance, etc.

D. Acquire and comply with State of California, Merced County, Encroachment Permits, and County Road maintenance requirements, as applicable.

1.05 PROJECT CONDITIONS

A. Include all applicable local authorities, including CALTRANS, Merced County, California Department of Fish and Wildlife, etc. to obtain necessary permits.

1. Other permits may be required.

B. The Contractor shall coordinate with COR in discussions with CALTRANS, Merced County, and California Department of Fish and Wildlife.

C. Refer to Section 51 00 80 – Environmental Reports, Records, and Permits.

D. Table 01 14 16A – Required Permits provides a list of permits that are required for the project. Additional permits may be required

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 16 - 3

Table 01 14 16A – Required Permits a Permit title(s) Encroachment

Permits Incidental

Take Permit

(ITP)*

Air Quality Permits**

Blasting Permits***

Water Quality Permits****

Permit obtained by

Contractor Government* Contractor Contractor See Section 01 57 30 – Water Pollution and Erosion Control

Permit compliance, sampling, testing, and monitoring

Contractor Contractor Contractor Contractor See Section 01 57 30 – Water Pollution and Erosion Control

Agency Issuing Permit

CALTRANS,

Merced County

California Department of Fish and Wildlife

San Joaquin Valley Air Pollution Control District

Varies See Section 01 57 30 – Water pollution and Erosion Control a Additional permits not shown in this table may be required.

* If needed, amendments shall be obtained by the Government after the Contractor provides required data.

** For information regarding air quality permits, refer to Section 01 57 20 – Environmental Controls.

*** For information regarding blasting permits, refer to Section 31 23 05 – Blasting.

**** For information regarding water quality permits, refer to Section 01 57 30 – Water Pollution and Erosion Control.

E. Obtain encroachment permits from CALTRANS and Merced County for work within State and County roadway corridor rights-of-way.

1. Includes Gonzaga Road from intersection with Highway 33 to the project site, if applicable.

2. Includes limited access to the site via Highway 152 near Visitor’s Center.

3. Contractor is responsible for providing the necessary information to CALTRANS and Merced County for review and approval.

F. Government will obtain a general Incidental Take Permit (ITP) from CDFW.

1. Contractor to comply with requirements of the permit.

2. Contractor shall coordinate with Government to obtain any additional permits and/or amendments.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 16 - 4

a. Includes environmental permits for work not covered under the General ITP permit.

b. Contractor is responsible for providing necessary information to DWR for review and approval.

G. Government will obtain a Master Lake and Streambed Alteration Agreement (LSAA) from CDFW.

1. Contractor to comply with requirements of the permit and sub-notifications.

Refer to Section 01 57 30 – Water Pollution and Erosion Control.

H. The following contact information is provided for coordinating with and obtaining other permits:

1. California Department of Fish and Wildlife:

a. California Department of Fish and Wildlife, 1234 East Shaw Ave., Fresno, CA 93710, 559-243-4005, www.wildlife.ca.gov.

I. The Contractor is responsible for obtaining air quality permits. Refer to Section 01 57 20

– Environmental Controls.

J. The Contractor is responsible for complying with clean water permits. Refer to Section 01 57 30 – Water Pollution and Erosion Control.

1. The Government will obtain the 401 and 404 permits, in accordance with Section

01 57 30 – Water Pollution and Erosion Control.

2. The Contractor shall obtain other required permits, in accordance with Section

01 57 30 – Water Pollution and Erosion Control.

K. The Contractor is responsible for obtaining permits required for blasting and transporting of blasting materials. Refer to Section 31 23 05 – Blasting.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used http://www.wildlife.ca.gov/

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Reservoir Operations

01 14 20 - 1

SECTION 01 14 20

RESERVOIR OPERATIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 DEFINITIONS

A. Active conservation capacity (active storage): The reservoir capacity assigned to regulate reservoir inflow for irrigation; power; municipal and industrial use; fish and wildlife;

navigation; recreation; water quality; and other purposes. It does not include exclusive flood control or joint use capacity. It extends from the top of the active conservation capacity to the top of the inactive capacity.

1.03 PROJECT CONDITIONS

A. Work performed for shear key excavations and spillway excavations are dependent on reservoir levels, in accordance with Section 01 14 12 – Work Restrictions.

B. Reservoir elevations referred to in the specifications are in datum NGVD29.

1. For conversion from NGVD29 to NAVD88, refer to Section 01 71 20 –

Surveying.

1.04 RESERVOIR OPERATIONS

A. B. F. Sisk Dam and San Luis Reservoir are operated by State of California Department of Water Resources (DWR).

B. The reservoir will be operated under normal operating conditions (i.e., no reservoir restrictions) for the duration of construction. DWR will maintain operational responsibility of the reservoir. The reservoir will be operated such that the maximum water surface will be El. 543.8.

C. The outlet works will remain operational throughout construction. DWR will maintain operational responsibility of the outlet works.

D. San Luis Reservoir historical monthly average water surface elevation data are shown in Section 51 00 40 – Historical Reservoir Elevation Data.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Reservoir Operations

01 14 20 - 2

1. When precipitation varies from typical levels, reservoir operations are adjusted accordingly. Historically, there are some years during which the reservoir does not drop below El. 510 for the entire year.

2. The reservoir is most commonly below El. 480 from mid-June to late-December.

E. As discussed in Section 01 14 12 – Work Restrictions, shear key work at SW36 and SW145 is limited to periods when the reservoir is below El. 480.

F. As discussed in Section 01 14 12 – Work Restrictions, shear key work at SW180 is limited to periods when the reservoir is below El. 500.

G. As discussed in Section 01 14 12 – Work Restrictions, spillway construction work is limited to periods when the reservoir is below El. 510.

H. The Government monitors reservoir levels continuously and will provide monthly reservoir level forecasts.

1. Actual reservoir level may vary from forecasted levels.

2. The Government and Contractor will meet monthly to discuss the monthly reservoir forecast and future construction operations subject to the work restrictions.

1.05 RESERVOIR RELEASES

A. The reservoir will be operated normally throughout construction with water levels fluctuating accordingly.

1. Reservoir releases will not be made for the purpose of accommodating construction activities.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Interruption of Service

01 14 30 - 1

SECTION 01 14 30

INTERRUPTION OF SERVICE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for items of work that require interruptions of service.

1.02 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 – Submittals.

B. RSN 01 14 30-1, Interruption of Service Requests:

1. Written request for each proposed outage 28 calendar days in advance of outage.

Include following in each request:

a. Equipment that will be out of service.

b. Outline of work to be performed including, but not limited to:

1) Specific safety precautions to be taken.

2) Type and location of barricades.

3) Warning signs.

4) Protective grounds and devices to be used.

c. Commencement time of interruption of service.

d. Duration of work and type of interruption of service as defined in Article

1.03 - Definitions.

e. Number of personnel involved with work performed during interruption of service and their classification.

f. Description of equipment to be used.

1) Include equipment to provide temporary power to maintain equipment and critical load, as detailed below. Describe methods to connect to existing facilities.

g. Information indicating that required equipment and materials are onsite or data indicating shipping dates of equipment and materials not onsite.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 30 - 2

1.03 DEFINITIONS

A. Complete Pump/Generation Outage: All pump-generator units out-of-service due to power loss or other circumstances.

B. Half Pump/Generation Outage: One of the two pump-generator units out-of-service due to power loss or other circumstances.

C. Roller-Mounted Gate Outage: Roller-mounted gates out-of-service due to power and control loss.

1.04 PROJECT CONDITIONS

A. Coordinate and schedule outages with COR:

1. Maximum Outage Duration: 12 hours; the COR may, at their discretion, approve longer outage requests. These requests will be evaluated and approved on a case-by-case basis.

2. Coordinate work with Government operations and other contractors.

3. No specific outage request will be considered unless:

a. COR has assurance that materials and equipment required for the work are onsite.

b. Contractor shall be prepared to start the work on date and complete all tasks during period requested for specific outage.

4. Allowable time and available outage periods will govern outage requests, work scheduling, on site delivery of materials, and prior approval of required drawings and data submittals.

5. Temporary power for critical loads is required if Contractor-performed work results in a loss of power to the critical load.

a. Critical Loads:

1) Roller Mounted Headgate(s) open and close operation (115 kVA at 480 V 3Ph).

b. Maximum outage for critical loads: 12 hours.

6. Government reserves right to schedule interruption of services for any period during a 24-hour day, any day of week.

B. Provide continuous fire watch during times of any outages to fire alarm or fire protection systems.

C. When work cannot be performed during an approved outage period, notify COR that the outage is not required. If needed, reschedule outage in accordance with this Section.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 30 - 3

D. Show interruption of service in construction schedule. Refer to Section 01 32 10 – Construction Program.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 14 30 - 4

SOD Modification, Phase 1 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Coordination Meetings

01 31 22 - 1

SECTION 01 31 22

COORDINATION MEETINGS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include cost of coordination meetings in prices offered in the Price Schedule for other items of work.

1.02 PRECONSTRUCTION SECURITY MEETING

A. The preconstruction security meeting shall be scheduled before the Contractor’s Site Security Plan has been submitted and accepted. The meeting will be coordinated between Contractor project management and COR. Topic covered will include:

1. Contractor’s Site Security Program.

1.03 PRECONSTRUCTION SAFETY MEETING

A. Coordinate preconstruction safety meeting with COR at work site project office before starting onsite work.

B. The meeting shall be scheduled after the Contractor’s Safety Program has been submitted and accepted. The meeting will be coordinated between Contractor project management, COR, and Reclamation Safety Manager. Topics covered will include:

1. Contractor’s Safety Program.

2. Required joint safety policy meetings.

3. Site Security Coordination.

4. Required toolbox safety meetings.

5. Weekly joint safety inspections.

6. Job hazard analyses (JHAs).

1.04 WEEKLY COORDINATION MEETINGS

A. Coordinate weekly meetings with the COR.

B. Weekly Coordination Meetings:

1. Contractor shall conduct weekly coordination meetings with Government.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 31 22 - 2

2. Purpose: Review past and future work activities and progress, non-contractor activities in the area, reservoir conditions, issue discussion, and contract administration with Government representatives.

3. Contractor Attendees: Contractor project manager, superintendent, and other representatives, as needed, who understand work, schedule, technical requirements, components, and contract administration.

4. Meeting will be convened and led by Contractor to discuss and provide updates for the following:

a. Work Schedule

b. Safety

c. Site Security

d. Reservoir Condition

e. Outages

f. Personnel

g. Environmental and Biological Topics

h. Weather Forecast / SWPPP

i. Project Monitoring / Slope Stability Monitoring

j. Contract Administration:

1) Required Submittals

2) Requests for Information

3) Requests for Change

4) Contract Modifications

5) Requests for Proposal

6) Requests for Substitution

7) Requests for Equitable Adjustment

8) Invoices

k. Quality Control / Test Results

l. Other outstanding issues.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 31 22 - 3

PART 3 EXECUTION

3.01 IMPLEMENTATION

A. Contractor

1. Coordinate meeting time, place, invite list, notifications, virtual meeting, and teleconference access with COR.

2. Prepare and distribute agendas, updated 3-week look-ahead schedules, and current

RSN and RFI logs for each meeting.

a. Distribute one business day prior to each scheduled meeting.

3. Compile and distribute meeting minutes after each meeting.

a. Provide draft minutes to COR for Government review and comment within one business day after each meeting. COR will return draft minutes with comments within three business days.

b. Distribute final minutes to all meeting invitees within two business days after receiving Government comments.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 31 22 - 4

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

Contract Document Management System (CDMS)

01 31 30 - 1

SECTION 01 31 30

CONTRACT DOCUMENT MANAGEMENT SYSTEM (CDMS)

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Contract Document Management System (CDMS):

1. Payment: Lump sum price offered in the Price Schedule.

a. Payment of the lump sum price offered will be made incrementally throughout the duration of the contract and will not be paid in full until completion of the contract.

1.02 DEFINITIONS

A. CDMS: Contract Document Management System:

1. Contract Documents include but are not limited to:

a. Specifications.

b. Contract drawings.

c. Submittals.

d. Approval Drawings (Contractor generated document).

e. Shop Drawings (Contractor generated document).

f. Final Drawings (Contractor generated document).

g. As-built Drawings (Contractor generated document).

h. REA: Request for Equitable Adjustment (Contractor generated document).

i. RFC: Request for Change (Contractor generated document).

j. RFI: Request for Information (Contractor generated document).

k. RFP: Request for Proposal (Government generated document).

l. RFS: Request for Substitution (Contractor generated document).

m. MOD: Contract Modification.

n. Value Engineering Proposals.

o. Government Inspection Reports.

p. Contract Schedules.

q. Meeting Agendas and Meeting Minutes.

r. Letters, Memos, and other typical contract correspondence.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 31 30 - 2

1.03 SUBMITTALS

A. Submit in accordance with Section 01 33 00 – Submittals.

B. RSN 01 31 30-1, Approval Data:

1. System provider experience, number of systems operating, references.

2. Documentation of system capabilities.

3. Instructions for system use.

C. RSN 01 31 30-2, Final Data:

1. Use IronKey, or similar, Encrypted Hard Drive or Encrypted Flash Drive, meeting

FIPS 140-2 requirements for Level 3 Security and chain-of-custody procedures.

Submit with all documents uploaded to CDMS.

1.04 QUALIFICATIONS

A. System Provider: At least 5 years successful performance in providing required services.

1.05 CDMS REQUIREMENTS

A. CDMS shall be capable of generating, storing, tracking, categorizing, and managing contract documents.

B. Access:

1. Web-Based:

a. Contract Documents are stored and accessed by authorized individuals via an internet site.

b. Compatible with web browsers MS Edge, MS Internet Explorer, Apple Safari, Mozilla Firefox, and Google Chrome.

2. Ability to upload Contract Documents and make available for user download in supported file formats, minimum:

a. Adobe Acrobat, Portable Document Format (.pdf).

b. Microsoft Word; Microsoft Word 97-2003 Document (.doc), Word

Document (.docx).

c. Microsoft Excel; Microsoft Excel 97-2003 Worksheet (.xls), Excel

Workbook (.xlsx).

d. Oracle Primavera P6 Project Manager, XML and XER file Extension (.xml and .xer) and P6 layout file (.plf).

e. Autodesk Drawing File AutoCAD 2018 (.dwg) or later.

3. Allow Contract Documents to be prepared by Contractor or by Government.

San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909

01 31 30 - 3

a. Preparing organization will control access of documents. See Document Security and Backup paragraph below.

4. Contractor and Government shall each have a project manager for CDMS:

a. Each project manager shall have capabilities to assign users within organization and assign user rights that control access to documents based on user class and document type.

b. Each organization shall be…