Attachment_B_1_Schedule_of_Prices_Amendment_0007_0007.xlsx
XLSX spreadsheet 19 KB Posted
- Solicitation number
- 140R2021R0004
About this file
This document contains a schedule of prices for a federal solicitation to perform safety modifications to the BF Sisk Dam. The solicitation is issued by the Bureau of Reclamation within the Department of the Interior and seeks construction services to address issues with the dam's select foundation materials and help prevent destabilization.
The schedule of prices lists 94 contract line item numbers with descriptions of supplies and services including construction of shear keys and stability berms, spillway modifications, concrete work, dewatering, excavation, backfill, drainage, fencing and restoration. Unit pricing is requested for some items while others are designated as lump sum. The total proposed price is listed as $0.00 pending offerors providing their proposed pricing.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| B.F. SISK Safety of Dams (SOD) Modifications, Phase I | Solicitation 140R2021R0004 | |||||
| Amendment 0007 | Section B, Schedule of Prices | |||||
| CLIN | Section | Supplies or Services | Quantity | Unit | Unit Price | TOTAL |
| 1 | WBR 1452.232-81 | Mobilization and Preparatory Work | For the lump sum of: | $0.00 | ||
| 2 | 01 31 30 | Contract Document Management System (CDMS) | For the lump sum of: | $0.00 | ||
| 3 | 01 35 50 | Site Security | For the lump sum of: | $0.00 | ||
| 4 | 01 52 10 | Gov. Field Office Delivery and Installation | For the lump sum of: | $0.00 | ||
| 5 | 01 52 10 | Gov. Field Office Maintenance | For the lump sum of: | $0.00 | ||
| 6 | 01 52 14 | Gov. Field Laboratory Facility Delivery and Installation | For the lump sum of: | $0.00 | ||
| 7 | 01 52 14 | Gov. Field Laboratory Facility Maintenance | For the lump sum of: | $0.00 | ||
| 8 | 01 55 20 | Traffic Control | For the lump sum of: | $0.00 | ||
| 9 | 01 55 28 | Temporary Post-Mounted Traffic Signs | For the lump sum of: | $0.00 | ||
| 10 | 01 56 32 | Temporary Safety Fence | For the lump sum of: | $0.00 | ||
| 11 | 01 56 34 | Exclusion Fence | For the lump sum of: | $0.00 | ||
| 11A | 01 57 20 | Purchase of Carbon Offsets | For the lump sum of: | $0.00 | ||
| 12 | 01 57 30 | Stormwater Pollution Prevention Plan (SWPPP) General Requirements | For the lump sum of: | $0.00 | ||
| 13 | 01 83 13 | Project Monitoring | For the lump sum of: | $0.00 | ||
| 14 | 02 01 60 | Wildlife Spillway Crossing | For the lump sum of: | $0.00 | ||
| 15 | 02 01 80 | Tule Elk Herd Management | For the lump sum of: | $0.00 | ||
| 16 | 02 21 34 | Structure Measurement Points | For the lump sum of: | $0.00 | ||
| 17 | 03 15 12 | PVC Waterstops | 140 | lin ft | $0.00 | $0.00 |
| 18 | 03 15 14 | PVC Retro-Fit Waterstop | 64 | lin ft | $0.00 | $0.00 |
| 19 | 03 20 00 | Concrete Reinforcing | 91,000 | lbs | $0.00 | $0.00 |
| 20 | 03 20 30 | Drilling Holes for Anchor Bars and Grouting Bars in Place | 42 | lin ft | $0.00 | $0.00 |
| 21 | 03 30 00 | Concrete | 480 | yd3 | $0.00 | $0.00 |
| 22 | 03 81 10 | Spillway Concrete Removal | For the lump sum of: | $0.00 | ||
| 23 | 03 81 10 | Saw Cutting Existing Concrete | For the lump sum of: | $0.00 | ||
| 24 | 05 50 00 | Metal Fabrications (Miscellaneous Metalwork) | For the lump sum of: | $0.00 | ||
| 25 | 26 05 06 | Removal and Disposal of Existing Electrical Equipment | For the lump sum of: | $0.00 | ||
| 26 | 26 05 10 | Conductors and Cables | For the lump sum of: | $0.00 | ||
| 27 | 26 05 22 | Medium-Voltage Power Cable | 1,300 | lin ft | $0.00 | $0.00 |
| 28 | 26 05 33 | Raceway and Boxes | For the lump sum of: | $0.00 | ||
| 29 | 31 02 10 | Water for Dust Abatement | For the lump sum of: | $0.00 | ||
| 30 | 31 02 30 | Dust Palliative | For the lump sum of: | $0.00 | ||
| 31 | 31 03 33 | Unwatering | For the lump sum of: | $0.00 | ||
| 32 | 31 03 33 | Well Points | 230 | lin ft | $0.00 | $0.00 |
| 33 | 31 03 33 | Supplementary Well Points Materials | 10 | ea. (well) | $0.00 | $0.00 |
| 34 | 31 03 33 | Supplementary Well Points Installation/Removal | 10 | ea. (well) | $0.00 | $0.00 |
| 35 | 31 03 33 | Dewatering Wells | 210 | lin ft | $0.00 | $0.00 |
| 36 | 31 03 33 | Supplementary Dewatering Wells Materials | 4 | ea. (well) | $0.00 | $0.00 |
| 37 | 31 03 33 | Supplementary Dewatering Wells Installation/Removal | 4 | ea. (well) | $0.00 | $0.00 |
| 38 | 31 03 33 | Dewatering Sumps | 18 | ea. (sump) | $0.00 | $0.00 |
| 39 | 31 03 33 | Supplementary Dewatering Sumps Materials | 9 | ea. (sump) | $0.00 | $0.00 |
| 40 | 31 03 33 | Supplementary Dewatering Sumps Installation/Removal | 9 | ea. (sump) | $0.00 | $0.00 |
| 41 | 31 03 33 | Temporary Observation Wells | 120 | lin ft | $0.00 | $0.00 |
| 42 | 31 03 33 | Supplementary Temporary Observation Wells Materials | 3 | ea. (well) | $0.00 | $0.00 |
| 43 | 31 03 33 | Supplementary Temporary Observation Wells Installation/Removal | 3 | ea. (well) | $0.00 | $0.00 |
| 44 | 31 03 33 | Well Points Operation | For the lump sum of: | $0.00 | ||
| 45 | 31 03 33 | Dewatering Wells Operation | For the lump sum of: | $0.00 | ||
| 46 | 31 03 33 | Dewatering Sump Operation | For the lump sum of: | $0.00 | ||
| 47 | 31 09 10 | Abandoning and Removing Existing Instrumentation | For the lump sum of: | $0.00 | ||
| 48 | 31 09 12 | Temporary Inclinometers | 20 | each | $0.00 | $0.00 |
| 49 | 31 09 13 | Slope Stability Monitoring | For the lump sum of: | $0.00 | ||
| 50 | 31 09 22 | Protecting Existing Instrumentation | For the lump sum of: | $0.00 | ||
| 51 | 31 11 00 | Clearing and Grubbing | 450 | acres | $0.00 | $0.00 |
| 52 | 31 14 10 | Stripping | 370,000 | yd3 | $0.00 | $0.00 |
| 53 | 31 23 11 | Common Excavation for Structures | 16,000 | yd3 | $0.00 | $0.00 |
| 54 | 31 23 11 | Rock Excavation for Structures | 860 | yd3 | $0.00 | $0.00 |
| 55 | 31 23 12 | Excavation for Electrical Trench | 700 | lin ft | $0.00 | $0.00 |
| 56 | 31 23 12 | Compacted Backfill for Electrical Trench | 700 | lin ft | $0.00 | $0.00 |
| 57 | 31 23 14 | Excavation of Rock Blanket Material | 31,000 | yd3 | $0.00 | $0.00 |
| 58 | 31 23 17 | Excavation of Shear Key | 440,000 | yd3 | $0.00 | $0.00 |
| 59 | 31 23 17 | Backfill Concrete Foundation Treatment | 400 | yd3 | $0.00 | $0.00 |
| 60 | 31 23 20 | Quarry Development | For the lump sum of: | $0.00 | ||
| 61 | 31 23 21 | Stockpiling of Riprap | 50,000 | yd3 | $0.00 | $0.00 |
| 62 | 31 23 22 | Constructing Haul Roads | For the lump sum of: | $0.00 | ||
| 63 | 31 23 22 | Basalt Hill Quarry Haul Roads | For the lump sum of: | $0.00 | ||
| 64 | 31 23 70 | Controlled Low Strength Material | 430 | yd3 | $0.00 | $0.00 |
| 65 | 31 24 13 | Zone 1, Impervious Fill | 50,000 | yd3 | $0.00 | $0.00 |
| 66 | 31 24 14 | Zone 9A, Sand Filter | 37,000 | yd3 | $0.00 | $0.00 |
| 67 | 31 24 14 | Zone 9B, Crest Sand Filter | 3,100 | yd3 | $0.00 | $0.00 |
| 68 | 31 24 15 | Zone 11, Gravel Drain | 2,800 | yd3 | $0.00 | $0.00 |
| 69 | 31 24 16 | Zone 8, Miscellaneous Fill | 1,700,000 | yd3 | $0.00 | $0.00 |
| 70 | 31 24 17 | Zone 10, Shear Key Rockfill | 320,000 | yd3 | $0.00 | $0.00 |
| 71 | 31 24 18 | Downstream Rock Blanket Material | 34,000 | yd3 | $0.00 | $0.00 |
| 72 | 31 24 19 | Zone 2A, Embankment Filter | 190,000 | yd3 | $0.00 | $0.00 |
| 73 | 31 24 20 | Zone 4A, Embankment Drain | 45,000 | yd3 | $0.00 | $0.00 |
| 74 | 31 32 32 | Geotextile | 6,800 | yd2 | $0.00 | $0.00 |
| 75 | 32 10 16 | Remove Existing Asphalt Pavement and Base Course | 3,100 | yd2 | $0.00 | $0.00 |
| 76 | 32 10 16 | Cold Plane Existing Asphalt Pavement | For the lump sum of: | $0.00 | ||
| 77 | 31 11 23 | Aggregate Base Course | 810 | yd3 | $0.00 | $0.00 |
| 78 | 32 12 22 | Asphalt Concrete Pavement | 3,300 | yd2 | $0.00 | $0.00 |
| 79 | 32 15 10 | Gravel Surfacing | 12,000 | yd2 | $0.00 | $0.00 |
| 80 | 32 17 20 | Traffic Lines and Markings | For the lump sum of: | $0.00 | ||
| 81 | 32 31 10 | Chain Link Fence | 60 | lin ft | $0.00 | $0.00 |
| 82 | 32 31 10 | Removal and Disposal of Existing Chain Link Fence | 230 | lin ft | $0.00 | $0.00 |
| 83 | 32 91 19 | Topsoil | 450 | acres | $0.00 | $0.00 |
| 84 | 32 92 20 | Restoration and Revegetation | 450 | acres | $0.00 | $0.00 |
| 85 | 33 05 31 | Toe Drain Terminal Wells | For the lump sum of: | $0.00 | ||
| 86 | 33 29 04 | Removing Existing Toe Drain Pipes | 250 | lin ft | $0.00 | $0.00 |
| 87 | 33 09 05 | Abandoning Existing Toe Drains Using Grout | 100 | yd3 | $0.00 | $0.00 |
| 88 | 33 46 36 | 12-inch Diameter Perforated HDPE Pipe | 1,700 | lin ft | $0.00 | $0.00 |
| 89 | 33 46 36 | 12-inch Diameter Nonperforated HDPE Pipe | 600 | lin ft | $0.00 | $0.00 |
| 90 | 33 46 36 | Drain Cleanouts | 6 | each | $0.00 | $0.00 |
| 91 | 33 46 42 | Weir Boxes | For the lump sum of: | $0.00 | ||
| 92 | 34 71 19 | Roadway Markers | For the lump sum of: | $0.00 | ||
| 93 | 35 21 95 | Spillway Vent Pipe Modifications | For the lump sum of: | $0.00 | ||
| Grand Total: | $0.00 |
File details come from the government source that posted it. Updated .