Amendment_No__0007_to_140R2021R0004_0007.pdf
PDF 4 MB Posted
- Solicitation number
- 140R2021R0004
About this file
This solicitation is for the BF Sisk Safety of Dams (SOD) Modifications, Phase I project. The project scope includes construction of shear keys, stability berms, and spillway modification to address issues with select foundation materials and help prevent destabilization of the BF Sisk Dam embankment in the event of seismic activity. The estimated cost range for the project is $100-500 million. The solicitation is an unrestricted procurement using NAICS code 237990 with a size standard of $39.5 million. Offers are due by November 19, 2021. The performance period is 1095 calendar days after NTP. The contracting agency is the Department of the Interior Bureau of Reclamation.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE
0007 11/02/2021
6. ISSUED BY CODE R20
Bureau of Reclamation Mid-Pacific Region
Regional Office
Division of Acquisition Services
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
1. CONTRACT ID CODE
4. REQUISITION/PURCHASE REQ. NO.
7. ADMINISTERED BY (If other than Item 6)
9A. AMENDMENT OF SOLICITATION NO.
140R2021R0004
X
9B. DATED (SEE ITEM 11)
09/20/2021
I
PAGE OF PAGES
1 I 5
5. PROJECT NO. (If applicable)
20-C0909
CODE I
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
IXI The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. Dis not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment. and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
ORDER NO. IN ITEM 10A.
E. IMPORTANT:
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Contractor Dis not Dis required to sign this document and return ______ _ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. TITLE: B.F. Sisk Dam SOD Modifications, Phase I
B. PURPOSE: The purpose of this amendment is to incorporate various changes to solicitation documents.
C. DESCRIPTION: This amendment hereby incorporates the following:
1) Offeror's Questions and Answers
2) Remove SF-1442 and replace with SF-1442, Amendment 0007 (incorporates November 19, 2021, Continued
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 1 0A, as heretofore changed, remains unchanged and in full force and effect .
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED
(Signature of person authorized to sign)
Previous edition unusable
Erik M. Danger
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
X
B.F. Sisk Dam SOD Modifications, Phase I - Offeror’s Questions and Answers Amendment 0007
Question 1: Drawings 60084, 60085 and 60086, Note 5.1 under stage 2 grouting, indicates grouting is complete when “1 Cubic yard of grout has been pumped and the COR concurs grouting is complete.”
Specification 33 29 05, Section 3.07, Paragraph E states, “Stage 2 backfill grouting is complete once one of three conditions has occurred” however, only two of the three conditions on the drawings are listed in the specifications. Please confirm what conditions must be met to complete stage 2 grouting.
Response 1: Drawings -60084, -60085, and -60086 have been updated to remove Note 5.1 from "Stage 2 grouting notes."
Question 2: Specification 05 50 00, measurement and payment for metal fabrications includes “covers, ladders and grab bars for access wells and terminal wells.” Specification 33 05 31, measurement and payment for toe drain terminal wells includes “…access ladders, well covers, and access hatches.” Please clarify which CLIN item ladders and covers are to be priced in.
Response 2: Ladders and covers are to be included in 33 05 31 - Toe Drain Terminal Wells.
This question has resulted in updates to 4 specification sections to be provided by amendment:
01 71 20 - Surveying 05 50 00 - Metal Fabrications 08 31 20 - Access Hatches 33 05 31 - Toe Drain Terminal Wells
Question 3: Reference Drawing 805-D-60044 – The sections H, J, K, L, and M all reference back to Drawing 805-D-60044, but these section views appear to be located on Drawing 805-D-60045. Please confirm that the drawings should reference Drawing 60045.
Response 3: Drawing 805-D-60044 has been updated to correct the subject section callouts.
Question 4: Drawing 805-D-60025 – Excavation Control Point Table - Points #3621-3638 – The elevation listed in the table appears to be Existing Grade, not Design Grade. Please clarify.
Response 4: Drawing 805-D-60025 has been updated to correct the subject point elevations.
Question 5: Section and Page 01 56 32-1, Section Title Temporary Safety Fence, Part 1.01.A.1 - This item of work is not shown on the drawings. Please change this bid item to a measurement and payment by LF.
Response 5: The "other areas as directed by the COR" (3.01-A-4) has been removed from 01 56 32 - Temporary Safety Fence, and from 01 56 34 - Exclusion Fence. CLINS 11, 12, and 13 will all be paid as lump sum.
Question 6: Section and Page 01 57 30 - 6, 7 & 11, Section Title Water Pollution and Erosion Control, Part
1.08 E.1,, F.1, I.1 - Please provide copies of these permits.
Response 6: Refer to Amendment No 0006 Q&A #6. Permits 1, 2 and 3 are pending issuance and are anticipated to be received before NTP. Permits 4, 5, and 6 are available through Kiteworks. Request the Kiteworks link by emailing Roxana Ahola at rahola@usbr.gov with a cc: to Erik Danger at edanger@usbr.gov.
Question 7: Specification 31 23 17, Part 1.02 J requires initial stockpiling of 5,000 cy of each of the shear key materials at each shear key excavation area. Part 3.01 F1 requires just 5,000 cy of Zone 9A Sand Filter to be stockpiled on-site, not at each shear key excavation area. Please clarify if just one 5,000 cy stockpile of Zone 9A Sand Filter will be sufficient or will a 5,000 cy stockpile of Zone 9A Sand Filter be required at each shear key excavation area?
Response 7: A 5,000 cy stockpile of Zone 9A Sand Filter will be required at each shear key excavation, as stated in Section 31 23 17, Part 1.02 J.
Question 8: According to Spec section “26 05 04 - 4 (1.03 - C -1.)” the above ground raceway is to be constructed to match as closely as possible to the existing raceway. Plan sheet 805-D-60122 references plan sheet 805-D-1805 for details on the Cable tray brackets. Plan sheet 805-D-1805 shows details for cable tray mounted on the bridge but not on the dam’s slope. There is no reference in the electrical plans or specs giving detail of the cable tray, the type of cable tray support, or on the concrete foundations that the supports attach to.
Please provide detail of manufacturer model numbers of the existing cable tray, tray Cover, and Supports.
Including a detail of the concrete foundation.
Response 8: Section 26 05 33 - Raceways and Boxes has been updated to provide additional information.
Question 9: The Mitigation Monitoring and Reporting Program (Chapter 5 of the Final EIR, August 2019) identifies Reclamation and DWR as Responsible Party(s) to complete Mitigation Measures TERR-1 through TERR-16. We would like an update of the current status of the completeness of these measures to-date or schedule to complete, as well as any data derived from completing the measures (e.g., locations and conditions of any special-status species findings) that may impact the schedule or cost of constructing this project.
Response 9: Pre-construction tasks were completed during design, and offerors shall assume that all findings have been incorporated into the available specifications and environmental documents.
Question 10: Table 01 14 16A identifies the Contractor as being responsible for permit compliance, sampling, testing, and monitoring of the Incidental Take Permit (ITP), to be issued to the Government from CDFW. Please provide a copy of the ITP so that Contractors are able to assess the schedule impacts and cost of complying with the requirements of the ITP.
Response 10: The ITP is pending issuance and is anticipated before NTP. The ITP will be provided once it is received. Assume the requirements of the ITP will be consistent with the requirements of the existing specification and biological opinion (BO).
Question 11: The RFP identifies permits to be obtained by the Government to allow for impacts to jurisdictional waters (Master Lake and Streambed Alteration Agreement, a 404 Permit, and a 401 Water Quality Certification). Will the Government provide those permits prior to bid date to allow for pricing and adjusting schedule if needed, or will the Government provide a Project Modification post award if these permits result in additional requirements that may impact schedule and cost of the project?
Response 11: Reclamation does not expect any additional requirements to be included in the currently unavailable permits that may impact the schedule and cost of the project.
Question 12: The RFP refers to requirements of the section "specification section 01 32 10 – Part 1.06.A, Schedules" for the "Coordinated Construction Schedule - Gantt Chart Schedule". However, Part 1.06.A refers to “General,” and Part 1.07.A refers to “Schedules.” Please confirm the correct reference. If the intent was to refer to specification section 01 32 10 – Part 1.07 Schedules, Clause A, there seems to be a disconnect between the Section L proposal submittal requirements and the specification section 01 32 10 -- Part 1.07.A requirements. Please confirm that the “Gantt Chart Schedule” required to be submitted in the technical proposal under Factor 1A should meet the requirements in Section L (i.e., includes such detail to show the sequencing of the principal and critical components of work contained in the solicitation […] and any other activities or information needed to accurately portray the offeror’s proposed schedule…).
Therefore, while the schedule submitted with the proposal will generally follow the requirements of the specifications in principle, we are correct in assuming that it is not required to meet all of the requirements for the Baseline Schedule (e.g., defining activities to level of detail resulting in their durations being no greater than 20 workdays).
Response 12: Refer to specifications section 01 32 10 1.07.A.6.a
Question 13: Paragraph 1.07 B states... Noise barriers and equipment mufflers required. Can BOR provide details of noise barriers and where they might be required?
Response 13: Contractors elected equipment may require sound barriers and or modified mufflers to reduce noise levels.
Question 14: Paragraph 1.07 B states... Refer to drawings showing the moderate to high sensitivity areas.
We cannot locate these areas on the drawings. Please advise.
Response 14: Section 01 57 90 has been updated to include figures showing the moderate and high sensitivity areas. References to additional drawings have been removed.
Question 15: Paragraph 1.01B Foundation Treatment states...Payment: Square yard price offered in the Price Schedule. a. Includes Zone 9A, Zone 11, and backfill concrete materials. There is significant difference in cost in treating with Zone9A/11 and Backfill Concrete. Can BOR provide a separate pay item for backfilling with concrete by the cubic foot?
Response 15: The Foundation Treatment Cost Item (Section 31 23 17) now refers exclusively to backfill concrete foundation treatment. The associated quantity has been updated, along with Section 00 00 50 - Section B.
The Zone 9A sand for foundation treatment will be included in CLIN 66 for Zond 9A Sand Filter material, and Zone 11 gravel for foundation treatment will be included in CLIN 68 for Zone 11 Gravel Drain material. Section 53 10 00 - Geotechnical Baseline Conditions has now been updated to provide assumed quantities of these foundation treatment materials as well.
Question 16: Paragraph 1.01A.1.a. Item 9a states... Removing constructed haul roads from Borrow Area 14 and adjacent contractor use area. a) Includes removing gravel surfacing, replacing topsoil, and revegetation.
Is this not paid for in items 83 Topsoil and 84 Restoration & Revegetation?
Response 16: Section 31 23 22 - Constructing Haul Roads has been updated to remove payment for topsoil and revegetation. Those tasks will be paid for under the separate CLINS.
Question 17: Per Section 805-D-60133 - Chart in referenced plan calls out Required Excavation/Schedule Item 58/ Excavation of Embankment/15,000CY. Line Item 58 in Schedule of Prices is for Shear Key Excavation total 440,000CY. Given this excavation is at the spillway structure, is the intent for the plan to say Schedule Item 53/Common Excavation for Structures/15,000CY?
Response 17: Correct. On drawing 805-D-60133, required excavation/Schedule Item 58/Excavation of Embankment has been changed to Required Excavation/Schedule Item 53/Common Excavation for Structures. Also, the amount has been changed from 15,000 to 16,000 cy.
Question 18: See paragraph 31 23 17-3.07 Foundation Mapping and Inspection. Which Schedule of Price Item is this work paid under? See paragraph 53 10 00-1.07B stating ... Assume 1 percent of the excavated foundation surface will require foundation treatment. Schedule of Price Item 59 Foundation Treatment calls for 80,000SY. Please clarify if the intent is to treat 80,000SY or 1% of that amount with zone 9a, Zone 11, and Backfill Concrete?
Response 18: Refer to the response for question #15. Additionally, it is confirmed that 80,000 SY represented the full foundation area, while 800 SY would represent the area to be treated, or 1% of the total foundation area.
Question 19: See paragraph 01 55 20-3.01F stating... Traffic control is required along Gonzaga Road from intersection with Basalt Road to Highway 33/Santa Nella Boulevard. This appears to be offsite, please clarify the scope of work intended to require stated traffic control.
Response 19: The subject paragraphs have been revised as part of an update to Section 01 55 20.
Question 20: See paragraph 01 55 20-3.01G.1 stating... Provide temporary signal to stop traffic when hauling. At which intersection is the temporary signal required? What traffic control is required to cross Basalt Rd from Borrow Area 14? Can the unnamed paved road between toe of dam and Basalt Rd be closed from Gonzaga Rd. to SW36?
Response 20: The reference to the temporary signal has been removed. Refer to updates to Section 01 55 00 - Vehicular Access and Parking. Refer to Section 01 55 20 - Traffic Control for necessary traffic control at intersections along roads. Yes, the unnamed paved road along the toe of the dam will be closed to public access. Refer to 01 55 00 - Vehicular Access and Parking.
Question 21: Per 805-D-60072 and 805-D-60074 - The drawing for Spillway Berm shows the same contours as does drawing for Spillway Excavation. For the areas beyond the limits of Spillway Berm Access Rd, what are the intended finish contours?
Response 21: Drawing 805-D-60074 has been updated with a new drawing title to reduce confusion.
Question 22: Reference section 01-56-32 - Temporary Safety Fence and Bid Item 10 - Temporary Safety Fence - 1 Lump Sum. Because this is a Lump Sum bid item, we request that either Part 3.01-A(4) - "Other areas as directed by the COR" be removed from the specifications or the bid item unit be changed to a price per LF that will be measured. It is impossible to determine how much "other" fence may be directed by the COR. This requirement of "as directed by the COR" occurs in Bid Items 11 and 12 and should be corrected as well.
Response 22: The "other areas as directed by the COR" (3.01-A-4) has been removed from 01 56 32 - Temporary Safety Fence, and from 01 56 34 - Exclusion Fence. CLINS 11, 12, and 13 will all be paid as lump sum.
Question 23: Environmental Controls 01 57 20 – 2 – Please inform the bidding Contractors what needs to be included in our bids regarding “purchase of carbon offsets before construction activities commence”.
How will the Contractor be able to quantify this requirement? Please provide a clarification to this section.
Response 23: A new cost item for carbon offsets is updated to section 01 57 20 - Environmental Controls, and Section 00 00 00 - Section B in this amendment. The cost item will be paid in a lump sum to address the updated project-level significance level threshold minimum of 104,537 MTCO2e to reduce emissions.
Question 24: Reference Section 31 23 17 EXCAVATION OF SHEAR KEY subsection 3.08 FOUNDATION TREATMENT B.3 states, “Placement of Zone 9A sand filter, Zone 11 gravel drain, or backfill concrete in/around identified joints and fractures.” Will the Agency please provide the foundation backfill concrete mix design specifications, and cure time to place embankment atop/against? Also, since foundation treatment bid item and work is paid by the square yard, and is to be directed in the field by COR, it is not possible to quantify backfill concrete, Z9a or Z11 material amount required. Will the agency consider adding an additional bid item(s) for Z9a, Z11 and Concrete Backfill to be paid by cubic yard?
Response 24: Refer to the response for question #18.
Question 25: In the Exploration and Test Plan Final Report BF Sisk Basalt Hill Quarry Exploration and Test Plan (October 2020). There are two recommendations of change in product gradations - 1) Section 3-30 Regarding Zone 4A Embankment Drain Material - This product would benefit from removing the 8” requirement and making it 100% passing the 5”. Even more important, it would be very beneficial to the efficiency and consistency in producing this material if the ¾” sieve specification was changed to 0-15% passing, and the 3/8” sieve removed. The proposed quantity for this product for the upcoming large dam modification is nearly 900,000 cubic yards. It is recommended that serious thought be given to the proposed gradation changes for the Zone 4A to avoid testing inconsistency, segregation, and reworking issues throughout the course of the contract. 2)Section 3-31 Regarding Zone 2A Embankment Filter Material - A recommendation for this product is to change the No. 8 sieve to 0 to 30% passing and remove the No. 16 sieve requirement entirely. Has there been a decision regarding the recommended adjustments in product gradations?
Response 25: Recommendations from the subject report have been incorporated into the material gradations, as appropriate. The Zone 4A material gradation will not be changed. The Zone 2A material gradation has been updated slightly, as shown in updated Section 31 24 19 - Zone 2A, Embankment Filter.
Question 26: Specification 33 46 36, paragraph 1.04.A Qualifications states “Fusion machine operator must have at least 5 years’ experience in welding HDPE pipe greater than 30 inches in diameter and DR ranging from 32.5 to 17.” The largest diameter on the project is 12”, suggest this spec is changed to read 12 inch in lieu of 30 inch.
Response 26: Section 33 46 36 has been updated to address this comment.
Question 27: Drawing 805-D-60119 Note 6. States, “Revise Drawing 805-D-3221 to reflect this drawing.”
Please provide drawing 805-D-3221.
Response 27: Drawing 805-D-3221 is provided as part of this amendment.
Question 28: Specification 53 10 00 Paragraph 1.07.B states “Assume 1 percent of the excavated foundation surface will require foundation treatment.” The Solicitation Section B, Schedule of Prices CLIN 59 – Foundation Treatment has a quantity of 80,000 square yards. Please clarify which quantity to provide pricing for.
Response 28: Refer to the response for question #15. Additionally, it is acknowledged that 80,000 SY represented the full foundation area, while 800 SY would represent the area to be treated, or 1% of the total foundation area.
Question 29: Specification 01 57 20 Paragraph 1.04 G states, “Purchase carbon offsets before construction activities commence in an amount sufficient to reduce greenhouse gas emissions to less than significant levels using DWR significance thresholds. A minimum of 120,575 MTCO2e is required to reduce emissions below the project-level significance threshold.” Please clarify which bid item the pricing for said carbon offsets should be included in.
Response 29: Refer to the response for question #23.
Question 30: Spec section 03 20 30 -2 calls out No. 6 reinforcing bar embedded 9 ¾” into un-cracked concrete with 4000 psi compressive strength. There is no reference or detail for installing grouted anchors in the plans. Please provide details and location of grouted anchors.
Response 30: Refer to Section 03 81 10 - Concrete Removal for locations of grouted anchors. Section 03 20 30 - Grouted Anchor Bars has also been updated to make this more clear.
Question 31: Drawing 805-D-60074, Detail F, horizontal drawing scale appears to be incorrect based off other details. Please confirm this drawing scale is correct or provide correct scale.
Response 31: Drawing 805-D-60074 has been updated to correct the scale.
Question 32: Please confirm if the zone 11 gravel drain is to be imported from a commercial source as shown on drawing numbers 65-67 or processed from the Basalt Quarry as described in specification 31.23.20-4 and shown on drawing number 68?
Response 32: Yes, Zone 11 "Gravel Drain" can be produced from the Basalt Hill Quarry. Please refer to specifications section 31-24-15-2.01.C "Source".
Question 33: Specification 01 57 90 PRESERVATION OF HISTORICAL AND ARCHAEOLOGICAL DATA 1.06 D. states, “Refer to drawings showing the moderate to high sensitivity areas.” Please clarify these locations.
Response 33: Refer to response from inquiry #14
Question 34: Reference Bid Item 20 – "Drilling holes for anchor bars and grouting bars in place" - 42 LF.
Please provide details for the following: size and diameter of the holes, number of holes, spacing of the holes, and type and size of the anchor bars.
Response 34: Refer to response from inquiry #30.
Question 35: Reference Specification Section 01-57-50 - Tree and Plant Protection. Please provide the quantity of trees outside of the disturbance limits that will be required to be protected or replaced.
Response 35: Section 01 57 50 - Tree and Plant Protection has been updated to remove the requirement to protect trees outside of the project footprint.
Question 36: Reference Specification Section 01-57-90 - Preservation of Historical and Archaeological Data. It appears that the contractor is responsible to provide an Archeologist on site at all times during ground-disturbing work identified in moderate or high sensitive areas. Please provide locations that are considered moderate or high sensitive areas.
Response 36: Refer to response from inquiry #14.
Question 37: Reference Specification Section 34-71-19 - Roadway Markers. Please provide plans and or quantities for the types of roadway markers that will be required so that costs can be calculated for the Lump Sum bid item 92.
Response 37: Roadway marker types and locations are discussed in Section 34 71 19 - Roadway Markers.
Question 38: General Earthfill Construction Specification Section 31 24 12 – 3.03. G. states, “Transverse bonding surfaces (surfaces perpendicular to the dam crest centerline) between previously constructed earth-fill and earth-fill to be placed are subject to approval of COR and shall not be steeper than 4H:1V. 1) Transverse bonding surfaces will not be permitted in Zone 1, Impervious Fill.”
Excavation of Shear Key Specification Section 31 23 17, Figure 31 23 17A – Illustration of “rolling excavation” concept shows 2:1 excavation and embankment. Bullet point 5. Excavation slopes for rolling excavation (in lateral direction) shall be at 2:1 slope, unless otherwise approved by the COR. We understand this is illustrative purpose only, but wouldn’t this illustration concept be better represented with embankment portions shown at 4:1 slopes? How will Zone 1 be place with each 150’ shear key embankment sections if no traverse bonding surfaces are permitted?
Response 38: Section 31 24 12 has been updated to address the requirements for transverse bonding surfaces within the Zone 1, Impervious Fill.
Question 39: Excavation of Shear Key Specification Section 31 23 17 - 3.08.B.3 Foundation Treatment states, “Placement of Zone 9A sand filter, Zone 11 gravel drain, or backfill concrete in/around identified joints and fractures.” Bid Item # 59 Foundation Treatment is paid by the square yard, and is to be directed by COR, will USBR please provide an estimated amount of these foundation treatment materials needed for each shear key foundation?
Response 39: Refer to the response for question #15.
Question 40: In regard to Spec Section 01 57 20 Environmental Controls Section 1.04 Regulatory Requirements Paragraph G “Purchase carbon offsets before construction activities commence in an amount sufficient to reduce greenhouse gas emissions to less than significant levels using DWR significance thresholds. A minimum of 120,575 MTCO2e is required to reduce emissions below the project-level significance threshold. Only emission offsets generated as part of CARB’s Compliance Offset Protocols (developed for the AB 32 cap‐and‐trade program) may be used to reduce GHG emissions.” Is the contractor to purchase the required tonnage of (A minimum of 120,575 MTCO2e) or is the owner purchasing the required tonnage of Carbon Offsets?
Response 40: Refer to the response for question #23.
Question 41: In a recent amendment, the PPQ criteria was changed, and the PPQ forms are being sent directly to you from past project representatives. You may have already received a PPQ form we no longer need to be reviewed based on the new criteria. How can we indicate which three projects we would like considered?
Response 41: Indicate in Volume II of your proposal the three (3) projects you would like considered for Past Performance.
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
8. ADDRESS OFFER TO
Bureau of Reclamation CGB-Great Basin, Region 10 Division of Acquisition 2800 Cottage Way, Room e-1815 Sacramento
Roxana Ahola
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
916-978-5549
20-C0909 x 09/20/2021
140R2021R0004
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
calendar days and complete it within 7___ 1095 calendar days after receiving
a. Sealed offers in original and
11/19/2021
NSN 7540-01-155-3212
x copies to perform the work required are due at the place specified in Item 8 by _____________ 14:00 (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
A.Title: BF SISK Safety of Dams (SOD) Modifications, Phase I B.Work Site location:
C.Site Visit Information: See Section L, FAR 52.236-27 Site
Visit (Construction) - Alt. 1 D.Estimated Price Range: The estimated cost of this project is between $100,000,000.00 and $500,000,00.00.
E.Set Aside Information: This requirement is an unrestricted procurement using NAICS 237990 and applicable size standard of $39.5 million.
F.Refer to Section L (Instructions to Offerors) for additional proposal requirements.
G.All inquiries pertaining to this solicitation (except where noted for the site visit) shall be submitted in writing to both the Contract Specialist, Roxana Ahola at rahola@usbr.gov and Contracting Officer, Erik Danger at edanger@usbr.gov no later than 12:00 PM Pacific, October 12, 2021. Responses pertinent to all prospective offerors will be included in an amendment to the solicitation.
x Section F x
BF Sisk Dam, 12 miles west of Los Banos, CA
X
Amendment 0007
EDanger Cross-Out
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
31a. NAME OF CONTRACTING OFFICER (Type or print)
Erik Danger
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140R2021R0004
Section B - Supplies and Services and Prices "AU" - Activity Unit is used solely for the purposes of allowing progress payments under the Department of Interior's Financial & Business Management System (FBMS).
BF SISK Safety of Dams (SOD) Modification Phase 1
Pricing Schedule:
CLIN 1-93
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
00010 1 AU
B. F. Sisk Dam SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
Traffic Control
01 55 20 - 1
SECTION 01 55 20
TRAFFIC CONTROL
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Traffic Control:
1. Payment: Lump sum price offered in the Price Schedule.
a. Includes constructing, maintaining, and removing detours.
b. Equal monthly progress payments as a percentage of the lump-sum price will be made over the duration of the contract.
c. Does not include water for dust abatement or dust palliative.
B. See Section 01 55 28 – Temporary Traffic Signs for payment of temporary traffic signs.
C. See Section 31 02 10 – Water for Dust Abatement for measurement and payment of water for dust abatement.
1.02 REFERENCE STANDARDS
A. California Department of Transportation (CALTRANS)
1. California MUTCD California Manual on Uniform Traffic
Control Devices, 2014 Edition, available at:
http://www.dot.ca.gov/programs/safety-programs
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 – Submittals.
B. RSN 01 55 20-1, Traffic Control Plan.
1. Provide details for all separate work areas, construction haul routes, construction access roads, and utilized public roads.
2. Details of traffic control provisions used to ensure safe public passage.
3. Details of traffic control provisions at any intersection within project area.
4. Provide plan to CALTRANS and Merced County for review and approval during
County Encroachment Permit process.
5. After approval by the Government, include plans in encroachment permits detailed in Section 01 14 16 – Permits.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 55 20 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 TRAFFIC CONTROL
A. Meet requirements of:
1. California MUTCD.
2. Section 01 55 00 – Vehicular Access and Parking.
B. Obtain necessary state, county, and local permits.
C. Provide cones, delineators, concrete safety barriers, barricades, flasher lights, danger signals, signs, and other temporary traffic control devices as required to protect work and public safety.
1. Refer to Section 01 55 28 – Temporary Traffic Signs for temporary traffic signs related to intersections identified as dangerous and to the detour route notification.
D. Provide flaggers and guards, as required, to prevent accidents and damage or injury to passing traffic.
E. Do not begin work along public or private roads until proper traffic control devices for warning, channeling, and protecting motorists are in place in accordance with approved traffic control plan.
F. Traffic control may be required along Gonzaga Road from intersection with Basalt Road to Highway 33/Santa Nella Boulevard, in accordance with required encroachment permits.
G. Provide appropriate traffic control on any roads where two-directional hauling will occur.
1. Deleted.
2. Deleted.
H. Maintain traffic flow and conduct construction operations to minimize obstruction and inconvenience to public traffic.
I. Provide unobstructed, smooth, and dustless passageway for one lane of traffic through construction operations.
J. Construct temporary connections for one lane of traffic between existing roadway and new construction.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 55 20 - 3
K. Protect roads closed to traffic with effective barricades and warning signs. Illuminate barricades and obstructions from sunset to sunrise.
L. Remove traffic control devices when no longer needed.
END OF SECTION
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 55 20 - 4
This page intentionally left blank.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
Temporary Safety Fence
01 56 32 - 1
SECTION 01 56 32
TEMPORARY SAFETY FENCE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Temporary Safety Fence:
1. Payment: Lump sum price offered in the Price Schedule.
a. Includes installation, maintenance and removal.
PART 2 PRODUCTS
2.01 SAFETY FENCE
A. Fence:
1. High-density polyethylene grid.
2. Minimum height: 48-inch.
3. Color: Safety orange.
4. Recovered Material Content:
a. 90 to 100 percent.
5. Postconsumer Content:
a. 60 to 100 percent.
B. Posts: Steel fence posts.
PART 3 EXECUTION
3.01 INSTALLATION
A. Erect fence in the following areas:
1. Where needed to protect aquatic resource areas adjacent to work areas, as shown on the drawings.
2. Where needed to protect other environmentally sensitive areas, as identified in
Section 01 57 60 – Protected Species.
3. Other areas, in accordance with approved RSN 01 14 10-1, Land Use and
Landscape Rehabilitation Plan.
4. As required for protection of employees and Government personnel.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
Temporary Safety Fence
01 56 32 - 2
B. Space posts 10 feet, maximum, on center.
C. Secure grid to posts.
3.02 MAINTENANCE AND REMOVAL
A. Maintain fence until work in area is complete and accepted by the COR.
B. Remove fence when no longer required.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
Exclusion Fence
01 56 34 - 1
SECTION 01 56 34
EXCLUSION FENCE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Exclusion Fence:
1. Payment: Lump sum price offered in the Price Schedule.
a. Includes installation and removal annually as required by Permits. Refer to Section 01 14 16 – Permits.
1.02 SUBMITTALS
A. Submit in accordance with Section 01 33 00 – Submittals.
B. RSN 01 56 34-1, Approval Data and Instructions
1. Manufacturer’s product data.
2. Manufacturer’s recommended installation method.
C. RSN 01 56 34-2, Installation Plan
1. Include locations and installation methods.
2. Submit updated annual plan prior to wet season.
PART 2 PRODUCTS
2.01 EXCLUSION FENCE
A. ERTEC Environmental Systems E-Fence™ Wildlife Exclusion Fence (https://ertecsystems.com/products/wildlife-exclusion-fence-special-status-species-protection/), or similar, with the following essential characteristics:
1. Small vertebrate exclusion and directional barriers.
2. Minimum height: 36-inch.
3. Not climbable by wildlife.
4. Continuous intact barrier to wildlife in accordance with the permits.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 56 34 - 2
PART 3 EXECUTION
3.01 INSTALLATION
A. Complete installation of required exclusion fence prior to the wet season (October 15 to April 30 of each year). Remove installed exclusion fence between April 30 and May 14 of each year.
B. Exclusion fence shall be installed at the following locations to reduce potential for road strikes on protected species listed in Section 01 57 60 – Protected Species:
1. A corridor along roadways at edge of disturbed ground within 600 meters of the pond locations shown on drawings, with the exact locations approved by the
COR.
2. A corridor along east edge of Basalt Road at edge of disturbed ground as it approaches within 600 meters of the Settling Ponds (east of the dam right abutment) shown on drawings.
3. Deleted.
C. Government will obtain a variance to allow the Contractor to install the fence during the wet season in the initial year of construction if access is required prior to April 30 of the first year.
1. Contractor shall install the fence in accordance with permit. Refer to Section
01 14 16 – Permits.
D. Installation of the fence requires full-time oversight by an approved biologist. Refer to Section 01 57 60 – Protected Species.
E. Extend above ground surface at least 2.5 feet.
F. Bury below ground surface at least 6 inches to prevent species from crawling under the fence.
G. Space posts 10 feet, maximum, on center.
H. Secure fence to posts.
I. Exclusion fence not required on dam face.
J. During work hours, a portion of fencing may be removed to facilitate work activities, then reinstalled at end of each day.
K. A Government biologist will be present to observe and approve exclusion fencing locations and installation.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 56 34 - 3
3.02 MAINTENANCE AND REMOVAL
A. Maintain fence until construction activities are completed or the wet season ends as accepted by the COR.
B. Remove fence annually outside of the wet season.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 56 34 - 4
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
Environmental Controls
01 57 20 - 1
SECTION 01 57 20
ENVIRONMENTAL CONTROLS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Purchase of Carbon Offsets:
1. Lump sum price offered in the Price Schedule.
B. Cost:
1. Include other environmental controls in prices offered in the Price Schedule for other items of work, except as specified.
2. Costs for damages and work stoppage are the Contractor's responsibility.
C. See Section 31 02 30 – Dust Palliative, for payment for applying dust palliative used for dust abatement within the rights-of-way.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards, including revisions posted at https://www.usbr.gov/safety/rshs/index.html
B. San Joaquin Valley Air Pollution Control District
1. Dust Control Plan San Joaquin Valley Air Pollution Control
District, Regulation VIII – Fugitive PM10 Prohibitions posted at https://www.valleyair.org/busind/comply/ PM10/compliance_PM10.htm
2. Indirect Source Review (ISR) Rule COVID-19 Emergency Measures posted at https://www.valleyair.org/ISR/ISRHome.
htm
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 57 20-1, Copy of Applicable Air Quality Permit:
1. Air Quality Permits are required for certain construction-related activities including, but not limited to, earthmoving, sandblasting, aggregate processing, https://www.usbr.gov/safety/rshs/index.html
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 57 20 - 2 welding, spray-coating operations, or other processes which discharge pollutants into the open air.
2. Air Quality Permits, and information concerning the requirements, are available from: San Joaquin Valley Air Pollution Control District, Northern Region, 4800 Enterprise Way, Modesto, CA 95356, 209-557-6400.
C. RSN 01 57 20-2, Dust Control Plan:
1. Include equipment, materials, methods, and frequencies to be used.
2. Provide copies of forms submitted to and approved copy of dust control plan from
San Joaquin Valley Air Pollution Control District.
D. RSN 01 57 20-3, Noise Control Plan:
1. Plans, procedures, and equipment used to control and monitor noise.
2. Prepared and signed by an acoustical engineer.
E. RSN 01 57 20-4, Pre-construction Noise Survey Results.
1. Include daytime and nighttime survey results.
F. RSN 01 57 20-5, Monthly Record Keeping Forms:
1. Regulation VIII Record Keeping Forms for applicable Area Water Application, Cleanup of Trackout and Carryout, Permanent / Long Term Dust Controls, and Water Application onto Unpaved Roads and Equipment Areas as required by San Joaquin Valley Air Pollution Control District, Northern Region
1.04 REGULATORY REQUIREMENTS
A. Comply with Federal, State, and local laws and regulations.
B. Register portable engines and portable engine driven equipment units with the California Resources Board (CARB) portable equipment registration program (PERP). Refer to the following website for information:
1. https://ww2.arb.ca.gov/our-work/programs/portable-equipment-registration-program-perp
C. Obtain any required permits from San Joaquin Valley Air Pollution Control District.
D. Comply with RSHS.
E. Comply with San Joaquin Valley Air Pollution Control District Dust Control Plan and Indirect Source Review (ISR) Rule.
F. Conform to most stringent requirement having jurisdiction in cases of conflict between specifications, regulatory requirements, and RSHS.
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 57 20 - 3
G. Purchase carbon offsets before construction activities commence in an amount sufficient to reduce greenhouse gas emissions to less than significant levels using DWR significance thresholds. A minimum of 104,537 MTCO2e is required to reduce emissions below the project-level significance threshold. Only emission offsets generated as part of CARB’s Compliance Offset Protocols (developed for the AB 32 cap‐ and‐trade program) may be used to reduce GHG emissions.
H. Contractor shall be responsible for damages resulting from dust originating from Contractor operations in accordance with clause at FAR 52.236-7, Permits and Responsibilities.
I. Comply with requirements in the FWS Biological Opinion, Record of Decision, and Final EIS/EIR. Refer to Section 51 00 80 – Environmental Reports, Records, and Permits.
J. The COR may stop construction activity in violation of Federal, State, or local laws and additional expenses resulting from work stoppage will be responsibility of Contractor.
1.05 DUST CONTROL
A. Comply with San Joaquin Valley Air Pollution Control District requirements regarding dust control.
1. As applicable, comply with Section 6.4 or 6.3 of District Rule 8021 of the San
Joaquin Valley Air Pollution Control District on Construction requirement for Notification or Dust Control Plan.
2. Refer to https://valleyair.org/busind/comply/PM10/compliance_PM10.htm.
Locate heading Plans & Forms, then Dust Control Plan/Construction Notifications. This is a revised document as of April 16, 2020. Submit applicable sections of the form as required to San Joaquin Valley Air Pollution Control District.
a. Dust control plan submitted to San Joaquin Valley Air Pollution Control
District will be reviewed, approved, conditionally approved, or disapproved by the District. The District has 30 days to reply after receipt of dust control plan.
3. Construction activities cannot begin until dust control plan has been approved or conditionally approved by the District.
4. Any District notifications have a 48-hour window prior to starting work activities.
B. Provide dust control and abatement during performance of work. Refer to Section 31 02 30 – Dust Palliative.
C. Prevent, control, and abate dust pollution on rights-of-way provided by Government, within the limits of disturbance or elsewhere during performance of work.
D. Provide labor, equipment, and materials, and use efficient methods wherever and whenever required to prevent dust nuisance or damage to persons, property, or activities, https://valleyair.org/busind/comply/PM10/compliance_PM10.htm
SOD Modifications, Phase 1 Amendment No. 0007 San Luis Unit, West San Joaquin Division, Central Valley Project, California Specifications No. 20-C0909
01 57 20 - 4 including, but not limited to, crops, orchards, cultivated fields, wildlife habitats, dwellings and residences, agricultural activities, recreational activities, traffic, and similar conditions.
E. Provide means for eliminating atmospheric discharges of dust during mixing, handling, processing, and storing of cement, pozzolan, and aggregate.
1. Use spray bars or turbine misters at material processing and conveying equipment.
F. Stabilize disturbed areas, including staging and stockpile areas not being actively used for construction purposes. Limit dust emissions using water, tarp, other suitable cover or vegetative ground cover.
G. Control land clearing, grubbing, scraping, excavation, land leveling, grading, cut and fill, and demolition activities to limit fugitive dust emissions by applying water or by presoaking.
H. Cover or wet material when materials are transported off site to limit visible dust emissions and maintain at least 6 inches of freeboard space from the top of the container.
I. Stabilize outdoor storage piles following the addition of materials to, or the removal of materials from, said piles to limit fugitive dust emissions using sufficient water.
1.06 AIR POLLUTION CONTROL
A. On-Road Vehicles:
1. Throughout duration of the project, all haul trucks, vendor trucks, and other vehicles operating onsite with on-road engines shall meet model year 2015 or better emission standards.
2. All haul trucks, vendor trucks, and…
This is the start of the file's text. The full file is on GovTribe.