This is a technical drawing and process plan for the Cow Creek Pool Filtration system at Death Valley National Park. The drawing is Sheet 023 D101, dated January 17, 2025, and is part of a larger project package (PMIS/PKG NO. 318717) managed by the National Park Service.

The process plan illustrates a pool filtration system layout at a scale of 1/2" = 1'-0" and includes mechanical components such as four circular filter vessels arranged vertically, a power supply unit, a Hayward saline cell rated at 11.0, and associated piping and valve manifolds. The primary keynote specifies the relocation of an existing Pitot tube flow meter to a similar location on the discharge manifold. The drawing was designed by JRC, technically reviewed by PKK, and prepared by JLC as part of the Death Valley National Park infrastructure project. This appears to be a construction or renovation document for pool filtration system modifications rather than a federal contract solicitation or procurement document.

View the file

Other files

File Type Posted
B09_Amd11_-_B08_Attach3_-_WD_CA20260020_Mod2_0011.pdf PDF
Sol_140P2025R0082_Amd_0011.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_42_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_38_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_01-C4_40_Jan2026_0010.pdf PDF
B09_Amd10_QR_Tracker_-_DEVA_318717_Final_0010.xlsx XLSX spreadsheet
B09_Amd10_-_QR55_Attach_Drawing_01-C4_39_Jan2026_0010.pdf PDF
B09_Amd10_-_QR55_Attach_Drawing_00-C8_27_Jan2026_0010.pdf PDF
B09_Amd10_-_QR86_Attach_Drawing_C1_40_0010.pdf PDF
B09_Amd10_-_Drawing_G1_22_0010.pdf PDF
B09_Amd10_-_QR86_Attach_Drawing_C1_40B_0010.pdf PDF
Sol_140P2025R0082_Amd_0010.pdf PDF
B09_Amd10_-_B08_Attach4_-_DetailedContractPriceSchedule_0010.xlsx XLSX spreadsheet
B09_Amd10_-_Drawing_G1_2_0010.pdf PDF
B09_Amd10_-_Drawing_Coversheet_00_DEVA_318717_Jan2026x_0010.pdf PDF
B09_Amd10_-_Drawing_G1_21_0010.pdf PDF
Sol_140P2025R0082_Amd_0009.pdf PDF
B09_Amd8_-_Drawing_02-C5_29_Jan2026_0008.pdf PDF
B09_Amd8_-_Spec_33_14_19_-_VALVES___HYDRANTS_FOR_WATER_UTILITY_SERVICE_0008.pdf PDF
B09_Amd8_-_Drawing_02-G1_16_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_08_33_22_-_ALUMINUM_ROLLING_OVERHEAD_DOORS_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_29_Jan2026_0008.pdf PDF
B09_Amd8_-_QR22_Attach_Drawing_00-C7_1_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C5_25_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_00-C8_30_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-C4_42_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C3_1_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_20_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_33_32_00_-_WASTEWATER_PUMPING_STATIONS_0008.pdf PDF
B09_Amd8_-_Spec_33_31_11_-_GRAVITY_SEWER_PIPELINE___MANHOLE_INSTALLATION_0008.pdf PDF
B09_Amd8_QR_Tracker_-_DEVA_318717_0008.xlsx XLSX spreadsheet
B09_Amd8_-_Drawing_Coversheet_00_DEVA_318717_Jan2026_0008.pdf PDF
Sol_140P2025R0082_Amd_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_31_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C6_7_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_15_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_00-G1_2_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-C7_5_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_33_11_13_-_POTABLE_WATER_SUPPLY_WELLS_0008.pdf PDF
B09_Amd8_-_Drawing_00-C3_18_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_02-C5_33_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_42_Jan2026_0008.pdf PDF
B09_Amd8_-_QR56_Attach_Drawing_02-C2_20_Dec2025_0008.pdf PDF
B09_Amd8_-_Spec_33_31_05_-_MANHOLE_LINING___REHABILITATION_0008.pdf PDF
B09_Amd8_-_Drawing_01-G1_15_Jan2026_0008.pdf PDF
B09_Amd8_-_QR56_Attach_Drawing_02-C2_18_Dec2025_0008.pdf PDF
B09_Amd8_-_Drawing_01-C1_67_Jan2026_0008.pdf PDF
B09_Amd8_-_Spec_46_33_11_-_CHEMICAL_FEED_-_LIQUID_SYSTEMS_0008.pdf PDF
B09_Amd8_-_Drawing_02-C2_22_Jan2026_0008.pdf PDF
B09_Amd8_-_Drawing_02-X1_2_Jan2026_0008.pdf PDF
Show 40 more

Latest 50 of 109 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

T T

023D301

023D301

HAYWARD

SALINE C 11.0

POWER

SUPPLY

4"-PL

ASCALE 1/2" = 1'-0"

2 0 2 4

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

N

P S

D

E V

A C o w

F u rn a c e

/1

P O

O L

F

IL

T E

R A

T

IO

N D

.r v t

/1

/2

:1

:0

A

M

D101

DEATH VALLEY NATIONAL PARK

318717

PROCESS PLAN

JRC

PKK

01.17.2025

JLC

178069023

COW CREEK POOL FILTRATION

SCALE A023D101

PROCESS PLAN1

KEYNOTES:

1. RELOCATE EXISTING PITOT TUBE FLOW METER

TO SIMILAR LOCATION ON DISCHARGE MANIFOLD.